HomeMy WebLinkAboutContract 57185 Mar 1, 2022 CSC No. 57185
FUTURE IMPROVEMENTS AGREEMENT
FOR
INFRASTRUCTURE IMPROVEMENTS
Newberry Point Phase 2
WHEREAS, the City of Fort Worth ("City") has entered into that certain
Community Facilities Agreement (CFA21-0047) ("CFA") with Pulte Homes of Texas, LP,
("Developer"); and
WHEREAS, the CFA includes Developer's proportionate share of the
construction of Paving, Storm Drain, Street Lights and Signs a portion of which is within
S. Hulen Street, as shown on Exhibit A; and
WHEREAS, in lieu of the Developer, pursuant to the CFA, constructing those
certain improvements for Paving, Storm Drain, Street Lights and Signs on Exhibit B
(the "Improvement"), Developer will contribute those funds it would have spent to
construct the Improvement and the City will instead construct the Improvement(s) at a
later time; and
WHEREAS, Developer desires to provide to the City funds in the amount of
$332,047.11 ("Developer Funds") for the City to construct the Improvement; and
WHEREAS, The City agrees to accept the Developer Funds and to construct the
Improvement; and
WHEREAS, the determination of the amount of Developer's Funds is not an
assessment pursuant to Chapter 313 of the Texas Transportation Code;
NOW THEREFORE, in consideration of the above recitals, incorporated herein
for all purposes, City and Developer, acting by and through their duly authorized
representatives, do hereby agree as follows:
1 .
The City may construct (or cause to be constructed) the Improvement at a time
convenient to the City provided that adequate public funds, including the Developer
Funds, for construction of the Improvement are secured.
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH, TX
Developer Funding Agreement—Newverry Point Phase 2
Page 1 of 4
2.
Concurrently herewith, Developer has paid to the City the amount of
$332,047.11 , such Developer Funds, the Developer and City agree, are the entire
amount of Developer's contribution for the cost to construct the Improvements.
By accepting the Funds and by execution of this Agreement, City agrees that the
Developer will have no further obligation to pay any amounts in addition to the
Developer Funds or take any further action with regard to the construction of the
Improvement, even if (a) the actual costs to construct the Improvement exceeds the
costs expected by the City as of the date of this Agreement, (b) the specifications,
composition, or other characteristics of the Improvement hereafter change for any
reason, (c) a mistake has been made (mutual or unilateral) in computing the costs of the
Improvement or otherwise, or (d) the costs or scope of the Improvement change for any
reason.
3.
This Agreement shall be binding upon and inure to the benefit of the City and
Developer and their respective successors and assigns. This Agreement, together with
any exhibits attached hereto, constitutes the entire agreement between the parties
hereto, and may not be amended except by a writing signed by all parties and dated
subsequent to the date hereof.
4.
The City will use its best reasonable efforts to construct the Improvement without
undue delay, but City's construction will be subject to City securing the additional
funding which may be necessary to fully construct the Work.
5.
Developer unless a sole proprietor, acknowledges that in accordance with
Chapter 2271 of the Texas Government Code, if Consultant has 10 or more full time-
employees and the contract value is $100,000 or more, the City is prohibited from
entering into a contract with a company unless the contract contains a written
verification from the company that it: (1) does not boycott Israel; and (2) will not boycott
Israel during the term of the contract. The terms "boycott Israel" and "company" shall
have the meanings ascribed to those terms in Section 808.001 of the Texas
Government Code. By signing this contract, Developer certifies that Developer's
signature provides written verification to the City that if Chapter 2271, Texas
Government Code applies, Developer: (1) does not boycott Israel; and (2) will not
boycott Israel during the term of the contract.
Developer Funding Agreement—Newverry Point Phase 2
Page 2 of 4
Executed by each party's duly designated and authorized representative; effective as of
the date subscribed by the City's designated Assistant City Manager.
CITY OF FORT WORTH DEVELOPER:
Pulte Homes of Texas, L.P.
Dghg Burck7doff _19MC)
Dana Burghdoff ar 1,2022 09:03 CST) Millward(Feb 16,2022 08:23 CST)
Dana Burghdoff Curt Millward
Assistant City Manager Director of Land Development
Marl, 2022 Feb 16, 2022
Date Date
ATTEST: �►o° 0,
7G1�'l�'1����c1 GDOG�GIGG p v 0 o=A
Jannette S.Goodall(Mar 1,2022 10:12 CST) o o
0 0
Jannette Goodall �d'� °°°°°°°°°°°°° 10
City Secretary 4.4?*XAl.
Contract Compliance Manager
By signing, I acknowledge that I am the
person responsible for the monitoring and
administration of this contract, including ensuring
all performance and reporting requirements
LI&�gab,rt-alf-6w"14(4�
APPROVED AS TO FORM Evelyn troberts on behalfof(Feb 21,202208:32CST)
Bev Planning Manager
DBlack(Feb 19,202211:48 CST) Janie S. Morales
Douglas W. Black
Sr. Assistant City Attorney
OFFICIAL RECORD
CITY SECRETARY
Developer Funding Agreement—Newverry Point Phase 2 FT.WORTH, TX
Page 3 of 4
EXHIBITS
Developer Funding Agreement—Newverry Point Phase 2
Page 4 of 4
KimlepMorn
Section 00 42 43
PROPOSAL FORM UNIT PRICE
Hulen Road(Newberry Point Phase 2)
Unit Price Bid Bidder's Application
PROJECT NAME: Newberry Point Phase 2 DATE: 3/21/2021
CITY: Fort Worth,TX CREATED BY: KEM
JOB NUMBER: 067705804 CHECKED BY: HCW
REVISED BY: KEM
A.STORM DRAIN IMPROVEMENTS
BIDLIST ITEM NO. I ITEM DESCRIPTION SPEC/F/CAT/ON SECT/ON NO. UNIT QUANTITY UNIT PRICE ITEM COST
3341.0309 36"R.C.P.,CLASS III 3241 10 LF 334 $ 128.57 $ 42,942.38
3341.0302 30"R.C.P.,CLASS III 3341 10 LF 674 $ 78.63 $ 52,996.62
3341.0201 21"R.C.P.,CLASS III 3341 10 LF 189 $ 67.49 $ 12,747.82
3349.0001 4'JUNCTION BOX 334920 EA 1 $ 4,360.62 $ 4,360.62
3349.5001 10'CURB INLET 334920 EA 2 $ 3,822.89 $ 7,645.78
3349.1007 36"FLARED HEADWALL 34 49 20 EA 1 $ 4,160.00 $ 4,160.00
3305.0109 TRENCH SAFETY 3305 10 LF 863 $ 1.12 $ 966.43
SUB-TOTAL STORM DRAIN IMPROVEMENTS $ 82,877.27
B.PAVING IMPROVEMENTS
BIDLIST ITEM NO. ITEM DESCRIPTION SPECIFICATION SECTION NO. UNIT QUANTITY UNIT PRICE ITEM COST
33213.0105 10"CONCRETE PAVEMENT 32 13 13 BY 1,274 $ 61.10 $ 77,841.40
3213.3010 4"CONCRETE SIDEWALK 32 1320 SF 6,228 $ 5.41 $ 33,693.48
3211.0502 8"LIME TREATMENT 32 11 29 BY 1,327 $ 3.63 $ 4,817.01
3211.0400 HYDRATED LIME 32 11 29 TN 24 $ 154.15 $ 3,682.03
241.1100 REMOVE ASPHALT PAVEMENT 0241 15 BY 1,560 $ 6.93 $ 10,810.80
3217.0008 4"SLID PAVEMENT MARKING TAPE(Y) 32 1723 LF 674 $ 3.28 $ 2,210.72
3217.0004 4"BRK PAVEMENT MARKING HAS(Y) 32 1723 LF 674 $ 1.43 $ 963.82
3291.0100 TOPSOIL 329119 CY 308 $ 22.66 $ 6,979.28
3292.0400 SEEDING,HYDROMULCH 329213 BY 924 $ 1.18 $ 1,090.32
3471.0001 TRAFFIC CONTROL 3471 13 MO 2 $ 3,768.26 $ 7,536.52
9999.0019 UNCLASSIFIED EXCAVATION 00 00 00 CY 1,481 $ 3.00 $ 4,443.50
SUB-TOTAL PAVING IMPROVEMENTS $154,068.88
1:55 PM
3/25/2021
Z:\DAL_Civil\067705804-Newberry Point\Fldmin\Bid Docs\FIA Agreement\20210316_Phase 2 FIA Agreement.xlsx 1 of 2
KimlepMorn
Section 00 42 43
PROPOSAL FORM UNIT PRICE
Hulen Road(Newberry Point Phase 2)
Unit Price Bid Bidder's Application
PROJECT NAME: Newberry Point Phase 2 DATE: 3/21/2021
CITY: Fort Worth,TX CREATED BY: KEM
JOB NUMBER: 067705804 CHECKED BY: HCW
REVISED BY: KEM
C.STREET SIGNS
B/DL/ST ITEM NO. 11TEMDESCRIPTION SPEC/1/CAT/ON SECT/ON NO. UNIT QUANTITY UNIT PRICE ITEM COST
11
3441.4006 INSTALL ALUM SIGN GROUND MOUNT 3441 30 EA 1 $ 410.16 $ 410.16
SUB-TOTAL STREET SIGNS $410.16
D.STREET LIGHTS
B/DL/ST ITEM NO. ITEM DESCR/PT/ON SPECIFICATION SECT/ON NO. UNIT QUANTITY UNIT PRICE ITEM COST
9999.0018 STREETLIGHTS 344120 EA 3 $ 4,500.00 $ 13,500.00
SUB-TOTAL STREET LIGHTS $13,500.00
E.BID SUMMARY
BASE B/D
STORM DRAIN IMPROVEMENTS $ 82,877.27
PAVING IMRPOVEMENTS $ 154,068.88
STREET SIGNS $ 410.16
STREET LIGHTS $ 13,500.00
TPW INSPECTION FEE(4%) $ 9,494.25
TPW MATERIAL TESTING(2%) $ 4,747.13
STREET LIGHTS INSPECTION COST(4%) $ 540.00
TOTAL BASE BID $ 265,637.69
CONTINGENCY
25% $ 66.409.42
TOTAL BID $ 332,047.11
1:55 PM
3/25/2021
Z:\DAL_Civil\067705804-Newberry Point\Fldmin\Bid Docs\FIA Agreement\20210316_Phase 2 FIA Agreement.xlsx 2 of 2
O�
Y
ME
J E TJ
Rsp
w
EB or_
_ m
w
U
NE ROAD PROJECT
LOCATION
8 VICINITY MAP
N.T.S. N
N
W E
3
Y`s
NEWBERRY POINT
PHASE 2
CITY PROJECT # 103045
LOCATED I N
CITY OF FORT WORTH, TEXAS
' MAPSCO NO. TAR-117B
OWNER/DEVELOPER Kimley>>>Horn
B PU LTE HOMES OF TEXAS,L.P. MAY Z O2 13455 Noel Road,Two Galleria Office Tower
J 9111 CYPRESS WATES BLVD. Suite 700
FSS SUITE100 DallasT exas 75240
CO at
TEL:(972)304-2849 Ste ofTexas Registration No.F-928
CONTACT CURT M.MI LLWARD
Y
N
Wm W E
rYrn _ III
r�rvar�ce I/1E x[ RANCHO VERDE
PARKWAY
rn —
ta to 0 100' 200'
mcvwu toocwwc
E
ta'ixot.mo n
NGa°nAs INMI tan � �P��T PROPOgD GRAPHIC SCALE 100'
r w�>Ert
pgpppgEp r tE90010E m IIEO1E01 P s.dOAnpIS 14
91MM MHCMflEN Is 1101E 61N�NOEpTw 3t.. 13 15
TYPICAL RESIDENTIAL SECTION _
Nrs I I 16 11
18
{
E$
EX.27"RCP I NEWBERRY POINT PHASE 1 _
PULTE HOMES OF TEXAS,L.P.
M M _
Y 2x ss
J —
,�; INC UDEDW TH PHA E1
= FU URE IMP OVEME TS
PHASE 1-27'RCP } AG EEMEN
PHASE 1-4'x4' 12 11 10 9 8 7
JUNCTION BOX
' PHA E 1-10' NLET I
PHASE 1-10,INLET }}-
O s i
28 ROW'
DEDICATION 10'CONCRETE FIRE HYDRANT
NEWBERRY POINT SIDEWALK
PHASE 1 21"RCP
10.18 ACRES 10'
TEXAS ELECTRIC SERVICE COMPANY
CITY OF FORT WORTH VOL.3564,PG.577,D.R.T.C.T. 9.375 ACRES
TARRANT COUNTY TEXAS ELECTRIC SERVICE COMPANY
OHE ULTIMATE 4'X4' I VOL.3554,PG.613,D.R.T.C.T.
OHE
OHE DROPINLET
I� OHE
4 X4'JUNCTION
21"RCP—14
s a s
J
10' NCRETE
D SID K
p { 32'ROW
DEDICATION ULTIMATE 0' 10'INLET
Z IINLET
I O
0 2"RCPI
p0"RCP 23 — —
= I 0' I 3
NEWBERRY POINT g 2 '
PHASE 2 3
NEWBERRY POINT PHASE 2
N o R I PULTE HOMES OF TEXAS,L.P.
wl I COUNTY LINE
i� z" b 2,
1 FIRE HYDRANWssr-
0 200' 400' _
CROWLEY INDEPENDENT SCHOOL DISTRICT Iz.
16"WA ER LINE FOBE
GRAPHIC SCALE 200' INST.NO.D207416955 I 0 INCLU ED WIT NEWBERRY
O.P.R.T.C.T. U O INFRAS FRUCTURE PLAN
LEGEND '� o
EXISTING CONCRETE oe U 10'CON RETE
PAVEMENT/SIDEWALK
PROPOSED CONCRETE ULTIMATE 10'INLET
— PAVEMENT/SIDEWALK 10'IN ATE
TRACT 3,9.999 ACRES
PROPOSED CONCRETE gg HERITAGE OF FAITH CHRISTIAN CENTER
E INST.NO.D204105020
PAVEMENT-PHASE1
21"RCP
O.P.R.T.C.T.
PROPOSED STORM DRAIN
9+41.10 WEST CLEBURNE-HULEN
— PROPOSED 10'CURB INLET ROAD END CONCRETE PVMT SECTION
BEGIN ASPHALT TRANSITION
PROPOSED JUNCTION BOX 36"RCP
} PROPOSED STREET LIGHT
�^ 36"SLOPED END PC STA 11+41.38 END
HEADWALL ASPHALT TRANSITION
FUTURE IMPROVEMENT COST ESTIMATE IS SHOWN AS PROPOSED IMPROVEMENTS ON THIS EXHIBIT
Newberry Point - Phase 2 Kimley>>)Horn
Exhibit B: West Cleburne/Hulen Road Sui 5700oel Road
Fort Worth,Texas Dallas,Texas 75240
March 2021 972-335-3580
State of Texas Registration No.F-928