HomeMy WebLinkAboutContract 55611-CO1 CSC No.55611-COI
FORT WORTH City of Fort Worth
Change Order Request
Project Name: 2018 CIP Bond year 2,Contract 14 City Sec No.: 1 55611
Project No,(s): 101475 DOE No. N/A City Proj.No.: 101475-2
Project Description: Replacing water line,Sanitary Sewer lines and repaving the streets.
Contractor: McClendon Construction Co.Inc. Change Order it Dale: 1 2/17/2022
City Project Mgr.1 Suby Varughese City Inspector: I Ryan Miller
Phone Number: (817)392-7803 Phone Number: (817)223 2256
Dept. Water Sewer TPW Totals Contract Time
(Calender days)
Original Contract Amount $1,592,913,00 $612,808.00 $1,791,793.00 $3,997,514.00 365
Extras to Dale
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,592,913.00 $612,808.00 $1,791,793.00 $3,997,514.00 365
Amount of Proposed Change Order $0.00 $30,482.00 $0.00 $30,482.00 30
Revised Contract Amount $1,592,913.00 $643,290.00 $1,791,793.00 $4,027,996.00 395
Original Funds Available for Change Orders $79,646.00 $30,640.00 $89,590.00 $199,876.00
Remaining Funds Available for this CO $79,646.00 $30,640.00 $89,590,00 $199,876.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0,76%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $4,996,892.50
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Change Order No. 1 provides for the rerouting of an existing sewer line that currently runs underneath
residential property into easement and public right-of-way on Madeline Place.
Staff recommends the addition of 30 calendar days to the project for the additional work to be performed to
reroute the sewer main.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Coritraotor's 0oriripany Name Contractor Name 'Co
McClendon ConshcUonCo.Inc. Justin Blair �, 1
Inspector Date Prole Mana er
Date . .
Ryan Miller Suby Varu here 2r21/2022
D[reotor' a r.De_t Date QQnsitruation iso_ P 'Date:.
���•- =,ten J Mar3,2022 •.�,,, Ir,
Assistant:Cit Attorney, Date AssistantQ1 Manager Date. ;
1,.I 12.221-1m Mar 3,2022 Mar 3,2022
anM„3,z� om
Council Action If Required) OFFICIAL RECORD
M&C Number NIA M&C Date Approved
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name 2018 CIP Bond year 2,Contract 14 City Sec No.: 55611
Project No.(s): 101475 DOE No. N/A City Proj.No.: 101475-2
Project Replacing water line,Sanitary Sewer lines and repaving the streets.
Description
Contractor McClendon Construction Co.Inc. Change Order:= Date:F 2/17/2022
City Project Mgr. Suby Varughese City Inspector Ryan Miller
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
5 4'Manhole Sewer 3.00 EA $7,000.00 $21,000.00
7 4'Extra depth Manhole(over 6') Sewer 8.00 VF $450.00 $3,600.00
9 4"Sewer Service w/2way Cleanout Sewer 1.00 EA $1,800.00 $1,800.00
12 Concrete Collar Sewer 2.00 EA $600.00 $1,200.00
13 Manhole Vacuume testing Sewer 3.00 EA $250.00 $750.00
17 Post CCTV inspection Sewer 216.00 LF $10.00 $2,160.00
18 Trench Safety Sewer 216.00 LF $2.00 $432.00
19 Remove 4'Manhole Sewer 1.00 EA $600.00 $600.00
22 Temporary Asphalt Paving repair(2"HMAC on 6"flexbase) Sewer 50.00 LF $30.00 $1,500.00
32 Traffic Control Sewer 0.50 $6,000.00 $3,000.00
38 8"Sewer Pipe PVC SDR-26 Class 160(ASTM-2241) Sewer 216.00 LF $165.00 $35,640.00
39 Sanitary Sewer Abondonment plug Sewer 2.00 EA $650.00 $1,300.00
40 Sanitary Sewer line grouting Sewer 2.00 CY $1,500.00 $3,000.00
41 Hand Tunnelling Sewer 10.00 LF $450.00 $4,500.00
Water
Sewer $80,482.00
TPW
t iige 3 of 1 Additions Sub Total
FORT VV"RTH City of Fort Worth
Change Order Deletions
Project Name 2018 CIP Bond year 2,Contract 14 City Sec No.: 1 55611
Project No.(s): 101475 DOE No. N/A City Proj. No.: 101475 2
Project Description Replacing water line,Sanitary Sewer lines and repaving the streets.
Contractor McClendon Construction Co. Inc. Change Order: � Date 2/17/2022
City Project Mgr. Suby Varughese City Inspector: Ryan Miller
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
37 Sanitary Sewer Construction Allowance Sewer 1.00 LS $50,000.00 $50,000.00
Water
Sewer $50,000.00
TPW
Page 1 of 1 IDeletions Sub Total J$50,000.00
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
Page 1 of 1
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
Signature
Suby Varughese
Name of Employee
Professional Engineer
Title
ATTEST: O °FORT LlA��
Tgnnette S. Goo�%ll �°Foy
.�
Jan nette S.Goodall(Mar4,2022 07:20 CST) P-o
V O=
P
O O
Jannette Goodall * °°° o°4d
°°°°O°
j� °O ICY
City Secretary ��SEX Asap
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Additional information on CPN-101475-2 Change order-1 pricing.
The Contractor provided two price options for additional sewer work(DIP sewer and Class 160 PVC).The
price for the DIP option was an exceptionally high with a 4-month additional time frame due to material
shortage.The project manager negotiated the proposed price for additional sewer line installation
(pressure rated Class 160 PVC option) with the Contractor.The Contractor agreed to reroute the sewer
line for the negotiated amount of$89,927 (proposed amount-$103,227).
McCLENDON CONSTRUCTION CO., INC.
P.O. Box 999 Burleson, Texas 76097 (817) 295-0066 Fax (817) 295-6796
February 8,2022
City of Fort Worth
Attn: Greg Robbins/Suby Varughese
Re: CPN 101475-2
2018 Bond Year 2—Contract 14
Suby,
Below is the price for the additional sewer work requested on Madeline Place. Most of
the work will be covered by existing contract items, but there are a few that will need to
be added.
Item Description Quantity Units Unit Total Price
Price
Existing Items
205 4 ' Manhole 3 Ea $7,000.00 $21,000.00
207 4 ' Extra Depth Manhole (Over 6') 8 VF $450.00 $3,600.00
208 1 1 Epoxy MH Liner-4' Sewer MH 10 VF $450.00 $4,500.00
209 4 " Sewer Service w/2 Way Cleanout I Ea $1,800.00 $1,800.00
212 Concrete Collar (MH) 2 Ea $600.00 $1,200.00
213 Manhole Vacuum Testing 3 Ea $250.00 $750.00
217 Post-CCTV Inspection 216 LF $10.00 $2,160.00
218 Trench Safety 216 LF $2.00 $432.00
219 Remove 4' Sewer Manhole 1 Ea $600.00 $600.00
221 Conc Pvmt Repair,Residential 11 SY $225.00 $2,475.00
222 Temporary Asphalt Paving Repair(2" HMAC on 6" 50 LF $30.00 $1,500.00
Flexbase
227 Topsoil 20 CY $26.00 $520.00
228 Block Sod Placement 90 SY $5.00 $450.00
232 Traffic Control 0.5 MO $6,000.00 $3,000.00
233 Imported Embedment/Backfill CSS 20 CY $75.00 $1,500.00
New Items
8 " Sewer Pipe PVC SDR-26 CL 160 (ASTM 2241) 216 LF 165 $35,640.00
Abandonment Plug 2 Ea $650.00 $1,300.00
Grouting 2 CY $1,500.00 $3,000.00
Hand Tunnel Retaining Wall 10 LF $450.00 $4,500.00
$89,927.00
To complete this work,we request 30 CD be added to the contract.
Respectfully,
Justin Blair
SDR-26 Class 160 pipe is available now with little to no lead time.
SDR-26 CL 160 Sewer Pipe Option
Item Description Quantity Units Unit Price Total Price
Existing Items
205 4 'Manhole 3 Ea $7,000.00 $21,000.00
207 4 'Extra Depth Manhole (Over 6') 8 VF $450.00 $3,600.00
208 Epoxy MH Liner-4' Sewer MH 12 VF $450.00 $5,400.00
209 4 " Sewer Service w/2 Way Cleanout 1 Ea $1,800.00 $1,800.00
212 Concrete Collar (MH) 2 Ea $600.00 $1,200.00
213 Manhole Vacuum Testing 3 Ea $250.00 $750.00
217 Post-CCTV Inspection 216 LF $10.00 $2,160.00
218 Trench Safety 216 LF $2.00 $432.00
219 Remove 4' Sewer Manhole 1 Ea $600.00 $600.00
220 1 Exploratory Excavation of Existing Utilities 1 Ea $1,500.00 $1,500.00
221 Cone Pvmt Repair,Residential 20 SY $225.00 $4,500.00
222 Temporary Asphalt Paving Repair 50 LF $30.00 $1,500.00
227 Topsoil 40 CY $26.00 $1,040.00
228 Block Sod Placement 90 SY $5.00 $450.00
232 Traffic Control 1 MO $6,000.00 $6,000.00
234 Imported Embedment/Backfill CLSM 35 CY $125.00 $4,375.00
New Items
8 " Sewer Pipe PVC SDR-26 CL 160 216 LF $170.00 $36,720.00
Abandonment Plug 2 Ea $650.00 $1,300.00
Grouting 6 CY $650.00 $3,900.00
Hand Tunnel Retaining Wall 10 LF $500.00 $5,000.00
Total $103,227.00
To complete this work,we request 30 CD be added to the contract. If DIP option is
selected additional time will need to be added to the contract, but that amount of time
cannot be determined until the pipe is delivered to the job site.
Respectfully,
Justin Blair
McCLENDON CONSTRUCTION CO., INC.
P.O. Box 999 Burleson, Texas 76097 (817) 295-0066 Fax (817) 295-6796
February 8, 2022
City of Fort Worth
Attn: Greg Robbins/Suby Varughese
Re: CPN 101475-2
2018 Bond Year 2—Contract 14
Suby,
Below are the 2 prices for the additional sewer work requested on Madeline Place. Most
of the work will be covered by existing contract items,but there are a few that will need
to be added.
NOTE: DIP pipe will be 4-6 lead time(possibly Ionizer) from the date the order is
confirmed and placed.
DIP Sewer Pipe Options
Item Description Quantity Units Unit Price Total Price
Existing Items
202 8 " DIP Sewer Pipe(with Protecto 401 Coating) 216 LF $195.00 $42,120.00
205 4 ' Manhole 3 Ea $7,000.00 $21,000.00
207 4 ' Extra Depth Manhole (Over 6') 8 VF $450.00 $3,600.00
208 Epoxy MH Liner-4' Sewer MH 12 VF $450.00 $5,400.00
209 14 " Sewer Service w/2 Way Cleanout 1 Ea $1,800.00 $1,800.00
212 Concrete Collar(MH) 2 Ea $600.00 $1,200.00
213 Manhole Vacuum Testing 3 Ea $250.00 $750.00
217 Post-CCTV Inspection 216 LF $10.00 $2,160.00
218 Trench Safety 216 LF $2.00 $432.00
219 Remove 4' Sewer Manhole 1 Ea $600.00 $600.00
220 Exploratory Excavation of Existing Utilities 1 Ea $1,500.00 $1,500.00
221 Conc Pvmt Repair,Residential 20 SY $225.00 $4,500.00
222 Temporary Asphalt Paving Repair 50 LF $30.00 $1,500.00
227 Topsoil 40 CY $26.00 $1,040.00
228 Block Sod Placement 90 SY $5.00 $450.00
232 Traffic Control 1 MO $6,000.00 $6,000.00
234 Imported Embedment/Backfill CLSM 35 CY $125.00 $4,375.00
New Items
Abandonment Plug 2 Ea $650.00 $1,300.00
Grouting 6 CY $650.00 $3,900.00
Hand Tunnel Retaining Wall 10 LF $500.00 $5,000.00
Total $108,627.00