HomeMy WebLinkAboutContract 52102-CO1 CSC No.52102-COl
Fc-'az_'1_ NAk�) -rn-i City of Fort Worth
Change Order Request
Project Name:1..Upper Big Fossil Creek Drainage Basin Parallel Relief Interceptor City Sec No.: 1 52102
ProjectNo.(s):1 66016 0700430 5740010 CO2515 DOE No. N/A CItyProj.No.:1 02515
Project Description: Construct Parallel Relief Interceptor in Upper Big Fossil Basin and Rehabilatate existing M-347 and M-386,
Contractor;1 William J.Schulz,Inc.dba Circle C Construction Co, Change Order Il C� Date: 1 1/21/2021
City Project M9r,1 Walter Norwood City Inspector: I David Johnson
Phone Number: (817)392-5026 Phone Number: (817)392-8455
—F
Dept. Water Sewer Totals Contract Time
Calenderdays)
Original Contract Amount $13,006,286.25 $13,006,286.25 456
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $13,006,286.25 $13,0062286.25 456
Amount of Proposed Change Order _ $0.00 i $0.00 180
Revised Contract Amount $13,006,286.25 $13,006,286.25 636
Original Funds Available for Change Orders $260,125.00 $260,126.00
Remaining Funds Available for this CO
Additional Funding(f necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00%
MAXALLOWABLECONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $16,257,857.81
JUSTIFICATION (REASONS)FOR CHANGE ORDER
Change Order No. 1 provides for:
• Additional sewer by other than open cut method in order to avoid potential damage to trees and houses in
the rear of lots close to Riverside Drive and a bridge crossing Riverside Drive,
• Conshield antimicrobial admixture to concrete manholes and junction structures in lieu of epoxy coating in
order to expedite construction of the project.
• The deletion of pay item quantities that are no longer needed on the project.
Staff recommends the addition of 180 calendar days to the project for the change order.
f
I
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order,
Contractor's Company Name Contractor Name Contractor Signature Dale
W IP1rJ Schua icc a!aOrciecConswcBon Co. Teti Skelly ;
Ins Odor Date Project Manager � Date
t -:�l
Direclur(Water Dept) Date Construction Supeivisor(Water Dept) Date
an 29,2021
Assistant City Allomey Date Assistant City Mianaer Dale
ebl,zozl Feb 2 2021
,e2+anr ;m, �cm
Council Action(If Required) OFFICIAL RECORD
M&C Number N/A M&C Dale Approved
CITY SECRETARY
FT. WORTH, TX
VyV, City of fort Worth
- --- Change Order Additions
Project Name Upper Big Fossil Creek Drainage Basin Parallel Relief Interceptor City Sec No.; 52102
Project No,(s): 56016 0700430 5740010 CO2515 DOE No. N A City Proj.No.; 02515
Project Description Construct Parallel Relief Interceptor in Upper Big Fossil Basin and Rehabilatate existing M-347 and M-386.
Contractor William J.Schulz,Inc.dba Circle C Construction Co, Change Order:= Date: 1/21/2021
City Project Mgr. Walter Norwood City Inspector David Johnson
Aooirioivs
DEPT Qt Unit Unit Cost Total
7 66"Casing By Ol er Than Open Cut Sewer 3. LF T900, 00 $245,700.00
8 48"Sewer Carrier Pipe Sewer 273.00 LF $250.00 $68,250.00
101 Conshield Antimicrobial in 5'Conshield Manhole Sewer 18.00 EA $1,800.00 $32,400.00
102 Conshleid Antimicrobial in 5'Extra Depth Conshield Manhole Sewer 223.00 VF $100.00 $22,300,00
103 Conshield Antimicrobial in 5'Tee Base Conshield Manhole Sewer 24.00 EA $4,000.00 $96,000.00
—TO-4— Conshield Antimicrobial in 5'Tee Base Drop Conshield Manhole Sewer 436.00 VF $50.00 $21,800.00
105 Conshield Antimicrobial in 5'Tee Base Extra Depth Conshield Manhole Sewer 4.00 EA $5,000,00 $20,000.00
106 Conshield Antimicrobial in 6'Manhole Sewer 1.00 EA $2,000.00 $2,000.00
107 Conshield Antimicrobial in 6'Extra Depth MH Sewer 8.00 VF $50.00 $400.00
108 Conshield Antimicrobial in Junction Structure#1 STA 0+96.55,SS LINE A) Sewer 1.00 EA $17,600.00 $17,600.00
109 Conshield Antimicrobial in Junction Structure#2(STA 3+97,77,SS LINE A) Sewer 1.00 EA $11,880.00 $11,880.00
110 Conshield Antimicrobial in Junction Structure 43(STA 1+15.00,LATERAL-1) Sewer 1.00 EA $7,920.00 $7,920.00
111 Conshield Antimicrobial in Junction Structure#4 STA 45+92,57,SS LINE A Sewer 1.00 EA $12,100.00 $12,100.00
112 Conshield Antimicrobial in Junction Structure#5(STA 1+13.74,LATERAL-3) Sewer 1.00 EA $8,360.00 $8,360.00
113 Conshield Antimicrobial in Junction Structure 46(STA 85+80.25,SS LINE A) Sewer 1.00 EA $14,520.00 $14,520.00
14 Conshield Antimicrobial in Junction Structure#7(STA 1+15.00,LATERAL4) Sewer 1.00 EA $13,420.00 $13,420.00
Water
Sewer $594.650.00
Page 1 of i Additions Sub Total $594,650.00
174:10R-F WOa-1'11-it City of Foils UV01-11
change Order Deletions
Project Name Upper Big Fossil Creek Drainage Basin Parallel Relief Interceptor City Sec No.: 52102
Project No.(s): 56016 0700430 5740010 CO2515 DOE No. N/A City Proj.No.: 02515
Project Description Consfnict Parallel Relief Interceptor in Upper Big Fossil Basin and Rehabilalate existing M-347 and M-386.
Contractor William J.Schulz,Inc.dba Circle C Construction Co. Change Order: ED Date 1/21/2021
City Project Mgr. Walter Norwood City Inspector; I David Johnson
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
777-40"Fiberglass Sewer Pipe,Select backfill, Sewer 273.00 LF $435.00 $118,755.00
45 Epoxy MH Liner(Warren Environmental) Sewer 843.00 VF $350.00 $309,050.00
49 Epoxy Structure Liner(Warren Environmental) Sewer 6975.00 VF $18.75 $130,781.25
85 Construction Allowance Sewer 0.18 LS $200,000.00$36,063,75
I
Water
Sewer $594,650.00
Page 1 of 1 Deletions Sub Total $594,650.00
_ MBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
Co## DATE AMOUNT
I
Total $0.00
E
Page 1 of 1
Contract Compliance Manager
BY signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
/0
Signature
NO/7'Lo-Y- Alypo&o
Name of Employee
Title
,d4UU��
ATTEST: oo�FORr��na
O00000000,00 a
r U� Cti°o �O�.Id
Mary J. Kayser 9 S
o
0
City Secretary , ° mod
T -ooa000- p
i
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
From: Black, Doug
To: Sholola.Tony
Cc: Soto.Vania Elizabeth; Norwood,Walter P;Sauceda. Norma
Subject: RE: Upper Big Fossil Creek Drainage Basin Parallel Relief Interceptor,CSC 52102(C01 and CO2)
Date: Tuesday, March 22,2022 4:31:35 PM
Ok to correct scrivener's errors.
DB
Douglas W Black
Senior Assistant City Attorney
200 Texas Street
Fort Worth,Texas 76102
817-392-7615 Direct
Dou .Black e,fortworthtexas.gov
City of Fort Worth Working together to build a strong community.
Fop.T WORTH.
RECIPIENTS -PLEASE CONTACT ME PRIOR TO FORWARDING MESSAGES
DESIGNATED AS ATTORNEY-CLIENT COMMUNICATIONS.
This e-mail and any files transmitted with it are confidential and are intended solely for the use of
the individual or entity to which they are addressed. This communication may contain material
protected by the attorney-client privilege. If you are not the intended recipient or the person
responsible for delivering the e-mail to the intended recipient,be advised that you have received this
e-mail in error and that any use,dissemination,forwarding,printing, or copying of this e-mail is
strictly prohibited. If you have received this e-mail in error,please immediately notify Doug Black at
the City of Fort Worth City Attorney's Office (817) 392-7615.
From: Sholola,Tony
Sent: Saturday, March 19, 2022 13:53
To: Black, Doug<Douglas.Black@fortworthtexas.gov>
Cc: Soto, Vania Elizabeth <Vania.Soto@fortworthtexas.gov>; Norwood, Walter P
<Walter.Norwood @fortworthtexas.gov>; Sauceda, Norma <Norma.Sauceda@fortworthtexas.gov>
Subject: Upper Big Fossil Creek Drainage Basin Parallel Relief Interceptor, CSC 52102 (C01 and CO2)
Doug:
For the subject project, please give Vania the okay to replace existing CO's 1 and 2 (first attachment)
with updated CO 1 and
CO 2 (second and third attachments).The deletion pages of the updated CO's have been revised to
show the item no for 48" Fiberglass Sewer Pipe, Select backfill as 5 instead of 4 that was
inadvertently listed.The deletions (from CO 1 and CO 2)were correctly made to item no. 5 and not
item no. 4 as shown on the fourth attachment.
Thanks