Loading...
HomeMy WebLinkAboutContract 53901-CO2 CSC No.53901-CO2 FORT WORTH. City of Fort Worth J Change Order Request Project Name 2020 Downtown Street Rehabilitation City Sec# 53901 Client Project#(s) 102103 Project Description Removal and replacement of non-compliant ADA Ramps,adjacent sidewalks and curb and gutter in downtown Fort Worth. Contractor C.C.Zamora Construction,Inc. Change Order# 2 Date 4/5/2022 City Project Mgr. Mary Hanna City Inspector Matt Cain Dept. TPW Contract Time Totals CD Original Contract Amount $941,945.00 $941,945.00 240 Extras to Date 51 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $941,945.00 $941,945.00 291 Amount of Proposed Change Order $0.00 236 Revised Contract Amount $941,945.00 $941,945.00 527 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,177,431.25 JUSTIFICATION(REASONS)FOR CHANGE ORDER The change order will provide a pay item for remobilization for the Contractor to replace the additional ramps along 7th St from Lamar to Florence.It will also add quantity for removing and replacing the inlet top at 7th St,and use Plowable fill(CLSM)to fill the void found under the sidewalk at the intersection of Cherry and Lamar St.This change order includes the repair cost for the underground basement that was found in the ROW at 411 W.7th St.Due to the additional scope and the conflict with the basement,the project experienced delays and staff approve the addition of 236 days to the contract time.Here's a breakdown of the delays: From 7/7/2021 to 9/5/2021:Time stopped to schedule the additional scope at Pecan and 2nd(60 days) From 9/17/2021 to 11/1/2021:Time stopped to schedule the additional work on 7th from Lamar St to Florence,including street permit and traffic control plans(45 days) From 11/1/2021 to 12/3/2021:Contractor moves back to work on the additional scope(32 days) From 12/4/2021 to 3/7/2022:No work performed,waiting on the City to resolve the issue with the basement on SEC 7th&Lamar St(93 days) From 3/8/2022 to 3/14/2022:Contractor work on the remaining ramps at 7th and Lamar(6 days) It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. IMEontractor's Company Namel Irontractor(NamM Contract Signature D CAB r C.C.Zamora Construction,Inc. Lupe Zamora -e 04/06/22 tar/Inspection Supervisor Date Project and Contract Compliance Manager Date M�ttClih 04/08/22 04/08/22 I I�-w 1z—»,osIoT, �.,, Program Manager Date Senior Capital Project Officer Date 04/08/22 04/08/22 744A-777Assistant Director(Dept) Date Director,Contracting Department(Dept) Date ee R-7ewi- 04/10/22 04/11/22 Assistant City Attorney Date JAssistant City Manager Date 04/11/22 04/11/22 Council Action(if required) M&C Number N/A M&C Date Approved ATTEST: �4anU4 Jannette Goodall,City Secretary Oo000 0.oao� 0 0��� 'o g�10 OFFICIAL RECORD o a*d CITY SECRETARY FT.WORTH, TX 0 Iy �o�oocoo° ,d ��nEXA5o4p FORTWORTH City of Fort Worth 1T� Change Order Additions Project Name 2020 Downtown Street Rehabilitation City Sec# 53901 Client Project# 102103 Contractor C.C.Zamora Construction,Inc. PM Mary Hanna Inspector Matt Cain Change Order Submittal# 0 Date 4/5/2022 ADDITIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total Remove and Replace inlet op 35 3305.0203 Imported Backfill,CLSM TPW 4.00000000 CY 215.00 36 Basement Repair @ 411 W 7th TPW 1.00000000 LS $5,320.05 37 Remobilization TPW 1.00000000 LS f4 57200 TPW S14,902.00 Sub Total Additions S14.902.00 Change Order Additions Page 2 of4 FORT 1 City of Fort Worth Change Order Deletions Project Name 2020 Downtown Street Rehabilitation City Sec# 53901 Client Project# 102103 Contractor C.C.Zamora Construction,Inc. PM Mary Hanna Inspector Matt Cain Change Order Submittal# 0 Date 4/5/2022 DELL I IUNS y Unit UnitCost o a zo onstruction owance TPW $14,902.00 Sub lotalDeletions Change Order Deletions Page 3 of 4 M/SBE for this Change Order M/SBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders co# DATE AMOUNT Total $0.00