HomeMy WebLinkAboutContract 55913-FP1 City Secretary 55913 -FP1
Contract No.
FORTWORTH. Date Received Apr 13, 2022
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Primrose Crossing Phase 6
City Project No.: 102851
Improvement Type(s): Water ❑x Sewer ❑x
Original Contract Price: $413,555.00
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Corrplete: $413,555.00
Jay Arne ll prs,202211:03 CDT) Apr 8,2022
Contractor Date
Project manager
Title
Conatser Construction Tx Lp
Company Name
Aaron Ybarra(Apr ,202212:59 CDT) A Y 8 2022
Project Inspector Date
C'J"A P. Apr 12,2022
Project Manager Date
CL� Apr 12,2022
J e Scarlett Morales(ADr 12.2022 14:27 CDT)
CFA Manager Date
awa
Dana Dana Bur�12,2�7:42 CDT) Apr 12,2022
Asst. City Manager Date
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH, TX Page 1 of 2
Notice of Project Completion
Project Name: Primrose Crossing Phase 6
City Project No.: 102851
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Pipe Report: ❑x Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 100 WD Days Charged: 137
Work Start Date: 7/23/2021 Work Complete Date: 4/5/2022
Completed number of Soil Lab Test: 235
Completed number of Water Test: 17
Page 2 of 2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name PRIMROSE CROSSING PHASE 6
Contract Limits
Project Type WATER&SEWER
City Project Numbers 102851
DOE Number 2851
Estimate Number 1 Payment Number 1 For Period Ending 4/5/2022
WD
City Secretary Contract Number Contract Time 109M
Contract Date 1/20/2021 Days Charged to Date 137
Project Manager NA
Contract is 100.00 Complete
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors OWEN,M / YBARRA,A
Friday,April 8,2022 Page 1 of 4
City Project Numbers 102851 DOE Number 2851
Contract Name PRIMROSE CROSSING PHASE 6 Estimate Number I
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 4/5/2022
Project Funding
UNIT L•WATER IMPROVEMENTS
Item Estimated Estimated Completed Completed
Description of Items Unit Unit Cost
No. Quanity Total Quanity Total
---------------------------------------
1 DUCTILE IRON WATER FITTINGS W/RES 0.96 TN $4,500.00 $4,320.00 0.96 $4,320.00
2 8"WATER PIPE 3130 LF $35.00 W9,550.00 3130 $109,550.00
3 FIRE HYDRANT 6 EA $4,250.00 $25,500.00 6 $25,500.00
4 CONNECTION TO EXISTING 4"-12"WATER 3 EA $1,000.00 $3,000.00 3 $3,000.00
MAIN
5 1"WATER SERVICE 107 EA $950.00 W1,650.00 107 $101,650.00
6 8"GATE VALVE 8 EA $1,300.00 $10,400.00 8 $10,400.00
7 3/4 IRRIGATION SERVICE 3 EA $1,500.00 $4,500.00 3 $4,500.00
Sub-Total of Previous Unit $258,920.00 $258,920.00
UNIT H:SANITARY SEWER IMPROVEMENTS
Item Estimated Estimated Completed Completed
Description of Items Unit Unit Cost
No. Quanity Total Quanity Total
---------------------------------------
1 POST-CCTV INSPECTION 1598 LF $3.00 $4,794.00 1598 $4,794.00
2 MANHOLE VACUUM TESTING 6 EA $150.00 $900.00 6 $900.00
3 MANHOLE ADJUSTMENT MINOR 7 EA $1,000.00 $7,000.00 7 $7,000.00
4 TRENCH SAFETY 1598 LF $1.00 $1,598.00 1598 $1,598.00
5 4"SEWER SERVICE 53 EA $650.00 $34,450.00 53 $34,450.00
6 8"SEWER PIPE SDR 26 1518 LF $42.00 $63,756.00 1518 $63,756.00
7 8"SEWR PIPE CSS BACKFILL 80 LF $52.00 $4,160.00 80 $4,160.00
8 EPDXY MANHOLE LINER 22.1 VF $385.00 $8,508.50 22.1 $8,508.50
9 4'MANHOLE 6 EA $4,000.00 $24,000.00 6 $24,000.00
10 4'EXTRA DEPTH MANHOLE 10.1 VF $185.00 $1,868.50 10.1 $1,868.50
11 CONNECT TO EXISTING LINE 3 EA $1,200.00 $3,600.00 3 $3,600.00
Sub-Total of Previous Unit $154,635.00 $154,635.00
Friday,April 8,2022 Page 2 of 4
City Project Numbers 102851 DOE Number 2851
Contract Name PRIMROSE CROSSING PHASE 6 Estimate Number I
Contract Limits Payment Number 1
Project Type WATER SEWER For Period Ending 4/5/2022
Project Funding
Contract Information Summary
Original Contract Amount $413,555.00
Change Orders
Total Contract Price $413,555.00
Total Cost of Work Completed $413,555.00
Less %Retained $0.00
Net Earned $413,555.00
Earned This Period $413,555.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $413,555.00
Friday,April 8,2022 Page 3 of 4
City Project Numbers 102851 DOE Number 2851
Contract Name PRIMROSE CROSSING PHASE 6 Estimate Number I
Contract Limits Payment Number 1
Project Type WATER SEWER For Period Ending 4/5/2022
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors OWEN,M / YBARRA,A Contract Date 1/20/2021
Contractor CONATSER CONSTRUCTION TxLP Contract Time 100 WD
5327 WICHITA ST Days Charged to Date 137 WD
FORT WORTH, TX 76119 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $413,555.00
Less %Retained $0.00
Net Earned $413,555.00
Earned This Period $413,555.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $413,555.00
Friday,April 8,2022 Page 4 of 4
FORTWORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME: Primrose Crossing Phase 6
PROJECT NUMBER: CPN 102851
DOE NUMBER:
WATER
PIPE LAID SIZE TYPE OF PIPE LF
Open cut 8" SDR-26 PVC 3130
FIRE HYDRANTS: 6 VALVES(16"OR LARGER) N/A
PIPE ABANDONED SIZE TYPE OF PIPE LF
N/A
DENSITIES: Taken-Passed
NEW SERVICES: 1" DOM Copper 2,070
3/4" IRR Copper 18
SEWER
PIPE LAID SIZE TYPE OF PIPE LF
Open Cut 8" C-900 DR-14 Class 200 1,598
PIPE ABANDONED SIZE TYPE OF PIPE LF
N/A
DENSITIES: Taken-Passed
NEW SERVICES: 4" PVC 590
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth• 1000 Throckmorton Street•Fort Worth,TX 76012-6311
(817)392-7941 •Fax: (817)392-7845
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
April 5, 2022
Conatser Construction TX,LP
5327 Wichita St
Ft. Worth Tx,76119
RE: Acceptance Letter
Project Name: Primrose Crossing Phase 6
Project Type: Sewer, Water, Storm Drain, Paving and Street Light Improvements
City Project No.: 102851
To Whom It May Concern:
On March 25, 2022 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on April 5, 2022. The final inspection and
the corrected punch list items indicate that the work meets the City of Fort Worth specifications and is
therefore accepted by the City. The warranty period will start on April 5, 2022, which is the date of the
punch list completion and will extend of two (2)years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
223-6251.
Sincerely,
Andrew Goodman P.E., Project Manager
Cc:Aaron Ybarra, Inspector
Mark Owen, Inspection Supervisor
Edwin R. Rodriguez, Sr., Senior Inspector
Yogesh Patel, P.E, Program Manager
LJA Engineering. INC, Consultant
Conatser Construction TX, LP, Contractor
Lennar Homes of Texas Land and Construction, LTD, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev.8/20/19
AMDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me,the undersigned authority,a Notary Public in the state and county aferoWd,
on this day personally appeared Brock Huggins,President of Conateet'MarAgemem Group,Inc.,
general partner of Conn=Construction TX.LP,known to me to be a credible pawn.who
being by me duly sworn,upon his oath deposed and said:
That all pemim,firms, associatiions,corporations or other organizations furnishing
labor and/or materials have bean paid in full;
That the wage scale established by she City Council in the Oly of Foil Worth, has
k-en;mid in full;Unti
That thcrc are no claims pending for personal injury uadior property damages,
On Contract described as:
PRIMROSE CROSSING PH.6
WATFR,SANITARV SEWER,STORM DRAIN,
PAVING,STREET SIGN A STREET LIGHT IMPROVEMENTS
DOE#: N/A
CPA PRJ#: 20.0127
CITY PROJECT#:I02851
CITY OF FORT WORTH
STATE OF TEXAS
CONATSER CONSTRUCTION TX,LP
A"-
Brock Ifuggi
Subscribed and sworn to before me this 25..day of March,202.2. {D7u
v Notary Public in Tarrant County.Texas
cai.n °�uapao�
CONSENT OF OWNER ❑
SURETY COMPANY ARCHITECT ❑
CONTRACTOR ❑
TO FINAL PAYMENT SURETY ❑
Corfarms with the A—noan tnrdnrte o-1 OTHER
Af&k0m,ArA oocumont 0707
Band No 0235125
PROJECT
{name,address)PrimroaeGroaainpPrusa6
Fprl VJprlh,TX
TO{Ownerl
CFFY OF FORT WORTH AND LEW041HpM Es OF ARCHrTECT'S PROJECT NO:CFA2"127
TEXAS LAND AND CONSTRLrGTiON,LTD. CONTRACT FOR:
I TP7 Marhe>aace$hd,5Dyt 100 YVlxr.Senrtary Sewer,Orah ge.Pang a SD Lght.0 tar
PrYant114[.rpylry Phow 0
L^Ina Tx 1508'° .J CONTRACT DATE:
CONTRACTQR;CONATSER CONSTRUCTION TX,L P
In eceardaF=with the provision of the Contract betwom tlx Owner and the Contractor sa indicated above,the
Ihw"-rem.Na sd*—et t-. Cee 0
BERXLEY INSURANCE COMPANY
475 Slewmbail Row
Greernw'�h CT 068M .SURETY COMPANY
on bond of 0.N:e.n..m...a.er...0 Cae.,dn.l
C ONATSER CONSTRUCTI ON TX.L P
5327 Nhchita S:
Fo't VW!h TX 761IM03,5 ,CONTRACTOR,
hrreby approves of the final payme j to Lhe Cormwtof,and agrees thu foul payment to the Contractor shell nW relieve
the Surety Company of any of ins obi ipLions to n.....r,.w,.....m. —&o—
C ITV OF FORT WORT.H ANp LENNAR HOMES OF TEXAS LAND AND CC NSTR LICTION LTD
1707 Mat1<e0h"DIvo Sute iOO
Irony TX 7SM3 .OWNER,
as IN forth in the said Surety Company's bond.
IN WITNESS,WHEREOF,
the Surety Compamy has beseunito set its hand this xsth day of MAWM.2C22
BERKLEY INSURANCE COMPANY
Surety Company
(Seal)� Signature of Authorized Rapresemamve
Remo Morales _ Anxnei-in,Fact
Title
NOTE iti Mm.w:P a IM"R!•—{�6—*to M DOCUMIN'T 12706,COKMk T9P'S AFFIDAVIT of PAYMENT 9F DERn AND CLAMS,
C1 EdDm
ONE PAGE