Developer and Project Information Cover Sheet:
Developer Company Name: 170 Northstar Ranch Developer,Inc.
Address, State,Zip Code: 3075 Lackland Road,Fort Worth,TX 76116
Phone &Email: 817-717-7136,kgill@sableholdings.com
Authorized Signatory,Title: Kimberly Gill,Assistant Vice President
Project Name: Northstar-Section 4 Phase 3
Brief Description: Water, Sewer,Paving, Storm Drain and Street Lighting
Project Location: Mapsco 5—E,F
Plat Case Number: PP-17-025 Plat Name: Northstar Section 4,Phase 2
Mapsco: 5—E,F Council District: 7
CFA Number: CFA22-0037 City Project Number: 103495
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
City of Fort Worth,Texas Page 1 of 16
Standard Community Facilities Agreement
Rev.9/21
City Contract Number: 57401
STANDARD COMMUNITY FACILITIES AGREEMENT
This COMMUNITY FACILITIES AGREEMENT("Agreement") is made and entered into by
and between the City of Fort Worth ("City"), a home-rule municipal corporation of the State of Texas,
acting by and through its duly authorized Assistant City Manager,and 170 Northstar Ranch Developer,
Inc. ("Developer"), acting by and through its duly authorized representative. City and Developer are
referred to herein individually as a"party"and collectively as the "parties."
WHEREAS, Developer is constructing private improvements or subdividing land within the
corporate limits of Fort Worth, Texas or its extraterritorial jurisdiction, for a project known as Northstar
Section 4,Phase 3("Project");and
WHEREAS, the City desires to ensure that all developments are adequately served by public
infrastructure and that the public infrastructure is constructed according to City standards; and
WHEREAS, as a condition of approval of the Project, Developer is required to bear a portion of
the costs of municipal infrastructure by constructing the public infrastructure necessary for the Project as
described in this Agreement("Community Facilities"or"Improvements"); and
WHEREAS,as a condition of approval of the Project,Developer is required to meet the additional
obligations contained in this Agreement,and Developer may be required to make dedications of land,pay
fees or construction costs,or meet other obligations that are not a part of this Agreement; and
WHEREAS,the City is not participating in the cost of the Improvements or Project;and
WHEREAS, the Developer and the City desire to enter into this Agreement in connection with
the collective Improvements for the Project;
NOW,THEREFORE,for and in consideration of the covenants and conditions contained herein,
the City and the Developer do hereby agree as follows:
1.
CFA Ordinance
The Community Facilities Agreements Ordinance("CFA Ordinance"),as amended,is incorporated
into this Agreement by reference, as if it was fully set out herein. Developer agrees to comply with all
provisions of the CFA Ordinance in the performance of Developer's duties and obligations pursuant to this
Agreement and to cause all contractors hired by Developer to comply with the CFA Ordinance in
connection with the work performed by the contractors. If a conflict exists between the terms and conditions
of this Agreement and the CFA Ordinance,the CFA Ordinance shall control.
City of Fort Worth,Texas Page 2 of 16
Standard Community Facilities Agreement
Rev.9/21
2.
Incorporation of Engineering Plans
The engineering plans for the Improvements that have been approved by the City ("Engineering
Plans")are incorporated into this Agreement by reference as if fully set out herein. Developer shall provide
at its expense, unless otherwise agreed to by City, all engineering drawings and documents necessary to
construct the Improvements required by this Agreement.
3.
Description of Improvements; Exhibits and Attachments
The following exhibits describe the general location, nature and extent of the Improvements that
are the subject of this Agreement and are attached hereto and incorporated herein by reference:
❑X Exhibit A: Water
❑X Exhibit A-1: Sewer
❑X Exhibit B: Paving
❑X Exhibit B-1: Storm Drain
❑X Exhibit C: Street Lights & Signs
The Location Map and Cost Estimates are also attached hereto and incorporated herein by
reference. To the extent that Exhibits A, A-1, B, B-1, C, the Location Map, or the Cost Estimates
conflict with the Engineering Plans, the Engineering Plans shall control. If applicable,Attachment I —
Changes to Standard Community Facilities Agreement, Attachment 2 — Phased CFA Provisions, and
Attachment 3 — Concurrent CFA Provisions, are attached hereto and incorporated herein for all
purposes.
4.
Construction of Improvements
Developer agrees to cause the construction of the Improvements contemplated by this Agreement
and that said construction shall be completed in a good and workmanlike manner and in accordance with
all City standards and specifications, the Engineering Plans, the Cost Estimates provided for the
Improvements,and this Agreement. Developer acknowledges that City will not accept the Improvements
until the City receives affidavits and lien releases signed by Developer's contractors verifying that the
contractors, and all subcontractors and material suppliers, have been paid in full for constructing the
Improvements, and consent of the surety on payment and performance bonds provided for the
Improvements.
5.
Financial Guarantee
Developer has provided the City with a financial guarantee in the form and amounts set forth in
this Agreement which guarantees the construction of the Improvements and payment by Developer of
all contractors, subcontractors, and material suppliers for the Improvements ("Financial Guarantee").
Developer shall keep the Financial Guarantee in full force and effect until released by the City and shall
not reduce the amount of the Financial Guarantee unless authorized by the City in accordance with the
CFA Ordinance.
City of Fort Worth,Texas Page 3 of 16
Standard Community Facilities Agreement
Rev.9/21
6.
Completion Deadline; Extension Periods
This Agreement shall be effective on the date this Agreement is executed by the City's Assistant
City Manager ("Effective Date"). Developer shall complete construction of the Improvements and
obtain the City's acceptance of the Improvements within two (2) years of the Effective Date ("Term").
If construction of the Improvements has started during the Term, the Developer may request that this
Agreement be extended for an additional period of time ("Extension Period"). All Extension Periods shall
be agreed to in writing by the City and the Developer as set forth in a written amendment to this Agreement.
In no event shall the Term of this Agreement plus any Extension Periods be for more than three years.
7.
Failure to Construct the Improvements
(a) The City may utilize the Developer's Financial Guarantee to cause the completion of the
construction of the Improvements if at the end of the Term, and any Extension Periods, the
Improvements have not been completed and accepted by the City.
(b) The City may utilize the Developer's Financial Guarantee to cause the completion of the
construction of the Improvements or to cause the payment of costs for construction of the
Improvements before the expiration of the Term, and any Extension Period, if the Developer
breaches this Agreement,becomes insolvent,or fails to pay costs of construction.
(c) If the Financial Guarantee is a Completion Agreement and the Developer's contractors or suppliers
are not paid for construction costs or materials supplied for the Improvements the contractors and
suppliers may place a lien upon any property which the City does not have an ownership interest
that is the subject of the Completion Agreement.
(d) Nothing contained herein is intended to limit the Developer's obligations under the CFA
Ordinance, this Agreement, the Financial Guarantee, Developer's agreements with Developer's
contractors,or other related agreements.
8.
Termination
If Developer desires to terminate this Agreement before Developer's contractors begin
constructing the Improvements, Developer agrees to the following:
(a) that Developer and City must execute a termination of this Agreement in writing;
(b) that Developer will vacate any final plats that have been filed with the county where the Project
is located; and
(c) to pay to the City all costs incurred by the City in connection with this Agreement, including
time spent by the City's inspectors at preconstruction meetings.
9.
Award of Construction Contracts
City of Fort Worth,Texas Page 4 of 16
Standard Community Facilities Agreement
Rev.9/21
(a) Developer will award all contracts for the construction of the Improvements and cause the
Improvements to be constructed in accordance with the CFA Ordinance.
(b) Developer will employ construction contractors who meet the requirements of the City to construct
the Improvements including,but not limited,to being prequalified,insured,licensed and bonded to
construct the Improvements in the City.
(c) Developer will require Developer's contractors to provide the City with payment and performance
bonds naming the City and the Developer as dual obligees, in the amount of one hundred percent
(100%) of the cost of the Improvements as required by the CFA Ordinance. The payment and
performance bonds shall guarantee construction of the Improvements and payment of all
subcontractors and material suppliers. Developer agrees to require Developer's contractors to
provide the City with a maintenance bond naming the City as an obligee, in the amount of one
hundred percent(100%) of the cost of the Improvements, that guarantees correction of defects in
materials and workmanship for the Improvements by the contractor and surety for a period of two
(2)years after completion and final acceptance of the Improvements by the City. All bonds must
be provided to the City before construction begins and must meet the requirements of the City's
Standard Conditions,Chapter 2253 of the Texas Government Code,and the Texas Insurance Code.
(d) Developer will require Developer's contractors to provide the City with insurance equal to or in
excess of the amounts required by the City's standard specifications and contract documents for
developer-awarded infrastructure construction contracts. The City must be named as an additional
insured on all insurance policies. The Developer must provide the City with a Certificate of
Insurance (ACORD or form approved by the State of Texas), supplied by each contractor's
insurance provider,which shall be made a part of the Project Manual.
(e) Developer will require the Developer's contractors to give forty-eight(48)hours' advance notice
of their intent to commence construction of the Improvements to the City's Construction Services
Division so that City inspection personnel will be available. Developer will require Developer's
contractors to allow construction of the Improvements to be subject to inspection at any and all
times by the City's inspectors. Developer will require Developer's contractors to not install or
relocate any sanitary sewer, storm drain,or water pipe unless a City inspector is present and gives
consent to proceed, and to allow such laboratory tests as may be required by the City.
(f) Developer will not allow Developer's contractors to begin construction of the Improvements until
a notice to proceed to construction is issued by the City.
(g) Developer will not allow Developer's contractors to connect buildings to service lines of sewer and
water mains constructed pursuant to this Agreement, if any, until said sewer, water mains and
service lines have been completed to the satisfaction of the City.
10.
Utilities
Developer shall cause the installation or adjustment of utilities required to: (1) serve the Project;
and (2) to construct the Improvements required herein. City shall not be responsible for payment of any
costs that may be incurred by Developer in the relocation of any utilities that are or may be in conflict with
any of the Improvements to be constructed pursuant to this Agreement.
City of Fort Worth,Texas Page 5 of 16
Standard Community Facilities Agreement
Rev.9/21
11.
Easements and Rights-of-Way
Developer agrees to provide,at its expense,all necessary rights-of-way and easements required for
the construction and dedication to the City of the Improvements provided for by this Agreement.
12.
Liability and Indemnification
(a) DEVELOPER HEREBY RELEASES AND AGREES TO INDEMNIFY, DEFEND AND
HOLD THE CITY HARMLESS FOR ANY INADEQUACIES IN THE PRELIMINARY
PLANS, SPECIFICATIONS, ENGINEERING PLANS, AND COST ESTIMATES
SUPPLIED BY THE DEVELOPER FOR THIS AGREEMENT.
(b) THE DEVELOPER COVENANTS AND AGREES TO,AND BY THESE PRESENTS DOES
HEREBY FULLY INDEMNIFY, HOLD HARMLESS AND DEFEND THE CITY, ITS
OFFICERS,AGENTS AND EMPLOYEES FROM ALL SUITS,ACTIONS OR CLAIMS OF
ANY CHARACTER, WHETHER REAL OR ASSERTED,BROUGHT FOR OR ONACCOUNT
OFANYINJURIES OR DAMAGES SUSTAINED B YANY PERSONS,INCL UDING DEATH,
OR TO ANY PROPERTY, RESULTING FROM OR IN CONNECTION WITH THE
CONSTRUCTION,DESIGN, PERFORMANCE OR COMPLETION OF ANY WORK TO BE
PERFORMED BY SAID DEVELOPER, ITS CONTRACTORS, SUBCONTRACTORS,
OFFICERS, AGENTS OR EMPLOYEES, OR IN CONSEQUENCE OF ANY FAILURE TO
PROPERL Y SAFEGUARD THE WORK, OR ON ACCOUNT OF ANY ACT,INTENTIONAL
OR OTHERWISE, NEGLECT OR MISCONDUCT OF SAID DEVELOPER, ITS
CONTRACTORS, SUB-CONTRACTORS, OFFICERS, AGENTS OR EMPLOYEES,
WHETHER OR NOT SUCHINJURIES,DEATH OR DAMAGESARE CAUSED,IN WHOLE
OR IN PART, BY THE ALLEGED NEGLIGENCE OF THE CITY OF FORT WORTH, ITS
OFFICERS,SERVANTS, OR EMPLOYEES.
(c) DEVELOPER WILL REQUIRE ITS CONTRACTORS TO INDEMNIFY, DEFEND AND
HOLD HARMLESS THE CITY, ITS OFFICERS, AGENTS AND EMPLOYEES FROM
AND AGAINST ANY AND ALL CLAIMS, SUITS OR CAUSES OF ACTION OF ANY
NATURE WHATSOEVER, WHETHER REAL OR ASSERTED, BROUGHT FOR OR ON
ACCOUNT OF ANY INJURIES OR DAMAGES TO PERSONS OR PROPERTY,
INCLUDING DEATH,RESULTING FROM, OR INANY WAY CONNECTED WITH, THE
CONSTRUCTION OF THE IMPROVEMENTS CONTEMPLATED HEREIN, WHETHER
OR NOT SUCH INJURIES, DEATH OR DAMAGES ARE CAUSED, IN WHOLE OR IN
PART, BY THE ALLEGED NEGLIGENCE OF THE CITY OF FORT WORTH, ITS
OFFICERS, SERVANTS, OR EMPLOYEES. FURTHER, DEVELOPER WILL REQUIRE
ITS CONTRACTORS TO INDEMNIFY, DEFEND, AND HOLD HARMLESS THE CITY
FOR ANY LOSSES, DAMAGES, COSTS OR EXPENSES SUFFERED BY THE CITY OR
CAUSED AS A RESULT OF SAID CONTRACTORS' FAILURE TO COMPLETE THE
WORK AND CONSTRUCT THE IMPROVEMENTS IN A GOOD AND WORKMANLIKE
MANNER, FREE FROM DEFECTS,IN CONFORMANCE WITH THE CFA ORDINANCE,
AND INACCORDANCE WITH ALL PLANS AND SPECIFICATIONS.
13.
Right to Enforce Contracts
City of Fort Worth,Texas Page 6 of 16
Standard Community Facilities Agreement
Rev.9/21
Upon completion of all work associated with the construction of the Improvements,Developer will
assign to the City a non-exclusive right to enforce the contracts entered into by Developer with its
contractors,along with an assignment of all warranties given by the contractors,whether express or implied.
Further,Developer agrees that all contracts with any contractor shall include provisions granting to the City
the right to enforce such contracts as an express intended third party beneficiary of such contracts.
14.
Estimated Fees Paid by Developer; Reconciliation
Prior to execution of this Agreement, Developer has paid to the City the estimated cost of
administrative material testing service fees, construction inspection service fees,and water testing lab fees
in the amounts set forth in the Cost Summary section of this Agreement. Upon completion of the
construction of the Improvements, the City will reconcile the actual cost of administrative material testing
service fees, construction inspection service fees, and water testing lab fees with the estimated fees paid
by Developer. If the actual costs of the fees are more than the estimated payments made by the Developer,
the Developer must pay the difference to the City before the Improvements will be accepted by the City. If
the actual costs of the fees are less than the estimated payments made by the Developer,the City will refund
the difference to the Developer.If the difference between the actual costs and the estimated payments made
by the Developer is less than fifty dollars($50.00),the City will not issue a refund and the Developer will
not be responsible for paying the difference. The financial guarantee will not be released by the City or
returned to the Developer until reconciliation has been completed by the City and any fees owed to the City
have been paid by the Developer.
15.
Material Testing
The City maintains a list of pre-approved material testing laboratories. The Developer must
contract with material testing laboratories on the City's list. Material testing laboratories will provide copies
of all test results directly to the City and the Developer. If the Improvements being constructed fail a test,
the Developer must correct or replace the Improvements until the Improvements pass all retests. The
Developer must pay the material testing laboratories directly for all material testing and retesting.The City
will obtain proof from the material testing laboratories that the material testing laboratories have been
paid in full by the Developer before the City will accept the Improvements.
16.
Notices
All notices required or permitted under this Agreement may be given to a party by hand-
delivery or by mail, addressed to such party at the address stated below. Any notice so given shall be
deemed to have been received when deposited in the United States mail so addressed with postage
prepaid:
CITY: DEVELOPER:
Development Coordination Office 170 Northstar Ranch Developer, Inc.
City of Fort Worth 3045 Lackland Road
200 Texas Street Fort Worth, TX 76116
Fort Worth, Texas 76102
City of Fort Worth,Texas Page 7 of 16
Standard Community Facilities Agreement
Rev.9/21
With copies to:
City Attorney's Office
City of Fort Worth
200 Texas Street
Fort Worth, Texas 76102
and
City Manager's Office
City of Fort Worth
200 Texas Street
Fort Worth, Texas 76102
Or to such other address one party may hereafter designate by notice in writing addressed and
mailed or delivered to the other party hereto.
17.
Right to Audit
Developer agrees that, until the expiration of three (3) years after acceptance by the City of the
Improvements constructed pursuant to this Agreement, that the City shall have access to and the right to
examine any directly pertinent books, documents, papers and records of the Developer involving
transactions relating to this Agreement. Developer agrees that the City shall have access during normal
working hours to all necessary Developer facilities and shall be provided adequate and appropriate
workspace in order to conduct audits in compliance with the provisions of this section. The City shall give
Developer reasonable advance notice of intended audits.
Developer further agrees to include in all contracts with Developer's contractors for the
Improvements a provision to the effect that the contractor agrees that the City shall,until the expiration of
three (3)years after final payment under the contract,have access to and the right to examine any directly
pertinent books, documents,papers and records of such contractor, involving transactions to the contract,
and further,that City shall have access during normal working hours to all of the contractor's facilities,and
shall be provided adequate and appropriate work space in order to conduct audits in compliance with the
provisions of this section. City shall give Developer's contractors reasonable advance notice of intended
audits.
18.
Independent Contractor
It is expressly understood and agreed that Developer and its employees, representative, agents,
servants,officers,contractors,subcontractors,and volunteers shall operate as independent contractors as to
all rights and privileges and work performed under this Agreement, and not as agents, representatives or
employees of the City. Subject to and in accordance with the conditions and provisions of this Agreement,
Developer shall have the exclusive right to control the details of its operations and activities and be solely
responsible for the acts and omissions of its employees, representatives, agents, servants, officers,
contractors, subcontractors, and volunteers. Developer acknowledges that the doctrine of respondeat
superior shall not apply as between the City and its officers, representatives, agents, servants and
employees, and Developer and its employees, representatives, agents, servants, officers, contractors,
City of Fort Worth,Texas Page 8 of 16
Standard Community Facilities Agreement
Rev.9/21
subcontractors, and volunteers. Developer further agrees that nothing herein shall be construed as the
creation of a partnership or joint enterprise between City and Developer. It is further understood that the
City shall in no way be considered a co-employer or a joint employer of Developer or any employees,
representatives, agents, servants, officers, contractors, subcontractors, and volunteers of Developer.
Neither Developer,nor any officers,agents, servants,employees or subcontractors of Developer shall be
entitled to any employment benefits from the City. Developer shall be responsible and liable for any and
all payment and reporting of taxes on behalf of itself, and any of employees, representatives, agents,
servants,officers,contractors, subcontractors,and volunteers.
The City,through its authorized representatives and employees, shall have the sole and exclusive
right to exercise jurisdiction and control over City employees.
19.
Applicable Law; Venue
This Agreement shall be construed under and in accordance with Texas law. Venue shall be in
the state courts located in Tarrant County, Texas or the United States District Court for the Northern
District of Texas,Fort Worth Division.
20.
Non-Waiver
The failure of the City to insist upon the performance of any term or provision of this Agreement
or to exercise any right herein conferred shall not be construed as a waiver or relinquishment to any extent
of City's right to assert or rely on any such term or right on any future occasion.
21.
Governmental Powers and Immunities.
It is understood that by execution of this Agreement, the City does not waive or surrender
any of its governmental powers or immunities.
22.
Headings
The paragraph headings contained herein are for the convenience in reference and are not intended
to define or limit the scope of any provision of this Agreement.
23.
Severability
In the event that any clause or provision of this Agreement shall be held to be invalid by any
court of competent jurisdiction, the invalidity of such clause or provision shall not affect any of the
remaining provisions hereof.
24.
Review of Counsel
City and Developer, and if they so choose,their attorneys, have had the opportunity to review
City of Fort Worth,Texas Page 9 of 16
Standard Community Facilities Agreement
Rev.9/21
and comment on this document;therefore any rule of contract construction or interpretation that would
normally call for the document to be interpreted as against the drafting party shall not apply in
interpretation of this Agreement, and each section, portion, and provision of this Agreement shall be
construed solely on the basis of the language contained therein, regardless of who authored such
language.
25.
Prohibition on Boycotting Israel
Developer acknowledges that in accordance with Chapter 2271 of the Texas Government Code,
the City is prohibited from entering into a contract with a company with 10 or more full-time employees
that has a value of$100,000 or more that is to be paid wholly or partly from public funds of the City for
goods or services unless the contract contains a written verification from the company that it: (1)does not
boycott Israel; and (2) will not boycott Israel during the term of the contract. The terms "boycott Israel"
and"company"have the meanings ascribed to those terms by Chapter 2271 of the Texas Government Code.
To the extent that Chapter 2271 of the Government Code is applicable to this Agreement,by signing this
Agreement, Developer certifies that Developer's signature provides written verification to the City that
Developer: (1)does not boycott Israel; and(2)will not boycott Israel during the term of this Agreement.
26.
Prohibition on Boycotting Energy Companies
Developer acknowledges that in accordance with Chapter 2274 of the Texas Government Code,as
added by Acts 2021, 87th Leg., R.S., S.B. 13, § 2,the City is prohibited from entering into a contract for
goods or services that has a value of$100,000 or more that is to be paid wholly or partly from public funds
of the City with a company with 10 or more full-time employees unless the contract contains a written
verification from the company that it: (1) does not boycott energy companies; and (2) will not boycott
energy companies during the term of the contract. The terms "boycott energy company" and "company"
have the meanings ascribed to those terms by Chapter 2274 of the Texas Government Code, as added by
Acts 2021, 87th Leg., R.S., S.B. 13, § 2. To the extent that Chapter 2274 of the Government Code is
applicable to this Agreement, by signing this Agreement, Developer certifies that Developer's signature
provides written verification to the City that Developer: (1) does not boycott energy companies; and (2)
will not boycott energy companies during the term of this Agreement.
27.
Prohibition on Discrimination Against Firearm and Ammunition Industries
Developer acknowledges that except as otherwise provided by Chapter 2274 of the Texas
Government Code,as added by Acts 2021,87th Leg.,R.S.,S.B. 19, § 1,the City is prohibited from entering
into a contract for goods or services that has a value of$100,000 or more that is to be paid wholly or partly
from public funds of the City with a company with 10 or more full-time employees unless the contract
contains a written verification from the company that it: (1) does not have a practice,policy, guidance, or
directive that discriminates against a firearm entity or firearm trade association;and(2)will not discriminate
during the term of the contract against a firearm entity or firearm trade association. The terms
"discriminate," "firearm entity" and "firearm trade association" have the meaning ascribed to those terms
by Chapter 2274 of the Texas Government Code,as added by Acts 2021, 87th Leg.,R.S., S.B. 19, § 1. To
the extent that Chapter 2274 of the Government Code is applicable to this Agreement, by signing this
Agreement, Developer certifies that Developer's signature provides written verification to the City that
Developer: (1) does not have a practice,policy, guidance, or directive that discriminates against a firearm
City of Fort Worth,Texas Page 10 of 16
Standard Community Facilities Agreement
Rev.9/21
entity or firearm trade association; and (2) will not discriminate against a firearm entity or firearm trade
association during the term of this Agreement.
28.
Immigration and Nationality Act
Developer shall verify the identity and employment eligibility of its employees who perform work
under this Agreement, including completing the Employment Eligibility Verification Form (I-9). Upon
request by City, Developer shall provide City with copies of all I-9 forms and supporting eligibility
documentation for each employee who performs work under this Agreement. Developer shall adhere to all
Federal and State laws as well as establish appropriate procedures and controls so that no services will be
performed by any Developer employee who is not legally eligible to perform such services.DEVELOPER
SHALL INDEMNIFY CITY AND HOLD CITY HARMLESS FROM ANY PENALTIES,
LIABILITIES, OR LOSSES DUE TO VIOLATIONS OF THIS PARAGRAPH BY DEVELOPER,
DEVELOPER'SEMPLOYEES,SUBCONTRACTORS,AGENTS,OR LICENSEES. City,upon written
notice to Developer, shall have the right to immediately terminate this Agreement for violations of this
provision by Developer.
29.
Amendment
No amendment,modification, or alteration of the terms of this Agreement shall be binding unless
the same is in writing,dated subsequent to the date hereof, and duly executed by the City and Developer.
30.
Assignment and Successors
Developer shall not assign or subcontract all or any part of its rights,privileges,or duties under this
Agreement without the prior written consent of City. Any attempted assignment or subcontract without the
City's prior written approval shall be void and constitute a breach of this Agreement.
31.
No Third-Party Beneficiaries
The provisions and conditions of this Agreement are solely for the benefit of the City and
Developer, and any lawful assign or successor of Developer, and are not intended to create any rights,
contractual or otherwise,to any other person or entity.
32.
Compliance with Laws,Ordinances,Rules and Regulations
Developer, its officers, agents, servants, employees, and contractors, shall abide by and comply
with all laws, federal, state and local, including all ordinances, rules and regulations of City. It is agreed
and understood that,if City calls to the attention of Developer any such violation on the part of Developer
or any of its officers, agents, servants, employees, or subcontractors, then Developer shall immediately
desist from and correct such violation.
33.
Signature Authority
City of Fort Worth,Texas Page 11 of 16
Standard Community Facilities Agreement
Rev.9/21
The person signing this Agreement on behalf of Developer warrants that he or she has the legal
authority to execute this Agreement on behalf of the Developer, and that such binding authority has been
granted by proper order,resolution,ordinance or other authorization of the entity. The City is fully entitled
to rely on this warranty and representation in entering into this Agreement.
34.
Counterparts
This Agreement may be executed in multiple counterparts, each of which will be deemed an
original, but which together will constitute one instrument.
35.
Entire Agreement
This written instrument, together with any attachments, exhibits, and appendices, constitutes the
entire understanding between the City and Developer concerning the work to be performed hereunder, and
any prior or contemporaneous, oral or written agreement that purports to vary from the terms hereof shall
be void.
[REMAINDER OF PAGE INTENTIONALLY BLANK]
City of Fort Worth,Texas Page 12 of 16
Standard Community Facilities Agreement
Rev.9/21
36.
Cost Summary Sheet
Pro]ectName: Northstar Section 4, Phase 3
CFA No.: CFA22-0037 City ProjectNo.: 103495 IPRC No.: IPRC21-0164
Items Developer's Cost
A. Water and Sewer Construction
1. Water Construction $ 459,662.00
2.Sewer Construction $ 471,375.40
Water and Sewer Construction Total $ 931,037.40
B. TPW Construction
1.Street $ 923,579.65
2.Storm Drain $ 567,539.00
3.Street Lights Installed by Developer $ 207,966.15
4. Signals $ -
TPW Construction Cost Total $ 1,699,084.80
Total Construction Cost(excluding the fees): $ 2,630,122.20
Estimated Construction Fees:
C. Construction Inspection Service Fee $61,000.00
D. Administrative Material Testing Service Fee $11,270.00
E. Water Testing Lab Fee $1,050.00
Total Estimated Construction Fees: $ 73,320.00
Choice
Financial Guarantee Options,choose one Amount (Mark one)
Bond= 100% $ 2,630,122.20
Completion Agreement= 100%/Holds Plat $ 2,630,122.20 X
Cash Escrow Water/Sanitary Sewer= 125% $ 1,163,796.75
Cash Escrow Paving/Storm Drain= 125% $ 2,123,856.00
Letter of Credit= 125% $ 3,287,652.75
City of Fort Worth,Texas Page 13 of 16
Standard Community Facilities Agreement
Rev.9/21
IN WITNESS WHEREOF,the City and Developer have each executed this Agreement by their
duly authorized signatories to be effective on the date executed by the City's Assistant City Manager.
CITY OF FORT WORTH DEVELOPER
170 Northstar Ranch Developer,Inc.
Daa hdS doff
f 3,202211:25 CDT) Kim Gill(Apr12,202214:38 CDT)
Dana Burghdoff Kimberly Gill
Assistant City Manager Assistant Vice President
Date: Apr 13,2022 Date: Apr 12,2022
Recommended by:
Jen nn! z�ernack(Apr 12,202216:01 CDT)
Evelyn Roberts/Jennifer Ezernack
Project Assistant
Planning and Development
Approved as to Form &Legality:
41:9— Contract Compliance Manager:
Richard A.McCracken(Apr 13,202210:31 CDT)
Richard A.McCracken By signing, I acknowledge that I am the person
Sr.Assistant City Attorney responsible for the monitoring and
M&C No. N/A administration of this contract,including
Date: ensuring all performance and reporting
0�440R requirements.
Form 1295. NSA p��pAo °°°�r�0���
..pIII!�0° .t� �r%a�c��Rribes�t�r 6eLc�Gf r
�i\o 00'2� Evelyn obertson behalfof(Apr13,202209:03CDT)
ATTEST: V 0 d
��1' �� Janie Scarlett Morales
�7�1l1GttG Gooal�CG aa�nExASb� Development Manager
Jan nette S.Goodall(Apr 13,2022 13:17 CDT)
Jannette S. Goodall/Ronald P. Gonzales
City Secretary Assistant City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
City of Fort Worth,Texas Page 14 of 16
Standard Community Facilities Agreement
Rev.9/21
The following attachments are incorporated into this Agreement. To the extent a
conflict exists between the main body of this Agreement and the following attachments, the
language in the main body of this Agreement shall be controlling.
Included Attachment
❑X Attachment 1 -Changes to Standard Community Facilities Agreement
❑ Attachment 2—Phased CFA Provisions
❑ Attachment 3 —Concurrent CFA Provisions
❑X Location Map
❑X Exhibit A: Water Improvements
❑X Exhibit A-1: Sewer Improvements
❑X Exhibit B: Paving Improvements
❑X Exhibit B-1: Storm Drain Improvements
❑X Exhibit C: Street Lights and Signs Improvements
❑X Cost Estimates
(Remainder of Page Intentionally Left Blank)
City of Fort Worth,Texas Page 15 of 16
Standard Community Facilities Agreement
Rev.9/21
ATTACHMENT"1"
Changes to Standard Community Facilities Agreement
City Project No. 103495
None
City of Fort Worth,Texas Page 16 of 16
Standard Community Facilities Agreement
Rev.9/21
UTILITY CONTRACT FORMS
D.T. UTILITY CONTRACTORS, INC.
00 41 00
DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY
Page I of 3
SECTION 00 4100
DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY
TO: 170 NORTHSTAR RANCH DEVELOPERS,INC.
3045 LACKLAND ROAD
FORT WORTH,TEXAS 76116
FOR: NORTHSTAR—SECTION 4 PHASE 3
WATER, SANITARY SEWER, STORM SEWER,PAVING AND STREET LIGHTS
IMPROVEMENTS
City Project 103495
No.:
Units/Sections: WATER,SANITARY AND STORM SEWER
1. Enter Into Agreement
The undersigned Bidder proposes
and agrees, if this Bid is accepted,to enter into an Agreement with Developer in the form included in the
Bidding Documents to perform and furnish all Work as specified or indicated in the Contract Documents
for the Bid Price and within the Contract Time indicated in this Bid and in accordance with the other
terms and conditions of the Contract Documents.
2. BIDDER Acknowledgements and Certification
2.1. In submitting this Bid,Bidder accepts all of the terms and conditions of the INVITATION TO
BIDDERS and INSTRUCTIONS TO BIDDERS, including without limitation those dealing
with the disposition of Bid Bond.
2.2. Bidder is aware of all costs to provide the required insurance,will do so pending contract
award,and will provide a valid insurance certificate meeting all requirements in the
construction contract.
2.3. Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any
undisclosed individual or entity and is not submitted in conformity with any collusive
agreement or rules of any group, association,organization, or corporation.
2.4. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or
sham Bid.
2.5. Bidder has not solicited or induced any individual or entity to refrain from bidding.
2.6. Bidder has not engaged in corrupt,fraudulent, collusive,or coercive practices in competing for
the Contract. For the purposes of this Paragraph:
a. "corrupt practice"means the offering, giving, receiving,or soliciting of anything of value
likely to influence the action of a public official in the bidding process.
CITY OF FORT WORTH
STANDARD CONSTRUCTION BID FORM—DEVELOPER AWARDED PROJECTS 00 4100 Bid Form—DAP.docx
Form Revised April 2,2014
00 41 00
DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY
Page 2 of 3
b. "fraudulent practice" means an intentional misrepresentation of facts made(a)to
influence the bidding process to the detriment of Developer(b)to establish Bid prices at
artificial non-competitive levels,or(c)to deprive Developer of the benefits of free and
open competition.
c. "collusive practice" means a scheme or arrangement between two or more Bidders,with
or without the knowledge of Developer, a purpose of which is to establish Bid prices at
artificial,non-competitive levels.
d. "coercive practice"means harming or threatening to harm,directly or indirectly,persons
or their property to influence their participation in the bidding process or affect the
execution of the Contract.
3. Prequalification
The Bidder acknowledges that the following work types must be performed only by prequalified
contractors and subcontractors:
a. WATER
b. SEWER COLLECTION SYSTEM(16-INCH DIAMETER FORCE
MAIN)
C. STORM SEWER
4. Time of Completion
4.1. The Work will be complete for Final Acceptance within 90 working days after the date when
the Contract Time commences to run as provided in the General Conditions.
4.2. Bidder accepts the provisions of the Agreement to liquidated damages, if applicable, in the event
of failure to complete the Work {and/or achievement of Milestones} within the times specified
in the Agreement.
5. Attached to this Bid
The following documents are attached to and made a part of this Bid:
a. This Bid Form, Section 00 41 00
b. Bid Bond(if required), Section 00 43 13 issued by a surety meeting the
requirements of the General Conditions.
c. Proposal Form, Section 00 42 43
d. MBE Forms (if required)
e. Prequalification Statement, Section 00 45 12
f. Any additional documents that may be required by Section 12 of the Instructions
to Bidders
g. Bidder pre-qualification application(optional)
6. Total Bid Amount
6.1. Bidder will complete the Work in accordance with the Contract Documents for the following
bid amount. In the space provided below, please enter the total bid amount for this project. Only
this figure will be read publicly by the City at the bid opening.
CITY OF FORT WORTH
STANDARD CONSTRUCTION BID FORM—DEVELOPER AWARDED PROJECTS 00 4100 Bid Form—DAP.docx
Form Revised April 2,2014
004100
DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY
Page 3 of 3
6.2, It is understood and agreed by the Bidder in signing this proposal that the total bid
amount entered below is subject to verification and/or modification by multiplying the unit
bid prices for each pay item by the respective estimated quantities shown in this proposal and
then totaling all of the extended amounts.
6.3. Evaluation of Alternate Bid Items <use this if applicable,otherwise delete>
Total Base Bid
$ 1,498,576.40
Alternate Bid
$0.00
Deductive Alternate
$0.00
Additive Alternate
$0.00
TOTAL BID $1,498,576.40
7. Bid Submittal
This Bid is submitted on: JULY 15,2021 by the entity named below
Respectfully submitted,
Receipt is acknowledged of
By: / % the following Addenda: Initial
(Signature)
-re (IC4-1- Addendum No. 1
nted Name) Addendum No.2
Title: U, ra. Addendum No. 3
<Title or Office>
Company: D.T.UTILITY CONTRACTORS,INC. Addendum No.4
<Company Name>
Address: 2614 CAUSBIE ROAD
<Address>
<Address if applicable,otherwise delete>
WEATHERFORD,TEXAS 76087
<City, State,Zip Code>
State of Incorporation: TEXAS
Email: colton@,dtutility.com
Phone: 817-304-2000
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION BID FORM—DEVELOPER AWARDED PROJECTS 004100 Bid Form—DAP.docz
Form Revised April 2,2014
00 42 43 BID PROPOSAL FORM
004243
DAP-BID PROPOSAL
Page 1 of 6
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM Final Contract 2/10/2022
NORTHSTAR-SECTION 4,PHASE 3(EAST TRACT) C.P.No.: 103495
UNIT PRICE BID Bidder's Application
Project Item Information Bidders Proposal
Bidlist Specification Unit of Bid
Item No. Description Section No. Measure Quantity Unit Price Bid Value
UNIT I:WATER IMPROVEMENTS
1-1 3311.0161 6"Water Pipe 33 11 12 LF 50 $36.00 $1,800,00
1-2 3311.0261 8"Water Pipe 33 11 12 LF 4,234 $52.00 $220,168.00
1-3 3312.3002 6"Gate Valve 33 1220 EA 7 $850.00 $5,950.00
1-4 3312.3003 8"Gate Valve 33 1220 EA 9 $2,000.00 $18,000.00
1-5 3312.0117 Connect.to Existing 4"-12"Water Main 33 1225 EA 3 $500.00 $1,500.00
1-6 3312.0001 Fire Hydrant 33 1240 EA 7 $6,000.00 $42,000.00
1 33 12 40 EA 1
9999.0010 Automatic Flusher and Fire Hydrant(end of Velora $8,500.00
Drive $8,500.00
1-8 331 1.0001 Ductile Iron Water Fittings w/Restraint 33 11 11 TON 4 $6,000.00 $24,000.00
1-9 3305.0109 Trench Safety 3305 10 LF 4,284 $0.50 $2,142.00
1-10 3312.2003 1"Water Service 33 12 10 EA 113 $1,200.00l $135,600.00
1-11 3471.0001 Traffic Control 3471 13 MO 2 $1.001 $2.00
TOTAL UNIT I:WATER IMPROVEMENTS $459,662.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Version April 2,2014 00 42 43-Final Bid Quantities-NORTHSTAR-SECTION 4,PHASE 3-02-21-22.x1s
004243
DAP-BID PR(N4LSAL
Page 2 of-4
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM Final Contract 2/10/2022
NORTHSTAR-SECTION 4,PHASE 3(EAST TRACT) C.P.No.: 103495
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist Specification Unit of Bid
Item No. Description Unit Price Bid Value
Section No. Measure Quantity
UNIT II:SANITARY SEWER IMPROVEMENTS
2-I 13331.4115 8"Sewer Pipe 33 11 10 LF 2,067 $43.00 $88,881.00
2-2 3331.4116 8"Sewer Pipe,CSS Backfill 33 11 10 LF 91 $85.00 $7,735.00
2-3 3331A201 10"Sewer Pipe 33 11 10 LF 1,447 $55.00 S79,585.00
24 3331.4202 10"Sewer Pipe,CSS Backfill 33 11 10 LF 20 $91.00 $1,820.00
2-5 9999.0020 10"Sewer Pipe,Concrete Backfill 33 11 10 LF 95 $1 15.00 $10,925.00
2-6 3331.4215 15"Sewer Pipe 33 11 10 LF 684 $70.00 $47,880.00
2-7 3339.1001 4'Manhole 33 39 20 EA 21 $3,800.00 $79,800.00
2-8 3339.1002 4'Drop Manhole 33 39 10 EA 3 $4,600.00 $13,800.00
2-9 3339.1003 4'Extra Depth Manhole 33 39 20 VF 110 $175.00 $19,250.00
2-10 3331.3102 4"Sewer Service,Two-way cleanout 33 31 50 EA 113 $825.00 $93,225.00
2-11 3301.0002 Post-CCTV Inspection 33 01 31 LF 4,404 $3.10 $13,652.4
2-12 3301.0101 Manhole Vacuum Testing 3301 30 EA 24 $150.00 S3,600.00
2-13 3339.0001 Epoxy Manhole Liner 33 39 60 VF 25 $300.00 $7,500.0-0
2-14 3305.0109 Trench Safety 3305 10 LF 3,720 $1.00 $3,720.00
2-15 9999.0021 Connect.to Existing 8"-15"Water Main 1 33 11 10 EA 2 $1.00 S2.00
TOTAL UNIT II:SANITARY SEWER IMPROVEMENTS $471,375.40
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Version Apri12,2014 00 42 43-Final Bid Quantities-NORTHSPAR-SECTION 4,PHASE 3-02-21-22.ck
004243
DAP-BID PROPOSAL
Page 3 of 4
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM Final Contract 2/10/2022
NORTHSTAR-SECTION 4,PHASE 3(EAST TRACT) C.P.No.: 103495
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist Specification Unit of Bid
Item No. Description Unit Price Bid Value
Section No. Measure Quantity
UNIT III:DRAINAGE IMPROVEMENTS
3-I 13305.0109 Trench Safety 3305 10 LF 1,709 S1.00 $1,709.00
3-2 3341.0602 60"RCP,Class III 3341 10 LF 17 $300.00 $5,100.00
3-3 3341.0502 54"RCP,Class III 3341 10 LF 1,463 $250.00 $365,750.
3.4 3341.0302 30 RCP,Class III 3341 10 LF 164
$95.00 $15,580.
3-5 3341.0205 24"RCP,Class III 3341 10 LF 65
$77.00 $5,005.0(
3-6 3349.0003 6'Storm Junction Box 33 49 10 EA 3 $8,750.00 $26,250.
3-7 3349.4115 60"TXDOT 4:l SET(1)(FW)End Treatment 33 49 40 EA 1 $9,350.00 $9,350.
3-8 3349.4107 30"TXDOT 4:I SET(1)(FW)End Treatment 33 49 40 EA 1 $3,400.00 $3,400.
3-9 3349.5004 30'Curb Inlet 33 49 20 EA 1 $17,500.00 $17,500.
3-10 3349.5003 20'Curb Inlet 33 49 20 EA 6 $11,000 00 $66,000
3-11 3137.0104 Medium Stone,Riprap,dry(18"/12') 31 37 00 Sy 541 S95.001 $51,395.
3-12 19999.0030 Connect.to Existing Storm Sewer 33 49 20 EA 1 $500.00 $500.
TOTAL UNIT III:DRAINAGE IMPROVEMENTS $567,539.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Version Aixil 2,2014 0042 43-Final Bid Quantities-NORTHSTAR-SECTION 4,PHASE 3-02-21-22.zk
004243
DAP-BID PROPOSAL
Pnc 4 of4
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM Final Contract 2/10/2022
NORTHSTAR-SECTION 4,PHASE 3(EAST TRACT) C.P.No.: 103495
UNIT PRICE BID Bidder's Application
Project Item Information Bidders Proposal
Bidlist Description Specification Unit of I Bid Unit Price Bid Value
Item No Section No. Measure I Quantity
Bid Summary
UNIT 1:WATER IMPROVEMENTS $459,662.00
UNIT II:SANITARY SEWER IMPROVEMENTS $471,375.40
UNIT III:DRAINAGE IMPROVEMENTS $567,539.00
----------
Total Construction Bid l i1,498,576.401
Contractor agrees to complete WORK for FINAL ACCEPTANCE within go dayS working days after the date when the
CONTRACT commences to run as provided in the General Conditions.
WATER IMPROVEMENTS 30 working days.
SANITARY SEWER IMPROVEMENTS 30 working days.
DRAINAGE IMPROVEMENTS 30 working days.
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECWICA17ON DOCUNIENTS-DEVELOPER AWARDED PROJECTS
Forrn Version April Z 2014 00 42 43-Final Bid Qwmitie -NORTHSTAR-SECTION 4,PHASE 3-02-21-22AIs
PAVING CONTRACT FORMS
GILCO CONTRACTING, INC.
00 41 00
DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY
Page I of 3
SECTION 00 4100
DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY
TO: 170 NORTHSTAR RANCH DEVELOPERS,INC.
3045 LACKLAND ROAD
FORT WORTH,TEXAS 76116
FOR: NORTHSTAR—SECTION 4,PHASE 3
WATER,SANITARY SEWER,STORM SEWER,PAVING
City Project 103495
No.:
Units/Sections: PAVING
1. Enter Into Agreement
The undersigned Bidder proposes
and agrees, if this Bid is accepted,to enter into an Agreement with Developer in the form included in the
Bidding Documents to perform and furnish all Work as specified or indicated in the Contract Documents
for the Bid Price and within the Contract Time indicated in this Bid and in accordance with the other
terms and conditions of the Contract Documents.
2. BIDDER Acknowledgements and Certification
2.1. In submitting this Bid, Bidder accepts all of the terms and conditions of the INVITATION TO
BIDDERS and INSTRUCTIONS TO BIDDERS, including without limitation those dealing
with the disposition of Bid Bond.
2.2. Bidder is aware of all costs to provide the required insurance,will do so pending contract
award, and will provide a valid insurance certificate meeting all requirements in the
construction contract.
2.3. Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any
undisclosed individual or entity and is not submitted in conformity with any collusive
agreement or rules of any group, association, organization,or corporation.
2.4. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or
sham Bid.
2.5. Bidder has not solicited or induced any individual or entity to refrain from bidding.
2.6. Bidder has not engaged in corrupt,fraudulent, collusive, or coercive practices in competing for
the Contract. For the purposes of this Paragraph:
a. "corrupt practice" means the offering, giving, receiving,or soliciting of anything of value
likely to influence the action of a public official in the bidding process.
b. "fraudulent practice"means an intentional misrepresentation of facts made(a)to
influence the bidding process to the detriment of Developer(b)to establish Bid prices at
CITY OF FORT WORTH
STANDARD CONSTRUCTION BID FORM—DEVELOPER AWARDED PROJECTS 00 4100 Bid Form—DAP.docx
Form Revised April 2,2014
00 41 00
DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY
Page 2 of 3
artificial non-competitive levels,or(c)to deprive Developer of the benefits of free and
open competition.
c. "collusive practice"means a scheme or arrangement between two or more Bidders,with
or without the knowledge of Developer,a purpose of which is to establish Bid prices at
artificial,non-competitive levels.
d. "coercive practice"means harming or threatening to harm,directly or indirectly,persons
or their property to influence their participation in the bidding process or affect the
execution of the Contract.
3. Prequalification
The Bidder acknowledges that the following work types must be performed only by prequalified
contractors and subcontractors:
a. PAVING IMPROVEMENTS
4. Time of Completion
4.1. The Work will be complete for Final Acceptance within 45 working days after the date when
the Contract Time commences to run as provided in the General Conditions.
4.2. Bidder accepts the provisions of the Agreement to liquidated damages,if applicable,in the event
of failure to complete the Work {and/or achievement of Milestones) within the times specified
in the Agreement.
5. Attached to this Bid
The following documents are attached to and made a part of this Bid:
a. This Bid Form, Section 00 41 00
b. Bid Bond(if required), Section 00 43 13 issued by a surety meeting the
requirements of the General Conditions.
c. Proposal Form,Section 00 42 43
d. MBE Forms (if required)
e. Prequalification Statement,Section 00 45 12
f. Any additional documents that may be required by Section 12 of the Instructions
to Bidders
g. Bidder pre-qualification application(optional)
6. Total Bid Amount
6.1. Bidder will complete the Work in accordance with the Contract Documents for the following
bid amount. In the space provided below,please enter the total bid amount for this project.Only
this figure will be read publicly by the City at the bid opening.
CITY OF FORT WORTH
STANDARD CONSTRUCTION BID FORM—DEVELOPER AWARDED PROJECTS 00 41 00 Bid Form—DAP.docx
Form Revised April 2,2014
0041 00
DAP BID FORA FOR PUBLICLY BID PROJECTS ONLY
Page 3 of 3
6.2. It is understood and agreed by the Bidder in signing this proposal that the total bid
amount entered below is subject to verification and/or modification by multiplying the unit
bid prices for each pay item by the respective estimated quantities shown in this proposal and
then totaling all of the extended amounts.
6.3. Evaluation of Alternate Bid Items <use this if applicable,otherwise delete>
Total Base Bid
$923,579.65
Alternate Bid
$0.00
Deductive Alternate
$0.00
Additive Alternate $0.00
TOTAL BID $923,579.65
7. Bid Submittal
This Bid is submitted on: JULY 15,2021 by the entity named below
Respectfully submitted,
Receipt is acknowledged of
By: the following Addenda: Initial
(Signature)
Leia McOuien Addendum No. I
(Printed Name) Addendum No.2
Title: Vice President,Operations Addendum No.3
<Title or Office>
Company: GILCO CONTRACTING,INC. Addendum No.4
<Company Name>
Address: 6331 Southwest Bvd.
<Address> 17
<Address if applicable,otherwise delete>
BENBROOK,TEXAS 76132
<City,State,Zip Code>
State of Incorporation: Texas
Email: leiaagilcocontracti np-.com
Phone: 817-735-1600
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION BID FORM—DEVELOPER AWARDED PROJECTS 00 4100 Bid Form—DAP.docx
Form Revised April 2,2014
00 42 43 BID PROPOSAL FORM
004243
DAP-BID PROPOSAL
Page 1 of 2
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM Final Contract 2/10/2022
NORTHSTAR-SECTION 4,PHASE 3(EAST TRACT) C.P.No.: 103495
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist Specification Unit of Bid
Item No. Description Unit PriceFBid Value
Section No. Measure Quantity
UNIT IV: PAVING IMPROVEMENTS
4-I 3213.0101 6"Core Pvmt(29'B-B) 32 13 13 Sy 15247.00 $47.25 $720,420.75
4-2 321 1.0501 6"Lime Treatment 32 11 29 Sy 16238.06 $3.65 $59,268.90
4-3 3211.0400 Hydrate Lime 32 11 29 TN 244.00 $205.85 $50,227.40
4-4 3292.0100 Block Sod Placement 3292 13 Sy 100
$10.00 $1,000.00
4-5 3292.0400 Seed,Hydromulch 3292 14 Sy 10,950 $2.00 $21,900.00
4-6 3213.0301 4"Concrete Sidewalk (5'Width) 32 1320 SF 2,547 $7.45 $18,975.15
4-7 3213.0501 Barrier Free Ramp-Type R-1 32 1320 EA 12 $2,925.95 $35,111.40
4 8 9999.0040 Furn./Install Alum.Sign and Decortive Post w/Stop(Rl- 3441 30 EA 9 $10,852.65
l $1,205.85
4-9 9999.0041 Street Name Plates for Street Intersections(D3-1) 3441 30 EA 22 $264.70 $5,823.40
TOTAL UNIT IV: PAVING IMPROVEMENTS $923,579.65
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Version April 2,2014 00 42 43-Final Bid Quantities-NORTHSTAR-SECTION 4,PHASE 3-03.23-22.xis
004243
DAP-BID PROPOSAL
Page 2 of
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM Final Contract 2/10/2022
NORTHSTAR-SECTION 4,PHASE 3(EAST TRACT) C.P.No.: 103495
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist. Description Specification Unit of I Bid Unit Price Bid Value
Item No Section No. Measure I Quantity
Bid Summary
UNIT IV:PAVING IMPROVEMENTS u rr $923,579.65
Total Construction Bid l $923,579.651
Contractor agrees to complete WORK for FINAL ACCEPTANCE within 45 days working days after the date when the
CONTRACT commences to run as provided in the General Conditions.
WATER IMPROVEMENTS 30 working days.
SANITARY SEWER IMPROVEMENTS 30 working days.
DRAINAGE IMPROVEMENTS 30 working days.
PAVING IMPROVEMENTS 45 working days.
STREET LIGHT IMPROVEMENTS 60 working days.
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Version April 2,2014 00 42 43-Final Bid Quantities-NORT14STAR-SECTION 4,PHASE 3-03-23-22.xls
STREET LIGHTS CONTRACT FORMS
BEAN ELECTRICAL, INC.
00 41 00
DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY
Page I of3
SECTION 00 4100
DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY
TO: 170 NORTHSTAR RANCH DEVELOPER,INC.
3045 LACKLAND ROAD
FORT WORTH,TEXAS 76116
FOR: NORTHSTAR—SECTION 4 PHASE 3
WATER,SANITARY SEWER,STORM SEWER,PAVING AND STREET LIGHTS
IMPROVEMENTS
City Project 103495
No.:
Units/Sections: STREET LIGHTS
1. Enter Into Agreement
The undersigned Bidder proposes
and agrees, if this Bid is accepted,to enter into an Agreement with Developer in the form included in the
Bidding Documents to perform and furnish all Work as specified or indicated in the Contract Documents
for the Bid Price and within the Contract Time indicated in this Bid and in accordance with the other
terms and conditions of the Contract Documents.
2. BIDDER Acknowledgements and Certification
2.1. In submitting this Bid,Bidder accepts all of the terms and conditions of the INVITATION TO
BIDDERS and INSTRUCTIONS TO BIDDERS, including without limitation those dealing
with the disposition of Bid Bond.
2.2. Bidder is aware of all costs to provide the required insurance,will do so pending contract
award,and will provide a valid insurance certificate meeting all requirements in the
construction contract.
2.3. Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any
undisclosed individual or entity and is not submitted in conformity with any collusive
agreement or rules of any group,association,organization,or corporation.
2.4. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or
sham Bid.
2.5. Bidder has not solicited or induced any individual or entity to refrain from bidding.
2.6. Bidder has not engaged in corrupt,fraudulent,collusive,or coercive practices in competing for
the Contract. For the purposes of this Paragraph:
a. "corrupt practice" means the offering,giving,receiving,or soliciting of anything of value
likely to influence the action of a public official in the bidding process.
b. "fraudulent practice"means an intentional misrepresentation of facts made(a)to
influence the bidding process to the detriment of Developer(b)to establish Bid prices at
CITY OF FORT WORTH
STANDARD CONSTRUCTION BID FORM—DEVELOPER AWARDED PROJECTS 00 4100 Bid Form—DAP.dccx
Form Revised April 2,2014
00 41 00
DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY
Page 2 of 3
artificial non-competitive levels,or(c)to deprive Developer of the benefits of free and
open competition.
c. 'collusive practice"means a scheme or arrangement between two or more Bidders,with
or without the knowledge of Developer,a purpose of which is to establish Bid prices at
artificial,non-competitive levels.
d. "coercive practice" means harming or threatening to harm,directly or indirectly,persons
or their property to influence their participation in the bidding process or affect the
execution of the Contract.
3. Prequalification
The Bidder acknowledges that the following work types must be performed only by prequalified
contractors and subcontractors:
a. STREET LIGHTS
4. Time of Completion
4.1. The Work will be complete for Final Acceptance within 60 working days after the date when
the Contract Time commences to run as provided in the General Conditions.
4.2. Bidder accepts the provisions of the Agreement to liquidated damages, if applicable, in the event
of failure to complete the Work {and/or achievement of Milestones} within the times specified
in the Agreement.
5. Attached to this Bid
The following documents are attached to and made a part of this Bid:
a. This Bid Form, Section 00 41 00
b. Bid Bond(if required), Section 00 43 13 issued by a surety meeting the
requirements of the General Conditions.
c. Proposal Form, Section 00 42 43
d. MBE Forms (if required)
e. Prequalification Statement, Section 00 45 12
f. Any additional documents that may be required by Section 12 of the Instructions
to Bidders
g. Bidder pre-qualification application(optional)
6. Total Bid Amount
6.1. Bidder will complete the Work in accordance with the Contract Documents for the following
bid amount. In the space provided below,please enter the total bid amount for this project.Only
this figure will be read publicly by the City at the bid opening.
6.2. It is understood and agreed by the Bidder in signing this proposal that the total bid
amount entered below is subject to verification and/or modification by multiplying the unit
bid prices for each pay item by the respective estimated quantities shown in this proposal and
then totaling all of the extended amounts.
CITY OF FORT WORTH
STANDARD CONSTRUCTION BID FORM—DEVELOPER AWARDED PROJECTS 00 4100 Bid Form—DAP.docx
Form Revised April 2,2014
0041 00
DAP BID FORM FOR PUBLICLY BID PROJECTS ONLY
Page 3 of 3
6.3. Evaluation of Alternate Bid Items <use this if applicable,otherwise delete>
Total Base Bid
$207,966.15
Alternate Bid
$0.00
Deductive Alternate
$0.00
Additive Alternate
$0.00
TOTAL BID $207,966.15
7. Bid Submittal
This Bid is submittered,
'JULY 15,2021 by the entity named below
su
Respectfullybmi
�
C/ Receipt is acknowledged of
By: the following Addenda: Initial
(Signature)
CHIP BEAN Addendum No. 1
(Printed Name) Addendum No. 2
Title: President Addendum No.3
<Title or Office>
Company: BEAN ELECTRICAL,INC. Addendum No. 4
<Company Name>
Address: 821 ENON AVENUE
<Address>
<Address if applicable,otherwise delete>
FORT WORTH, TEXAS 76140
<City, State,Zip Code>
State of Incorporation: TEXAS
Email: Che ll1 uwheallelectI-ial.Coml
Phone: 817-561-7400
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION BID FORM—DEVELOPER AWARDED PROJECTS 00 4100 Bid Form—DAP.docx
Form Revised April 2,2014
00 42 43 BID PROPOSAL FORM
004243
DAP-BID PROPOSAL
Pw I o12
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM Final Contract 2/10/2022
NORTHSTAR-SECTION 4,PHASE 3(EAST TRACT) C.P.No.: 103495
UNIT PRICE BID Bidder's Application
UNIT V:STREET LIGHTING IMPROVEMENTS
9999.0050 Fumish/Install-Holophane-Columbia Aluminum
5-1 Pole,Washington-14.5'Luminaire WFCL2-070HO-30K-AS-BK- 3441 20 EA 34 $3,720.00 $126,480.00
L5-RFD-AO-H-PCS
5-2 3441.3303 Fumish/Install Rdwy Illum Foundation TY 7 3441 20 EA 34 $1,125.00 S38,250.00
5-3 2605.3015 Fumish/Install 2-Inch Conduit PVC SCH 80(T) 26 05 33 LF 2089 $16.50 $34,468.50
5-4 13441.3401 Fumish/Install#10 Copper Electric Conductor 3441 10 CLF 2089 $3.85 $8,042.65
5-5 3441.1501 Furnish/Install Ground Box Type B 3441 10 EA 1 $725.00 $725.00
'Note: Co-Serve is the electric provider and on this
project the "will not"provide the street light pole.
TOTAL UNIT V:STREET LIGHTING IMPROVEMENTS $207,966.15
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Version April 2.2014 00 42 43-Final Bid Quantities-NORTHSTAR-SECTION 4,PHASE 3-02-21-22.x1s
004243
DAP-81DPROPOSAL
PW 2 o£2
SEC71ON 00 42 43
Developer Awarded Projects-PROPOSAL FORM Final Contract 2/10/2022
NORTHSTAR-SECTION 4,PHASE 3(EAST TRACT) C.P.No.: 103495
UNIT PRICE BID Bidder's Application
UNIT V:STREET LIGHTING IMPROVEMENTS $207,966.15
Total Construction Bid $207,966.15
Contractor agrees to complete WORK for FINAL ACCEPTANCE within 60 days working days after the date when the
CONTRACT commences to run as provided in the General Conditions.
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUNM-NTS-DEVELOPER AWARDED PROJECTS
Form Version April 2,2014 00 42 43-Final Bid Quantities-NORTHSTAR-SECTION 4,PHASE 3-02-2 t-21.ls
81 �G
287 Oti
PROJECT
LOCATION
NORTHSTAR
z
N ° N.T.S.
81
718 a a 287 y
mOf
� CREEK Q N �9�
03
�+ z AVONDALE—HASLET
cn BOAZ
c�
z
AVONDALE �—�N
B287 3:
P O
81
TINSLEY AVON 287
BLUE MOUND
MAPSCO NO. 4F
IPRC NO. 21-0164
CITY PROJECT NO. 103495
LOCATION MAP FID NO. 30114-0200431-103495-EO7685
"NORTHSTAR SECTION 4, PHASE 3" STREET/STORM DRAIN NO. W-2806
X-27178
OWNER/DEVELOPER: ENGINEER:
170 NORTHSTAR RANCH DEVELOPER, INC. '*IrZ'WELCH ENGINEERING, INC.
3045 LACKLAND BOULEVARD 1308 NORWOOD DRIVE, SUITE 200
FORT WORTH, TEXAS 76116 BEDFORD, TEXAS 76022
P_ROP. 8"W PROP. 8"W
\ PROP. 8"W 3 oR_�I ILvE�o�` pR• /
L �O
��/�� PROP. 8"w• PROP. 8"W
ROP. 8"W PROP. 8"W I d' Q�• PROP. 8"W
/ kF�lrq EXIST e"w
EXIST16"W �� Q r�/ XI
R PROP.
EXIST
N �
LEGEND
100% DEVELOPER'S COST SCALE: 1"=300'
B,d 8" WATER LINES, FIRE HYDRANTS,
GATE VALVES AND ASSOCIATED
APPURTENANCES
EXHIBIT "A" IPRC NO. 21-0164
CITY PROJECT NO. 103495
WATER IMPROVEMENTS FID NO. 30114-0200431-103495—EO7685
"NORTHSTAR SECTION 4, PHASE 3 X-27178STORM DRAIN N0. W-2806
OWNER/DEVELOPER: ENGINEER:
170 NORTHSTAR RANCH DEVELOPER, INC. 'bYJrZ'WELCH ENGINEERING, INC.
3045 LACKLAND BOULEVARD 1308 NORWOOD DRIVE, SUITE 200
FORT WORTH, TEXAS 76116 BEDFORD, TEXAS 76022
I � �
� PROP. 15"SS
x
PROP.
PROP. 15"SS\
PROP. 10"SS
\ _
�J� CPROP. 10"SS
!` PROP. 10"- i
\ ix xx� Exrsr. /o ss• � � ��kF lr ~ [E�� x O'Q 9�/S\
PROP. 8'
RTjySTq
. // ��. �� �' �•�� \y, � N°RAN '� � \ �
LEGEND
SCALE: 1"=300'
100% DEVELOPER'S COST
8" AND 10" SANITARY SEWER LINES
AND ASSOCIATED APPURTENANCES
EXHIBIT "A- 1" IPRC NO. 21-0164
CITY PROJECT NO. 103495
SANITARY SEWER IMPROVEMENTS FID NO. 30114-0200431-103495-EO7685
ST
"NORTHSTAR SECTION 4, PHASE 3" X-27178STORM DRAIN N0. W-2806
OWNER/DEVELOPER: ENGINEER:
170 NORTHSTAR RANCH DEVELOPER, INC. 'bYJrZ'WELCH ENGINEERING, INC.
3045 LACKLAND BOULEVARD 1308 NORWOOD DRIVE, SUITE 200
FORT WORTH, TEXAS 76116 BEDFORD, TEXAS 76022
i
29'B B � r
. VFs Oh'A O ORA DR• 1101
O
bu
olk
c/) — �R'CNS'CP�
7 / J
1-7
LEGEND
100% DEVELOPER'S COST
6" PAVEMENT W/2% CROSS SLOPE
ON 6" LIME SUBGRADE
SIDEWALK BY DEVELOPER
-- SIDEWALK BY HOMEBUILDER
O ADA RAMPS BY DEVELOPER
SCALE: 1"=300'
EXHIBIT 99 B 99 IPRC NO. 21-0164
CITY PROJECT NO. 103495
PAVING IMPROVEMENTS FID NO. 30114-0200431-103495—EO7685
"NORTHSTAR SECTION 4, PHASE 3" XT27178STORM DRAIN N0. W-2806
OWNER/DEVELOPER: ENGINEER:
170 NORTHSTAR RANCH DEVELOPER, INC. 'bYJrZ'WELCH ENGINEERING, INC.
3045 LACKLAND BOULEVARD 1308 NORWOOD DRIVE, SUITE 200
FORT WORTH, TEXAS 76116 BEDFORD, TEXAS 76022
, \<
I
' I 24"RCP
—
\ 20
0
P 24"RCP 54"RCP 30"RCP
54"RC � — 24"RCP
\\\\\ \ 20 00 20• / , 20•\ S //
/ /� 30"RCP Q' ' /
Ix
EX')4 RCP
ooe
\ / \ p NpR
iv
LEGEND
10', 15, OR 20' INLETS
100% DEVELOPER'S COST
STORM DRAIN AND INLET
AND ASSOCIATED APPURTENANCES
STORM DRAIN AND TxDOT
TYPE CH-PW-0 HEADWALL
SCALE: 1"=300'
STORM DRAIN AND TxDOT
TYPE SET(1)(FW) END TREATMENT
EXHIBIT "B- 1" IPRC NO. 21-0164
CITY PROJECT NO. 103495
STORM DRAIN IMPROVEMENTS FID NO. 30114-0200431-103495-EO7685
"NORTHSTAR SECTION 4, PHASE 3" STREET/STORM DRAIN NO. W-2806
X-27178
OWNER/DEVELOPER: ENGINEER:
170 NORTHSTAR RANCH DEVELOPER, INC. 'bYJrZ'WELCH ENGINEERING, INC.
3045 LACKLAND BOULEVARD 1308 NORWOOD DRIVE, SUITE 200
FORT WORTH, TEXAS 76116 BEDFORD, TEXAS 76022
� I
VF�0 I pR• 6
cl
loIx
ZID
0
LEGEND
* -- PROPOSED STREET LIGHT (100% DEVELOPER'S COST)
0 -- PROPOSED STREET SIGN (100% DEVELOPER'S COST)
■ -- PROPOSED GROUND BOX (100% DEVELOPER'S COST)
SCALE: 1"=300'
-- EXISTING STREET LIGHT
EXHIBIT 99C1" IPRC NO. 21-0164
CITY PROJECT NO. 103495
STREET NAME SIGNS AND STREET LIGHTS FID NO. 30114-0200431-103495—EO7685
"NORTHSTAR SECTION 4, PHASE 3" STREET/STORM DRAIN N0. W-2806
X—27178
OWNER/DEVELOPER: ENGINEER:
170 NORTHSTAR RANCH DEVELOPER, INC. 'bYJrZ'WELCH ENGINEERING, INC.
3045 LACKLAND BOULEVARD 1308 NORWOOD DRIVE, SUITE 200
FORT WORTH, TEXAS 76116 BEDFORD, TEXAS 76022
COMPLETION AGREEMENT—LENDER FUNDED
This Completion Agreement("Agreement)is made and entered into by and among the City
of Fort Worth ("City"), and 170 Northstar Ranch Developer, Inc, a Texas CORPORATION
("Developer"), and SIMMONS BANK, an Arkansas State Bank, as successor-in-interest by
merger to Southwest Bank, a Texas State Bank("Lender"), effective as of the date subscribed by
the City's City Manager or Assistant City Manager. The City, the Developer and the Lender are
hereinafter collectively called the "Parties".
WITNESSETH:
WHEREAS, the Developer owns that certain tract of real property that contains
approximately 27.4478 ACRES[acres that is located in the City,the legal description of which tract
of real property is marked Exhibit "A" — Legal Description, attached hereto and incorporated
herein for all purposes ("Property"); and
WHEREAS, the Developer intends to develop the Property as an addition to the City
through plat FP PP-17-025 or FS<Number>; and
WHEREAS, the Developer and the City have entered into a Community Facilities
Agreement relating to the development of Northstar Section 4, Phase 3 ("CIA"); and
WHEREAS, the City has required certain assurances of the availability of funds to
complete the water and sewer utilities, streets/paving, storm drain, street lights and street signs for
the development of the Property("Improvements"), and
WHEREAS, in order to provide such assurances as have been required by the City, the
Lender has agreed to advance certain funds to the City for Hard Costs (which term is hereinafter
defined)subject to,and in accordance with,the terms,provisions and conditions of this Agreement;
and
WHEREAS, the Developer has granted to the Lender as additional security for the Loan
(which term is hereinafter defined) a security interest in all plans and specifications for the
development of the Property (collectively,the "Plans"); and
WHEREAS, the Parties desire to set forth the terms and conditions of such
accommodations as are described above.
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 JLE
CFA Official Release Date:07.01.2015
Page 1 of 17
NOW THEREFORE,for and in consideration of the benefits to be derived from the mutual
observance by the Parties of the terms and conditions hereof, and for and in consideration of Ten
Dollars ($10.00) and other good and valuable consideration, the receipt, adequacy and sufficiency
of which are hereby acknowledged, the Parties agree as follows:
1. Recitals. The foregoing recitals are true, correct and complete and constitute the
basis for this Agreement and they are incorporated into this Agreement for all purposes.
2. The Completion Amount. The City and the Developer agree that the Hard Costs
required to complete the Improvements in the aggregate should not exceed the sum of TWO
MILLION SIX HUNDRED THIRTY THOUSAND ONE HUNDRED TWENTY-TWO AND
20/100 Dollars ($2,630,122.20), hereinafter called the "Completion Amount".
Notwithstanding the foregoing, it is acknowledged that the actual costs of completion of the
Improvements may vary as a result of change orders agreed to by the Parties, but such variances
for the purposes of this Agreement shall not affect the Completion Amount as used herein.
3. Adjustments to the Completion Amount. The Lender may from time to time make
advances to the Developer for the development of the Property under the development loan that
has been made by the Lender to the Developer for the purpose of financing the costs of constructing
the Improvements for the Property (the "Loan") subject to, and in accordance with, the terms,
conditions and provisions of the Loan Documents (which term is hereinafter defined) evidencing
and securing the Loan. Some of those advances shall be for Hard Costs as specified in the
"Approved Budget" relating to the Loan, a copy of which Approved Budget is marked Exhibit
"B", attached hereto and incorporated herein for all purposes, with the Hard Costs line items
highlighted. The term "Hard Costs" shall mean the actual costs of construction and installation of
the Improvements. To the extent that advances under the Loan are for the payment of Hard Costs,
the Completion Amount shall be deemed reduced, dollar for dollar. The Lender may withhold
statutory retainage from any advances under the Loan or pursuant to this Agreement. All such
retainage withheld, to the extent it is attributable to Hard Costs, shall also reduce the Completion
Amount dollar for dollar. All retainage withheld by the Lender for Hard Costs that are advanced
to the City pursuant to this Agreement shall be released to the City as provided in the Texas
Property Code upon expiration of the statutory retainage period.
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 JLE
CFA Official Release Date:07.01.2015
Page 2 of 17
4. Completion by the Developer. The Developer agrees to complete the
Improvements on or before the date for completion that is established in the Loan Documents plus
thirty (30) days (the "Completion Date"), in accordance with the CIA,the Plans approved by the
Lender and the City and all documents evidencing or securing the Loan (collectively, the "Loan
Documents"). For the purposes of this Agreement, the development of the Property shall be
deemed complete upon acceptance by the City of the Improvements. The City shall promptly
notify the Lender and the Developer upon such acceptance.
5. Completion by the City. In the event that either: (A) the development of the
Property is not completed by the Completion Date for any reason whatsoever,or(B)the Developer
is in default under the Loan, then the Lender, at its sole option, may request the City to complete
development. The City may, at its sole option and at the cost and expense of the Developer,within
10 days from receipt of Lender's request, notify Lender that it will undertake to complete the
Improvements and the City shall then commence, pursue, and complete the Improvements in a
reasonably timely, diligent and workmanlike manner in accordance with the Plans, subject to the
terms of this Agreement. The Lender and the Developer agree that the City may use the Plans as
necessary to complete the Improvements.
If the City does not timely elect to complete the construction of the Improvements or if the
Lender does not request the City to complete construction of the Improvements, then the Lender
may at its election terminate this Agreement, or at its option, proceed to complete the
Improvements, or foreclose on any of its collateral, or take any and all such action as may be
provided under the Loan Documents.
6. Advance of Completion Costs to the City and Delivery of Hard Costs Collateral to
the Ci . In the event the Lender has requested the City and the City has elected to complete the
Improvements, Lender shall transfer to the City all remaining undisbursed Hard Costs specified in
the Approved Budget within 10 days of the date that the City elected to complete and provided
Lender with written notice of such election.
The Developer hereby authorizes and instructs the Lender to make the transfer of any
remaining undisbursed Hard Costs specified in the Approved Budget to the City within 10 days of
notification that the City elects to complete the Improvements.
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015
Page 3 of 17
In the event the cost to complete the Improvements exceeds the moneys transferred to the
City, City shall notify Lender and Developer in writing of the need of additional funds. The
additional funds required to complete the Improvements shall be delivered to the City within 10
business days following notification to Lender and Developer. Failure to deliver the additional
funds shall relieve the City of the obligation to complete the Improvements, in which event City
shall use the Hard Costs funds in its possession to pay the contractor(s) all funds due it/them. Any
remaining undisbursed Hard Costs shall be returned to Lender within a reasonable time.
7. Completion by the Lender. The Lender may, at its discretion, but shall not be
obligated to, undertake to complete the Improvements if there is any default under any Loan
Documents in lieu of requesting the City to complete the Improvements. If the Lender elects to
complete the Improvements, any Hard Costs it expends shall, dollar for dollar, reduce the
Completion Amount.
8. Easements. In the event the City or the Lender undertakes the completion of the
Improvements, the Developer (and to the extent necessary the Lender) grants to the City and the
Lender open access to the Property and shall execute and deliver such temporary easements over
and across the entirety of the Property for the purpose of access and use for the completion of the
construction of the Improvements in accordance with this Agreement. To the extent requested by
the City and the Lender, written temporary construction easements in form acceptable to the City
and the Lender shall be executed by the Developer and filed of record. Nothing in this paragraph
shall reduce any rights of the Lender or obligations of the Developer under the Loan Documents.
9. Lender's Rights. Nothing in this Agreement shall affect any portion of the Lender's
collateral for the Loan or limit or impair the Lender's right to foreclose the same or deal with the
collateral as it elects in accordance with the Loan Documents.
10. Satisfaction of the City Requirements. The City agrees that the assurances and
covenants contained in this Agreement satisfy all requirements of the City with respect to
Developer's performance bond or other financial security in connection with the development of
the Property and the completion of the Improvements that are contained in the CIA or in any other
agreement relating thereto, and the City hereby accepts the assurances and covenants contained
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015
Page 4of17
herein in lieu thereof. To the extent the CIA irreconcilably conflicts with this Agreement, the
provisions of this Agreement shall control.
11. Termination. This Agreement shall terminate upon the earlier to occur of the
following: (a) acceptance by the City of the Improvements; (b) mutual written agreement of
all of the Parties; or(c)the reduction of the Completion Amount to zero. However, release of the
plat shall be governed by paragraph 12 hereof and termination pursuant to (b) or (c) of this
paragraph 11 shall not require the City to release the plat.
12. Final Plat. The Parties acknowledge and agree that the City shall hold the final plat
of the Property until the Improvements are completed and accepted by the City and all Hard Costs
contractors have been paid, less retainage. Upon acceptance by the City and receipt of evidence
from the Developer showing that all Hard Costs contractors have been paid, including but not
necessarily limited to lien waivers and bills paid affidavits, the City shall within a reasonable time
file the final plat for the Property in the Plat Records of the county where the Property is located.
The purpose of the City retaining the final plat of the Property as provided herein is to guarantee
the Developer's obligations under the CIA are completed.
13. Construction Contracts. Developer agrees to include in each Construction contract
that it enters into for the completion of the Improvements the following:
a.A statement that the City is not holding any security to guarantee any payment for work
performed on the Improvements;
b. A statement that the Property is private property and that same may be subject to
mechanic's and materialman's liens;
c.A requirement that each contractor contracting with the Developer release the City from
any claim that is related to the Property of the Improvements; and
d. A requirement that each contractor contracting with the Developer include in each
subcontract the statements contained in a., b., and c. above.
14. Miscellaneous.
A. Non-Assignment of Agreement. This Agreement may not be assigned by any of the Parties
without the prior written consent of all the other Parties.
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015
Page 5of17
B. Notice. Any notice required or permitted to be delivered under this Agreement shall be
deemed received on actual receipt by the appropriate party at the following addresses:
(i) Notice to the City shall be addressed and delivered as follows:
City of Fort Worth
Planning and Development Department
200 Texas Street
Fort Worth,Texas 76102
Attention: CFA Division
Janie Morales, Development Manager
Email: Janie.Morales@fortworthtexas.gov
Confirmation Number: 817-392-7810
and/or
Attention: CFA Division
Email: cfa@fortworthtexas.gov
Confirmation Number: 817-392-2025
With a copy thereof addressed and delivered as follows:
Richard A. McCracken
Office of the City Attorney
City of Fort Worth
200 Texas Street
Fort Worth,Texas 76102
Confirmation Number: 817-392-7611
(ii) Notice to the Developer shall be addressed and delivered as follows:
170 Northstar Ranch Developer, Inc. - Kim Gill
3045 Lackland Road
Fort Worth, Texas 76116
Email: kgill@sableholdings.com
(iii) Notice to the Lender shall be addressed and delivered as follows:
Simmons Bank, J. David Hassell
2200 West 7Tn Street, Suite 112
Fort Worth,Texas 76102, Loan Nq;
Email: David.Hassell@SimmonsBank.com
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015
Page 6of17
A party may change its address for notice upon prior written notice to the other parties pursuant to
the terms hereof.
C. Texas Law to Apply. This Agreement shall be construed under and in accordance with the
laws of the State of Texas.
D. Parties Bound. This Agreement shall be binding upon and inure to the benefit of the Parties
and their respective legal representatives, successors and assigns.
E. Legal Construction. In case any one or more of the provisions contained in this Agreement
shall for any reason is held to be invalid, illegal, or unenforceable in any respect, such
invalidity, illegality, or unenforceability shall not affect any other provision of this
Agreement, and this Agreement shall be construed as if such invalid, illegal, or
unenforceable provision had never been contained in this Agreement.
F. Prior Agreements Superseded. This Agreement constitutes the sole and only agreement of
the Parties with respect to the subject matter hereof and supersedes any prior
understandings or written or oral agreements among the Parties concerning the subject
matter hereof, provided, however, that this Agreement shall not supersede, amend or
modify any of the Loan Documents or any portion thereof.
G. Amendment. This Agreement may only be amended by a written instrument executed by
all of the Parties to his Agreement.
H. Headings. The headings that are used in this Agreement are used for reference and
convenience purposes only and do not constitute substantive matters to be considered in
construing the terms and provisions of this Agreement.
(REMAINDER OF PAGE INTENTIONALLY LEFT BLANK)
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 JLE
CFA Official Release Date:07.01.2015
Page 7of17
ACCORDINGLY,the City of Fort Worth, Developer and Lender have each caused this
instrument to be executed in quadruplicate in each entity's respective name by its duly
authorized signatories effective as of the date executed by the City's City Manager or his/her
designee.:
CITY OF FORT WORTH: DEVELOPER:
170 Northstar Ranch Developer, Inc.
Da a euruh'S4
Dana Bur411 pr13,202211:25 CDT)
Dana Burgdoff Kim Gill(Apr12,202214:38 CDT)
Assistant City Manager Name: Kimberly Gill
Title: President
Date: Apr 13,2022
Date: Apr 12,2022
Approved as to Form and Legality:
LENDER:
SIMMONS BANK
Richard A.--k-(Apr 13,202210:31 CDT)
Richard A. McCracken ���
Assistant City Attorney David Hassell(Apr 12,202215:55 CDT)
Name: J. David Hassell
ATTEST: Title: Market Executive
od�FORD d
7q���i`i`� GOOG�GIGG 0°°°° °°° p d
Jannette S.Goodall(Apr13,2022 13:17 CDT) ° Contract Compliance Manager:
a�° °o'p�d
�.�° 0
Jannette S. Goodall Avg g=o.
City Secretary �p o° °0 By signing, I acknowledge that I am the
�aa °°°°°°°°°° a� person responsible for the morning and
M&C: ��nEXAS-oA'
administration of this contract, including
Date: ensuring all performance and reporting
requirements.
EveG'�Ra6ert�a�6el�a,/�o-�
Evelyn obertr on behalf of(Apr 13,202209:03CDT)
Janie Scarlett Morales
Development Manager
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015 OFFICIAL RECORD
Page 8of17
CITY SECRETARY
FT.WORTH,TX
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015
Page 9of17
KIMBERLY GILL, the Guarantor of the Development Loan, is executing this Completion
Agreement for the sole purpose of acknowledging that advances that are made by the Lender
pursuant to this Completion Agreement shall be deemed to be advances that are made under the
Loan that shall be subject to and covered by the Loan Documents and the Guaranty Agreement
that was executed by KIMBERLY GILL.
GUARANTOR
By: Kim Gi H(Apr12,202214:38 CDT)
Name: Kimberly Gill
Title: President
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 JLE
CFA Official Release Date:07.01.2015
Page 10of17
List of Exhibits to the Completion Agreement
Attachment 1 —Changes to the Standard Completion Agreement
Exhibit A- Legal Description
Exhibit B - Approved Budget
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015
Page 11 of 17
ATTACHMENT"1"
Changes to Standard Completion Agreement
None
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 JLE
CFA Official Release Date:07.01.2015
Page 12of17
EXHIBIT A
WHEREAS 170 NORTHSTAR RANCH DEVELOPER,INC. is the sole owner of a 27.4478 acre
tract of land located in the Matthew Ashton Survey,Abstract No. 8, Tarrant County, Texas, said
27.4478 acre tract being a portion of the remainder of a called 402.614 acre tract of land conveyed
to 170 NORTHSTAR RANCH DEVELOPER, INC., by deed thereof filed for record in Tarrant
County Clerk's Instrument No. D219181265, Official Public Records, Tarrant County, Texas
(O.P.R.T.C.T.), Wise County Clerk's Instrument No. 201909720, Official Public Records, Wise
County,Texas, and Denton County Clerk's Instrument No. 2019-100295, Official Public Records,
Denton County Texas, said 27.4478 acre tract of land being more particularly described by metes
and bounds as follows:
BEGINNING at a 1/2 inch iron rod with a cap stamped"RPLS 4818" found at a northeast property
corner of the said 402.614 acre tract, same being the southeast property corner of a called 66.901
acre tract of land conveyed to John P. Wilson, by deed thereof filed for record in Tarrant County
Clerk's Instrument No. D217049752, O.P.R.T.C.T.;
THENCE South 55°50'38" East, over and across the said 402.614 acre tract, a distance of 545.64
feet to an iron rod with a cap stamped"SPOONER 5922" set(hereinafter referred to as an iron rod
set) on the north right-of-way line of Northstar Parkway (being a variable width public right-of-
way as shown on and dedicated by the plat thereof filed for record in Tarrant county Clerk's
Instrument No. D220241646, O.P.R.T.C.T.), and being at the beginning of a non-tangent curve to
the right having a radius of 1,225.00 feet;
THENCE along the said north right-of-way line the following courses and distances:
With said curve to the right, an arc length of 161.30 feet, and across a chord which bears South
40'18'11" West, a chord length of 161.18 feet to an iron rod set;
North 89°52'21" West, a distance of 13.94 feet to an iron rod set;
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015
Page 13of17
North 44°03'14" West, a distance of 4.10 feet to an iron rod set;
South 45°56'46" West, a distance of 60.00 feet to an iron rod set;
South 44°03'14" East, a distance of 4.10 feet to the most northerly lot corner of Lot 1X, Block 5
of said Northstar Parkway, and being at the beginning of a non-tangent curve to the right having a
radius of 1,215.00 feet;
THENCE departing the said right-of-way line and along the northerly lot line of said Lot 1X,Block
65,with said curve to the right, an arc length of 930.63 feet, and across a chord which bears South
69°18'14"West, a chord length of 908.05 feet to an iron rod set at the most westerly corner of said
lot 1X, Block 65;
THENCE departing the said lot line and along the said right-of-way line the following courses and
distances:
North 02°39'42" East, a distance of 4.10 feet to an iron rod set;
North 87°20'18" West, a distance of 60.00 feet to an iron rod set;
South 02°39'42" West, a distance of 4.10 feet to an iron rod set at the most easterly lot corner of
Lot 1X, Block 64 of said Northstar Parkway, and being at the beginning of a non-tangent curve to
the right having a radius of 1,215.00 feet;
THENCE departing the said right-of-way line and along the northeasterly lot line of said Lot 1X,
Block 64,with said curve to the right, an arc length of 789.36 feet, and across a chord which bears
North 67°18'41" West, a chord distance of 775.55 feet to an iron rod set at the most northerly lot
corner of said Lot 1X, Block 64;
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015
Page 14of17
THENCE along the said right-of-way line the following courses and distances:
North 42°42'56" East, a distance of 4.10 feet to an iron rod set;
North 47°17'04" West, a distance of 60.00 feet to an iron rod set;
South 42°42'56" West, a distance of 4.10 feet to an iron rod set at the most southerly southeast lot
corner of Lot 1X, Block 62 of said Northstar Parkway, being at the beginning of a non-tangent
curve to the right having a radius of 1,215.00 feet;
THENCE departing the said right-of-way line, along the said lot line of Lot 1X, Block 62 the
following courses and distances:
With said curve to the right, an arc length of 340.02 feet, and across a chord which bears North
375 F09" West, a chord length of 338.91 feet to an iron rod set;
North 29°50'08" West, a distance of 133.32 feet to an iron rod set;
North 29°50'50" East, a distance of 25.83 feet to an iron rod set;
North 89°31'32" East, a distance of 396.81 feet to an iron rod set;
North 00°28'28" West, a distance of 30.00 feet to to an iron rod set on a north property line of the
said 402.614 acre tract, same being the south property line of the aforesaid 66.901 acre tract, from
which a 5/8 inch iron rod with a cap (illegible) found at the southwest property corner of said
66.901 acre tract bears South 89°31'32" West, a distance of 439.27 feet;
THENCE North 89°31'32"East,along the said property lines, a distance of 1,243.74 to the POINT
OF BEGINNING of the herein described tract of land.
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015
Page 15of17
The hereinabove described tract of land contains a computed area of 27.4478 acres (1,195,624
square feet) of land, more or less.
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015
Page 16of17
EXHIBIT B
APPROVED BUDGET
Section I
Water $459,662.00
Sewer $471,375.40
Subtotal $931,037.40
Section II
Interior Streets $923,579.65
Stonn Drains $567,539.00
Subtotal $1,491,118.65
Section III
Street Lights $207,966.15
Sub-total $207,966.15
TOTAL $2,630,122.20
City of Fort Worth,Texas
Standard Completion Agreement—Lender-Funded Revised 09.07.2017 ME
CFA Official Release Date:07.01.2015
Page 17of17