HomeMy WebLinkAboutOrdinance 25454-04-2022 ORDINANCE NO.25454-04-2022
AN ORDINANCE ADJUSTING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER&SEWER CAPITAL PROJECT 2018 FUND,
BY INCREASING RECEIPTS AND APPRPRIATIONS IN THE LAKE
ARLINGTON LIFT STATION AND FORCE MAIN(CITY PROJECT NO.100995)
IN THE AMOUNT OF $323,249.00 AND DECREASING RECEIPTS AND
APPROPRIATIONS IN THE UNSPECIFIED PROJECT (CITY PROJECT NO.
UNSPEC)) BY THE SAME AMOUNT; PROVIDING FOR A SEVERABILITY
CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;
AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2021-2022 in the
Budget of the City Manager,there shall also be adjusted estimated receipts and appropriations in the Water&
Sewer Capital Project 2018 Fund,by increasing receipts and appropriations in the Lake Arlington Lift Station
and Force Main (City Project No.100995) in the amount of $323,249.00 and decreasing receipts and
appropriations in the UNSPECIFIED PROJECT(CITY PROJECT NO.UNSPEC)by the same amount.
SECTION 2.
That should any portion,section or part of a section of this ordinance be declared invalid,inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 25073-09-2021 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
annO`tO S. aoodali
DBlack(Apr 13,2022 22:09 CDT) Jannette S.Goodall(Apr 14,2022 07:13 CDT
Douglas W.Black Jannette S.Goodall F�R
Assistant City Attorney City Secretary ����• "' ' Tti
ADOPTED AND EFFECTIVE:April 12,2022 ;_
MAYOR AND COUNCIL COMMUNICATION MAP
60LALSFMA5-FNI
xr1i n �r�� ,.�iati h 0 � Nm
Tr - } (
a a¢�" a }
tR �H7014,
Al s
-" mmisq F- RAMEY
H Yrpcn, . �o' �� ELIZABETH RDA J `
x�—
E
ui
co w
J 'shy yx ii ..
UJ
ff EASTCAND ST9,r> Amp
^�
AYSON ST
p / LAKE
uj
ARDEMAN ST ARLINGTON p r{
WILBARGERyST ,, � x -ilk_!k
t WIL'BARGERST- L_
up
FORCE '.
FORT WORTI , '�Cb MAIN
MARTIN ST Jill
N'
+� SUN VAL'L'EY,DR; '-0 p -
•�71
j.V'"` (ia.-- 10
=0
1sr
Mi
LIFT
�! —20` STATION
— ` reS3 ..rr
INV
r FREEMAN DALE �F`
FORT WORTH hJi � r
City of Fort Worth,Texas
Mayor and Council Communication
DATE: 04/12/22 M&C FILE NUMBER: M&C 22-0290
LOG NAME: 60LALSFMA5-FNI
SUBJECT
(CD 5 and City of Kennedale)Authorize Execution of Amendment No.5 in the Amount of$323,249.00 to an Engineering Agreement with Freese
and Nichols,Inc.for the Lake Arlington Lift Station and Force Main,and Adopt the Attached Appropriation Ordinance to Effect a Portion of Water's
Contribution to the Fiscal Years 2022-2026 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Amendment No.5,in the amount of$323,249.00,to City Secretary Contract No.50312,an engineering agreement
with Freese and Nichols, Inc.for the Lake Arlington Lift Station and Force Main project for a revised contract amount of$4,622,381.00;and
2. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the Water&Sewer Capital Project 2018
Fund by increasing estimated receipts and appropriations in the amount of$323,249.00 for Lake Arlington Lift Station and Force Main(City
Project No.100995)and decreasing estimated receipts and appropriations in the Unspecified project(City Project No.UNSPEC)by the
same amount to effect a portion of Water's contribution to the Fiscal Years 2022-2026 Capital Improvement Program.
DISCUSSION:
On January 30,2018,Mayor and Council Communication(M&C)C-28566 authorized an engineering agreement with Freese and Nichols, Inc.,
(City Secretary Contract No.50312)in the amount of$3,099,361.00 for the preparation of plans and specifications for the Lake Arlington Lift
Station and Force Main project.The agreement was subsequent revised by Amendment No. 1 in the amount of$229,755.00(M&C C-29067,
March 19,2019)that provided for the design of 1,000 linear foot aerial crossing of the force main across Lake Arlington additional geotechnical
investigations at 8 locations along the force main;Amendment No.2 in the amount of$366,004.00(M&C C-29178,July 25,2019)that provided
for the preparation of plans and specifications for additional tunneling design,archeological survey,additional survey along Quail Road,lead
testing along lift station access road and design for erosion improvements on Village Creek Tributary near Salt Rd;Amendment No.3 in the
amount of$211,344.00(M&C 20-0137, March 3,2020)that provided for preparation of additional temporary and permanent easement
documents, urban forestry permit application,and additional subsurface utility engineering(SUE)services,and Amendment No.4 in the amount of
$392,668.00(M&C 20-0460,June 32,2020)that provided for resident project representation(RPR)and start up assistance on Lake Arlington Lift
Station.
Amendment No.5 will provide for additional easement acquisition assistance, plan redesigns,aerial crossing design and additional resident
project representation support.
It is the practice of the Water Department to appropriate its Capital Improvement Program(CIP)plan throughout the fiscal year as projects
commence,additional funding needs are identified,and to comply with bond covenants.The actions in the M&C will appropriate funds in support
of the Water's portion of the City of Fort Worth's Fiscal Years 2022-2026 Capital Improvement Program,as follows:
60LALSFMA5-FNI
Capital Fund
Budget Revised
FY2022 CIP Change
Name Project Name Appropriations Authority (Increase/ FY2022
Decrease) Budget
W&S Capital 100995—Lake
Project 2018- Arlington,FM,LS $ 0.00 This M&C $323,249.00 $323,249.00
Fund 56014 and SS
Funding for the Lake Arlington Lift Station and Force Main project is depicted in the table below:
Existing
FUND Additional Appropriationsifroject Total'`
Appropriations
W&S Capital Project 2018- $9,306,709.00 _ $323,249.00 $9,629,958.00
Fund 56014
Fund 560al Project 2020A- $11,064,526.00 $0.00 $11,064,526.00
Project Total $20,371,235.00 $323,249.00$20,694,484.00
*Numbers rounded for presentation purposes.
Funding is currently available in the Unspecified-All Funds project within the W&S Capital Project 2018 Fund for the purpose of funding the Lake
Arlington,FM, LS and SS project.
Business Equity: Freese and Nichols, Inc., is in compliance with the City's BDE Ordinance by committing to 20.81 percent SBE participation on
this project.The City's SBE goal on this project is 10 percent.
The project is located in COUNCIL DISTRICT 5 and CITY OF KENNEDALE.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Unspecified-All Fund project within the W&S Capital Proj 2018 Fund and
upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds will be available in the W&S Capital
Proj 2018 Fund for the Lake Arlington,FM, LS and SS project to support the approval of the above recommendations and execution of the
amendment to the agreement and contract.Prior to an expenditure being incurred,the Water Department has the responsibility of verifying the
availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating_Business Unit Head: Chris Harder 5020
Additional Information Contact: Pratima Poudyal 6149