HomeMy WebLinkAboutContract 57092-CO1 CSC No.57092-COI
FORT WORTH. City of Fort Worth
Change Order Request
Project Name Intersection Improvements at Bonds Ranch&FM 156 City Sec# 57092
Client Project#(s) 101009-2
Intersection improvements including widening Bond Ranch Rd to provide left turn lanes onto Farm to Market Road 156,improve raddi for northbound to
Project Description eastbound traffic,minor storm Brian improvemnets and a new traffic signal with pedestrain access.
Contractor Texas Materials Group,Inc.dba TexasBit Change Order# 1 Date 4/14/2022
City Project Mgr. Brendan McInnes,PE City Inspector Habte Taezaz
Contract Time
Dept. TPW Totals (CD)
Original Contract Amount $1,180,676.20 $1,180,676.20 300
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process) $0.00
Contract Cost to Date $1,180,676.20 $1,180,676.20 300
Amount of Proposed Change Order $24,220.00 $24,220.00
Revised Contract Amount $1,204,896.20 $1,204,896.20 300
Original Funds Available for Change Orders $24,220.00 $24,220.00
Remaining Funds Available for this CO $24,220.00 $24,220.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 2.05%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25916) $1,475,845.25
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Adding a powder coat finish to all signal and pedestrain pole equipment.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements.
Contractor's Company Name I Contractor(Name) I Contract Signature I Date
TexasBit Adam Newsom I.4da ,/ "50in 04/19/22
Inspector/Inspection Supervisor Date Project and Contract Compliance Manager Date
04/19/22 Sae��s M�/ er I'-- 04/19/22
w ion �wos,z�z,a—J
Program Manager Date Senior Capital Project Officer Date
.c..a zzzo„0913�on 04/22/22 � 04/22/22
Assistant Director(Dept) Date Director,Contracting Department(Dept) Date
n p 04/22/22 W' 0 04/24/22
Date Assists erP Date
.z�z,z3s�n 04/25/22 04/25/22
Council Action(if required)
M&C Number M&C Date Approved
ATTEST:
air pO`°°ppO °°°O
Jannette Goodall,City Secretary �co Oaf
d
p~°
�voo o=� OFFICIAL RECORD
P °° °°*d
dd °°°°°°°°°° p CITY SECRETARY
aatTnEXASoap FT.WORTH,TX
FORTWORTH City of Fort Worth
I---- Change Order Additions
Project Name Intersection Improvements at Bonds Ranch&FM 156 City Sec# 57092
Cl ient Project# 101009-2
Contractor Texas Materials Group,Inc.dba TexasBit PM Brendan McInnes,PE Inspector Habte Taezaz
Change Order Submittal# O1 Date 4/14/2022
ADDITIONS
ITEM DESCRIPTION DEPT City Unit Unit Cost Total
Ins I rt biU Hi Am(s)lrm um Powder Coat Black
96 Ins m s rm um How der oat ac TPW 2.00000000 EA 548,107.00
9999.0019 Ped Pole Assembly Powder Coat Black TPW 3.00000000 EA
TPW S148,702.35
Sub Total Additions S
Change Order Additions Page 2 of 4
Foa_ T�H City of Fort Worth
Change Order Deletions
Project Name Intersection Improvements at Bonds Ranch&FM 156 City Sec# 57092
Client Project# 101009-2
Contractor Texas Materials Group,Inc.dba TexasBit PM Brendan McInnes,PE Inspector Habte Taezaz
Change Order Submittal# O1 Date 1 4/14/2022
DELL I IUNS
y Unit Unit Cost I o a
Ins Trf SO PI Arr s)lrm um
Ins I rt SiO HI Am(s)lrm um
Ped Pole Assembly
TPW $124,482.35
�iub I otal Deletions
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total 1 $0.00
TEXAS Texas Bit TEXAS
A CRN COMPANY A CRN COMPANY
PROPOSED CHANGE ORDER# 1
OWNER: City of Fort Worth PROJECT MANAGER: Brendan McInnes
attn:Brendan McInnes
Address:200 Texas St PROJECT: CPN 101009-2 Intersection Improvements at
Fort Worth,Texas 76012 Bonds Ranch Road&FM 156
DATE: April 12,2022
DESCRIPTION OF CHANGE AND/OR EXTRA WORK: SIGNAL POLE POWDER COATING
UNIT
ADD: Description Quantity Unit PRICE AMOUNT
CO-1 Powder Coat(ONLY)Trf Sig PI Am(s)1 Arm(48')Lum 2.00 EA $ 3,210.00 $ 6,420.00
CO-1 Powder Coat(ONLY)Trf Sig PI Am(s)1 Arm(55')Lum 2.00 EA $ 7,250.00 $ 14,500.00
CO-1 Powder Coat(ONLY)Ped Pole Assembly 3.00 EA $ 1,100.00 $ 3,300.00
UNIT
DEDUCT: Description Quantity Unit PRICE AMOUNT
Change Order Add $ 24,220.00
Change Order Deduct $ -
Total Change Order Amount= $ 24,220.00
All other items and conditions of our contract with you remain the same and this order
is made a part thereof.
Kindly signify your acceptance and approval of this agreement by signing and returning
to us the enclosed copy.
ACCEPTED BY OWNER: Submitted By:
Texas Bit
Texas Materials Group, Inc-a CRH Company
By: By: -46 V►?�.�.SD/rL
Date: Adam Newsom
Project Manager
adam.newsom(a)texas bit.com
214 912 4282