HomeMy WebLinkAboutContract 55162-CO1 CSC No. 55162-COl
FOR�T WORTH City of Fort Worth
Change Order Request
Project Name 2021 Resurfacing Project City Sec# 55162
Client Project#(s) 102864
Project Description Pulverization of existing street and 3 inch asphalt overlay at various locaitons
Contractor Peachtree Construciton Ltd Change Order# 1 Date 4/1/2022
City Project Mgr. Tariqul Islam City Inspector Robert Riley
Contract Time
Dept. TPW Totals (CD)
Original Contract Amount $1,563,752.00 $1,563,752.00 230
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,563,752.00 $1,563,752.00 230
Amount of Proposed Change Order $54,481.20 $54,481.20 30
Revised Contract Amount $1,618,233.20 $1,618,233.20 260
Original Funds Available for Change Orders $100,000.00 $100,000.00
Remaining Funds Available for this CO $100,000.00 $100,000.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 3.48%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,954,690.00
JUSTIFICATION(REASONS)FOR CHANGE OR DE
This change order is to add$54,481.20 to contract#55162 with a revised contract amount of$1,618,233.20. The rehabilitaiton work for Rendon Rd from Shelby Rd to S.City
limit and Rockwood Park Dr from White Settlement Rd to Lakewood Dr and 30 addtional calendar days have been added to this contract through M&C 22-0147,dated 3/8/2022.
These two streets need new pavement markings after repaving which were not originally included in this contract.The quantity of item for this work has been determined based
on proposed pavement marking plan provided by traffic management.Staff considered contractor's quote for this proposed pavement marking item is reasonable.The quote is
attached to this document as reference.Adequate fund is availabe in this project to cover the change order cost.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements.
Contractor's Company Nam ontractor(Name) Contract Signaturm Date
Peachtree Construciton Ltd. Brendan Taylor 04/22/22
Inspector/Inspection Super vi Da Project and Contract Compliance Manager Date
04/15/22 AIW 04/15/22
Program Manager Date Senior Capital Project Officer Date
Omar Elba alAti 04/25/22 04/25/22
oDe t) Date JjNJALContracting Department(Dept) Date
04/25/22 04/26/22
ow z �n
ssistant City Attorney Date Assistant City Manager Date M� 04/26/22 04/28/22
DBI
Council Ac ion require
M&C Number M&C Date Approved 0
ATTEST aaala/L A��FOI;p��a�
� 0 O!°°°°°°°°oo- - OFFICIAL RECORD
Jannette Goodall,City Secretary P�o° ° d
!=o o� CITY SECRETARY
00o o=0
o a* FT.WORTH, TX
�d °
oO000000° ,d
an nEXlo'!
FORT WORTH City of Fort Worth
Change Order Additions
Project Name 2021 Resurfacing Project City Sec# 55162 ###
Client Project# 102864
Contractor Pulverization and asphalt overlay at various locaitons PM Tariqul Islam Inspector Robert Riley
Peachtree Construciton Ltd O1 Date 4/1/2022 4/1/2022
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
45 6 inch solid white/yellow spray thermo (90 mil.) TPW 23,000.00000000 LF $2.01 $46,230.00
46 8 inch solid white/yellow spray thermo (90 mil.) TPW 175.00000000 LF $2.65
47 18 inch solid yellow spray thermo (90 mil.) TPW 166.00000000 LF $11.79 $1,957.14
48 24 inch solid extrude thermo (125 mil.) TPW 54.00000000 LF $16.39
49 4"reflective marker,type II-A/A TPW 167.00000000 EA $5.00 $835.00
50 4"reflective marker,type II C-R TPW 9.00000000 EA $5.00
51 Thermo preformed(125 mil.)single head straight/curved arrow TPW 8.00000000 EA $316.25 $2,530.00
52 Thermo preformed(125 mil.)word"ONLY" TPW 1.00000000 EA $373.75
53 Thermoplastic Preformed(125 mil.)(36X24)Yield Symbol TPW 13.00000000 EA $51.75 $672.75
54 Thermoplastic Yeild Triangle(125 mil.)Symbol TPW 1.00000000 EA $488.75
TPW $54,481.20
Sub Total Additions $54,481.20
Change Order Additions Page 2 of 4
FOR_ r � City of Fort Worth
Change Order Deletions
Project Name 2021 Resurfacing Project City Sec# 55162 ###
Client Project# 102864
Contractor PM Tariqul Islam Inspectof Robert Riley
Peachtree Construciton Ltd O1 Date 4/1/2022 4/1/2022
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
TPW $0.00
Sub Total Deletions $0.00
Change Order Deletions Page 3 of 4
MISBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
2021 Resurfacing Project
102864
Pulverization and asphalt overlay at various locai
Total $0.00
Peachtree Construciton Ltd
Previous Change Orders
Co# DATE AMOUNT
Total $0.00
PEACHTRI E E CONSTRUCTION
580I Park Vista Cir. •KeIler, TX 76244 • (817) 741-4658 • Fax (817) 741-4648
April 05, 2022
City of Fort Worth TPW
Attn: Tariqul Islam
Re: 102864 Request Pavement Marking Pricing
Mr. Islam,
Regarding your request for pricing, please see the items below:
6 inch solid white/yellow spray Thermo $2.01/LF
8 inch solid white/yellow spray Thermo $2.65/1-F
18 inch solid yellow spray Thermo $11.79/1-F
24 inch White Thermo Stripe $16.39/LF
4" reflective marker, type II-A/A—per EA $5.00/EA
4" reflective marker, type II C-R—per EA $5.00/EA
Thermo preformed (125 mil.) single head straight/curved arrow—per EA $316.25/EA
Thermo preformed (125 mil.) word "ONLY"—per EA $373.75/EA
Thermo Yield Triangles $51.75/EA
Thermo "YIELD" Word $488.75/EA
Sincerely,
Brendan Taylor
Peachtree Construction
Specializing in HMAC Paving
M&C Review Page 1 of 2
Official site of the City of Fort Worth,Texas
CITY COUNCIL AGENDA FT NVO TIi
Create New From This M&C
REFERENCE **M&C 22- 20202021 RESURFACING
DATE: 3/8/2022 NO.: 0147 LOG NAME: PROJECT CHANGE ORDER
1
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: (CD 7 and CD 8) Authorize Execution of Change Order No. 1 to City Secretary Contract
No. 55162 with Peachtree Construction Ltd., to Remove Paving of Redbud Lane, Slate
Street and Mockingbird Lane and Add Sections of Rockwood Park Drive and Rendon
Road at No Additional Contract Cost and Authorize Additional 30 Calendar Days for
Completion of the Contract
RECOMMENDATION:
It is recommended that the City Council authorize execution of Change Order No. 1 to City
Secretary Contract No. 55162 with Peachtree Construction Ltd., to remove paving of Redbud
Lane, Slate Street and Mockingbird Lane and add section of Rockwood Park Drive and Rendon
Road at no additional cost and authorize additional 30 calendar days for completion of the
contract.
DISCUSSION:
On December 15, 2020, Mayor and Council Communication (M&C 20-0947) awarded City Secretary
Contract No. 55162 in the amount of$1,563,752.00 to Peachtree Construction Ltd., for 2021
Resurfacing Project (City Project No. 102864) on approximately six lane miles of eight street
segments including Redbud Lane, Slate Street and Mockingbird Lane.
The street segments originally included in this project were initially cleared of utility
conflicts; however, prior to starting construction the City was notified that new franchise utility
projects on Redbud Lane, Slate Street and Mockingbird Lane are upcoming. Change Order No. 1
will remove these three street segments and add Rockwood Park Drive from White Settlement
Road to Lakewood Drive and Rendon Road from Shelby Road to south City limit. This Change
Order does not require an increase in the contract amount as sufficient funds are available in the
contract. To complete this additional work, it is requested that the contract time be extended by 30
calendar days.
Pay-as-you-go funding is budgeted in the TPW Highway & Streets Department's General Capital
Projects Fund for the purpose of funding the 2021 Resurfacing Project, as appropriated.
The project is located in COUNCIL DISTRICTS 7 and 8.
This contract legally does not require City Council approval.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that approval of the recommendation will have no material effect on
City funds.
TO
Fund Department Account Project Program Activity Budget Reference# Amount
ID ID Year (Chartfield 2)
FROM
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=29699&councildate=3/8/2022 3/9/2022
M&C Review Page 2 of 2
' Fund ' Department Account Project Program Activity Budget Reference# Amount
ID ID Year (ChartField 2)
Submitted for City Manager's Office by: Dana Burghdoff(8018)
Originating Department Head: William Johnson (7801)
Additional Information Contact: Monty Hall (8662)
ATTACHMENTS
201029 MBE Compliance Memo - Peachtree Const - 2021 Resurfacing Proiect.pdf (CFW
Internal)
Council Map01 Change Order 1 CPN102864.pdf (Public)
Council Map02_Change Order 1_CPN102864.pdf (Public)
FID Table 2021 Resurfacing Proiect.xlsx (CFW Internal)
Form 1295 CPN 102864.pdf (CFW Internal)
SAM search Results_Peachtree.pdf (CFW Internal)
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=29699&councildate=3/8/2022 3/9/2022