HomeMy WebLinkAboutOrdinance 25482-04-2022 Ordinance No 25482-04-2022
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER AND SEWER BOND 2017A FUND IN THE AMOUNT OF $405,067.00, FROM
AVAILABLE FUNDS, FOR THE PURPOSE OF FUNDING THE CHURCHILL ROAD
WATER AND SANITARY SEWER IMPROVEMENTS PROJECT (CITY PROJECT NO.
100888); PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE
CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH;AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2021-2022 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Water
and Sewer Fund in the amount of$405,067.00,from available funds, for the purpose of funding the Churchill
Road Water and Sanitary Sewer Improvements project (City Project No. 100888).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion orjudgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 25073-09-2021 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
0-1A zanneff -S �artr7�CG
Mack(Apr 29,202217:03 CDT) Jannette S.Goodall(May 2,2022 07:21 CDT)
Douglas W. Black Jannette S. Goodall
Assistant City Attorney City Secretary
ORT lrvG.
ADOPTED AND EFFECTIVE: April 26, 2022
'�XPS
# �Ilk �:=�� 3 „a � � � 4�i�i�`+ � .;• II ; �`- }'.
Aad
�. all
10
ro
lk
jr
ilk
q. jk 61. x 11P
PIN a
MW
don
dw
yaw T11
ILL
#3 � � �•
c L 4 , }+rRFT'Ji� 44y`
CIPT
b.
� `� to �I +� � s �� �• -� � � ,�- y.. I
�Ja�•1" a■rw � a�,rt ,r,�
UrAW '16'Mill' dill
•- F a CIF '� "' WF
'' � ' �
46
may_ilY/h � !- * FL •i i T # ,f k + F : f t
Ik
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 04/26/22 M&C FILE NUMBER: M&C 22-0318
LOG NAME: 60CHURCHILLROADCO2-FLOWLINE
SUBJECT
(CD 2 and City of River Oaks)Authorize Execution of Change Order No.2 in the Amount of$405,066.09 and the Addition of 62 Calendar Days to
a Contract with Flow-Line Construction, Inc.for the Churchill Road Water and Sanitary Sewer Improvements for a Revised Contract Amount of
$8,564,726.79,and Adopt Attached Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2022-2026 Capital
Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Change Order No.2, in the amount of$405,066.09 and the addition of 62 calendar days,to City Secretary Contract
No.52902,a contract with Flow-Line Construction, Inc.for the Churchill Road Water and Sanitary Sewer Improvements project for a revised
contract amount of$8,564,726.79-1 and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water&Sewer Bond 2017A Fund, in
the amount of$405,067.00,from available funds,for Churchill Road Water and Sanitary Sewer Improvements(City Project No.100888)to
effect a portion of Water's contribution to the Fiscal Years 2022-2026 Capital Improvement Program.
DISCUSSION:
On September 24,2019,Mayor and Council Communication (M&C) 19-0197 authorized a contract with Flow-Line Construction, Inc., (City
Secretary Contract No.52902)in the amount of$8,136,955.00 for the Churchill Road Water and Sanitary Sewer Improvements Project.The
agreement was subsequently revised by Change Order No. 1 with a net total amount of$22,705.70, administratively authorized on September 3,
2021,that provided for installation of special levee backfill material, relocation of a manhole at the levee and an additional storm water pollution
prevention plan.
Change Order No.2 will provide for the installation of additional backfill material that was installed at the levee crossing as required by the United
States Army Corps of Engineers,the installation of 8, 16, and 24-inch ductile iron pipe encasing pipes instead of 8, 16,and 24-inch PVC pipe
encasing pipes as specified at the time of bid opening, additional excavation and backfill of bore pits in order to clear a gas main conflict, and
additional backfill material that was necessary on the project due to unstable material that was encountered during construction.
Staff has reviewed and verified the quantities for the additional work under this Change Order No.2.Additionally,to complete this work,staff
recommended that the contract time to be extended by 62 calendar days.
It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year as projects commence,additional funding needs
are identified,and to comply with bond covenants.The actions in the M&C will appropriate funds in support of the Water's portion of the City of
Fort Worth's Fiscal Years 2022-2026 Capital Improvement Program,as follows:
60CHURCHILLROADCO2-FLOWLINE
I Budget
Capital Fund Project ( FY2022 CIP Change I Revised
Name Name Appropriations Authority (Increase/ FY2022
Decrease) I
Budget
56011 —Water 100888—
&Sewer Bond Churchill RD $ _ This M&C $405,067.00'$405,067.00
2017A Fund WL&SSImprov
Funding for the Churchill Road Water and Sanitary Sewer Improvements project is depicted in the table below:
Existing Additional
Fund Project Total*
Appropriationsi Appropriations
W&S Capital
Projects—Fund $35,400.00 $0.00 $35,400.00
56002
Water and Sewer
Bond 2017A-Fund $653,804.00 $405,067.00 $1,058,871.00
56011
W&S Water&Sewer
Bond 2020A-Fund $8,903,938.00 $0.00$8,903,938.00
56017
Project Total $9,593,142.00 $405,067.00 J:01.
*Numbers rounded for presentation purposes.
Funding is currently available in the Unspecified-All Funds project within the Water&Sewer Bond 2017A fund for the purpose of funding the
Churchill RD WL&SS Improv project.
Business Equity: Flow-Line Construction, Inc.agrees to maintain its initial MM/BE commitment of four percent that it made on the original
contract and extend and maintain that same MM/BE commitment of four percent to all prior change orders up to and inclusive of this Change
Order No.2.Therefore Flow-Line Construction,Inc.remains in compliance with the City's MM/BE Ordinance and attests to its commitment by its
signature on the Acceptance of Previous MM/BE Commitment form executed by an authorized representative of its company.
The project is located in COUNCIL DISTRICT 2 and CITY OF RIVER OAKS.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Unspecified-All Funds project within the Water&Sewer Bond 2017A
Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds will be available in the Water
&Sewer Bond 2017A Fund for the Churchill RD WL&SS Improv project to support the approval of the above recommendation and execution of
the change order. Prior to an expenditure being incurred,the Water Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating_Business Unit Head: Chris Harder 5020
Additional Information Contact: Lawrence Hamilton 2626