HomeMy WebLinkAboutContract 52582-R2 CSC No.52582-R2
CITY OF FORT WORTH
SECOND RENEWAL OF AGREEMENT
WHEREAS, this SECOND RENEWAL of City Secretary 952582, as renewed and
amended,is between the City of Fort Worth,("CITY"),and Shield Engineering Group,PLLC
("CONSULTANT"), for the PROJECT generally described as: Staff Extension Services in
Managing Transportation and Public Works Stormwater Capital Projects; and
WHEREAS, the original agreement, authorized by M&C C-29150, provided for
renewals and was renewed in the original amount authorized under Ordinance 24161-04-
2020 and ratified by M&C 20-0530 (8/11/2020); and
WHEREAS, the original agreement in the amount of$1,100,000.00, as renewed,
was amended to provide for additional funds in the amount of $1,300,000.00 for a
revised contract amount of $2,400,000.00 authorized under Ordinance 24161-04-2020
and ratified by M&C 20-0530 (8/11/2020); and
WHEREAS, Staff has determined it is necessary to renew the agreement, as
renewed and amended; and
WHEREAS, sufficient funds for this renewal have been appropriated;
NOW, THEREFORE, it is agreed by the CITY and CONSULTANT as follows:
Article I
The Scope of Services as set forth in the original agreement has not changed.
Article II
The CONSULTANT's compensation for this SECOND RENEWAL shall be
an amount not to exceed $2,400,000.00, which staff deems fair and reasonable for the
renewal and scope of services.
EXECUTED and EFFECTIVE as of the date subscribed by the City's designated
Assistant City Manager.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Second Renewal of Agreement CS#52582 Page 1 of 2
Shield Engineering Group
APPROVED:
City of Fort Worth Shield Engineering Group,PLLC
Dana Burg hdoff(A r29,20221 :38 CDT) c.
Dana Burghdoff J n-Marie Alexander,P.E.
Assistant City Manager COO
DATE: 04/29/22 DATE: �l �13 /zGz 2 -
APPROVAL RECOMMENDED:
Zl-)A L- SaL
William Johnson(A 29,2022 05:32 CDT)
William Johnson
Director, Transportation/Public Works Department
APPROVED AS TO FORM AND LEGALITY:
Form 1295: 2022-842889
W-A M&C: 22-0160
DBlack(Apr 29,202217:09 CDT) Date: 3/8/2022
Douglas W. Black
Sr.Assistant City Attorney
ATTEST:
��*0 -F�RrlyaaO
Tgnnette S. Goo�gll 0.o %00 o
JannetteS.Goodall(May 4,202209:14CDT) �vo00=d
Jannette S. Goodall ���'� o
O000OQo b
City Secretary Gall nEXASoA
Contract Compliance Manager:
By signing, I acknowledge that I am the
person responsible for the monitoring and
administration of this contract, including
ensuring all performance and reporting
requirements.
Linda Young OFFICIAL RECORD
Engineering Manager CITY SECRETARY
FT. WORTH, TX
Second Renewal of Agreement CS#52582 Page 2 of 2
Shield Engineering Group
SHIELD
ENGINEERING GROUP
2022 HOURLY RATE SCHEDULE
Principal / Director $249
Sr. Project Manager $221
Project Manager $197
Senior Professional Engineer $188
Professional Engineer $165
EIT II $136
EIT I $103
Designer $140
CAD Drafter $110
Support/ Admin $ 95
Senior RPLS $210
RPLS $165
GIS Analyst $125
SIT $125
Survey Technician $115
Party Chief $115
Survey Crew Member $ 70
Hourly Rate Schedule as of the date of this contract is subject to change without notice.
1600 West 7th Street, Suite 200, Fort Worth, TX 76102 • 817.810.0696
info@segpllc.com . www.SHIELDENGINEERINGGROUP.com
TBPE FIRM #F-11039 • TBPLS FIRM #10193890
SHIELD
ENGINEERING GROUP
CPM 2023 HOURLY RATE SCHEDULE
Sr. Project Manager $230
Project Manager $205
Professional Engineer $172
EIT II $141
EIT I $107
Hourly Rate Schedule as of the date of this contract is subject to change without notice.
1600 West 7th Street, Suite 200, Fort Worth, TX 76102 • 817.810.0696
info@segpllc.com . www.SHIELDENGINEERINGGROUP.com
TBPE FIRM #F-11039 • TBPLS FIRM #10193890
SHIELD
ENGINEERING GROUP
April 14, 2022
Linda S. Young, PE, PMP
Program Manager, TPW Capital Delivery
City of Fort Worth
200 Texas Street
Fort Worth, TX 76102
RE: City of Fort Worth Stormwater Capital Project Management— Renewal 2
CSN 52582-NA2
Dear Ms. Young,
Shield Engineering Group, PLLC is pleased to submit the following services to renew the
contract shown above per the attached Level of Effort Spreadsheets. Additionally, the new
contract will be amended in the amount of$2,000,000 for a revised contract amount of
$7,900,000. Shield plans to provide Senior Project Managers, Project Managers, EIT 2, and EIT
1 services.
Original contract $1,100,000
Renewal 1 $1,100,000
Amendment 1 $2,400,000
Renewal 2 $2,400,000
Amendment 2 $2,000,000
Revised contract $7,900,000
Please see the attached Level of Effort spreadsheet which includes the assumptions and
estimations for the hourly efforts.
Please feel free to contact me with any questions or comments.
Sincerely,
Jean-Marie Alexander, P.E.
COO
Shield Engineering Group, PLLC
Attachments: Attachment B LOE for CPM amendment and renewal 1
1600 West 7th Street, Suite 200, Fort Worth, TX 76102 - 817.810.0696
info@segpllc.com - www.SHIELDENGINEERINGGROUP.com
TBPE FIRM #F-1 1039 - TBPLS FIRM #10193890
M&C Review
Official
CITY COUNCIL AGENDA FORT '4'ORfll
Create New From This M&C
DATE: 3/8/2022 REFERENCE **M&C 22- LOG NAME: 20SWM SHIELD 19
NO.: 0160 RENEWAL 2
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: (ALL) Authorize the Second Renewal of?a Professional Services Agreement,
as Renewed and Amended, with Shield Engineering Group, PLLC for Stormwater
Capital Project Management Services?in the Amount of $2,400,000.00 and Authorize
the Second Amendment to the Agreement, as Renewed,?to Add Additional Funds to
the Contract in the Amount of$2,000,000.00 for a Total Contract Amount of?
$4,400,000.00
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of the second renewal, in the amount of $2,400,000.00, to City Secretary
Contract No. 52582, as renewed and amended, a professional services agreement with Shield
Engineering Group, PLLC for?Stormwater Capital Project Management Services; and
2. Authorize the second amendment to City Secretary Contract No. 52582, as renewed and
amended,?to add additional funds in the amount of $2,000,000.00, for a total contract amount
of?$4,400,000.00.
DISCUSSION:
Approval of this Mayor and Council Communication (M&C) will authorize the second renewal of
City Secretary Contract No. 52582, a professional services agreement with Shield Engineering
Group PLLC (Shield) in the amount of$2,400,000.00, for staff extension services in managing
Stormwater Capital Projects and the second amendment to the contract, as renewed and
amended, for additional funds in the amount of $2,000,000.00 for a revised contract
amount of$4,400,000.00. The actions in this M&C will add $4,400,000.00 to the current project
amount of$3,500,000.00 for a revised project amount of $7,900,000.00. The amendment will
also add specific language to the contract regarding renewals to conform with the intent of staff and
the City Council.
In May 2018, the Stormwater Management Division published a Request for Qualifications for
various technical services associated with drainage engineering, including capital project
management.??Shield was selected as the most qualified engineering consultant for this service.
On June 18, 2019 (M&C C-29150), the City Council approved the original agreement in an amount
not to exceed $1,100,000.00. That M&C allowed for additional renewal periods, contingent upon
City Council approval, for the purpose of maintaining continuity and efficiency in the delivery of the
Stormwater capital program.?Staff, by this M&C, seeks City Council authorization for this second
renewal so that delivery of capital projects under the current 5-year Stormwater revenue bond
program can continue without disruption.
On August 11, 2020 (M&C 20-0530), the initial contract was renewed in the amount of
$1,100,000.00 and amended to add additional funds in the amount
of$1,300,000.00 to establish a revised contract amount of $2,400,000.00. This action
increased the total project amount to $3,500,000.00.
http://apps.cfwnet.org/council_packet/mc review.asp?ID=29712&councildate=3/8/2022[4/14/2022 5:24:26 PM]
M&C Review
The next round of staff extension services is projected to cost $4,400,000.00. Under this renewal
and amendment, Shield is expected to provide project management services for approximately 130
projects over approximately 21 months.? Project management services will cover stormwater
project development, design, construction management, and project closeout. This amended
amount is based upon the estimated number of projects for this timeframe, and the expected cost
is in proportion to the project management costs experienced for the smaller, PayGo-
funded, Stormwater capital program prior to the 2020 bond program.? The contract will remain in
effect until funds are expended or the work is completed.
Due to the fluctuation of funding for capital improvements, the Stormwater Program
uses consultant staff augmentation to assist with project delivery as opposed to having the
number of full-time City staff adequate to manage the peak workload. The Stormwater Utility fee
increase approved by the City Council in October 2019 made possible a revenue bond sale.
The revenue bond issuance in 2020 more than doubled the Stormwater capital delivery capacity
compared to the strictly PayGo-funded program of the preceding years, requiring more project
management resources.?
Projects to be constructed and managed through this contract include hazardous roadway
overtopping mitigation projects, storm drain pipe rehabilitation projects, flood
mitigation improvements, and channel restoration improvements. Anticipated bond spending for
these projects is reflected in the Fiscal Years 2022-2026 Stormwater Management Capital
Improvement Program. ?
Funding is budgeted in the Consultant & Other Professional Service account of the Transportation
& Public Works Dept Highway & Streets Department's Stormwater Capital Projects and Stormwater
Revenue Bonds 2020 Funds for the purpose of funding the various projects, as appropriated.
DVIN Office - Shield Engineering Group, PLLC is in compliance with the City's Business Equity
Ordinance by committing to 11\% Business Equity participation on this project.The City's Business
Equity goal on this project is 11\%.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current?capital budget, as
previously appropriated, in the?Stormwater Capital Projects and Stormwater Rev Bonds 2020
Funds for various projects to support the approval of the above recommendations and execution of
the renewal and amendment to the contract . Prior to any expenditure being incurred, the
Transportation & Public Works Department has the responsibility to validate the availability of
funds.
TO
Fund Department Account Project Program Activity Budget Reference# Amount
ID ID Year (Chartfield 2)
FROM
Fund Department Account Project Program Activity Budget Reference# Amount
ID I I ID I Year (Chartfield 2)
Submitted for City Manager's Office by: Dana Burghdoff (8018)
Originating Department Head: William Johnson (7801)
Additional Information Contact: Linda Young (2485)
http://apps.cfwnet.org/council_packet/mc review.asp?ID=29712&councildate=3/8/2022[4/14/2022 5:24:26 PM]
M&C Review
ATTACHMENTS
20SWM SHIELD 19 RENEWAL 2 FID Table - rey.xlsx (CFW Internal)
20SWM SHIELD 19 RENEWAL 2 funds availability_pdf (CFW Internal)
52582 Stormwater Capital Delivery Prom Mamt Staff Aug Compliance Memo 020422 NW.pdf (CFW Internal)
Form 1295 Certificate 100864728 sicni ed.pdf (CFW Internal)
SAM._ocovv_Search.pdf (CFW Internal)
http://apps.cfwnet.org/council_packet/mc review.asp?ID=29712&councildate=3/8/2022[4/14/2022 5:24:26 PM]