FORT WORTH. City of Fort Worth
Change Order Request
Project Name Taxiway Papa Extension Phase 1 Construction City Sec# 54827
Client Project#(s) 102845 and 103000
Project Extension of Taxiway Papa at Fort Worth Alliance Airport
Description
Contractor Mario Sinacola&Sons Excavating,Inc. Change Order# 1 Date 5/10/2022
City Project Mgr. Tyler Dale City Inspector
Dept. Aviation Contract Time
Totals (CD)
Original Contract Amount $7,713,696.13 $7,713,696.13 215
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $7,713,696.13 $7,713,696.13 215
Amount of Proposed Change Order $70,945.23 $70,945.23 149
Revised Contract Amount $7,784,641.36 $7,784,641.36 364
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00
Additional Funding(if necessary) $70,945.23 $70,945.23
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.92%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $9,642,120.18
JUSTIFICATION(REASONS)FOR CHANGE ORDER
1. Increased width of the mow strip beneath the new airfield fence.
2. Removal of buried Southwestern Bell Manhole that was discovered during construction.
3. Additional fence removal&installation,dirt and rock removal,recompacting of utility backfill and adjustments to the water valve vault.
4. Additional taxiway edge light fixtures,bases and conduit.
5. Obtaining access rights for the re-established construction haul route.
6. Changes related to Phase II of the Project beginning sooner than expected.
7. Additional calendar days for weather and obtaining access rights for the re-established construction haul route.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and
reporting requirements.
NEContractors Company Nam-'I Contractor(Name Contract Signature Date
Mario Sinacola&Sons Excavating,Inc. Lyle Clark May 11,2022
Inspector/Inspection Supervisor Date Project and Contract Compliance Manager Date
-10hV May 11,2022
Program Manager Date Senior Capital Project Officer Date
Assistant Director(Dept) Date Director,Contracting Department(Dept) E& Date
- May 11,2022
Assistant City Attorney Date Assistant City Manager Date
May 13,2022 May 14,2022
e,,ghaoff ay1a212211:1111T)
ouncil Action(drequired)
M&C Number N/A M&C Date Approved N/A
ATTEST:
,7ghhatta C GoodaCC ,Opp*on
�oaa
Jannette Goodall,City Secretary p��o°° o��d
d-8 odd
Pvo o P.
C�*a °a*�
aa�at T000000 py OFFICIAL RECORD
�nnao4� CITY SECRETARY
FT.WORTH,TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Taxiway Papa Extension Phase 1 Construction City Sec# 54827
Client Project# 102845 and 103000
Contractor Mario Sinacola&Sons Excavating,Inc. PM Tyler Dale Inspector
Change Order Submittal# O1 Date 5I10I2022
AUUI I IONS
y Unit ni os o
Aviation
Aviation
17 P-152 UNCLASSIFIED EXCAVATION Aviation 1,100.00000000 CY 5.00
wa ion .
49 L-105 REMOVE AND SALVAGE RETROREFLECTIVE MARKER Aviation 5.00000000 EA 150.00
Aviation
53 L-108 NO.8 AWG,L-824C 5KV CABLE INSTALLED IN CONDUIT OR DUC Aviation 247.00000000 LF 2.00
via ion
59 L-110 2"SCHED 40 PVC DIRECT BURIED IN EARTH Aviation 57.00000000 LF 12.00
via ion
60 L-110 2"SCHED 40 PVC DRAIN Aviation 6.00000000 LF 10.00
Aviation
62 L-1102-WAY X 4"SCHED 40 PVC,CONCRETE ENCASED DUCTS Aviation 56.00000000 LF 115.00
via ion
72 L-125 L-867B BASE CAN WITH BLANK COVER Aviation 4.00000000 EA 850.00
via ion
74 L-125 NEW ISOLATION XFMR AND CONNECTOR KIT FOR LIGHT Aviation 2.00000000 EA 300.00
Aviation 1.00000000 EA $3,458.06 $3,4b8.06
76 P-152 RECOMPACT EXISTING 16"WATER LINE BACKFILL Aviation 402.00000000 LF 35.35
via ion
78 P-156 INSTALL AND REMOVE ROCK FILTER DAM TYPE 2 Aviation 34.00000000 LF 6.10
via ion
80 P-152 ROCK EXCAVATION Aviation 532.00000000 CY 129.75
Aviation 1.00000000 LS $9,158.43 $9,lb8.43
82 P-101 REMOVE EXISTING CTB Aviation 130.00000000 SY 13.51
via ion
84 P-156 ADDITIONAL SWPPP WEST OF NEW PERIMETER ROAD Aviation 1.00000000 LS 8,974.50
wa ion
86 P-620 EXPEDITED MOBILIZATION TOPAINT TAXIWAY CENTERLINE IN F Aviation 1.00000000 LS 1,500.00
Aviation 1.00000000 LS $995.00 $99b.00
Aviation $453,570.14
Sub Total Additions 453,570.14
Change Order Additions Page 2 of 4
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Taxiway Papa Extension Phase 1 Construction City Sec# 54827
Client Project# 102845 and 103000
Contractor Mario Sinacola&Sons Excavating,Inc. PM Tyler Dale Inspector
Change Order Submittal# O1 Date 5I10I2022
JELL1IONS
y Unit ni os o
Aviation
P-101 REMOVE 24"RCP wa ion
9 P-101 REMOVE 21"RCP Aviation 40.00000000 LF 25.00
wa ion
22 P-209 21"CRUSHED AGGREGATE BASE COURSE Aviation 533.50000000 SY 30.00
Aviation
27 P-602 BITUMINOUS PRIME COAT Aviation 160.05000000 GAL 5.05
wa ion
32 F-162 TEMPORARY AOA FENCE Aviation 11.00000000 LF 38.00
via ion
41 T-901 SEEDING Aviation 17.00000000 AC 1,290.00
Aviation
43 T-905 4"TOPSOIL Aviation 65,009.00000000 SY 1.00
via ion .
64 L-115 ADJUST ELEV OF EXISTING STRUCTURE Aviation 1.00000000 EA 2,200.00
Aviation $382,624.91
Sub Total Deletions 382,624.91
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00