Developer and Project Information Cover Sheet:
Developer Company Name: PR III/Crow Building E,F,G&L,LP
Address, State,Zip Code: 2100 McKenney Avenue,Dallas,TX,75201
Phone &Email: 214-863-4276,jmarks(atrammellcrow.com
Authorized Signatory,Title: Jake Marks, Senior Vice President
Project Name: 35 Eagle Phase III Industrial Development
Brief Description: Water, Sewer,Paving, Street Lights
Project Location: NW Corner of Eagle Parkway and IH35W SBFR
Plat Case Number: FP-22-003 Plat Name: Trammell Crow 35 Eagle Addition
Mapsco: Not Provided Council District: 7
CFA Number: CFA22-0027 City Project Number: 1039021 IPRC22-0017
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH, TX
City of Fort Worth,Texas Page 1 of 17
Standard Community Facilities Agreement
Rev.9/21
City Contract Number: 57559
STANDARD COMMUNITY FACILITIES AGREEMENT
This COMMUNITY FACILITIES AGREEMENT("Agreement") is made and entered into by
and between the City of Fort Worth ("City"), a home-rule municipal corporation of the State of Texas,
acting by and through its duly authorized Assistant City Manager,and PR III/Crow Building E,F,G&L,
LP("Developer"),acting by and through its duly authorized representative.City and Developer are referred
to herein individually as a"party" and collectively as the "parties."
WHEREAS, Developer is constructing private improvements or subdividing land within the
corporate limits of Fort Worth, Texas or its extraterritorial jurisdiction, for a project known as 35 Eagle
Phase III Industrial Development("Project"); and
WHEREAS, the City desires to ensure that all developments are adequately served by public
infrastructure and that the public infrastructure is constructed according to City standards;and
WHEREAS, as a condition of approval of the Project, Developer is required to bear a portion of
the costs of municipal infrastructure by constructing the public infrastructure necessary for the Project as
described in this Agreement("Community Facilities"or"Improvements");and
WHEREAS,as a condition of approval of the Project,Developer is required to meet the additional
obligations contained in this Agreement,and Developer may be required to make dedications of land,pay
fees or construction costs,or meet other obligations that are not a part of this Agreement; and
WHEREAS,the City is not participating in the cost of the Improvements or Project;and
WHEREAS, the Developer and the City desire to enter into this Agreement in connection with
the collective Improvements for the Project;
NOW,THEREFORE,for and in consideration of the covenants and conditions contained herein,
the City and the Developer do hereby agree as follows:
1.
CFA Ordinance
The Community Facilities Agreements Ordinance("CFA Ordinance"),as amended,is incorporated
into this Agreement by reference, as if it was fully set out herein. Developer agrees to comply with all
provisions of the CFA Ordinance in the performance of Developer's duties and obligations pursuant to this
Agreement and to cause all contractors hired by Developer to comply with the CFA Ordinance in
connection with the work performed by the contractors. If a conflict exists between the terms and conditions
of this Agreement and the CFA Ordinance,the CFA Ordinance shall control.
City of Fort Worth,Texas Page 2 of 17
Standard Community Facilities Agreement
Rev.9/21
2.
Incorporation of Engineering Plans
The engineering plans for the Improvements that have been approved by the City ("Engineering
Plans")are incorporated into this Agreement by reference as if fully set out herein. Developer shall provide
at its expense, unless otherwise agreed to by City, all engineering drawings and documents necessary to
construct the Improvements required by this Agreement.
3.
Description of Improvements; Exhibits and Attachments
The following exhibits describe the general location, nature and extent of the Improvements that
are the subject of this Agreement and are attached hereto and incorporated herein by reference:
❑X Exhibit A: Water
❑X Exhibit A-1: Sewer
❑X Exhibit B: Paving
❑ Exhibit B-1: Storm Drain
❑X Exhibit C: Street Lights & Signs
The Location Map and Cost Estimates are also attached hereto and incorporated herein by
reference. To the extent that Exhibits A, A-1, B, B-1, C, the Location Map, or the Cost Estimates
conflict with the Engineering Plans, the Engineering Plans shall control. If applicable,Attachment I —
Changes to Standard Community Facilities Agreement, Attachment 2 — Phased CFA Provisions, and
Attachment 3 — Concurrent CFA Provisions, are attached hereto and incorporated herein for all
purposes.
4.
Construction of Improvements
Developer agrees to cause the construction of the Improvements contemplated by this Agreement
and that said construction shall be completed in a good and workmanlike manner and in accordance with
all City standards and specifications, the Engineering Plans, the Cost Estimates provided for the
Improvements,and this Agreement. Developer acknowledges that City will not accept the Improvements
until the City receives affidavits and lien releases signed by Developer's contractors verifying that the
contractors, and all subcontractors and material suppliers, have been paid in full for constructing the
Improvements, and consent of the surety on payment and performance bonds provided for the
Improvements.
5.
Financial Guarantee
Developer has provided the City with a financial guarantee in the form and amounts set forth in
this Agreement which guarantees the construction of the Improvements and payment by Developer of
all contractors, subcontractors, and material suppliers for the Improvements ("Financial Guarantee").
Developer shall keep the Financial Guarantee in full force and effect until released by the City and shall
not reduce the amount of the Financial Guarantee unless authorized by the City in accordance with the
CFA Ordinance.
City of Fort Worth,Texas Page 3 of 17
Standard Community Facilities Agreement
Rev.9/21
6.
Completion Deadline; Extension Periods
This Agreement shall be effective on the date this Agreement is executed by the City's Assistant
City Manager ("Effective Date"). Developer shall complete construction of the Improvements and
obtain the City's acceptance of the Improvements within two (2)years of the Effective Date ("Term").
If construction of the Improvements has started during the Term, the Developer may request that this
Agreement be extended for an additional period of time ("Extension Period"). All Extension Periods shall
be agreed to in writing by the City and the Developer as set forth in a written amendment to this Agreement.
In no event shall the Term of this Agreement plus any Extension Periods be for more than three years.
7.
Failure to Construct the Improvements
(a) The City may utilize the Developer's Financial Guarantee to cause the completion of the
construction of the Improvements if at the end of the Term, and any Extension Periods, the
Improvements have not been completed and accepted by the City.
(b) The City may utilize the Developer's Financial Guarantee to cause the completion of the
construction of the Improvements or to cause the payment of costs for construction of the
Improvements before the expiration of the Term, and any Extension Period, if the Developer
breaches this Agreement,becomes insolvent,or fails to pay costs of construction.
(c) If the Financial Guarantee is a Completion Agreement and the Developer's contractors or suppliers
are not paid for construction costs or materials supplied for the Improvements the contractors and
suppliers may place a lien upon any property which the City does not have an ownership interest
that is the subject of the Completion Agreement.
(d) Nothing contained herein is intended to limit the Developer's obligations under the CFA
Ordinance, this Agreement, the Financial Guarantee, Developer's agreements with Developer's
contractors,or other related agreements.
8.
Termination
If Developer desires to terminate this Agreement before Developer's contractors begin
constructing the Improvements, Developer agrees to the following:
(a) that Developer and City must execute a termination of this Agreement in writing;
(b) that Developer will vacate any final plats that have been filed with the county where the Project
is located; and
(c) to pay to the City all costs incurred by the City in connection with this Agreement, including
time spent by the City's inspectors at preconstruction meetings.
9.
Award of Construction Contracts
City of Fort Worth,Texas Page 4 of 17
Standard Community Facilities Agreement
Rev.9/21
(a) Developer will award all contracts for the construction of the Improvements and cause the
Improvements to be constructed in accordance with the CFA Ordinance.
(b) Developer will employ construction contractors who meet the requirements of the City to construct
the Improvements including,but not limited,to being prequalified,insured,licensed and bonded to
construct the Improvements in the City.
(c) Developer will require Developer's contractors to provide the City with payment and performance
bonds naming the City and the Developer as dual obligees, in the amount of one hundred percent
(100%) of the cost of the Improvements as required by the CFA Ordinance. The payment and
performance bonds shall guarantee construction of the Improvements and payment of all
subcontractors and material suppliers. Developer agrees to require Developer's contractors to
provide the City with a maintenance bond naming the City as an obligee, in the amount of one
hundred percent(100%) of the cost of the Improvements, that guarantees correction of defects in
materials and workmanship for the Improvements by the contractor and surety for a period of two
(2)years after completion and final acceptance of the Improvements by the City. All bonds must
be provided to the City before construction begins and must meet the requirements of the City's
Standard Conditions,Chapter 2253 of the Texas Government Code,and the Texas Insurance Code.
(d) Developer will require Developer's contractors to provide the City with insurance equal to or in
excess of the amounts required by the City's standard specifications and contract documents for
developer-awarded infrastructure construction contracts. The City must be named as an additional
insured on all insurance policies. The Developer must provide the City with a Certificate of
Insurance (ACORD or form approved by the State of Texas), supplied by each contractor's
insurance provider,which shall be made a part of the Project Manual.
(e) Developer will require the Developer's contractors to give forty-eight(48)hours' advance notice
of their intent to commence construction of the Improvements to the City's Construction Services
Division so that City inspection personnel will be available. Developer will require Developer's
contractors to allow construction of the Improvements to be subject to inspection at any and all
times by the City's inspectors. Developer will require Developer's contractors to not install or
relocate any sanitary sewer, storm drain,or water pipe unless a City inspector is present and gives
consent to proceed, and to allow such laboratory tests as may be required by the City.
(f) Developer will not allow Developer's contractors to begin construction of the Improvements until
a notice to proceed to construction is issued by the City.
(g) Developer will not allow Developer's contractors to connect buildings to service lines of sewer and
water mains constructed pursuant to this Agreement, if any, until said sewer, water mains and
service lines have been completed to the satisfaction of the City.
10.
Utilities
Developer shall cause the installation or adjustment of utilities required to: (1) serve the Project;
and (2) to construct the Improvements required herein. City shall not be responsible for payment of any
costs that may be incurred by Developer in the relocation of any utilities that are or may be in conflict with
any of the Improvements to be constructed pursuant to this Agreement.
City of Fort Worth,Texas Page 5 of 17
Standard Community Facilities Agreement
Rev.9/21
11.
Easements and Rights-of-Way
Developer agrees to provide,at its expense,all necessary rights-of-way and easements required for
the construction and dedication to the City of the Improvements provided for by this Agreement.
12.
Liability and Indemnification
(a) DEVELOPER HEREBY RELEASES AND AGREES TO INDEMNIFY, DEFEND AND
HOLD THE CITY HARMLESS FOR ANY INADEQUACIES IN THE PRELIMINARY
PLANS, SPECIFICATIONS, ENGINEERING PLANS, AND COST ESTIMATES
SUPPLIED BY THE DEVELOPER FOR THIS AGREEMENT.
(b) THE DEVELOPER COVENANTS AND AGREES TO,AND BY THESE PRESENTS DOES
HEREBY FULLY INDEMNIFY, HOLD HARMLESS AND DEFEND THE CITY, ITS
OFFICERS,AGENTS AND EMPLOYEES FROM ALL SUITS,ACTIONS OR CLAIMS OF
ANY CHARACTER, WHETHER REAL OR ASSERTED,BROUGHT FOR OR ONACCOUNT
OFANYINJURIES OR DAMAGES SUSTAINED B YANY PERSONS,INCL UDING DEATH,
OR TO ANY PROPERTY, RESULTING FROM OR IN CONNECTION WITH THE
CONSTRUCTION,DESIGN, PERFORMANCE OR COMPLETION OF ANY WORK TO BE
PERFORMED BY SAID DEVELOPER, ITS CONTRACTORS, SUBCONTRACTORS,
OFFICERS, AGENTS OR EMPLOYEES, OR IN CONSEQUENCE OF ANY FAILURE TO
PROPERL Y SAFEGUARD THE WORK, OR ON ACCOUNT OF ANY ACT,INTENTIONAL
OR OTHERWISE, NEGLECT OR MISCONDUCT OF SAID DEVELOPER, ITS
CONTRACTORS, SUB-CONTRACTORS, OFFICERS, AGENTS OR EMPLOYEES,
WHETHER OR NOT SUCHINJURIES,DEATH OR DAMAGESARE CAUSED,IN WHOLE
OR IN PART, BY THE ALLEGED NEGLIGENCE OF THE CITY OF FORT WORTH, ITS
OFFICERS,SERVANTS, OR EMPLOYEES.
(c) DEVELOPER WILL REQUIRE ITS CONTRACTORS TO INDEMNIFY, DEFEND AND
HOLD HARMLESS THE CITY, ITS OFFICERS, AGENTS AND EMPLOYEES FROM
AND AGAINST ANY AND ALL CLAIMS, SUITS OR CAUSES OF ACTION OF ANY
NATURE WHATSOEVER, WHETHER REAL OR ASSERTED, BROUGHT FOR OR ON
ACCOUNT OF ANY INJURIES OR DAMAGES TO PERSONS OR PROPERTY,
INCLUDING DEATH,RESULTING FROM, OR INANY WAY CONNECTED WITH, THE
CONSTRUCTION OF THE IMPROVEMENTS CONTEMPLATED HEREIN, WHETHER
OR NOT SUCH INJURIES, DEATH OR DAMAGES ARE CAUSED, IN WHOLE OR IN
PART, BY THE ALLEGED NEGLIGENCE OF THE CITY OF FORT WORTH, ITS
OFFICERS, SERVANTS, OR EMPLOYEES. FURTHER, DEVELOPER WILL REQUIRE
ITS CONTRACTORS TO INDEMNIFY, DEFEND, AND HOLD HARMLESS THE CITY
FOR ANY LOSSES, DAMAGES, COSTS OR EXPENSES SUFFERED BY THE CITY OR
CAUSED AS A RESULT OF SAID CONTRACTORS' FAILURE TO COMPLETE THE
WORK AND CONSTRUCT THE IMPROVEMENTS IN A GOOD AND WORKMANLIKE
MANNER, FREE FROM DEFECTS,IN CONFORMANCE WITH THE CFA ORDINANCE,
AND INACCORDANCE WITH ALL PLANS AND SPECIFICATIONS.
13.
Right to Enforce Contracts
City of Fort Worth,Texas Page 6 of 17
Standard Community Facilities Agreement
Rev.9/21
Upon completion of all work associated with the construction of the Improvements,Developer will
assign to the City a non-exclusive right to enforce the contracts entered into by Developer with its
contractors,along with an assignment of all warranties given by the contractors,whether express or implied.
Further,Developer agrees that all contracts with any contractor shall include provisions granting to the City
the right to enforce such contracts as an express intended third party beneficiary of such contracts.
14.
Estimated Fees Paid by Developer; Reconciliation
Prior to execution of this Agreement, Developer has paid to the City the estimated cost of
administrative material testing service fees, construction inspection service fees,and water testing lab fees
in the amounts set forth in the Cost Summary section of this Agreement. Upon completion of the
construction of the Improvements, the City will reconcile the actual cost of administrative material testing
service fees, construction inspection service fees, and water testing lab fees with the estimated fees paid
by Developer. If the actual costs of the fees are more than the estimated payments made by the Developer,
the Developer must pay the difference to the City before the Improvements will be accepted by the City. If
the actual costs of the fees are less than the estimated payments made by the Developer,the City will refund
the difference to the Developer.If the difference between the actual costs and the estimated payments made
by the Developer is less than fifty dollars($50.00),the City will not issue a refund and the Developer will
not be responsible for paying the difference. The financial guarantee will not be released by the City or
returned to the Developer until reconciliation has been completed by the City and any fees owed to the City
have been paid by the Developer.
15.
Material Testing
The City maintains a list of pre-approved material testing laboratories. The Developer must
contract with material testing laboratories on the City's list. Material testing laboratories will provide copies
of all test results directly to the City and the Developer. If the Improvements being constructed fail a test,
the Developer must correct or replace the Improvements until the Improvements pass all retests. The
Developer must pay the material testing laboratories directly for all material testing and retesting.The City
will obtain proof from the material testing laboratories that the material testing laboratories have been
paid in full by the Developer before the City will accept the Improvements.
16.
Notices
All notices required or permitted under this Agreement may be given to a party by hand-
delivery or by mail, addressed to such party at the address stated below. Any notice so given shall be
deemed to have been received when deposited in the United States mail so addressed with postage
prepaid:
CITY: DEVELOPER:
Development Coordination Office PR III/Crow Building E,F,G& L,LP
City of Fort Worth 2100 McKinney Avenue
200 Texas Street Dallas, TX, 75201
Fort Worth, Texas 76102
City of Fort Worth,Texas Page 7 of 17
Standard Community Facilities Agreement
Rev.9/21
With copies to:
City Attorney's Office
City of Fort Worth
200 Texas Street
Fort Worth, Texas 76102
and
City Manager's Office
City of Fort Worth
200 Texas Street
Fort Worth, Texas 76102
Or to such other address one party may hereafter designate by notice in writing addressed and
mailed or delivered to the other party hereto.
17.
Right to Audit
Developer agrees that, until the expiration of three (3) years after acceptance by the City of the
Improvements constructed pursuant to this Agreement, that the City shall have access to and the right to
examine any directly pertinent books, documents, papers and records of the Developer involving
transactions relating to this Agreement. Developer agrees that the City shall have access during normal
working hours to all necessary Developer facilities and shall be provided adequate and appropriate
workspace in order to conduct audits in compliance with the provisions of this section. The City shall give
Developer reasonable advance notice of intended audits.
Developer further agrees to include in all contracts with Developer's contractors for the
Improvements a provision to the effect that the contractor agrees that the City shall,until the expiration of
three (3)years after final payment under the contract,have access to and the right to examine any directly
pertinent books, documents,papers and records of such contractor, involving transactions to the contract,
and further,that City shall have access during normal working hours to all of the contractor's facilities,and
shall be provided adequate and appropriate work space in order to conduct audits in compliance with the
provisions of this section. City shall give Developer's contractors reasonable advance notice of intended
audits.
18.
Independent Contractor
It is expressly understood and agreed that Developer and its employees, representative, agents,
servants,officers,contractors,subcontractors,and volunteers shall operate as independent contractors as to
all rights and privileges and work performed under this Agreement, and not as agents, representatives or
employees of the City. Subject to and in accordance with the conditions and provisions of this Agreement,
Developer shall have the exclusive right to control the details of its operations and activities and be solely
responsible for the acts and omissions of its employees, representatives, agents, servants, officers,
contractors, subcontractors, and volunteers. Developer acknowledges that the doctrine of respondeat
superior shall not apply as between the City and its officers, representatives, agents, servants and
employees, and Developer and its employees, representatives, agents, servants, officers, contractors,
City of Fort Worth,Texas Page 8 of 17
Standard Community Facilities Agreement
Rev.9/21
subcontractors, and volunteers. Developer further agrees that nothing herein shall be construed as the
creation of a partnership or joint enterprise between City and Developer. It is further understood that the
City shall in no way be considered a co-employer or a joint employer of Developer or any employees,
representatives, agents, servants, officers, contractors, subcontractors, and volunteers of Developer.
Neither Developer,nor any officers,agents, servants,employees or subcontractors of Developer shall be
entitled to any employment benefits from the City. Developer shall be responsible and liable for any and
all payment and reporting of taxes on behalf of itself, and any of employees, representatives, agents,
servants,officers,contractors, subcontractors,and volunteers.
The City,through its authorized representatives and employees, shall have the sole and exclusive
right to exercise jurisdiction and control over City employees.
19.
Applicable Law; Venue
This Agreement shall be construed under and in accordance with Texas law. Venue shall be in
the state courts located in Tarrant County, Texas or the United States District Court for the Northern
District of Texas,Fort Worth Division.
20.
Non-Waiver
The failure of the City to insist upon the performance of any term or provision of this Agreement
or to exercise any right herein conferred shall not be construed as a waiver or relinquishment to any extent
of City's right to assert or rely on any such term or right on any future occasion.
21.
Governmental Powers and Immunities.
It is understood that by execution of this Agreement, the City does not waive or surrender
any of its governmental powers or immunities.
22.
Headings
The paragraph headings contained herein are for the convenience in reference and are not intended
to define or limit the scope of any provision of this Agreement.
23.
Severability
In the event that any clause or provision of this Agreement shall be held to be invalid by any
court of competent jurisdiction, the invalidity of such clause or provision shall not affect any of the
remaining provisions hereof.
24.
Review of Counsel
City and Developer, and if they so choose,their attorneys, have had the opportunity to review
City of Fort Worth,Texas Page 9 of 17
Standard Community Facilities Agreement
Rev.9/21
and comment on this document;therefore any rule of contract construction or interpretation that would
normally call for the document to be interpreted as against the drafting party shall not apply in
interpretation of this Agreement, and each section, portion, and provision of this Agreement shall be
construed solely on the basis of the language contained therein, regardless of who authored such
language.
25.
Prohibition on Boycotting Israel
Developer acknowledges that in accordance with Chapter 2271 of the Texas Government Code,
the City is prohibited from entering into a contract with a company with 10 or more full-time employees
that has a value of$100,000 or more that is to be paid wholly or partly from public funds of the City for
goods or services unless the contract contains a written verification from the company that it: (1)does not
boycott Israel; and (2) will not boycott Israel during the term of the contract. The terms "boycott Israel"
and"company"have the meanings ascribed to those terms by Chapter 2271 of the Texas Government Code.
To the extent that Chapter 2271 of the Government Code is applicable to this Agreement,by signing this
Agreement, Developer certifies that Developer's signature provides written verification to the City that
Developer: (1)does not boycott Israel; and(2)will not boycott Israel during the term of this Agreement.
26.
Prohibition on Boycotting Energy Companies
Developer acknowledges that in accordance with Chapter 2274 of the Texas Government Code,as
added by Acts 2021, 87th Leg., R.S., S.B. 13, § 2,the City is prohibited from entering into a contract for
goods or services that has a value of$100,000 or more that is to be paid wholly or partly from public funds
of the City with a company with 10 or more full-time employees unless the contract contains a written
verification from the company that it: (1) does not boycott energy companies; and (2) will not boycott
energy companies during the term of the contract. The terms "boycott energy company" and "company"
have the meanings ascribed to those terms by Chapter 2274 of the Texas Government Code, as added by
Acts 2021, 87th Leg., R.S., S.B. 13, § 2. To the extent that Chapter 2274 of the Government Code is
applicable to this Agreement, by signing this Agreement, Developer certifies that Developer's signature
provides written verification to the City that Developer: (1) does not boycott energy companies; and (2)
will not boycott energy companies during the term of this Agreement.
27.
Prohibition on Discrimination Against Firearm and Ammunition Industries
Developer acknowledges that except as otherwise provided by Chapter 2274 of the Texas
Government Code,as added by Acts 2021,87th Leg.,R.S.,S.B. 19, § 1,the City is prohibited from entering
into a contract for goods or services that has a value of$100,000 or more that is to be paid wholly or partly
from public funds of the City with a company with 10 or more full-time employees unless the contract
contains a written verification from the company that it: (1) does not have a practice,policy, guidance, or
directive that discriminates against a firearm entity or firearm trade association;and(2)will not discriminate
during the term of the contract against a firearm entity or firearm trade association. The terms
"discriminate," "firearm entity" and "firearm trade association" have the meaning ascribed to those terms
by Chapter 2274 of the Texas Government Code,as added by Acts 2021, 87th Leg.,R.S., S.B. 19, § 1. To
the extent that Chapter 2274 of the Government Code is applicable to this Agreement, by signing this
Agreement, Developer certifies that Developer's signature provides written verification to the City that
Developer: (1) does not have a practice,policy, guidance, or directive that discriminates against a firearm
City of Fort Worth,Texas Page 10 of 17
Standard Community Facilities Agreement
Rev.9/21
entity or firearm trade association; and (2) will not discriminate against a firearm entity or firearm trade
association during the term of this Agreement.
28.
Immigration and Nationality Act
Developer shall verify the identity and employment eligibility of its employees who perform work
under this Agreement, including completing the Employment Eligibility Verification Form (I-9). Upon
request by City, Developer shall provide City with copies of all I-9 forms and supporting eligibility
documentation for each employee who performs work under this Agreement. Developer shall adhere to all
Federal and State laws as well as establish appropriate procedures and controls so that no services will be
performed by any Developer employee who is not legally eligible to perform such services.DEVELOPER
SHALL INDEMNIFY CITY AND HOLD CITY HARMLESS FROM ANY PENALTIES,
LIABILITIES, OR LOSSES DUE TO VIOLATIONS OF THIS PARAGRAPH BY DEVELOPER,
DEVELOPER'SEMPLOYEES,SUBCONTRACTORS,AGENTS,OR LICENSEES. City,upon written
notice to Developer, shall have the right to immediately terminate this Agreement for violations of this
provision by Developer.
29.
Amendment
No amendment,modification, or alteration of the terms of this Agreement shall be binding unless
the same is in writing,dated subsequent to the date hereof, and duly executed by the City and Developer.
30.
Assignment and Successors
Developer shall not assign or subcontract all or any part of its rights,privileges,or duties under this
Agreement without the prior written consent of City. Any attempted assignment or subcontract without the
City's prior written approval shall be void and constitute a breach of this Agreement.
31.
No Third-Party Beneficiaries
The provisions and conditions of this Agreement are solely for the benefit of the City and
Developer, and any lawful assign or successor of Developer, and are not intended to create any rights,
contractual or otherwise,to any other person or entity.
32.
Compliance with Laws,Ordinances,Rules and Regulations
Developer, its officers, agents, servants, employees, and contractors, shall abide by and comply
with all laws, federal, state and local, including all ordinances, rules and regulations of City. It is agreed
and understood that,if City calls to the attention of Developer any such violation on the part of Developer
or any of its officers, agents, servants, employees, or subcontractors, then Developer shall immediately
desist from and correct such violation.
33.
Signature Authority
City of Fort Worth,Texas Page 11 of 17
Standard Community Facilities Agreement
Rev.9/21
The person signing this Agreement on behalf of Developer warrants that he or she has the legal
authority to execute this Agreement on behalf of the Developer, and that such binding authority has been
granted by proper order,resolution,ordinance or other authorization of the entity. The City is fully entitled
to rely on this warranty and representation in entering into this Agreement.
34.
Counterparts
This Agreement may be executed in multiple counterparts, each of which will be deemed an
original, but which together will constitute one instrument.
35.
Entire Agreement
This written instrument, together with any attachments, exhibits, and appendices, constitutes the
entire understanding between the City and Developer concerning the work to be performed hereunder, and
any prior or contemporaneous, oral or written agreement that purports to vary from the terms hereof shall
be void.
[REMAINDER OF PAGE INTENTIONALLY BLANK]
City of Fort Worth,Texas Page 12 of 17
Standard Community Facilities Agreement
Rev.9/21
36.
Cost Summary Sheet
Pro]ectName: 35 Eagle Phase III Industrial Development
CFA No.: CFA22-0027 City Project No.: 103902
Items Developer's Cost
A. Water and Sewer Construction
1. Water Construction $ 74,840.00
2.Sewer Construction $ 21,339.00
Water and Sewer Construction Total $ 96,179.00
B. TPW Construction
1.Street $ 304,979.00
2.Storm Drain $ -
3.Street Lights Installed by Developer $ 13,050.00
4. Signals $ -
TPW Construction Cost Total $ 318,029.00
Total Construction Cost(excluding the fees): $ 414,208.00
Estimated Construction Fees:
C. Construction Inspection Service Fee $23,500.00
D. Administrative Material Testing Service Fee $2,793.00
E. Water Testing Lab Fee $750.00
Total Estimated Construction Fees: $ 27,043.00
Choice
Financial Guarantee Options,choose one Amount (Mark one)
Bond= 100% $ 414,208.00 x
Completion Agreement= 100%/Holds Plat $ 414,208.00
Cash Escrow Water/Sanitary Sewer= 125% $ 120,223.75
Cash Escrow Paving/Storm Drain = 125% $ 397,536.25
Letter of Credit= 125% $ 517,760.00
City of Fort Worth,Texas Page 13 of 17
Standard Community Facilities Agreement
Rev.9/21
IN WITNESS WHEREOF,the City and Developer have each executed this Agreement by their
duly authorized signatories to be effective on the date executed by the City's Assistant City Manager.
CITY OF FORT WORTH DEVELOPER
[Signature on following page]
Dana 24L( hdoAc
Dana Burghdoff ay 13,202217:11 CDT)
Dana Burghdoff
Assistant City Manager
Date: May 13,2022
Recommended by:
Jennifer Ez�rnack(May 13,2022 08:18 CDT)
Jennifer Ezernack
Contract Compliance Specialist
Planning and Development
Contract Compliance Manager:
By signing, I acknowledge that I am the person
Approved as to Form &Legality: responsible for the monitoring and
administration of this contract,including
4K2r— ensuring all performance and reporting
Richard A.McCracken(May 13,2022 10:24 CDT) requirements.
Richard A.McCracken
Sr.Assistant City Attorney � s
M&C No. Janie Scarlett Morales(May 13,2022 08:29 CDT)
Date: May 13,2022 Janie Scarlett Morales
Form 1295:
Development Manager
ATTEST:
A` F°F�R�°�Da�
:7�`I`IGl`l`G c1 GDOG��GG ° a
Jannette S.Goodall(May 16,2022 08:06 CDT) ^0 0��d
Jannette S. Goodall P o o o=d
City Secretary ����o °o�c
° ICY
0000000 °
���nEXAS.o�p
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH, TX
City of Fort Worth,Texas Page 14 of 17
Standard Community Facilities Agreement
Rev.9/21
DEVELOPER
PR III/Crow Building E, F, G & L, LP
By: PR III/Crow Building E, F, G & L GP, LLC
Its General Partner
By: PR III/Crow Building C, E, F, G& L Holdings, LLC
A Delaware limited liability company
Its sole member and manager
By: TC Eagle CEFGL Development, LLC
A Delaware limited liability company
Its authorized signatory
By: TCDFW Industrial Development Inc.,
A Delaware corporation
Its managing member
24:��4
Jake Marks
Senior Vice President
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH, TX
City of Fort Worth,Texas Page 15 of 17
Standard Community Facilities Agreement
Rev.9/21
The following attachments are incorporated into this Agreement. To the extent a
conflict exists between the main body of this Agreement and the following attachments, the
language in the main body of this Agreement shall be controlling.
Included Attachment
❑X Attachment 1 -Changes to Standard Community Facilities Agreement
❑ Attachment 2—Phased CFA Provisions
❑ Attachment 3 —Concurrent CFA Provisions
❑X Location Map
❑X Exhibit A: Water Improvements
❑X Exhibit A-1: Sewer Improvements
❑X Exhibit B: Paving Improvements
❑ Exhibit B-1: Storm Drain Improvements
❑X Exhibit C: Street Lights and Signs Improvements
❑X Cost Estimates
(Remainder of Page Intentionally Left Blank)
City of Fort Worth,Texas Page 16 of 17
Standard Community Facilities Agreement
Rev.9/21
ATTACHMENT"1"
Changes to Standard Community Facilities Agreement
City Proj ect No. 103902
None
City of Fort Worth,Texas Page 17 of 17
Standard Community Facilities Agreement
Rev.9/21
N
0 500 1000 1500 2000
SCALE: 1"=1000'
� f
i
PROJECT
LOCATION
w
Q
U
U
N
0
Q
U
y a LVI
o� 4
Uw 3 5 W N BEACH ST
II/
IIFVFI C1PFR/ '.'MNFR I /
1 TRAMROBERT BR COMPANY I
ROBERT BRANDY
2100 MDALLA,AVENUE,SUITE 900
N OALL214 TEXAS 75201
(2141 nli 49
CONTACT:ROBERT BRANDY
■■■ 35 EAGLE PHASE III
mom HALFF6 VICINITY MAP- MAPSCO NO. 654A INDUSTRIAL DEVELOPMENT
mom
3tl03 PARKWOOD BLVD,SUITE tl00 IPRC 22-0017
FRISCO, 618-4 75o34-22640 FDATE:02/23/2022 AVO: 34575 CITY PROJECT NO. 103902
TEL(214 fi 18-4570
TBP�F,"M#F-317Z FORT WORTH,TEXAS
LA
0 150 300 450 600
II II N
r I E I II III II lii SCALE: 1"=300'
SITE f HART 35 I IIIIII II HART 35
EAGLE LLC I I II �\ EAGLE LLC
Fq��F LOT 4, BLOCK 1 I II II \ �\\ LOT 5R1, BLOCK 1
LOCATION MAP
N.T.S.
8"WATER LINE 'F' 8"WATER LINE 'G' \
35 EAGLE
/ ADDITION
•;'� LOT 1, BLOCK 2 /
10"WATER LINE 'E'
EX. 16"WATERLINE
HART 35
LL EAGLE LLC / // / / 8"WATER LINE ID'
LL LOT 3, BLOCK 1
/ // F+ERITAGE PKWY;�:
35 EAGLE /
10"WATER LINE 'C' ADDITION
/ LOT 2, BLOCK 2
8"WATER LINE 'B'
i 8"WATER LINE IA'
INTERSTATE 35W
35 EAGLE
l ADDITION
LOT 3, BLOCK 2 /� /
T
L
EAGLE — —
PKWY �
LEGEND:
nFVFI nPFR/n1NNFR PROPOSED WATER
1 TRAMMELLCROW COMPANY
ROBERTBRANDT EXISTING WATER
2100 McKINNEV AVENUE,SUITE W,
? DALLAS,TEXAS 75201
(214 n8 '649
CO NTACT:ROBERTBRANDT
■■■ 35 EAGLE PHASE III
loom HALFF6 WATER EXHIBIT"A" INDUSTRIAL DEVELOPMENT
■■■ CITY PROJECT NO. 103902
3tl IS O,TEXAS
7 D34D SUITE 800 IPRC 22-0017
R's 618-4 75°54�64° FDATE:02/15/2022 FAVO: 34575 CFA 22-0027
3 0(214 fil&4570
TBP�F,"M#F-312 FORT WORTH,TEXAS
�'�'' I I Ij ,Iljllii II
SITE J „ III
� HART 35 i
II ,I �I EAGLE LLC
LOT 5R1, BLOCK 1
6" SEWER LAT'D' /
LOCATION MAP / / /��,,��� CONNECT TO EX. /
N.T.S. —I / // �, // ���\ 12SEWER LINE
6" SEWER LAT'C'
\ HART 35 35 EAGLE
EAGLE LLC � // ADDITION
LOT 4, BLOCK 1 LOT 1, BLOCK 2
HART 35
EAGLE LLC
LOT 3, BLOCK 1 / / 6" SEWER LAT'B'
LL
10
ITAGE
EAGLE
/ 6" SEWER LAT IN ADDITION
BLOCK 2 f /
INTERSTATE 35W
35 EAGLE /
ADDITION
LOT 3, BLOCK 2 /� /
s
0 150 300 450 600
EAGLE / SCALE: 1"=300'
PKWY ��J� LEGEND:
nFVFI nPFRn1NNRR PROPOSED SSM H
1 TRAMMELLCROW COMPANY
ROBERT BRANDS \ EXISTING SS LINE
2100 MDALLA,TEXASAVENUE,SUITE 900
OALLAS,TEXAS 75201
(2141 n3 '649
CONTACT:ROBERTBRANDT
■■■ 35 EAGLE PHASE III
MEN HALFF6 SEWER EXHIBIT"A-1" INDUSTRIAL DEVELOPMENT
■■■ CITY PROJECT NO. 103902
3tl03 PARKWOOD BLVD,SUITE 800 IPRC 22-0017
R's 618-4 75034 640 DATE:02/15/2022 AVO: 34575 cFA 22-0027
TEL(2114 fi 18-4570
TeP�F,"M#-457 FORT WORTH,TEXAS
�`.�,, I I II illlllii 0 150 300 450 600
ICI N
! I II III ICI Ijj SCALE: 1"=300'
III III
SITE f HART 35 f I II III II �� HART 35
EAGLE LLC ! I II II �I �\ EAGLE LLC
F4�F LOT 4, BLOCK 1 I II II \ �\\ LOT 5R1, BLOCK 1
_---__ ///
PROPOSED RAMP
LOCATION MAP l i —I
N.T.S. / PROPOSED
DRIVEWAY
PROPOSED RAMP
S SIDEWALK PROPOSED
DRIVEWAY
PROPOSED RAMP /
35 EAGLE
/ ADDITION
LOT 1, BLOCK 2
PROPOSED RAMP PROPOSED DRIVEWAY
HART 35
EAGLE LLC
LOT 3, BLOCK 1
35
/ % ' HERITAGE PKWY; ADDITION /r
LOT 2, BLOCK 2 / r
PROPOSED RAMP ;( /
PROPOSED DRIVEWAY
/ r
/ S SIDEWALK
< e /
35 EAGLE INTERSTATE 35W/ / n
PROPOSED RAMP ADDITION
LOT 3, BLOCK 2 /��/
i
� L
EAGLE - -
PKWY `�� / LEGEND:
PROPOSED CONCRETE SIDEWALK
PROPOSED CONCRETE PAVEMENT
nFVFinaFRirnn1MFR PROPOSED RAMP
3 TRAMROBE RT BR COMPANY
RORERT BRANDY
2100 MDALLA,TEXASAVENUE,SUITE 900
DALLAS,TEXAS 75201
(214) 3649
CONTACT:ROBERT BRAN DT
■■■ 35 EAGLE PHASE III
MEN HALFF6 F PAVING EXHIBIT"B" INDUSTRIAL DEVELOPMENT
■■■ CITY PROJECT NO. 103902
3803 PARKUJOOD BLVD,SUITE 800 IPRC 22-0017
FR'S°a, 6 18-5 75034�640 FDATE:02/15/2022 IFAVO: 34575 CFA 22-0027
TEL(214 fi 18-4570
TBP�FI°M OF-312 FORT WORTH,TEXAS
�`.�,, I I II illlllii 0 150 300 450 600
I I III N
II III III Ilj SCALE: 1"=300'
III III
SITE f HART 35 f I II III II �� HART 35
EAGLE LLC I II II��I �\ EAGLE LLC
F4�F LOT 4, BLOCK 1 I II II \ �\\ LOT 5R1, BLOCK 1
LOCATION MAP
N.T.S.
35 EAGLE
ADDITION
LOT 1, BLOCK 2
HART 35 / // / //// "'/�/ //�/\�,, �/ ////, `,Y:•; j/
LL EAGLE LLC
LOT 3, BLOCK 1
/ /� // • '`� 35 EAGLE
' HERITAGE PKWY;` ADDITION
LOT 2, BLOCK 2
REMOVE AND REPLACE
/ ROADWAY ILLUMINATION /
FOUNDATION/POLE G
/
INTERSTATE 35W
35 EAGLE
l ADDITION
LOT 3, BLOCK 2 /� /
•T
L
EAGLE - -
/
PKWY
LEGEND:
i
nFVFi ,2FR mMFR PROPOSED STREET LIGHT
3 TRAMROBE RT BRANDT
COMPANY \�\\
ROBERT ENUE,
2100 MDALLA,TEXAS E,SUITE 900
DALLAS,TEXAS 75101
(218363649
CONTACT:41 ROBERT BRANDY
■■■ 35 EAGLE PHASE III
MEN HALFF6 F STREET LIGHTS EXHIBIT "Cl" INDUSTRIAL DEVELOPMENT
■■■ CITY PROJECT NO. 103902
3803 PARKUJOOD BLVD,SUITE 800 IPRC 22-0017
FR'S°4, 618-575034 64° DATE:02/15/2022 IFAVO: 34575 CFA 22-0027
TEL 4 fi18-4570
TeP�FI°MU-457 FORT WORTH,TEXAS
00 42 43
DAP-BID PROPOSAL
Page I of 5
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist Item Description Specification Section No. Unit of Bid Unit Price Bid Value
No. Measure Quantity
UNIT I:WATER IMPROVEMENTS
1 0241.1016 Remove 16"Water Line 0241 14 LF 235 $8.00 $1,880.00
2 0241.1106 16"Pressure Plug 0241 14 EA 1 $350.00 $350.00
3 0241.1109 24"Pressure Plug 0241 14 EA 1 $500.00 $500.00
4 0241.1118 4"-12"Pressure Plug 0241 14 EA 7 $150.00 $1,050.00
5 0241.1301 Remove 10"Water Valve 0241 14 EA 2 $150.00 $300.00
6 0241.1602 Remove 10"Concrete Water Vault 0241 14 EA 2 $1,250.00 $2,500.00
7 3305.0109 Trench Safety 3305 10 LF 602 $1.00 $602.00
8 3305.0203 Imported EmbedmentBackfill,CLSM 3305 10 LF 160 $35.00 $5,600.00
9 3311.0001 Ductile Iron Water Fittings w/Restraint 33 11 11 LS 1 $3,500.00 $3,500.00
10 3311.0251 8"DIP Water Pipe 33 11 10 LF 141 $68.00 $9,588.00
11 3311.0261 8"PVC WaterPipe 33 11 10 LF 268 $48.00 $12,864.00
12 3311.0351 10"DIP Water Pipe 33 11 10 LF 91 $72.00 $6,552.00
13 3311.0361 10"PVC Water Pipe 33 11 10 LF 102 $52.00 $5,304.00
14 3312.3003 8"Gate Valve 33 1220 EA 5 $1,250.00 $6,250.00
15 3312.3004 10"Gate Valve 33 1220 EA 2 $1,500.00 $3,000.00
�63312.3006 16"Gate Valve w/Vault 33 1220 EA 1 $15,000.00 $15,000.00
TOTAL UNIT I:WATER IMPROVEMENTS $74,840.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Vmion May 22,2019 00 42 43_Bid Proposal_DAP.xIs
00 42 43
DAP-BID PROPOSAL
Page 2 of 5
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist Item Description Specification Section No. Unit r Bid Unit Price Bid Value
No. Measure Quantity
UNIT II:SANITARY SEWER IMPROVEMENTS
1 0241.2102 6"Sewer Abandonment Plug 0241 14 EA 4 $150.00 $600.00
2 3301.0002 Post-CCTV Inspection 33 01 31 LF 29 $75.00 $2,175.00
3 3301.0101 Manhole Vacuum Testing 33 01 30 EA 4 $100.00 $400.00
4 3305.0107 Manhole Adjustment,Minor 3305 14 EA 1 $500.00 $500.00
5 3305.0109 Trench Safety 3305 10 LF 29 $1.00 $29.00
6 3331.4108 6"SDR 26 PVC Sanitary Sewer Pipe 33 11 10 LF 29 $65.00 $1,885.00
7 3339.0001 Epoxy Manhole Liner 33 39 60 VF 15 $300.00 $4,500.00
8 3339.1001 4'Manhole 33 39 10,33 39 20 EA 3 $2,500.00 $7,500.00
91 3339.1003 4'Extra Depth Manhole 33 39 10,33 39 20 VF 15 $250.00 $3,750.00
TOTAL UNIT II:SANITARY SEWER IMPROVEMENTS $21,339.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Vmion May 22,2019 00 42 43_Bid Proposal_DAP.xls
00 42 43
DAP-BID PROPOSAL
Page 3 of 5
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist Item Description Specification Section No. Unit of Bid Unit Price Bid Value
No. Measure Quantity
UNIT III:PAVING IMPROVEMENTS
1 0241.0100 Remove Sidewalk 0241 13 SF 300 $2.00 $600.00
2 0241.0800 Remove Rip Rap 0241 13 SF 302 $2.00 $604.00
3 0241.1000 Remove Conc Pvmt 0241 15 SY 1450 $12.00 $17,400.00
4 0241.1300 Remove Conc Curb&Gutter 0241 15 LF 900 $8.00 $7,200.00
5 3123.0101 Unclassified Excavation by Plan(Cut) 3123 16 CY 755 $15.00 $11,325.00
6 3125.0101 SWPPP >1 acre 31 25 00 LS 1 $2,000.00 $2,000.00
7 3211.0400 Hydrated Lime 321129 TN 70 $165.00 $11,550.00
8 3211.0501 6"Lime Treatment 32 1129 SY 2100 $4.00 $8,400.00
9 3213.0104 9"Conc Pvmt 32 13 13 SY 2100 $61.00 $128,100.00
10 3213.0301 4"Conc Sidewalk 32 1320 SF 17170 $5.00 $85,850.00
11 3213.0504 Barrier Free Ramp,Type M-2 32 1320 EA 1 $500.00 $500.00
12 3213.0506 Barrier Free Ramp,Type P-1 32 1320 EA 14 $500.00 $7,000.00
13 3216.0101 6"Conc Curb and Gutter 32 1613 LF 600 $5.00 $3,000.00
14 3291.0100 Topsoil 3291 19 CY 525 $6.00 $3,150.00
15 3292.0100 Block Sod Placement 3292 13 SY 3200 $4.00 $12,800.00
16 3471.0001 Traffic Control 3471 13 MO 3 $1,500.00 $4,500.00
17 9999.0001 Striping Replacement 99 99 01 LS 1 $1,000.001 $1,000.00
TOTAL UNIT III:PAVING IMPROVEMENTS $304,979.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Vmion May 22,2019 00 42 43_Bid Proposal_DAP.xls
00 42 43
DAP-BID PROPOSAL
Page 4 of 5
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist Item Description Specification Section No. Unit r Bid Unit Price Bid Value
No. Measure Quantity
UNIT IV:STREET LIGHTING IMPROVEMENTS
1 2605.3015 2"CONDT PVC SCH 80(T) 26 05 33 LF 85 $15.00 $1,275.00
2 3441.1405 NO 2 Insulated Elec Condr 3441 10 LF 255 $5.00 $1,275.00
3 3441.1502 Ground Box Type B,w/Apron 3441 10 EA 2 $1,250.00 $2,500.00
4 3441.3003 Rdwy Illum Assmbly TY 18,18A 19,and D-40 34 41 20 EA 1 $2,500.00 $2,500.00
5 3441.3201 LED Lighting Fixture 344120 EA 1 $1,500.00 $1,500.00
6 3441.3302 Rdwy Illum Foundation TY 3,5,6,and 8 34 41 20 EA 1 $1,000.00 $1,000.00
7 3441.3347 Rdwy Illum TY D-40-9 Pole 34 41 20 EA 1 $2,500.00 $2,500.00
8 9999.0001 Remove Roadway Illumination Foundation 99 99 05 EA 1 $500.00 $500.00
TOTAL UNIT IV:STREET LIGHTING IMPROVEMENTS $13,050.00
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Vmion May 22,2019 00 42 43_Bid Proposal_DAP.xIs
00 42 43
DAP-BID PROPOSAL
Page 5 of 5
SECTION 00 42 43
Developer Awarded Projects-PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Bid Summary
UNIT I:WATER IMPROVEMENTS $74,840.00
UNIT II:SANITARY SEWER IMPROVEMENTS $21,339.00
UNIT IV:PAVING IMPROVEMENTS $304,979.00
UNIT V:STREET LIGHTING IMPROVEMENTS $13,050.00
Total Construction Bid $414,208.00
This Bid is submitted by the entity named below:
BIDDER: BY:Zac �user
North Texas Contracting,Inc.
c/o Zach Fusilier
4999 Keller-Haslet Road TITLE:Vice President
Keller,Texas 76244 DATE:03/24/2022
Contractor agrees to complete WORK for FINAL ACCEPTANCE within 75 working days after the date when the
CONTRACT commences to run as provided in the General Conditions.
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS-DEVELOPER AWARDED PROJECTS
Form Vmion May 22,2019 00 42 43_Bid Proposal_DAP.xls