Loading...
HomeMy WebLinkAboutContract 54148-CO4 FORT WORTH City of Fort Worth CSC No. 54148-004 Change Order Request Project Name:1 VCWRF Sludge Thickening Improvements City Sec No.: 54148 Project No.(s): 56019/0700430/1780 DOE No. N/A City Proj.No.: CO2647 Project Description: Upgrading/modificationsof primary and WAS thickening processes;including improvements to existing GBT and sludge buildings,gravity thickeners, WAS storage&sludge blend tanks,Dissolved Air Flotation Tanks(DAFT),and backwash clarifier. Contractor:I Eagle Contracting, LP Change Order# ® Date: 5/12/2022 City Project Mgr.1 Farida Goderya City Inspector: I Kevin Sidebottom Phone Number:1 817-392-8214 Phone Number: 817-874-9330 Dept. Sewer Totals Contract Time (Calender days) Original Contract Amount $17,480,000.00 $17,480,000.00 730 Extras to Date $277,586.00 $277,586.00 026 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $17,757,586.00 $17,757,586.00 756 Amount of Proposed Change Order $399,750.00 $399,750.00 030 Revised Contract Amount $18,157,336.00 $18,157,336.00 786 Original Funds Available for Change Orders $305,900.00 $305,900.00 Remaining Funds Available for this CO $28,314.00 $28,314.00 Additional Funding(if necessary) 1 $371,436.00 $371,436.00 CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 3.87% MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $21,850,000.00 JUSTIFICATION (REASONS) FOR CHANGE ORDER This Change Order#04 will provide for the following: • Rehabilitation, painting and modifications to Blend Tank piping as well as wall coatings • Structural repair and modification for the Blend Tank lid-cover • Necessary ancillary work Staff recommends approval of additional 30 calendar days for this Change Order. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. Cofilmaor's Cwtipnny Nome _ ontfa,tar Name Cr•7lraalo-Si.npture Gate _ i �tillc C stllr�u_: t[l,LF 7hilln Bennett n"R ..Nor oalo Pra ail Vallagor bate _C __. 5/18/22 <�:rt Farida Gode a,PE �'4� 5/25/2022 Clrec-►,ar rR'ale ernl) -- .-- - C�rIE� Cranslruclif;7 5u t;visor Dale 7 May 26,7022 N/A �.ssislnnt Get�hlloinny Dale I hssJslsnt C,;NJ.tt:n) er Dale '� � _w._—�_,��~���� MaV 27 2022 �� Ma 27 2022 Bla,k(MZU y 27,20221G22 CDT) + na ,ur doff(ay2],20 16:32CDT) Council Action If Required) OFFICIAL RECORD M&C Number 22-0359 M&C Date Approved 5 0 2022 CITY SECRETARY FT. WORTH, TX FORT WORTH City of Fort Worth Change Order Additions Project Name VCWRF Sludge Thickening Improvements City Sec No.: 54148 Project No.(s): 56019/0700430/1780 DOE No. N/A City Proj. No.: CO2647 Project buildings,gravity thickeners,WAS storage&sludge blend tanks, Dissolved Air Flotation Tanks(DAFT), and backwash Description .F.�r Contractor Eagle Contracting, LP Change Order:® Date: 5/12/2022 City Project Mgr. Farida Goderya City Inspector F Kevin Sidebottom ADDITIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total 1 PCM 012 Blend Tank Piping and Walls Coating Sewer 1.00 LS $196,515.00 $196,515.00 2 PCM 018 Blend Tank Lid-Cover Repairs Sewer 1.00 LS $203,235.00 $203,235.00 Sewer $399,750.00 Page 2 of 4 Additions Sub Total $399,750.00 FC3 RT' WO 12T H City of Fort Worth Change Order Deletions Project Name VCWRF Sludge Thickening Improvements City Sec No.: 54148 Project No.(s): 56019/0700430/1780 DOE No. N/A City Proj. No.: CO2647 Project Description Upgradinglmodificationsof primary and WAS thickening processes; including improvements to existing GBT and sludge buildings,gravity thickeners,WAS storage&sludge blend tanks, Dissolved Air Flotation Tanks DAFT , and Contractor Eagle Contracting, LP Change Order: ® Date 5/12/2022 City Project Mgr. Farida Goderya City Inspector: Kevin Sidebottom DELETIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total Sewer Page 3 of 4 Deletions Sub Total MWWBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Same as original Contract Miscellaneous $399,750.00 Total $399,750.00 Previous Change Orders Co# DATE AMOUNT 1 1/12/2021 $91,838.00 2 6/11/2021 $97,017.00 3 3/11/2022 $88,731.00 Total $277,586.00 Page 4 of 4 5/13/2022 CPN CO2647 VCWRF Sludge Thickening Improvements Change Request 4 Notes Staff has reviewed the proposed unit prices in the attached PCM's and considers them to be fair and reasonable. .Contract Compliance Manager By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. Signature Farida Goderya,PhD,PE Name of Employee Senior Project Manager Title ATTEST: �� ORr � F)OOOO ° o ° 4#fiette S.Goodall(May 27,2022 16 CDT) V p d 0 00 °O °° Jannette Goodall a 000000 a City Secretary OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX City of Fort Worth, Texas Mayor and Council Communication DATE: Tuesday, May 10, 2022 REFERENCE NO.: **M&C 22-0359 LOG NAME: 60VCWRF THICKENING C04 — EAGLE SUBJECT: (CD 5) Authorize Execution of Change Order No. 4 in the Amount of$399,750.00 to the Contract with Eagle Contracting, LP, for the Village Creek Water Reclamation Facility Sludge Thickening Improvements for a Revised Contract Amount of$18,157,336.00, and Adopt the Attached Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2022-2026 Capital Improvement Program RECOMMENDATION: It is recommended that the City Council: 1. Authorize execution of Change Order No. 4 in the Amount of$399,750.00 to City Secretary Contract No. 54148, a contract with Eagle Contracting, LP, for the Village Creek Water Reclamation Facility Thickener Process Improvements project for a revised contract amount of$18,157,336.00; and 2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water & Sewer Bond 2017A Fund in the amount of$399,750.00, from available funds, for the purpose of funding the Village Creek Water Reclamation Facility Thickener Process Improvement Project (City Project Number CO2647) to effect a portion of Water's contribution to the Fiscal Years 2022-2026 Capital Improvement Program. DISCUSSION: On June 23, 2020, Mayor and Council Communication (M&C) 20-0464, authorized a contract with Eagle Contracting LP, City Secretary Contract No. (CSC No. 54148) in the amount of$17,480,000.00 for the Village Creek Reclamation Facility Thickener Process Improvements project. The contract was subsequently revised by Change Order No. 1 in the amount of$91,838.00, administratively authorized January 22, 2021, that provided for concrete demo and repair, cast stone replacements and feed pump motors; Change Order No. 2 in the amount of$97,017.00 (M&C 21-0371) authorized by City Council, June 8, 2021 that primarily provided for primary grit sludge header pipe rehabilitation and Change Order No. 3, administratively authorized February 21, 2022, in the amount of$88,731.00, that provided lead abatement at the thickening facility, odor control foundation, bypass work at the blend tank and annular seals. Change Order No. 4 will provide for the following:,rehabilitation, painting and modifications to Blend Tank piping as well as wall coatings, structural repair and modification for the Blend Tank lid-cover, and necessary ancillary work. It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds in support of the Water's portion of the City of Fort Worth's Fiscal Years 2022-2026 Capital Improvement Program, as follows: 60VCWRF THICKENING C04— EAGLE Budget Revised Capital Fund FY2022 CIP Change Name Project Name Appropriations Authority (Increase/ FY2022 Decrease) Budget Water & Sewer CO2647 — � $ - This M&C �$399,750.901$399,750.00 CERTIFICATIONS: Submitted for City Manager's Office by_ Dana Burghdoff (8018) Originating Department Head: Chris Harder (5020) Additional Information Contact: Faridya Goderya (8214) ATTACHMENTS 1. 60VCWRF THICKENING C04-EAGLE.docx (CFW Internal) 2. 60VCWRF THICKENING CO4 - EAGLE 1295.pdf (CFW Internal) 3. 60VCWRF THICKENING CO4 - EAGLE APC CPN CO2647.pdf (CFW Internal) 4. 60VCWRF THICKENING CO4 - EAGLE FID Table (WCF 03.23.22).xlsx (CFW Internal) 5. 60VCWRF THICKENING CO4 - EAGLE MAP.pdf (Public) 6. 60VCWRF THICKENING CO4 - EAGLE PBS CPN CO2647.pdf (Public) 7. 60VCWRF THICKENING CO4 - EAGLE SAM.pdf (CFW Internal) 8. 60VCWRF THICKENING CO4 — EAGLE 56011 AO22(r2).docx (Public) -n T T C C C • O_ • • O_ • • • • Q m 0 m a v • D D D _ _ n _ n O O O O • O O m m am a a m • C • • m - - 0 m c m m e m e d CL xIm d d rL m 1+ m Nm N0 NO I '.. ""11 z "a A _ m m = QQ Lo Ol �'' 01 O1 m 3 X a rt r 3 f+ 3 3 o M O O c gyp' c c Z • m • • CL e. c c c O O O (A 4A m m m x x x m m m Proposed Contract Modification Project VCWRF Sludge Thickening Improvements Project Number Owner City of Fort Worth CO2647 Contractor Eagle Contracting, LP Construction Manager Freese and Nichols, Inc. Design Professional Freese and Nichols, Inc. PCM No. 012 REV 2 Description Blend Tank Feed Lines and Wall Coating NOTIFICATION TO CONTRACTOR: The Owner proposes to make the additions, modifications or deletions to the Work described in the Contract Documents as shown in Attachment"A". We request that you take the following action within 10 calendar days: Notify us that you concur that this change does not require a change in Contract time or amount. A Field Order will be issued. Submit a Price/Credit Proposal with detailed cost breakdown of labor, materials, equipment and all other costs related to this change. Impacts on Contract Time shall be shown in a revised schedule, included with the submitted proposal. F- Proceed with the change. Payment will be made at the unit price bid. F Proceed with the change under the time and materials provisions of the Contract. Authorization to proceed with changes must be approved by the Owner through Change Order in accordance with the Contract Documents. BY: Nick Landes DATE: 12 8 2021 CONTRACTOR'S RESPONSE: We respond to your request as follows: F- We propose that this is a no cost or time change. Issue Field Order. I� We submit the attached Price/Credit Proposal with detailed cost breakdown and revised schedule for performing the described change. We are proceeding with the change at the unit price bid. F We are proceeding with the change under the time and materials provisions of the Contract, BY: Philip Bennett DATE: 3 4 2022 ACTION TAKEN: r Proposed Contract Modification rejected. Field Order will be issued. Change Order will be issued. BY: Chad Simmons DATE: 3 8 2022 Approved for $196,515 with additional 30 Contract Days. ATTACHMENT A The Owner proposes to make the following additions, modifications or deletions to the work described in the Contract Documents. Authorization to proceed with these changes must be approved by Field Order or Change Order in accordance with the Contract Documents,prior to commencing the work involved. Changes: Provide a price proposal for the following changes resulting from this modification. Modify the existing inlet pipes (8-TWS-S, 12-DP-S)and proposed inlet pipes (10-TS/TWS-DI)to the Blend Tank as indicated in the attached drawing BT-M3. Coat the interior concrete walls of the Blend Tank per Specification 09 96 01 as indicated in the attached drawings. The coating shall be from the bottom to the top of the side wall. The floor will not be coated. Coat the existing ductile iron effluent pipe that runs along the floor and well as the existing ductile iron overflow pipe per Specification 09 96 00.01 2 Village Creek WRF-Sludge Thickening Improvements PCM-No.12-REV 1 Date:3-4-22 Work Description L`t�l T E Modify the existing inlet pipes(including coring existing walls), j-Yr, i (—� coat the interior walls of the tank per 09 96 01,and paint the CONTRACTING, L.P. existing effluent pipe on the floor and overflow pipe per 09 96 00.01. Owner: Engineer: Contractor: Fort Worth Water Utilities Freese&Nichols Eagle Contracting 4055 International Plaza,Ste 200 5700 Park Vista Circle Ft.Worth,TX 76109 Ft Worth,Texas 76244 Chad Simmons Labor Material Equipment Subcontractor TOTALS: $ 5,730.40 $ 23,256.56 $ 8,605.88 $ 143,699.50 $181,292.34 Eagle Insurance 0.25% $453.23 Overhead&Profit-5%Subcontracted Work $7,184.98 Overhead&Profit-15%Self Performed Work $5,638.93 Subtotal $194,569.47 Bond @ 1% $1,945.69 Subtotal $196,515.16 Total Amount This Cost Proposal $196,515.16 I Time Extension Required-30 Days I Includes time for scope in PCM-18(Lid Repairs),etc. V ROUNDED $ 196,515.00 NOTE: Per direction of Fort Worth, Eagle has adjusted the time of the work for both PCM-12 and PCM-18 to be 30 days total. Should the work take longer than 30 days,Eagle reserves the right to request the additional time be added. Proposed Contract Modification Project VCWRF Sludge Thickening Improvements Project Number Owner City of Fort Worth CO2647 Contractor Eagle Contracting, L.P Construction Manager Freese and Nichols, Inc. Design Professional Freese and Nichols, Inc. PCM No. 018 Description Blend Tank Cover NOTIFICATION TO CONTRACTOR: The Owner proposes to make the additions, modifications or deletions to the Work described in the Contract Documents as shown in Attachment "A". We request that you take the following action within 10 calendar days: Notify us that you concur that this change does not require a change in Contract time or amount. A Field Order will be issued. Submit a Price/Credit Proposal with detailed cost breakdown of labor, materials, equipment and all other costs related to this change. Impacts on Contract Time shall be shown in a revised schedule, included with the submitted proposal. I I Proceed with the change. Payment will be made at the unit price bid. I Proceed with the change under the time and materials provisions of the Contract. Authorization to proceed with changes must be approved by the Owner through Change Order in accordance with the Contract Documents. BY: Chad Simmons DATE: 1 20 2022 CONTRACTOR'S RESPONSE: We respond to your request as follows: 1-1 We propose that this is a no cost or time change. Issue Field Order. 1°I We submit the attached Price/Credit Proposal with detailed cost breakdown and revised schedule for performing the described change. 1 I We are proceeding with the change at the unit price bid. 1 We are proceeding with the change under the time and materials provisions of the Contract. _ BY: Philip Bennett DATE: 3 7 2022 ACTION TAKEN: rl Proposed Contract Modification rejected. i I Field Order will be issued. Change Order will be issued. BY: Chad Simmons DATE: 3 9 2022 Approved for $203,235 with 0 additional Contract Days. ATTACHMENT A The Owner-proposes to make the following additions, modifications or deletions to the work described in the Contract Documents. Authorization to proceed with these changes must be approved by Field Order or Change Order in accordance with the Contract Documents,prior to commencing the work involved. Changes: Provide a cost proposal for the following changes resulting from this modification. Provide structural modifications to the Blend Tank cover per the attached. All welding shall be completed by AWS certified welders in the welding process with which the welder is working. Surface preparation and coating of the cover shall be per requirements of the Contract,Specification 09 96 00.01 "High-Performance Coatings". 2 Village Creek WRF-Sludge Thickening Improvements PCM-No.18-REV 4 Date:3-7-22 Work Description 1�� T, Blast Blend Tank lid,inspect surface of metal,remove / components of structural beams,etc,weld new plates,stiffeners, CONTRACTING, L P. angles,and repair concrete with SIKATOP 123 Plus. Owner: Engineer: Contractor: Fort Worth Water Utilities Freese&Nichols Eagle Contracting 4055 International Plaza,Ste 200 5700 Park Vista Circle Ft.Worth,TX 76109 Ft Worth,Texas 76244 Chad Simmons Labor Material Equipment Subcontractor TOTALS: $ 4,611.68 $ 51,004.78 $ 1,597.99 $ 128,535.00 $185,749.45 Eagle Insurance 0.25% $464.37 Overhead&Profit-5%Subcontracted Work $6,426.75 Overhead&Profit-15%Self Performed Work $8,582.17 Subtotal $201,222.74 Bond @ 1% $2,012.23 Subtotal $203,234.96 Total Amount This Cost Proposal $203,234.96 I Time Extension Required- In unison with PCM-12 scope of work I V ROUNDED $ 203,235.00 NOTE: 1.The pricing currently includes two(2)plate patches per Dtl 5/BT-S2. Eagle reserves the right to price up additional patches at the rate of$55/sf that may become apparent after the first blasting. 2.An additional blasting will be required because the lid will have to be initially blasted to prepare the surface to install the new steel components.Subsequently,the lid will need to be reblasted(per contract)in order to remove any rust that accumulates during the repairs,and prior to being coated. 3.The pricing includes 4 places approximately 2'x 2'of SIKATOP 123 Plus repair per Dtl 5/BT-S3. Any additional areas required will be subject to additional cost beyond this pricing. Additional patches will be at the rate of S85/sf