HomeMy WebLinkAboutContract 56638-CO2 CSC No. 56638-0O2
FORT WORTH City of Fort Worth
Change Order Request
Project Name: 2018 Bond Yr 2-Contract 6 City Sec No.: 56638
Project No.(s): 56002/0700430/5740010 M&C: 22-0294 City Proj.No.: 101452-2
Project Description: Water,Sanitary Sewer followed by Paving improvement on several streets in CD 3
Contractor: Texas Materials Group dba Texas Bit Change Order# Date: 1 5/3/2022
City Project Mgr. Brenda Oropeza City Inspector: Steve Cisneros
Phone Number: 817-392-8271 Phone Number: 817-392-7925
Dept. Water Sewer Paving Totals Contract Time
(Calender days)
Original Contract Amount $2,079,497.19 $3,115,607.22 $1,997,562.10 $7,192,666.51 450
Extras to Date $851,816.79 $851,816.79 060
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $2,079,497.19 $3,967,424.01 $1,997,562.10 $8,044,483.30 510
Amount of Proposed Change Order $0.00 -$211.09 $0.00 .$211.09 0
Revised Contract Amount $2,079,497.19 $3,967,212.92 $1,997,562.10 $8,044,272.21 510
Original Funds Available for Change Orders $83,180.81 $124,624.78 $99,878.00 $307,683.59
Remaining Funds Available for this CO $83,180.81 $124,625.78 $99,878.00 $307,684.59
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 11.84%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+2591o) $8,990,833.14
JUSTIFICATION (REASONS)FOR CHANGE ORDER
This change order will provide for the following:
The replacement of ductile iron pipe for PVC(C-900)pipe due to non-availability of ductile iron pipe
The reduction in the cost of the project by-pass pumping due to the reduction in the overall length of by-pass pumping that is required as a
segment of the project no longer required by-pass pumping.
Rehab of an existing junction structure with epoxy coating
The installation of a 4'diameter drop manhole in lieu of a standard 4'diamter manhole due to a connecting line that was encountered at a
different elevation than indication on the project plans.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name ontr ctor Signature Date
Texas Materials Group dba Texas Bit Jamie Greenway 5-10-2022
Inspector Date Project Manag Date
Steve Cisneros. 5-11-22
Director Water Dept Date Construction Supervisor TPW Dept) Date
May 31,2022 IA42A, 5/10/22
Assistant City Attorney Date Assistant City Man er Date
�k� ,p May 31,2022 pry Jun 1,2022
Council Action If Required OFFICIAL RECORD
M&C Number N/A M&C Date Approved CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name 2018 Bond Yr 2-Contract 6 City Sec No.: 56638
Project No.(s): 56002/0700430/5740010 DOE No. 22-0294 City Proj.No.: 101452-2
Project Description Water,Sanitary Sewer followed by Paving improvement on several streets in CD 3
Contractor Texas Materials Group dba Texas Bit I Change Order:= Date: 5/3/2022
City Project Mgr. Brenda Oropeza City Inspector Fsteve Cisneros
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
II-74 24"C-900 DR-25-Green Sewer 325.00 LF $328.90 $106,892.50
II-75 Connect to Junction Box Sewer 1.00 EA $10,292.50 $10,292.50
II-76 30"Hole&Cover in Junction Box Sewer 1.00 EA $3,105.00 $3,105.00
II-77 Rehab and coat existing junction structure Sewer 1.00 EA $26,063.60 $26,063.60
II-78 Bypass Pumping Sewer 1.00 LS $263,034.91 $263,034.91
II-79 4'Drop Manhole Sewer 1.00 EA $15,400.00 $15,400.00
Water
Sewer $424,788.51
Paving
Page 2 of 4 Additions Sub Total $424,788.51
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name 2018 Bond Yr 2-Contract 6 City Sec No.: 56638
Project No.(s): 56002/0700430/5740010 DOE No. 22-02 City Proj. No.: 101452-2
Project Description Water,Sanitary Sewer followed by Paving improvement on several streets in CD 3
Contractor Texas Materials Group dba Texas Bit Change Order: 111 Date 5/3/2022
City Project Mgr. Brenda Oropeza City Inspector: Steve Cisneros
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
3 24"D.I.SS(401 Liner) Sewer 173.00 LF $333.86 $57,757.78
7 339.1001 4'Manhole Sewer 1.00 EA $6,567.66 $6,567.66
13 Bypass Pumping Sewer 1.00 LS $295,544.84 $295,544.84
40 Remove Sewer Junction Structure Sewer 1.00 LS $4,925.74 $4,925.74
70A Sanitary Sewer Junction Box,Standard Concrete with Conshield A Sewer 1.00 LS $60,203.58 $60,203.58
Water
Sewer $424,999.60
Paving
Deletions Sub Total $424,999.60
Page 3 of 4
MNVBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
Page 4 of 4
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Brenda Oropeza
Name of Employee
Graduate Engineer
Title
a ti
ATTEST: � !°�OR 0k
° o
�o °o���
9ah.r�e�te Sr7�CG v g o=A
O °y
Jannette S.Goodall(Jun 1, HST) o° °°o T�
o T
Jannette Goodall ��� 0000000 a
�SEX A`'.00Ap
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
5/18/22
CPN 101452-2
2018 Bond Yr 2 — Contract 6
Change Request 2 Notes
The contract modification request is attached. This change order will address the pipe
material change from ductile iron pipe with protecto 401 coating to PVC (C-900) pipe
due to non-availability of DIP as well as coating issues. This contract modification will
also account for the removal of one of the two bypass pump locations and the
rehabilitation and coating of a junction structure rather than full replacement. The
change order will also replace a standard 4' manhole with a drop manhole due to
existing conditions encountered during construction. Staff reviewed recently bid projects
and considers the proposed unit prices to be fair and reasonable.