Loading...
HomeMy WebLinkAboutContract 46526 (2) �C/ITTYSECRETARY FORTWORT, �� VVia N�51CT NOe - PROJECT MANUAL FOR THE CONSTRUCTION OF MARY'S CREEK RECYCLING CENTER TREE PLANTING and IRRIGATION SYSTEM City Project No.01239 Betsy Price David Cooke Mayor City Manager Andrew Cronberg, P.E. Interim Director, Water Department Prepared for The City of Fort Worth Water Department 2014 �: '•S 1t1 i MICHAEL R. H098S rn TranSystems r 108644 i 500 W. 7' Street, Suite #1100 'f tit � �/ • '� ' Fort Worth, TX 76102 /� ` S, • • . cc a =- OFFICIAL RECORD CITY SECRETARY FT'.WORTHY TX 000000-0 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 0 of 2 SECTION 00 00 00 TABLE OF CONTENTS Division 00-General Conditions 00 05 10 Mayor and Council Communication 0005 15 Addenda 0011 13 Invitation to Bidders 0021 13 Instructions to Bidders 0035 13 Conflict of Interest Affidavit 00 41 00 Bid Form 00 42 43 Proposal Form Unit Price 0043 13 Bid Bond 00 43 37 Vendor Compliance to State Law Nonresident Bidder 00 45 11 Bidders Prequalifications 0045 12 Prequalification Statement 00 45 13 Bidder Prequalification Application 00 45 26 Contractor Compliance with Workers'Compensation Law 00 45 40 Minority Business Enterprise Goal 00 52 43 Agreement 0061 13 Performance Bond 0061 14 Payment Bond 0061 19 Maintenance Bond 00 61 25 Certificate of Insurance 00 72 00 General Conditions 00 73 00 Supplementary Conditions Division 01 -General Requirements 01 1100 Summary of Work 01 2500 Substitution Procedures 01 31 19 Preconstruction Meeting 01 3120 Project Meetings 01 32 16 Construction Progress Schedule 01 3233 Preconstruction Video 01 33 00 Submittals 01 35 13 Special Project Procedures 01 45 23 Testing and Inspection Services 01 50 00 Temporary Facilities and Controls 01 55 26 Street Use Permit and Modifications to Traffic Control 01 57 13 Storm Water Pollution Prevention Plan 0158 13 Temporary Project Signage 01 60 00 Product Requirements 01 66 00 Product Storage and Handling Requirements 01 70 00 Mobilization and Remobilization 01 71 23 Construction Staking and Survey 01 74 23 Cleaning 01 77 19 Closeout Requirements 01 78 23 Operation and Maintenance Data 01 78 39 Project Record Documents CrrY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 22,2013 00 00 00-1 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 1 of 2 Technical Specifications which have been modified by the Engineer specifically for this Project; hard copies are included in the Project's Contract Documents Division 32-Exterior Improvements 32 90 10 Landscape Irrigation System 3291 19 Topsoil Placement and Finishing of Parkways 32 93 43 Trees and Shrubs Division 34-Transportation 34 41 30 Aluminum Signs Appendix GC-6.061) Minority and Women Owned Business Enterprise Compliance GC-6.07 Wage Rates END OF SECTION CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 22,2013 C"11tv of Fort Worth, Texas CommunicationMayor and Council COUNCIL ACTION: Approved on 2/3/2015 DATE: Tuesday,February 03, 2015 REFERENCE NO.: **C-27171 LOG NAME: 60MARY'S CREEK WRC TREE PLANTING&IRRIGATION SUBJECT: Authorize Execution of a Contract with C. Green Scaping,LP,in the Amount of$98,492.09 for Mary's Creek Water Reclamation Facility Site Tree Planting and Irrigation System,Located Along Chapin Road in Western Tarrant County and Provide for Project Costs and Contingencies for a Total Project Cost of$108,492.09 (ADJACENT TO COUNCIL DISTRICT 3) RECOMMENDATION: It is recommended that the City Council authorize the execution of a contract with C. Green Scaping,LP, in the amount of$98,492.09 for Mary's Creek Water reclamation facility site tree planting and irrigation system,located along Chapin Road in western Tarrant County and provide for project costs and contingencies for a total project cost of$108,492.09. DISCUSSION: On February 24, 2009, (M&C C&minus;23367) the City Council authorized the City Manager to execute an Engineering Agreement in the amount of$247,407.00 with TranSystems to conduct site selection of a Water Reclamation Facility (WRF) within the Mary's Creek drainage basin west of Loop 820 West. On July 26, 2011 (M&C L&minus;15222),the City Council authorized the City Manager to acquire 100 acres of land located along Chapin Road in western Tarrant County for the future Mary's Creek WRF. The Fort Worth Water Department is planting trees along the northern property line to provide an aesthetic natural barrier for the future Mary's Creek WRF. This project was advertised for bid on October 30, 2014 and November 6,2014 in the Fort Worth Star—Telegram. On December 3, 2014,the following bid was received: BIDDER kMOUNT C. GREEN SCAPING,LP 1$98,492.09 In addition to the contract cost,$5,000.00 is required for Staff time and$5,000.00 is provided for project contingencies. M/WBE Office—C. Green Scaping, LP,is in compliance with the City's BDE Ordinance by submission of the prime contractor waiver form. The City's MBE goal on this project is 10 percent. Additionally, C. Green Scaping,LP,is a certified M/WBE firm. This project is located adjacent to COUNCIL DISTRICT 3, Mapsco 71L. FISCAL INFORMATION: The Financial Management Services Director certifies that funds are available in the current capital budget, as appropriated, of the Sewer Capital Projects Fund. FUND CENTERS: TO Fund/Account/Centers FROM Fund/Account/Centers P258 541200 703190123980 $98,492.09 CERTIFICATIONS: Submitted for City Manager's Office by: Fernando Costa (6122) Originating Department Head: Andy Cronberg (5020) Additional Information Contact: Farida Goderya (8214) ATTACHMENTS 1. 60MARYS CREEK WRC TREE PLANTING IRRIGATION MAP Revised 18 15.pdf 2. 60MARYS CREEK WRC TREE PLANTING IRRIGATION MWBE.pdf 3. C Green Scaring LP SAM SEARCH.pdf 4. FAR-00006 CIP#01239 P258.pdf 5. P258 467045 701139990100.docx 0005 15-1 ADDENDA Page 1 of I 1 SECTION 00 05 15 2 ADDENDA 3 4 5 6 [Assembler: For Contract Document execution, remove this page and replace with any addenda 7 issued during bidding.] 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 END OF SECTION CITY OF FORT WORT" Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised July 1,2011 0011 13-1 INVITATION TO BIDDERS Page 1 of 2 1 SECTION 00 1113 2 INVITATION TO BIDDERS 3 4 RECEIPT OF BIDS 5 Sealed bids for the construction of Mary's Creek Recycling Center Tree Planting and Irrigation, 6 City Project No. 01239,will be received by the City of Fort Worth Purchasing Office: 7 8 City of Fort Worth 9 Purchasing Division 10 1000 Throckmorton Street I I Fort Worth,Texas 76102 12 until 1:30 P.M. CST,Thursday, December 4,2014, and bids will be opened publicly and read 13 aloud at 2:00 PM CST in the Council Chambers. 14 15 GENERAL DESCRIPTION OF WORK 16 The major work will consist of the(approximate)following: 17 18 Furnish and install 23 trees of various types,transport and install 20 furnished trees and 19 install drip irrigation system. 20 2I PREQUALIFICATION 22 The improvements included in this project do not require a contractor who is pre-qualified by the 23 City for this scope of work. 24 25 DOCUMENT EXAMINATION AND PROCUREMENTS 26 The Bidding and Contract Documents may be examined or obtained on-line by visiting the City 27 of Fort Worth's Purchasing Division website at http:r/www.fortworthaov.org/purchasina/and 28 clicking on the Buzzsaw link to the advertised project folders on the City's Buzzsaw site.The 29 Contract Documents may be downloaded, viewed,and printed by interested contractors and/or 30 suppliers. 31 32 Copies of the Bidding and Contract Documents may be purchased from 33 TranSystems 34 500 West 71h Street, Suite 1100 35 Fort Worth,Texas 76102 36 37 The cost of Bidding and Contract Documents is: 38 Set of Bidding and Contract Documents with full size drawings: $100.00. A 24-hour advance 39 notice is needed prior to picking up contract documents and drawings. 40 41 Set of Bidding and Contract Documents with half size(if available)drawings: N/A 42 43 PREBID CONFERENCE 44 A prebid conference will not be held for this project. 45 46 47 CITY'S RIGHT TO ACCEPT OR REJECT BIDS 48 City reserves the right to waive irregularities and to accept or reject bids. 49 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised July 1,2011 001113-2 INVITATION TO BIDDERS Page 2 of 2 l INQUIRIES 2 All inquiries relative to this procurement should be addressed to the following: 3 Attn: Farida S. Goderya, PhD, PE,City of Fort Worth 4 Email: Farida.Goderya@fortworthtexas.gov 5 Phone: 817-392-8214 6 AND/OR 7 Attn: Michael Hobbs, PE,TranSystems 8 EmaiI: mrhobbs@transystems.com 9 Phone: 817-334-4449 10 11 ADVERTISEMENT DATES 12 October 30, 2014 13 November 6, 2014 14 15 END OF SECTION CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 0021 13-1 INSTRUCTIONS TO BIDDERS Page 1 of 9 i SECTION 00 2113 2 INSTRUCTIONS TO BIDDERS 3 1. Defined Terms 4 5 1.1.Terms used in these INSTRUCTIONS TO BIDDERS,which are defined in Section 00 72 6 00-GENERAL CONDITIONS. 7 8 1.2.Certain additional terns used in these INSTRUCTIONS TO BIDDERS have the 9 meanings indicated below which are applicable to both the singular and plural thereof. 10 11 1.2.1. Bidder: Any person, firm, partnership,company,association,or corporation acting 12 directly through a duly authorized representative,submitting a bid for performing 13 the work contemplated under the Contract Documents. 14 15 1.2.2, Nonresident Bidder: Any person, firm, partnership,company,association,or 16 corporation acting directly through a duly authorized representative,submitting a 17 bid for performing the work contemplated under the Contract Documents whose 18 principal place of business is not in the State of Texas. 19 20 1.2.3. Successful Bidder: The lowest responsible and responsive Bidder to whom City 21 (on the basis of City's evaluation as hereinafter provided) makes an award. 22 23 2. Copies of Bidding Documents 24 25 2.1.Neither City nor Engineer shall assume any responsibility for errors or misinterpretations 26 resulting from the Bidders use of incomplete sets of Bidding Documents. 27 28 2.2.City and Engineer in making copies of Bidding Documents available do so only for the 29 purpose of obtaining Bids for the Work and do not authorize or confer a license or grant 30 for any other use. 31 32 3. Prequalification of Bidders(Prime Contractors and Subcontractors) 33 34 3.1.All Bidders and their subcontractors are required to be prequalified for the work types 35 requiring prequalification at the time of bidding. Bids received from contractors who are 36 not prequalified(even if inadvertently opened)shall not be considered. Prequalification 37 requirement work types and documentation are as follows: 38 39 3.1.1. Paving---Requirements document located at; 40 https://projectpoint.buzzsaw.com/fortworthgov Resources/02%20- 41 %20Construction*o2ODocumentsF`Contractor°/o20Prequalification/TPW%20Paving 42 %20Contractor°/o2OPregualification%20Program/PREQUALIFICATION%20REQ 43 UI REM ENTS%20FOR%20PAVING%2000NTRACTORS.PDF?public 44 45 3.1.2. Roadway and Pedestrian Lighting—Requirements document located at; 46 https://projectpoint.buzzsaw.com/fortNvorthl;ov/Resources/02%`20- 47 %20Construction%2ODocuments!Contractor/o2OPrequalification/TPW%2OPavine 48 %20Contractoi4i62OPrequalification%2OProaram/PREQUALIFICATION%20REQ 49 UI REM ENTS%20FOR%20PAVING%2000NTRACTORS.PDF?public CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised November 27,2012 0021 13-2 INSTRUCTIONS TO BIDDERS Page 2 of l 2 3.1.3. Water and Sanitary Sewer—Requirements document located at; 3 https://Vroiectpoint.buzzsaw.com/fortworthaov/Resources//02%20- 4 %20Construction%2ODocumentslContractoO/o2OPrequaliFication/Waterl,o20and%2 5 OSanitary%2OSewero/o20Contractor%2OPrequalification%2OProgram/WSS%20pre 6 qua 1%20reguirements.doc?public 7 8 9 3.2.Each Bidder unless currently prequalified,must be prepared to submit to City within 10 seven(7)calendar days prior to Bid opening, the documentation identified in Section 00 11 45 11, BIDDERS PREQUALIFICATIONS. 12 13 3.2.1. Submission of and/or questions related to prequalification should be addressed to 14 the City contact as provided in Paragraph 6.1. 15 16 17 3.3.The City reserves the right to require any pre-qualified contractor who is the apparent low 18 bidder(s) for a project to submit such additional information as the City, in its sole 19 discretion may require, including but not limited to manpower and equipment records, 20 information about key personnel to be assigned to the project,and construction schedule, 21 to assist the City in evaluating and assessing the ability of the apparent low bidder(s)to 22 deliver a quality product and successfully complete projects for the amount bid within 23 the stipulated time frame. Based upon the City's assessment of the submitted . 24 information, a recommendation regarding the award of a contract will be made to the 25 City Council. Failure to submit the additional information, if*requested,may be grounds 6 for rejecting the apparent low bidder as non-responsive. Affected contractors will be 27 notified in writing of a recommendation to the City Council. 28 29 3.4.In addition to prequalification,additional requirements for qualification may be required 30 within various sections of the Contract Documents. 31 32 3.5.Special qualifications required for this project include the following: N/A 33 34 4. Examination of Bidding and Contract Documents,Other Related Data,and Site 35 36 4.1.Before submitting a Bid, each Bidder shall: 37 38 4.1.1. Examine and carefully study the Contract Documents and other related data 39 identified in the Bidding Documents(including"technical data" referred to in 40 Paragraph 4.2. below).No information given by City or any representative of the 41 City other than that contained in the Contract Documents and officially 42 promulgated addenda thereto,shall be binding upon the City. 43 44 4.1.2. Visit the site to become familiar with and satisfy Bidder as to the general, local and 45 site conditions that may affect cost,progress, performance or furnishing of the 46 Work. 47 48 4.1.3. Consider federal, state and local Laws and Regulations that may affect cost, 49 progress,performance or furnishing of the Work. 0 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 27,2012 0021 13.3 INSTRUCTIONS TO BIDDERS Page 3 of 9 1 4.1.4. Study all: (i)reports of explorations and tests of subsurface conditions at or 2 contiguous to the Site and all drawings of physical conditions relating to existing 3 surface or subsurface structures at the Site(except Underground Facilities) that 4 have been identified in the Contract Documents as containing reliable "technical 5 data"and(ii) reports and drawings of Hazardous Environmental Conditions,if any, 6 at the Site that have been identified in the Contract Documents as containing 7 reliable"technical data." 8 9 4.1.5. Be advised that the Contract Documents on file with the City shall constitute all of 10 the information which the City will furnish. All additional information and data I 1 which the City will supply after promulgation of the formal Contract Documents 12 shall be issued in the form of written addenda and shall become part of the Contract 13 Documents just as though such addenda were actually written into the original 14 Contract Documents. No information given by the City other than that contained in 15 the Contract Documents and officially promulgated addenda thereto,shall be 16 binding upon the City. 17 18 4.1.6. Perform independent research, investigations,tests,borings, and such other means 19 as may be necessary to gain a complete knowledge of the conditions which will be 20 encountered during the construction of the project. On request, City may provide 21 each Bidder access to the site to conduct such examinations, investigations, 22 explorations, tests and studies as each Bidder deems necessary for submission of a 23 Bid. Bidder must fill all holes and clean up and restore the site to its former 24 conditions upon completion of such explorations, investigations,tests and studies. 25 26 4.1.7. Determine the difficulties of the Work and all attending circumstances affecting the 27 cost of doing the Work, time required for its completion, and obtain all information 28 required to make a proposal. Bidders shall rely exclusively and solely upon their 29 own estimates,investigation,research,tests,explorations,and other data which are 30 necessary for full and complete information upon which the proposal is to be based. 31 It is understood that the submission of a proposal is prima-facie evidence that the 32 Bidder has made the investigation, examinations and tests herein required. Claims 33 for additional compensation due to variations between conditions actually 34 encountered in construction and as indicated in the Contract Documents will not be 35 allowed. 36 37 4.1.8. Promptly notify City of all conflicts,errors, ambiguities or discrepancies in or 38 between the Contract Documents and such other related documents.The Contractor 39 shall not take advantage of any gross error or omission in the Contract Documents, 40 and the City shall be permitted to make such corrections or interpretations as may 41 be deemed necessary for fulfillment of the intent of the Contract Documents. 42 43 4.2. Reference is made to Section 00 73 00 Supplementary Conditions for identification of: 44 45 4.2.1. those reports of explorations and tests of subsurface conditions at or contiguous to 46 the site which have been utilized by City in preparation of the Contract Documents. 47 The logs of Soil Borings, if any, on the plans are for general information only. 48 Neither the City nor the Engineer guarantee that the data shown is representative of 49 conditions which actually exist. 50 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 27,2012 0021 13-4 INSTRUCTIONS TO BIDDERS Page 4 of 9 I 4.2.2. those drawings of physical conditions in or relating to existing surface and 2 subsurface structures(except Underground Facilities)which are at or contiguous to 3 the site that have been utilized by City in preparation of the Contract Documents. 4 5 4.2.3. copies of such reports and drawings will be made available by City to any Bidder 6 on request. Those reports and drawings may not be part of the Contract 7 Documents, but the"technical data"contained therein upon which Bidder is entitled 8 to rely as provided in Paragraph 4.02.of the General Conditions has been identified 9 and established in Paragraph SC 4.02 of the Supplementary Conditions. Bidder is 10 responsible for any interpretation or conclusion drawn from any"technical data"or I I any other data,interpretations,opinions or information. 12 13 4.3.The submission of a Bid will constitute an incontrovertible representation by Bidder(i) 14 that Bidder has complied with every requirement of this Paragraph 4,(ii)that without 15 exception the Bid is premised upon performing and furnishing the Work required by the 16 Contract Documents and applying the specific means, methods, techniques,sequences or 17 procedures of construction(if any) that may be shown or indicated or expressly required 18 by the Contract Documents, (iii)that Bidder has given City written notice of all 19 conflicts,errors,ambiguities and discrepancies in the Contract Documents and the 20 written resolutions thereof by City are acceptable to Bidder,and when said conflicts, 21 etc.,have not been resolved through the interpretations by City as described in 22 Paragraph 6., and(iv) that the Contract Documents are generally sufficient to indicate 23 and convey understanding of all terms and conditions for performing and furnishing the 24 Work. 25 26 4.4.The provisions of this Paragraph 4, inclusive,do not apply to Asbestos, Polychlorinated 27 biphenyls(PCBs), Petroleum,Hazardous Waste or Radioactive Material covered by 28 Paragraph 4.06. of the General Conditions, unless specifically identified in the Contract 29 Documents. 30 31 5. Availability of Lands for Work, Etc. 32 33 5.1.The lands upon which the Work is to be performed, rights-of-way and easements for 34 access thereto and other lands designated for use by Contractor in performing the Work 35 are identified in the Contract Documents. All additional lands and access thereto 36 required for temporary construction facilities,construction equipment or storage of 37 materials and equipment to be incorporated in the Work are to be obtained and paid for 38 by Contractor. Easements for permanent structures or permanent changes in existing 39 facilities are to be obtained and paid for by City unless otherwise provided in-the 40 Contract Documents. 41 42 5.2.Outstanding right-of-way, easements, and/or permits to be acquired by the City are listed 43 in Paragraph SC 4.01 of the Supplementary Conditions. In the event the necessary right- 44 of-way, easements, and/or permits are not obtained, the City reserves the right to cancel 45 the award of contract at any time before the Bidder begins any construction work on the 46 project. 47 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 27,2012 0021 13-5 INSTRUCTIONS TO BIDDERS Page5 or9 1 5.3. The Bidder shall be prepared to commence construction without all executed right-of- 2 way, easements,and/or permits,and shall submit a schedule to the City of how 3 construction will proceed in the other areas of the project that do not require permits 4 and/or easements. 5 6 6. Interpretations and Addenda 7 8 6.1.All questions about the meaning or intent of the Bidding Documents are to be directed to 9 City in writing on or before 2 p.m.,the Monday prior to the Bid opening. Questions to received after this day may not be responded to. Interpretations or clarifications I I considered necessary by City in response to such questions will be issued by Addenda 12 delivered to all parties recorded by City as having received the Bidding Documents. 13 Only questions answered by formal written Addenda will be binding. Oral and other 14 interpretations or clarifications will be without legal effect. 15 16 Address questions to: 17 18 City of Fort Worth 19 1000 Throckmorton Street 20 Fort Worth,TX 76102 21 Attn: Farida S. Goderya, PhD, PE, Water Department 22 Email: farida.goderya@fortworthtexas.gov 23 Phone: 817-392-8214 24 25 26 6.2.Addenda may also be issued to modify the Bidding Documents as deemed advisable by 27 City. 28 29 6.3.Addenda or clarifications may be posted via Buzzsaw at 30 httpv:ll` +•ojectpoittt.bttzz.sattt.co)ttI b_ rest,'lieb.,Hontelliidev?folder-17491#,% b, r,esti1V 31 eb.11tetti.'ItentsJ61cler=12 0 32 33 6.4.A prebid conference may be held at the time and place indicated in the Advertisement or 34 INVITATION TO BIDDERS. Representatives of City will be present to discuss the 35 Project. Bidders are encouraged to attend and participate in the conference. City will 36 transmit to all prospective Bidders of record such Addenda as City considers necessary 37 in response to questions arising at the conference. Oral statements may not be relied 38 upon and will not be binding or legally effective. 39 40 7. Bid Security 41 42 7.1.Each Bid must be accompanied by Bid Bond made payable to City in an amount of five 43 (5) percent of Bidder's maximum Bid price on form attached, issued by a surety meeting 44 the requirements of Paragraphs 5.0I of the General Conditions. 45 CITY OF FORT WORTH Mary's Cm-ek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 27,2012 0021 13•6 INSTRUCTIONS TO BIDDERS Page 6 of 9 1 7.2.The Bid Bond of all Bidders will be retained until the conditions of the Notice of Award 2 have been satisfied. If the Successful Bidder fails to execute and deliver the complete 3 Agreement within 10 days after the Notice of Award,City may consider Bidder to be in 4 default,rescind the Notice of Award,and the Bid Bond of that Bidder will be forfeited. 5 Such forfeiture shall be City's exclusive remedy if Bidder defaults. The Bid Bond of all 6 other Bidders whom City believes to have a reasonable chance of receiving the award 7 will be retained by City until final contract execution. 8 9 8. Contract Times 10 The number of days within which,or the dates by which, Milestones are to be achieved in 11 accordance with the General Requirements and the Work is to be completed and ready for 12 Final Acceptance is set forth in the Agreement or incorporated therein by reference to the 13 attached Bid Form, 14 15 9. Liquidated Damages 16 Provisions for liquidated damages are set forth in the Agreement. 17 18 10. Substitute and "Or-Equal" Items 19 The Contract, if awarded,will be on the basis of materials and equipment described in the 20 Bidding Documents without consideration of possible substitute or"or-equal" items, 21 Whenever it is indicated or specified in the Bidding Documents that a "substitute" or"or- 22 equal" item of material or equipment may be furnished or used by Contractor if acceptable to 23 City, application for such acceptance will not be considered by City until after the Effective 24 Date of the Agreement. The procedure for submission of any such application by Contractor 25 and consideration by City is set forth in Paragraphs 6.05A., 6.05B. and 6,05C.of the General )6 Conditions and is supplemented in Section 0125 00 of the General Requirements. 27 28 11, Subcontractors,Suppliers and Others 29 30 11.1. In accordance with the City's Business Diversity Enterprise Ordinance No. 20020- 31 12-2011 (as amended), the City has goals for the participation of minority business 32 and/or small business enterprises in City contracts. A copy of the Ordinance can be 33 obtained from the Office of the City Secretary. The Bidder shall submit the MBE and 34 SBE Utilization Form,Subcontractor/Supplier Utilization Form, Prime Contractor 35 Waiver Form and/or Good Faith Effort Form with documentation and/or Joint 36 Venture Form as appropriate. The Forms including documentation must be received 37 by the City no later than 5:00 P.M. CST, five(5) City business days after the bid 38 opening date.The Bidder shall obtain a receipt from the City as evidence the 39 documentation was received. Failure to comply shall render the bid as non- 40 responsive. 41 42 11.2. No Contractor shall be required to employ any Subcontractor, Supplier,other person 43 or organization against whom Contractor has reasonable objection. 44 45 12. Bid Form 46 47 12.1. The Bid Form is included with the Bidding Documents; additional copies maybe 48 obtained from the City. 49 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 27,2012 0021 13-7 INSTRUCTIONS TO BIDDERS Page 7 of 9 1 12.2. All blanks on the Bid Form must be completed by printing in ink and the Bid Form 2 signed in ink. Erasures or alterations shall be initialed in ink by the person signing 3 the Bid Form. A Bid price shall be indicated for each Bid item, alternative, and unit 4 price item listed therein. In the case of optional alternatives,the words "No Bid," 5 "No Change," or"Not Applicable" may be entered. Bidder shall state the prices, 6 written in ink in both words and numerals, for which the Bidder proposes to do the 7 work contemplated or furnish materials required. Ail prices shall be written legibly. 8 In case of discrepancy between price in written words and the price in written 9 numerals, the price in written words shall govern. 10 11 12.3. Bids by corporations shall be executed in the corporate name by the president or a 12 vice-president or other corporate officer accompanied by evidence of authority to 13 sign. The corporate seal shall be affixed. The corporate address and state of 14 incorporation shall be shown below the signature. 15 16 12.4. Bids by partnerships shall be executed in the partnership name and signed by a 17 partner, whose title must appear under the signature accompanied by evidence of 18 authority to sign. The official address of the partnership shall be shown below the 19 signature. 20 21 12.5. Bids by limited liability companies shall be executed in the name of the firm by a 22 member and accompanied by evidence of authority to sign. The state of formation of 23 the firm and the official address of the firm shall be shown. 24 25 12.6. Bids by individuals shall show the Bidder's name and official address. 26 27 12.7. Bids by joint ventures shall be executed by each joint venturer in the manner 28 indicated on the Bid Form. The official address of the joint venture shall be shown. 29 30 12.8. All names shall be typed or printed in ink below the signature. 31 32 12.9. The Bid shall contain an acknowledgement of receipt of all Addenda,the numbers of 33 which shall be filled in on the Bid Form. 34 35 12.10. Postal and e-mail addresses and telephone number for communications regarding the 36 Bid shall be shown. 37 38 12.11. Evidence of authority to conduct business as a Nonresident Bidder in the state of 39 Texas shall be provided in accordance with Section 00 43 37^Vendor Compliance 40 to State Law Non Resident Bidder. 41 42 13. Submission of Bids 43 Bids shall be submitted on the prescribed Bid Form,provided with the Bidding Documents, 44 at the time and place indicated in the Advertisement or INVITATION TO BIDDERS, 45 addressed to City Manager of the City, and shall be enclosed in an opaque sealed envelope, 46 marked with the City Project Number, Project title, the name and address of Bidder,and 47 accompanied by the Bid security and other required documents. If the Bid is sent through the 48 mail or other delivery system,the sealed envelope shall be enclosed in a separate envelope 49 with the notation "BID ENCLOSED" on the face of it. 50 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 27,2012 0021 13-8 INSTRUCTIONS TO BIDDERS Page 8 of 9 1 14. Modification and Withdrawal of Bids 2 3 14.1. Bids addressed to the City Manager and filed with the Purchasing Office cannot be 4 withdrawn prior to the time set for bid opening. A request for withdrawal must be 5 made in writing by an appropriate document duly executed in the manner that a Bid 6 must be executed and delivered to the place where Bids are to be submitted at any 7 time prior to the opening of Bids. After all Bids not requested for withdrawal are 8 opened and publicly read aloud,the Bids for which a withdrawal request has been 9 properly filed may,at the option of the City, be returned unopened. 10 11 14.2. Bidders may modify their Bid by electronic communication at any time prior to the 12 time set for the closing of Bid receipt. 13 14 15. Opening of Bids 15 Bids will be opened and read aloud publicly at the place where Bids are to be submitted. An 16 abstract of the amounts of the base Bids and major alternates(if any)will be made available 17 to Bidders after the opening of Bids. 18 19 16. Bids to Remain Subject to Acceptance 20 All Bids will remain subject to acceptance for the time period specified for Notice of Award 21 and execution and delivery of a complete Agreement by Successful Bidder. City may, at 22 City's sole discretion,release any Bid and nullify the Bid security prior to that date. 23 24 17. Evaluation of Bids and Award of Contract 25 26 17.1. City reserves the right to reject any or all Bids, including without limitation the rights 27 to reject any or all nonconforming,nonresponsive,unbalanced or conditional Bids 28 and to reject the Bid of any Bidder if City believes that it would not be in the best 29 interest of the Project to make an award to that Bidder,whether because the Bid is 30 not responsive or the Bidder is unqualified or of doubtful financial ability or fails to 31 meet any other pertinent standard or criteria established by City. City also reserves 32 the right to waive informalities not involving price,contract time or changes in the 33 Work with the Successful Bidder. Discrepancies between the multiplication of units 34 of Work and unit prices will be resolved in favor of the unit prices. Discrepancies 35 between the indicated sum of any column of figures and the correct sum thereof will 36 be resolved in favor of the correct sum. Discrepancies between words and figures 37 will be resolved in favor of the words. 38 39 17.1.1. Any or all bids will be rejected if City has reason to believe that collusion exists 40 among the Bidders, Bidder is an interested party to any litigation against City, 41 City or Bidder may have a claim against the other or be engaged in litigation, 42 Bidder is in arrears on any existing contract or has defaulted on a previous 43 contract, Bidder has performed a prior contract in an unsatisfactory manner, or 44 Bidder has uncompleted work which in the judgment of the City will prevent or 45 hinder the prompt completion of additional work if awarded. 46 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 27.2012 0021 13-9 INSTRUCTIONS TO BIDDERS Page 9 of 1 17.2. City may consider the qualifications and experience of Subcontractors, Suppliers,and 2 other persons and organizations proposed for those portions of the Work as to which 3 the identity of Subcontractors, Suppliers,and other persons and organizations must 4 be submitted as provided in the Contract Documents or upon the request of the City. 5 City also may consider the operating costs, maintenance requirements,performance 6 data and guarantees of major items of materials and equipment proposed for 7 incorporation in the Work when such data is required to be submitted prior to the 8 Notice of Award. 9 10 17.3. City may conduct such investigations as City deems necessary to assist in the 1 I evaluation of any Bid and to establish the responsibility, qualifications,and financial 12 ability of Bidders,proposed Subcontractors,Suppliers and other persons and 13 organizations to perform and furnish the Work in accordance with the Contract 14 Documents to City's satisfaction within the prescribed time. 15 16 17.4. Contractor shall perform with his own organization,work of a value not less than 17 35%of the value embraced on the Contract,unless otherwise approved by the City. 18 19 17.5. If the Contract is to be awarded, it will be awarded to lowest responsible and 20 responsive Bidder whose evaluation by City indicates that the award will be in the 21 best interests of the City. 22 23 17.6. Pursuant to Texas Government Code Chapter 2252.001, the City will not award 24 contract to a Nonresident Bidder unless the Nonresident Bidder's bid is lower than 25 the lowest bid submitted by a responsible Texas Bidder by the same amount that a 26 Texas resident bidder would be required to underbid a Nonresident Bidder to obtain a 27 comparable contract in the state in which the nonresident's principal place of 28 business is located. 29 30 17.7. A contract is not awarded until formal City Council authorization. If the Contract is 31 to be awarded,City will award the Contract within 90 days after the day of the Bid 32 opening unless extended in writing. No other act of City or others will constitute 33 acceptance of a Bid. Upon the contractor award a Notice of Award will be issued by 34 the City. 35 36 17.8. Failure or refusal to comply with the requirements may result in rejection of Bid. 37 38 18. Signing of Agreement 39 When City issues a Notice of Award to the Successful Bidder, it will be accompanied by the 40 required number of unsigned counterparts of the Agreement. Within 14 days thereafter 41 Contractor shall sign and deliver the required number of counterparts of the Agreement to 42 City with the required Bonds,Certificates of Insurance,and all other required documentation. 43 City shall thereafter deliver one fully signed counterpart to Contractor. 44 45 46 47 END OF SECTION CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 27,2012 00 35 13 BID FORM Page 9 of 9 SECTION 00 35 13 CONFLICT OF INTEREST AFFIDAVIT Each bidder, offeror, or respondent (hereinafter also referred to as "you") to a City of Fort Worth (also referred to as "City") procurement are required to complete Conflict of Interest Questionnaire (the attached CIQ Form) and Local Government Officer Conflicts Disclosure Statement (the attached CIS Form) below pursuant to state law. This affidavit will certify that the Bidder has on file with the City Secretary the required documentation and is eligible to bid on City Work. The referenced forms may also be downloaded from the website links provided below. http://www.ethics.state.tx.us/forms/CIQ.pdf N/A http://www.ethics.state.tx.us/forms/CIS.Pdf CIQ Form is on file with City Secretary ❑ CIQ Form is being provided to the City Secretary CIS Form is on File with City Secretary ❑ CIS Form is being provided to the City Secretary BIDDER: C. Green Scaping, LP By: Curtis J. Green 2401 Handley Ederville Rd. Signature: Ft. Worth, TX 76118 Title: Vice President END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Form Revised 20120327 Ft.Worth-Mary's Creek Recycling Tree Planting 0041 00 BID FORM Page 1 of 3 SECTION 00 41 00 BID FORM TO: The City Manager c/o: The Purchasing Department 1000 Throckmorton Street City of Fort Worth, Texas 76102 FOR: Marys Creek Recycling Center Tree Planting and Irrigation System City Project No.: 1239 Units/Sections: Unit 1 - Landscape/Irrigation 1. Enter Into Agreement The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with City in the form included in the Bidding Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Bid Price and within the Contract Time indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents. 2. BIDDER Acknowledgements and Certification 2.1. In submitting this Bid, Bidder accepts all of the terms and conditions of the INVITATION TO BIDDERS and INSTRUCTIONS TO BIDDERS, including without limitation those dealing with the disposition of Bid Bond. 2.2. Bidder is aware of all costs to provide the required insurance, will do so pending contract award, and will provide a valid insurance certificate meeting all requirements within 14 days of notification of award. 2.3. Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation. 2.4. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid. 2.5. Bidder has not solicited or induced any individual or entity to refrain from bidding. 2.6. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph: a. "corrupt practice" means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process. b. "fraudulent practice" means an intentional misrepresentation of facts made (a)to influence the bidding process to the detriment of City(b)to establish Bid prices at artificial non-competitive levels, or(c)to deprive City of the benefits of free and open competition. c. "collusive practice" means a scheme or arrangement between two or more Bidders, with or without the knowledge of City, a purpose of which is to establish Bid prices at artificial, non-competitive levels. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Form Revised 20120327 Ft.Worth-Mary's Creek Recycling Tree Planting 0041 00 BID FORM Page 2 of 3 d. "coercive practice"means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract. 3. Prequalification The Bidder acknowledges that the following work types must be performed only by prequalified contractors and subcontractors: a. All work performed by Green Scaping staff and crews. b. C. d. 4. Time of Completion 4.1. The Work will be complete for Final Acceptance within 90 days after the date when the the Contract Time commences to run as provided in Paragraph 2.03 of the General Conditions. 4.2. Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work{and/or achievement of Milestones)within the times specified in the Agreement. 5. Attached to this Bid The following documents are attached to and made a part of this Bid: a. This Bid Form, Section 00 41 00 b. Required Bid Bond, Section 00 43 13 issued by a surety meeting the requirements of Paragraph 5.01 of the General Conditions. c. Proposal Form, Section 00 42 43 d. Vendor Compliance to State Law Non Resident Bidder, Section 00 43 37 e. MWBE Forms (optional at time of bid) f. Prequalification Statement, Section 00 45 12 g. Conflict of Interest Affidavit, Section 00 35 13 *If necessary, CIQ or CIS forms are to be provided directly to City Secretary h. Any additional documents that may be required by Section 12 of the Instructions to Bidders 6. Total Bid Amount 6.1. Bidder will complete the Work in accordance with the Contract Documents for the following bid amount. In the space provided below, please enter the total bid amount for this project. Only this figure will be read publicly by the City at the bid opening. 6.2. It is understood and agreed by the Bidder in signing this proposal that the total bid amount entered below is CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Form Revised 20120327 Ft.Worth-Mary's Creek Recycling Tree Planting 0041 00 BID FORM Page 3 of 3 subject to verification and/or modification by multiplying the unit bid prices for each pay item by the respective estimated quantities shown in this proposal and then totaling all of the extended amounts. 6.3. Evaluation of Alternate Bid Items <use this if applicable, otherwise delete> Total Base Bid <use this if applicable, otherwise delete $98,492.09 Alternate Bid <use this if applicable, otherwise delete> $0.00 Deductive Alternate<use this if applicable, otherwise $0.00 Additive Alternate <use this if applicable, otherwise $0.00 Total Bid $98,492.09 7. Bid Submittal This Bid is submitted on 12/4/14 by the entity named below. Respectfully submitted, Receipt is acknowledged of the Initial following Addenda: By: Addendum No. 1: (Signature) Addendum No. 2: Addendum No. 3: Curtis J. Green JAddendum No. 4: (Printed Name) Title: Vice President Company: C. Green Scaping, LP Corporate Seal: Address: 2401 Handley Ederville Rd. Ft. Worth, TX 76118 State of Incorporation: TX Email: cgreen(a)greenscaping.com Phone: 817-577-9299 m END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Form Revised 20120327 Ft.Worth-Mary's Creek Recycling Tree Planting 00 42 43 BID PROPOSAL Page 5 of 9 SECTION 00 42 43 PROPOSALFORM UNIT PRICE DID Bidder's Application Project Item Information Bidder's Proposal Bidlist Description Specification Unit of Bid Unit Price Bid Value Item No. Section No. Measure Quantity Unit 1 -Landscape/Irrigation 1 Furnish and Install Trees-3"Cal 32 93 43 EA 20 $940.00 $18,800.00 2 Transport and install Trees-3"Cal 32 93 43 EA 23 $830.00 $19,090.00 _3_ Drip Irrigation System 32 90 10 LS 1 $39,000.00 $39,000.00 4 Associated Well Services LS 1 $15,802.09 $15,802.09 Furnish and Install Ground Mounted Sign and Post 5 Assemblies 3441 30 EA 1 $5,800.00 $5 800.00 Unit 1 Bid Total $98,492.09 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Form Revised 20120120 Ft.Worth-Mary's Creek Recycling Tree Planting 00 42 43 BID PROPOSAL Page 6 of 9 SECTION 00 42 43 PROPOSALFORM UNIT PRICE BID Bidder's Application Project Item Information Bidder's Proposal Bidlist Description Specification Unit of Bid Unit Price Bid Value Item No. Section No. Measure Quantity Bid Summary Base Bid Unit 1 - Landscape/Irrigation $98,492.09 Total Base Bid $98,492.09 Alternate Bid Total Alternate Bid Deductive Alternate Bid Total Deductive Alternate Bid Additive Alternate Bid Total Additive Alternate Bid Total Bid $98,492.09 END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Form Revised 20120120 Ft.North-Mary's Creek Recycling Tree Planting 00 43 13 BID BOND Page 1ofI SECTION 00 43 13 BID BOND KNOW ALL BY THESE PRESENTS: That we, (Bidder Name) Company Name Here hereinafter called the Principal,and(Surety Name) Surety'Na`me Here a corporation or firm duly authorized to transact surely business in the State of Texas, hereinafter called the Surety, are held and firmly bound unto the City, hereinafter called the Obligee, in the sum of Spell Out Numbers Here and No/100 Dollars ($ Numerals Here .00), the payment of which sum will be well and truly made and the said Principal and the said Surety, bind ourselves,our heirs, executors, administrators, successors and assigns,jointly and severally, firm by these presents. WHEREAS, the Principal has submitted a proposal to perform work for the following project of the Obligee, identified as (Project Name and Limits Here) NOW, THEREFORE, if the Obligee shall award the Contract for the foregoing project to the Principal, and the Principal shall satisfy all requirements and conditions required for the execution of the Contract and shall enter into the Contract in writing with the Obligee in accordance with the terms of such proposal, then this bond shall be null and void. If the Principal fails to execute such Contract in accordance with the terms of such proposal or fails to satisfy all requirements and conditions required for the execution of the Contract in accordance with the proposal or fails to satisfy all requirements and conditions required for the execution of the Contract in accordance with the proposal, this bond shall become the property of the Obligee, without recourse of the Principal and/or Surety, not to exceed the penalty hereof, and shall be used to compensate Obligee for the difference between Principal's Total Bid Amount and the next selected Bidder's Total Bid Amount. SIGNED this day of , 2014. By: Company Name Here (Signature and Title of Principal) *By: Surety Name Here (Signature of Attorney-of-Fact) "Attach Power of Attorney(Surety)for Attorney-in-Fact Impressed Surety Seal Only END OF SECTION C1TY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Form Revised 20110627 00 410000 43 13_00 42 43 00 43 37_00 45 12_00 35 13 Bid Proposal Workbook As 00 43 37 VENDOR COMPLIANCE TO STATE LAW Page 7 of 9 SECTION 00 43 37 VENDOR COMPLIANCE TO STATE LAW NON RESIDENT BIDDER Texas Government Code Chapter 2252 was adopted for the award of contracts to nonresident bidders. This law provides that, in order to be awarded a contract as low bidder, nonresident bidders (out-of-state contractors whose corporate offices or principal place of business are outside the State of Texas) bid projects for construction, improvements, supplies or services in Texas at an amount lower than the lowest Texas resident bidder by the same amount that a Texas resident bidder would be required to underbid a nonresident bidder in order to obtain a comparable contract in the State which the nonresident's principal place of business is located. The appropriate blanks in Section A must be filled out by all nonresident bidders in order for your bid to meet specifications. The failure of nonresident bidders to do so will automatically disqualify that bidder. Resident bidders must check the box in Section B. A. Nonresident bidders in the State of State Here or Blank , our principal place of business, are required to be % Here percent lower than resident bidders by State Law. A copy of the statute is attached. Nonresident bidders in the State of State Here or Blank , our principal place of business, are not required to underbnresident bidders. B. The principal place of business of our company or our parent company or majority owner is in the State of Texas. X BIDDER: C. Green Scaping, LP By: Curtis J. Green 2401 Handley Ederville Rd. (Signature) Ft. Worth, TX 76118 Title: Vice President Date: END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Form Revised 20110627 Ft.Worth-Mary's Creek Recycling Tree Planting 00 45 11- 1 BIDDERS PREQUALIFICATIONS Page I of 3 ! SECTION 00 45 11 2 BIDDERS PREQUALIFICATIONS 3 4 1. Summary.All contractors are required to be prequalified by the City prior to submitting 5 bids.To be eligible to bid the contractor must submit Section 00 45 12, Prequalification 6 Statement for the work type(s)listed with their Bid. Any contractor or subcontractor who is 7 not prequalified for the work type(s)listed must submit Section 00 45 13, Bidder 8 Prequalification Application in accordance with the requirements below. 9 10 The prequalification process will establish a bid limit based on a technical evaluation and I I financial analysis of the contractor.The information must be submitted seven(7)days prior 12 to the date of the opening of bids. For example,a contractor wishing to submit bids on 13 projects to be opened on the 7th of April must file the information by the 31 st day of March 14 in order to bid on these projects. In order to expedite and facilitate the approval of a Bidder's 15 Prequalification Application,the following must accompany the submission. 16 a. A complete set of audited or reviewed financial statements. 17 (1) Classified Balance Sheet 18 (2) Income Statement 19 (3) Statement of Cash Flows 20 (4) Statement of Retained Earnings 21 (5) Notes to the Financial Statements, if any 22 b. A certified copy of the firm's organizational documents(Corporate Charter, Articles 23 of Incorporation,Articles of Organization,Certificate of Formation, LLC 24 Regulations,Certificate of Limited Partnership Agreement). 25 c. A completed Bidder Prequalification Application. 26 (1) The firm's Texas Taxpayer Identification Number as issued by the Texas 27 Comptroller of Public Accounts.To obtain a Texas Taxpayer Identification 28 number visit the Texas Comptroller of Public Accounts online at the 29 following web address www.window.state.tx.us/taxpermit/and fill out the 30 application to apply for your Texas tax ID. 31 (2) The firm's e-mail address and fax number. 32 (3) The firm's DUNS number as issued by Dun& Bradstreet.This number 33 is used by the City for required reporting on Federal Aid projects.The DUNS 34 number may be obtained at www.dnb.com. 35 d. Resumes reflecting the construction experience of the principles of the firm for firms 36 submitting their initial prequalification. These resumes should include the size and 37 scope of the work performed. 38 e. Other information as requested by the City. 39 40 2. Prequalification Requirements 41 a. Financial Statements. Financial statement submission must be provided in 42 accordance with the following: 43 (1) The City requires that the original Financial Statement or a certified copy 44 be submitted for consideration. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 0045 11 -2 BIDDERS PREQUALIFICATIONS Page 2 of 1 (2) To be satisfactory,the financial statements must be audited or reviewed 2 by an independent,certified public accounting firm registered and in 3 good standing in any state. Current Texas statues also require that 4 accounting firms performing audits or reviews on business entities within 5 the State of Texas be properly licensed or registered with the Texas State 6 Board of Public Accountancy. 7 (3) The accounting firm should state in the audit report or review whether 8 the contractor is an individual,corporation, or limited liability company. 9 (4) Financial Statements must be presented in U.S. dollars at the current rate 10 of exchange of the Balance Sheet date. 11 (5) The City will not recognize any certified public accountant as 12 independent who is not,in fact, independent. 13 (6) The accountant's opinion on the financial statements of the contracting 14 company should state that the audit or review has been conducted in 15 accordance with auditing standards generally accepted in the United 16 States of America.This must be stated in the accounting firm's opinion. 17 It should: (1)express an unqualified opinion,or(2)express a qualified 18 opinion on the statements taken as a whole. 19 (7) The City reserves the right to require a new statement at any time. 20 (8) The financial statement must be prepared as of the last day of any month, 21 not more than one year old and must be on file with the City 16 months 22 thereafter, in accordance with Paragraph 1. 23 (9) The City will determine a contractor's bidding capacity for the purposes 24 of awarding contracts. Bidding capacity is determined by multiplying the 25 positive net working capital (working capital =current assets--current 26 liabilities)by a factor of 10.Only those statements reflecting a positive 27 net working capital position will be considered satisfactory for 28 prequalification purposes. 29 (10) In the case that a bidding date falls within the time a new financial 30 statement is being prepared, the previous statement shall be updated with 31 proper verification. 32 b. Bidder Prequaliftcation Application. A Bidder Prequalifieation Application must be 33 submitted along with audited or reviewed financial statements by firms wishing to be 34 eligible to bid on all classes of construction and maintenance projects. Incomplete 35 Applications will be rejected. 36 (1) In those schedules where there is nothing to report,the notation of 37 "None"or"N/A"should be inserted. 38 (2) A minimum of five(5)references of related work must be provided. 39 (3) Submission of an equipment schedule which indicates equipment under 40 the control of the Contractor and which is related to the type of work for 41 which the Contactor is seeking prequalification. The schedule must 42 include the manufacturer,model and general common description of 43 each piece of equipment. Abbreviations or means of describing 44 equipment other than provided above will not be accepted. 45 46 3. Eligibility to Bid 47 a. The City shall be the sole judge as to a contractor's prequalification. 48 b. The City may reject,suspend,or modify any prequalification for failure by the 49 contractor to demonstrate acceptable financial ability or performance. 50 c. The City will issue a Ietter as to the status of the prequalification approval. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 0045 11-3 BIDDERS PREQUALIFICATIONS Page 3 of 3 I d. If a contractor has a valid prequalification letter,the contractor will be eligible to bid 2 the prequalified work types until the expiration date stated in the letter. 3 a 5 6 7 8 END OF SECTION 9 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 00 45 12 BID FORM Page 8 of 9 SECTION 00 45 12 PREQUALIFICATION STATEMENT Each Bidder for a City procurement is required to complete the information below by identifying the prequalified contractors and/or subcontractors whom they intend to utilize for the major work type(s) listed. Major Work Type Contractor/Subcontractor Company Name Prequalification Expiration Date Company Name Here or space Date Here or space 0 Company Name Here or space Date Here or space 0 Company Name Here or space Date Here or space 0 Company Name Here or space Date Here or space The undersigned hereby certifies that the contractors and/or subcontractors described in the table above are currently prequalified for the work types listed. BIDDER: C. Green Scaping, LP By: Cu 2401 Handley Ederville Rd. (Signature) Ft. Worth, TX 76118 Title: Vice President Date: END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Form Revised 20120120 Ft.Worth-Mary's Creek Recycling Tree Planting FORTWORTH SECTION 00 45 13 BIDDER PREQUALIFICATION APPLICATION Date of Balance Sheet Mark only one: Individual Limited Partnership General Partnership Name under which you wish to qualify Corporation Limited Liability Company Post Office Box City State Zip Code Street Address(required) City State Zip Code ( 1 { 1 Telephone Fax Email Texas Taxpayer Identification No. Federal Employers Identification No. DUNS No. (if applicable) MAIL THIS QUESTIONAIRE ALONG WITH FINANCIAL STATEMENTS TO: CITY OF FORT WORTH TEXAS 1000 THROCKMORTON STREET FORT WORTH,TEXAS 76102-6311 AND MARK THE ENVELOPE: `BIDDER PREQUALIF[CATION APPLICATION" 004513-2 BIDDER PREQUALIFICATION APPLICATION Page 2 of S BUSINESS CLASSIFICATION The following should be completed in order that we may properly classify your firm: (Check the block(s)which are applicable--Block 3 is to be left blank if Block 1 and/or Block 2 is checked) ® Has fewer than 100 employees and/or Has less than $6,000,000.00 in annual gross receipts OR Does not meet the criteria for being designated a small business as provided in Section 2006.001 of the Texas Government Code. The classification of your firm as a small or large business is not a factor in determining eligibility to become prequalified. MAJOR WORK CATEGORIES Water Department Augur Boring-24-inch diameter casing and less Augur Boring-Greater than 24-inch diameter casing and greater Tunneling 36-Inches—60 inches, and 350 LF or less Tunneling-36-Inches—60 inches,and greater than 350 LF Tunneling—66"and greater,350 LF and greater Tunneling—66"and greater,350 LF or Less Cathodic Protection Water Distribution, Development, 8-inch diameter and smaller Water Distribution, Urban and Renewal, 8-inch diameter and smaller Water Distribution, Development, 12-inch diameter and smaller Water Distribution,Urban and Renewal, 12-inch diameter and smaller Water Transmission, Development, 24-inches and smaller Water Transmission,Urban/Renewal,24-inches and smaller Water Transmission,Development,42-inches and smaller Water Transmission, Urban/Renewal,42-inches and smaller Water Transmission, Development,All Sizes Water Transmission, Urban/Renewal,All Sizes Sewer Bypass Pumping, 18-inches and smaller Sewer Bypass Pumping, 18-inches 36-inches Sewer Bypass Pumping 42-inches and larger CCTV, 8-inches and smaller CCTV, 12-inches and smaller CCTV, 18-inches and smaller CCTV, 24-inches and smaller CCTV,42-inches and smaller CCTV,48-inches and smaller CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 004513.3 BIDDER PREQUALIFICATION APPLICATION Page 3 of 8 MAJOR WORK CATEGORIES,CONTINUED Sewer CIPP, 12-inches and smaller Sewer CIPP,24-inches and smaller Sewer CIPP,42-inches and smaller Sewer CIPP,All Sizes Sewer Collection System, Development, 8-inches and smaller Sewer Collection System, Urban/Renewal, 8-inches and smaller Sewer Collection System, Development, 12-inches and smaller Sewer Collection System, Urban/Renewal, 12-inches and smaller Sewer Interceptors, Development, 24-inches and smaller Sewer Interceptors, Urban/Renewal,24-inches and smaller Sewer Interceptors, Development,42-inches and smaller Sewer Interceptors, Urban/Renewal,42-inches and smaller Sewer Interceptors, Development,48-inches and smaller Sewer Interceptors, Urban/Renewal,48-inches and smaller Sewer Pipe Enlargement 12-inches and smaller Sewer Pipe Enlargement 24-inches and smaller Sewer Pipe Enlargement,All Sizes Sewer Cleaning,24-inches and smaller Sewer Cleaning,42-inches and smaller Sewer Cleaning,All Sizes Sewer Cleaning, 8-inches and smaller Sewer Cleaning, 12-inches and smaller Sewer Siphons 12-inches or less Sewer Siphons 24-inches or less Sewer Siphons 42-inches or less Sewer Siphons All Sizes Transportation Public Works Asphalt Paving Construction/Reconstruction(LESS THAN 15,000 square yards) Asphalt Paving Construction/Reconstruction(15,000 square yards and GREATER) Asphalt Paving Heavy Maintenance(UNDER$1,000,000) Asphalt Paving Heavy Maintenance($1,000,000 and OVER) Concrete Paving Construction/Reconstruction(LESS THAN 15,000 square yards) Concrete Paving Construction/Reconstruction(15,000 square yards and GREATER) Roadway and Pedestrian Lighting CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised December 20,2012 0045 13-4 BIDDER PREQUALIFICATION APPLICATION Page 4 of 8 1. List equipment you do not own but which is available by renting DESCRIPTION OF EQUIPMENT NAME AND DETAILED ADDRESS OF OWNER 2. How many years has your organization been in business as a general contractor under your present name? List previous business names: 3. How many years of experience in construction work has your organization had: (a) As a General Contractor: (b) As a Sub-Contractor: 4. *What projects has your organization completed in Texas and elsewhere? CLASS LOCATION NAME AND DETAILED CONTRACT OF DATE CITY-COUNTY- ADDRESS OF OFFICIAL TO AMOUNT WORK COMPLETED STATE WHOM YOU REFER *If requalifyng only show work performed since last statement. 5.Have you ever failed to complete any work awarded to you? If so,where and why? 6.Has any officer or owner of your organization ever been an officer of another organization that failed to complete a contract? If so,state the name of the individual,other organization and reason. 7.Has any officer or owner of your organization ever failed to complete a contract executed in his/her name? If so,state the name of the individual, name of owner and reason. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 0045 13-5 BIDDER PR)QUALIFICATION APPLICATION Page 5 of 8. In what other lines of business are you financially interested?__ 9. Have you ever performed any work for the City? If so,when and to whom do you refer? 10. State names and detailed addresses of all producers from whom you have purchased principal materials during the last three years. NAME OF FIRM OR COMPANY DETAILED ADDRESS 11. Give the names of any affiliates or relatives currently debarred by the City. Indicate your relationship to this person or firm. 12. What is the construction experience of the principal individuals in your organization? PRESENT MAGNITUDE POSITION OR YEARS OF AND TYPE OF IN WHAT NAME OFFICE EXPERIENCE WORK CAPACITY 13. If any owner, officer, director,or stockholder of your firm is an employee of the City,or shares the same household with a City employee,please list the name of the City employee and the relationship. In addition, list any City employee who is the spouse, child,or parent of an owner,officer, stockholder,or director who does not live in the same household but who receives care and assistance from that person as a direct result of a documented medical condition.This includes foster children or those related by adoption or marriage. CrrY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 0045 13-6 BIDDER PREQUALIFICATION APPLICATION Page 6 of 8 CORPORATION BLOCK PARTNERSHIP BLOCK If a corporation: If a partnership: Date of Incorporation State of Organization Charter/File No. Date of organization President Is partnership general, limited,or registered limited liability partnership? Vice Presidents File No. (if Limited Partnership) General Partners/Officers Secretary Limited Partners(if applicable) Treasurer LIMITED LIABILITY COMPANY BLOCK If a corporation: State of Incorporation Date of organization File No. Individuals authorized to sign for Partnership Officers or Managers(with titles, if any) Except for limited partners,the individuals listed in the blocks above are presumed to have full signature authority for your firm unless otherwise advised.Should you wish to grant signature authority for additional individuals, please attach a certified copy of the corporate resolution, corporate minutes,partnership agreement,power of attorney or other legal documentation which grants this authority. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 00 45 13 7 BIDDER PREQUALIFICATION APPLICATION Page 7 of 8 14. Equipment $ TOTAL BALANCE SHEET ITEM QUANTITY ITEM DESCRIPTION VALUE l 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 3 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Various- TOTAL Similar types of equipment may be lumped together. If your firm has more than 30 types of equipment, you may show these 30 types and show the remainder as "various".The City, by allowing you to show only 30 types of equipment, reserves the right to request a complete,detailed list of all your equipment. The equipment list is a representation of equipment under the control of the firm and which is related to the type of work for which the firm is seeking qualification. In the description include,the manufacturer, model,and general common description of each. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 0045 13-8. BIDDER PREQUALIFICATION APPLICATION Page 8 of 8 BIDDER PREQUALIFICATION AFFIDAVIT STATE OF COUNTY OF The undersigned hereby declares that the foregoing is a true statement of the financial condition of the entity herein first named, as of the date herein first given; that this statement is for the express purpose of inducing the party to whom it is submitted to award the submitter a contract; and that the accountant who prepared the balance sheet accompanying this report as well as any depository, vendor or any other agency herein named is hereby authorized to supply each party with any information,white this statement is in force, necessary to verify said statement. being duly sworn, deposes and says that he/she is the of , the entity described in and which executed the foregoing statement that he/she is familiar with the books of the said entity showing its financial condition; that the foregoing financial statement taken from the books of the said entity as of the date thereof and that the answers to the questions of the foregoing Bidder Prequalification Application are correct and true as of the date of this affidavit. Firm Name: Signature: Sworn to before me this day of , Notary Public Notary Public must not be an officer,director,or stockholder or relative thereof. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 00 45 40- 1 MINORITY AND WOMEN BUSINESS ENTERPRISE GOAL. Page I of I I SECTION 00 45 40 2 MINORITY BUSINESS ENTERPRISE GOAL 3 APPLICATION OF POLICY 4 If the total dollar value of the contract is greater than $50,000, then the MBE subcontracting goal 5 may be applicable. If the total dollar value of the contract is $50,000 or less, the MBE 6 subcontracting goal is not applicable. 7 8 POLICY STATEMENT 9 It is the policy of the City of Fort Worth to ensure the full and equitable participation by Minority 10 Business Enterprises (MBE) in the procurement of all goods and services. All requirements and 11 regulations stated in the City's current Business Diversity Enterprise Ordinance apply to this bid. 12 13 MBE PROJECT GOAL 14 The City's MBE goal on this project is 10% of the total bid (Base bid applies to Parks and 15 Community Services). Note: If both MBE and SBE subcontracting goals are established for this 16 project, then an Offeror must submit both a MBE Utilization Form and a SBE Utilization Form to be 17 deemed responsive. 18 19 COMPLIANCE TO BID SPECIFICATIONS 20 On City contracts greater than $50,000 where a MBE subcontracting goal is applied, bidders are 21 required to comply with the intent of the City's Business Diversity Ordinance by one of the 22 following: 23 1. Meet or exceed the above stated MBE goal through MBE subcontracting participation,or 24 2. Meet or exceed the above stated MBE goal through MBE Joint Venture participation,or 25 3. Good Faith Effort documentation,or; 26 4. Waiver documentation. 27 Failure to comply with the City's M/WBE Ordinance, shall result in the Bid being considered non- 28 responsive. Any questions,please contact the MIWBE Office at(817)392-6104. 29 30 SUBMITTAL OF REQUIRED DOCUMENTATION 31 The applicable documents must be received by the Managing Department, within the following 32 times allocated, in order for the entire bid to be considered responsive to the specifications. The m_ __ _ _ i _ _., _ p _ _ p y __ gig 33 Offeror shall deliver the MBE`documentatioa in; erson to the'appropriate em to employee afthe Mana ' 34 Department and'obtain a,dateltime receipt. Such-liecdipt shall be evidence.that the C ty.received the 35 documentation in the1ime allocated. A,faxed; opywill not be2cce ted 1. Subcontractor Utilization Form,if goal is met received by 5:00 p.m., five (5) City business days after or exceeded: the bid opening date,exclusive of the bid opening date. 2. Good Faith Effort and Subcontractor received by 5:00 p.m., five (5) City business days after Utilization Form,if participation is less than the bid opening date,exclusive of the bid opening date. statedgoal: 3. Good Faith Effort and Subcontractor received by 5:00 p.m., five (5) City business days after Utilization Form,if no MBE participation: the bid opening date,exclusive of the bid opening date. 4. Prime Contractor Waiver Form,if firm will received by 5:00 p.m., five (5) City business days after perform all subcontracting/supplier work: the bid opening date,exclusive of the bid opening date. 5. Joint Venture Form,if utilizing a joint venture received by 5:00 p.m., five (5) City business days after to meet or exceed goal. the bid oeening date,exclusive of the bid opening date. 36 END OF SECTION CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 -1 Agreement Page 1 of SECTION 00 52 43 AGREEMENT THIS AGREEMENT, authorized on February 3, 2015 is made by and between the City of Forth Worth, a Texas home rule municipality,acting by and through its duly authorized City Manager, ("City"), and C. Green Scaping, LP, authorized to do business in Texas, acting by and through its duly authorized representative,("Contractor"). City and Contractor,in consideration of the mutual covenants hereinafter set forth, agree as follows: Article 1.WORD Contractor shall complete all Work as specified or indicated in the Contract Documents for the Project identified herein. Article 2.PROJECT The project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows: Mar3,'s Creek Recycling Center Tree Planting City Project No. 01239 Article 3. CONTRACT TIME 3.1 Time is of the essence. All time limits for Milestones,if any, and Final Acceptance as stated in the Contract Documents are Of the essence to this Contract. 3.2 Final Acceptance. The Work will be complete for Final Acceptance within 90 days after the date when the Contract Time commences to run as provided in Paragraph 2.03 of the General Conditions. 3.3 Liquidated damages Contractor recognizes that time is of the essence of this Agreement and that City will suffer financial loss if the Work is not completed within the times specified in Paragraph 3.2 above,plus any extension thereof allowed in accordance with Article 12 of the General Conditions. The Contractor also recognizes the delays, expense and difficulties involved in proving in a legal proceeding the actual loss suffered by the City if the Work is not completed on time. Accordingly, instead of requiring any such proof, Contractor agrees that as liquidated damages for delay (but not as a penalty), Contractor shall pay City Three Hundred Dollars ($300.00) for each day that expires after the time specified in Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of Acceptance. Article 4. CONTRACT PRICE City agrees to pay Contractor for performance of the Work in accordance with the Contract Documents an amount in current funds of Ninety-eight thousand, four hundred ninety-two and nine cents Dollars ($98,492.Q9J n Article 5. CONTRACT DOCUMENTS 5.1 CONTENTS: A..The Contract Documents which comprise the entire agreement llety--Pen (_pity and Contractor concerning the Work consist of the following: CITY OF FORT WORTH ��s:R!r q : 9-c' �8tea e Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS in., " c No.01239 Revised August 17,2012 �TX SECRETARY' -2 Agreement Page 2 of 4 1. This Agreement. 2. Attachments to this Agreement: a. Bid Form 1) Proposal Form 2) Vendor Compliance to State Law Non-Resident Bidder 3) Prequalification Statement 4) State and Federal documents (project specific) b. Current Prevailing Wage Rate Table c. Insurance ACORD Form(s) d. Payment Bond e. Performance Bond f. Maintenance Bond g. Power of Attorney for the Bonds h. Worker's Compensation Affidavit i. MBE and/or SBE Commitment Form 3. General Conditions. 4. Supplementary Conditions. 5. Specifications specifically made a part of the Contract Documents by attachment or, if not attached,. as incorporated by reference and described in the Table of Contents of the Project's Contract Documents. 6. Drawings. 7. Addenda. 8. Documentation submitted by Contractor prior to Notice of Award. 9. The following which may be delivered or issued after the Effective Date of the Agreement and, if issued,become an incorporated part of the Contract Documents: a. Notice to Proceed. b. Field Orders. c. Change Orders. d. Letter of Final Acceptance. OFFICIAL RECORD CITY SECRETARY . W THe YX CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.0 123 9 Revised August 17,2012 -3 Agreement Page 3 of 4 Article 6.INDEMNIFICATION 1' 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the city, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the contractor, its officers, agents, employees, subcontractors, licenses or invitees under this contract. This indemnification provision is specifically intended to operate and be effective even if it is alleged or proven that all or some of the damages being sought were caused, in whole or in part, by any act, omission or negligence of the city. This indemnity provision is intended to include, without Iimitation, indemnity for costs, expenses and legal fees incurred by the city in defending against such claims and causes of actions. 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense,the city, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the city, arising out of, or alleged to arise out of, the work and services to be performed by the contractor, its officers, agents, employees, subcontractors, licensees or invitees under this contract. This indemnification provision is specifically intended to operate and be effective even if it is alleged or proven that all or some of the damages being sought were caused,in whole or in part,by any act, omission or negligence of the city. Article 7.MISCELLANEOUS 7.1 Terms. Terms used in this Agreement which are defined in Article 1 of the General Conditions will have the meanings indicated in the General Conditions. 7.2 Assignment of Contract. This Agreement, including all of the Contract Documents may not be assigned by the Contractor without the advanced express written consent of the City. 7.3 Successors and Assigns. City and Contractor each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, in respect to all covenants, agreements and obligations contained_ in the Contract Documents. . 7.4 Severability. Any provision or-part of the Contract Documents held to be unconstitutional,void or unenforceable by a court of competent jurisdiction shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon CITY and CONTRACTOR. 7.5 Governing Law and Venue. This Agreement, including all of the Contract Documents is performable in the State of Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the Northern District of Texas,Fort Worth Division. 7.6 Other Provisions. The Contractor agrees to pay at least minimum wage per hour for all labor as the same is classified, promulgated and set out by the City, a copy of which is attached hereto and made a part hereof the same as if it were copied verbatim herein. EOFFICIALRECORDCITY OF FORT WORTH M 's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTSRETARY City Project No.01239 Revised August 17,2012 Ha J) -4 Agreement Page 4 of 4 7.7 Authority to Sign. 9 Contractor shall attach evidence of authority to sign Agreement, if other than duly authorized signatory of the Contractor. IN WITNESS WHEREOF,City and Contractor have executed this Agreement in multiple counterparts. This Agreement is effective as of the last date signed by the Parties(`'Effective Date"). Contractor: C. Green Scaping,LP City of Fort Worth / Fernando Costa By: Assistant City Manager (Sign % Date 3 /7 / Cathleen Ruiz Attest:gretaryl (Printed Name) City S IT � (Seal) +'° ,0 Title:President �° % ®$ o� Address: g o 2401 Handley Ederville Rd. M&C C z 7 l` °° Date: 2 'Lo k 15 S City/State/Zip: Ft.Worth,TX 76118 Approved as to Form and Legality: Date Douglas W.Black Assistant City Attorney APPROV COMME ED: Andrew rg, E. C Interim Director Water Department OFFICIAL RECORD ' Cj"r�-*, avrMPTA,RV CITY OF FORT WORTH Iv�ar �`�zeeh Rg�}+lig nter Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS 4 J" Ci roject No.01239 Revised August 17,2012 00 45 26-1 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Page I of I I SECTION 00 45 26 2 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW 3 Pursuant to Texas Labor Code Section 406.096(a),as amended,Contractor certifies that it 4 provides worker's compensation insurance coverage for all of its employees employed on City 5 Project No.01239.Contractor further certifies that,pursuant to Texas Labor Code,Section 6 406.096(b),as amended,it will provide to City its subcontractor's certificates of compliance with 7 worker's compensation coverage. 8 9 CONTRACTOR: 10 11 12 Company C � Zsv2trioje Pri t) Z:) 14 nature: 15 Address 16 17 r Title: 18 City/State/Zip (Please Print) 19 20 21 THE STATE OF TEXAS § 72 23 COUNTY OF TARRANT § 24 25 BEFORE E the under igned authority,on this day personally appeared 26 e� �al Z known to me to be the person whose name is 27 subscribed to the fore oing instrumen and acknowledgej�o me that he/she executed the same as 28 the act and deed of - -for the purposes and 29 consideration therein expressed and in the capacity erein stated. 30 31 GIVEN UNDER MY HAND AND SEAL OF OFFICE this !p day of 32 L�l ne-c--, , 201 33 - - — 34 35 � lt 36 "% STACY GEIGENMILLER Notary Public and for State of Texas {`� U��i ° Notary Public,State of Texas 37 r•.��; = My Commission Expires Mprch 13, 2018 38 END OF SECTION 39 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 Bond No. 022036911 0061 13-1 PERFORMANCE BOND Page I of t 1. SECTION 00 6113 2 PERFORMANCE BOND 3 4 THE STATE OF TEXAS §` 5 § KNOW ALL BY THESE PRESENTS; 6 COUNTY OF TARRANT § 7 That we, C. Green Scaping, LP ,known as 8 "Principal"herein and West American Insurance Company ,a corporate 9 surety(sureties, if more than one)duty authorized to do business in the State of Texas,known as to "Surety"herein(whether one or more),are held and firmly bound unto the City of Fort Worth,a 11 municipal corporation created pursuant to the laws of Texas;known as"City"herein,in the penal 12 sum of, Ninety Eight Thousand Four Hundred Ninety Two Dollars 13 ($ 98,492.00 ),lawful money of the United States,to be paid in Fort Worth, 14 Tarrant County,Texas for the payment of which sum well and truly to be made,we bind 1.5 ourselves,:our heirs,executors,administrators,successors and assigns,jointly and severally, 16 firmly by'these presents. 17 WHEREAS,the Principal has entered into a certain written contract with the City 18 awarded the 3rd day of February ,2015 ,which Contract is hereby referred to and 19 made a part hereof for all-purposes as if fully set forth herein,to furnish all materials,equipment 20 labor and other accessories defined by law,in the prosecution of the Work,including any Change 21 Orders,as provided for in said_Contract designated as Mary's Creek Recycling Center Tree 22 Planting,City Project No.01239. 23 NOW,THEREFORE,the condition of this obligation is such that if the said Principal 24 shall faithfully perform it obligations under-the Contract and shall in all respects duly and 25 faithfully perform the,Work,including Change Orders,under the Contract,according to the plans, 26 specifications,and contract documents therein referred to,and as well during any period of 27 extension of the Contract that may be granted on the part of the City,then this obligation shall be 28 and become null and void,otherwise to remain in full force and effect. 29 PROVIDED FURTHER,that if any legal action be filed on this.Bond,venue shall lie in 30 Tarrant County,Texas or the United States District.Court for the Northern District of Texas,Fort 31 Worth Division. -- OFFICIAL RECORD CITY-SECRETARY CITY OF FORT WORTH -1,1W C=1,_K cliny'Cenicr Tree`Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1.2011 0061 13'-2 PERFORMANCE BOND Page 2 of2 .t This bond is made and executed in compliance with the provisions of Chapter 2253 of the 2 Texas Government Code,as amended,and all liabilities on this bond shall be determined in 3 accordance With the provisions of said statue. 4 IN WITNESS WHEREOF,the Principal and the Surety have SIGNED and.SEALED 5 this instrument by duly authorized agents and officers on this the. 3rd day of 6 February 2015 7 P CIPAL: 8 9 to 11 BY:: 12 Signature 13 ATTEST: 5 A l 16 (Principal)Pcretary Q Name and Title 17 18 Address: 2401 Handley Ederville Rd. 19 Fort Worth TX 76118 o''- ` - - 22 Witness as to Principal :23 SURETY: 24 West American Insurance Company 25 26 27 g 2 . Signatur 29 Xylie Kelsoe-Attorney in Fact 3o 34 Name and Title 32 33 Address: 320 Eagle Drive, Ste_210 34 Denton,TTX 76201 T 35 , 36 37 Mwiss as to Surety Telephone Number. 940-382-9691 38 39 40 41 *Note: If signed;by an officer of the Surety Company,there,must be on file a certified extract 42 from the by-laws showing that this:person has authority to sign such obligation. if 43 Surety's physical address is different from its mailing address,both must be provided. 44 The date of the bondshall,not_be prior to the date the Co act is awarded. 45 OFFICIAL RECORD ry SECRETARY Crry OF FORT WORTH. Mary's Creek Recycling.Center 7rce!'lancing STIAND R.D CONSTRUCTION SPECiF'ICA710N DOCUMENTS City rtajc�tNo,01239- Revised July 1,:2011 THIS POWER OF ATTORNEY IS NOT VALID UNLESS IT IS PRINTED ON RED BACKGROUND. This Power of Attorney limits the acts of those named herein,and they have no authority to bind the Company except in the manner and to the extent herein stated. Certificate No:6849222 American Fire and Casualty Company Liberty Mutual Insurance Company The Ohio Casualty Insurance Company West American Insurance Company POWER OF ATTORNEY KNOWN ALL PERSONS BY THESE PRESENTS: That American Fire&Casualty Company and The Ohio Casualty Insurance Company are corporations duly organized under the laws of the State of New Hampshire,that Liberty Mutual Insurance Company is a corporation duly organized under the laws of the State of Massachusetts,and West American Insurance Company is a corporation duly organized under the taws of the State of Indiana(herein collectively called the"Companies"),pursuant to and by authority herein set forth;does hereby name,constitute and appoint, James E King;Jeff P.King:Kylie Keisoe•Rachel Mullins all of the city of Denton ,state of TX each individually if there be more than one named,its true and lawful attomey-in-fact to make,execute,seal,acknowledge and deliver,for and on its behalf as surety and as its act and deed,any and all undertakings,bonds,recognizances and other surety obligations,in pursuance of thesepresents and shall be as binding upon the Companies as if they have been duly signed by the president and attested by the secretary of the Companies in their own proper persons. IN WITNESS WHEREOF,this Power of Attorney has been subscribed by authorized officer or official of the Companies and the corporate seals of the Companies have been affixed thereto this 27th day of January: 2015 >, American Fire and Casualty Company The Ohio Casualty Insurance Company N f{ n t r Liberty Mutual Insurance Company C `. West American Insurance Company to By: � O STATE OF PENNSYLVANIA ss David M.Care ;Assistant Secretary COUNTY OF MONTGOMERY C _ O Cn On this 27th day of January 2015 , before me personally appeared David M. Carey,who acknowledged himself to be the Assistant Secretary of American Fire and v F v c> Casualty Company,Liberty Mutual Insurance Company,The Ohio Casualty Insurance Company,and West American Insurance Company,and that he,as such,being authorized so to do, -AW p R execute the foregoing instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer. i E a> > IN WITNESS WHEREOF,I have hereunto subscribedmy-nano and affixed my notarial seal at Plymouth Meeting,Pennsylvania,on the day and year first above written. O CL 16 �' i 2 c 3..'s,.'c i s t` _aOF cos }Jd'.st°8.� 1 co ��Z�Ct J O O a 3 By: Teresa Pastella,Notary Public d K � x R E IL M C This Power of Attorney is made and executed puisuanffo andby`nthority of the following By-laws and Authorizations of American Fire and Casualty Company,The Ohio Casualty Insurance N p ` Company,Liberty Mutual Insurance Company,an WestAmelican Insurance Company which resolutions are now in full force and effect reading as follows: (i ARTICLE IV—OFFICERS—Section 12.Power of Attorney.Any officer or other official of the Corporation authorized for that purpose in writing by the Chairman or the President,and subject O r (; to such limitation as the Chairman or the President may prescribe,shall appoint such attomeys-in-fact,as may be necessary to act in behalf of the Corporation to make;execute,seal, O O S acknowledge and deliver as surety any and all undertakings,bonds,recognizances and other surety obligations. Such attomeys-in-fact,subject to the limitations set forth in their respective 'a 3 E powers of attorney,shall have full power to bind the Corporation by their signature and execution of any such instruments and to attach thereto the seal of the Corporation. When so ,'� m O executed,such instruments shall be as binding as if signed by the President and attested to by the Secretary.Any power or authority granted to any representative or attomey-in-fact under > the provisions of this article may be revoked at any by the Board,the Chairman,the President or by the officer or officers granting such power or authority. IV N _ ARTICLE XIII—Execution of Contracts—SECTION 5..Surety Bonds and Undertakings.Any officer of the Company authorized for that purpose in writing by the chairman or the president, iand subject to such limitations as the chairman or the president may prescribe,shall appoint such attorneys-in-fact,as maybe necessary to actin behalf of the Company to make,execute, M O a seal,acknowledge and deliver as surety any and all undertakings,bonds,recognizances and other surety obligations. Such attomeys-in-fact subject to the limitations set forth in their =oQ Z v respective powers of attorney,shall have full powerto bind the Company by their signature and execution of any such instruments and to attach thereto the seal of the Company. When so v c executed such instruments shall be as binding as if signed by the president and attested by the secretary. o cs Certificate of Designation—The President of the Company,acting pursuant to the Bylaws of the Company,authorizes David M.Carey,Assistant Secretary to appoint such attomeys-in- ~r fact as may be necessary to act on behalf of the Company to make,execute,seal,acknowledge and deliver as surety any and all undertakings,bonds,recognizances and other surety obligations; Authorization—By unanimous consent of the Companys Board of Directors,the Company consents that facsimile or mechanically reproduced signature of any assistant secretary of the Company,wherever appearing upon a certified copy of any power of attorney issued by the Company in connection with surety bonds,shall be valid and binding upon the Company with the same force and effect as though manually affixed. I,Gregory W.Davenport,the undersigned,Assistant Secretary;of American Fire and Casualty Company,The Ohio Casualty Insurance Company,Liberty Mutual Insurance Company,and West American Insurance Company do hereby certify that the original power of attorney of which the foregoing is a full,true and correct copy of the Power ofAttomey executed by said Companies,is in full force and effect and has not been revoked. IN TESTIMONY WHEREOF,I have hereunto set my hand and affixed the seals of said Companies this day of 2015 . v Gregory W.Davenport,Assistant Secretary = m , LMS 12873 122013 25 of 100 Bond No. 022036911 o0 61 14-1 PAYMENrBOND Page I or2 1 SECTION 00 6114 2 PAYMENT BOND 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7 That we, C. Green Scaping, LP known as 8 "Principal"herein, and West American Insurance Company ,, a 9 corporate surety (sureties), duly authorized to do business in the State of Texas, known as 10 "Surety"herein(whether one or more),are held and firmly bound unto the.City of Fort Worth,a I I municipal corporation created pursuant to the Jaws of the State of Texas, known as"City"herein, 12 in the penal sum of Ninety Eight Thousand Four Hundred Ninety Two Dollars 13 ($ 98,492.00 }, :lawful money of the United States, to be paid in Fort Worth, 14 Tarrant County,Texas, for the payment of which sum well and truly be made,we bind ourselves, 15 our heirs, executors,administrators, successors and assigns,jointly and severally, firmly by these 16 presents; 17 WHEREAS, Principal has entered into a certain written Contract with City, awarded the 18 1rd day of February , 20 15 , which Contract is hereby referred to and 19 made a part hereof for all purposes as if fullyset forth herein,to furnish all materials,equipment, 20 labor and other accessories as defined by law, in the prosecution of the Work as provided for in 21 said Contract and designated as Mary's,Creek Recycling Center Tree Planting, City Project No. 22 01239. 23 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if 24 Principal shall.pay all. monies owing to any (and all) payment bond beneficiary (as defined in. 25 Chapter 2253 of the Texas Government Code,as amended) in the prosecution of the Work under 26 the Contract, then this obligation shall be.and become null and void•, otherwise to remain in full 27 force and effect. 28 This bond is made and executed in compliance with the provisions of Chapter 2253 of the 29 Texas Government Code, as amended, and all liabilities on this bond shall be determined in 30 accordance with the provisions of said statute. 31 4 CrrY OF FORS'WORTH Marys Creek ycling iCc tcr'rree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City rojcct No.01239 Revised July 1,2011 00 61 14-2 PAYMENT BOND Page 2 of 2 1 IN WITNESS WHEREOF, the,Principal and Surety have each SIGNED and SEALED. 2 this instrument by duty authorized agents and officers on this the 3rd day of 3. February .2Q 155 4 PR CID L- A ATTEST: BY: Q S` attire lko {Principal?S. retary Name and Title Address: 2401 Handley Edervil e _ Fort Worth, TX 76118 Witness as to Principal - SURETY: West American Insurance Company ATTEST: B. Kylie'Kelsoe-Attorney in Fact (Surety)Secretary — Name and Title Address: 320 Eagle Drive, Ste 210 enton, TX 7620 Witness 4torety Telephone Number. 940-382-9691 5 b Note: If signed by an officer of the Surety, there must be on file.a certified extract from the Z bylaws showing that ibis person has authority to sign such obligation. If Surety's physical -8 address is different from its mailing address,both must be provided. 9 I0 The date of the.bond shall not be:prior to the date the Contract is awarded.: i t END OF SECTION 12 OFFICIAL RECORD CAYY SECRETARY !MWORTMo TX .CITY,OF FORT WORTH Mary's Creek Recycling Center Tree Planting ST ANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised July I,2011 THIS POWER OF ATTORNEY IS NOT VALID UNLESS IT IS PRINTED ON RED BACKGROUND. This Power of Attorney limits the acts of those named herein,and they have no authority to bind the Company except in the manner and to the extent herein stated. Certificate No.6aa9221 American Fire and Casualty Company Liberty Mutual Insurance Company The Ohio Casualty Insurance Company West American Insurance Company POWER OF ATTORNEY KNOWN ALL PERSONS BY THESE PRESENTS: That American Fire&Casualty Company and The Ohio Casualty Insurance Company are corporations duly organized under the laws of the State of New Hampshire,that Liberty Mutual Insurance Company is a corporation duly organized under the laws of the State of Massachusetts,and West American Insurance Company is a corporation duly organized under the laws of the State of Indiana(herein collectively called the"Companies°),pursuant to and by authority herein set forth,does hereby name,constitute and appoint, James E.King,•Jeff P.King:Kylie Kelsoe:Rachel Mullins all of the city of Denton state of TX each individually if there be more than one named,its true and lawful attomey-in-fact to make,execute,seal,acknowledge and deliver,for and on its behalf as surety and as its act and deed,any and all undertakings,bonds,recognizances and other surety obligations,in pursuance of these presents and shall be as binding upon the Companies as if they have been duly signed by the president and attested by secretary of the Companies in their own proper persons. IN WITNESS WHEREOF,this Power of Attorney has been subscribed by an authorized officer or official of the Companies and the corporate seals of the Companies have been affixed thereto this 27th day of January 2015 >, American Fire and Casualty Company ¢ iiiY The Ohio Casualty Insurance Company N Liberty Mutual Insurance Company d €t> 2 r r - West American Insurance Company S Gi By. David M.Care ,Assistant Secretary _ STATE OF PENNSYLVANIA ss ca R COUNTY OF MONTGOMERY C _ O d tm On this 27th day of January 2015 , before me personally appeared David M.Carey,who acknowledged himself to be the Assistant Secretary of American Fire and v w Casualty Company,Liberty Mutual Insurance Company,The Ohio Casualty Insurance Company,and West American Insurance Company,and that he,as such,being authorized so to do, W p execute the foregoing instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer. i ar > IN WITNESS WHEREOF,I have hereunto subscribed mrname and affixed my notarial seal at Plymouth Meeting Pennsylvania,on the day and year first above written. O Q- O r Teresa Pastella,Notary Public y O , d 02 r tC C M This Power of Attorney is made and executedpurstk'tt?fld�and byvauthority of the following By-laws and Authorizations of American Fire and Casualty Company,The Ohio Casualty Insurance L o a-,; Company,Liberty Mutual Insurance Company,aniiWest Ameencan Insurance Company which resolutions are now in full force and effect reading as follows: m L ARTICLE IV—OFFICERS—Section 12.Power of Attorney.Any officer or other official of the Corporation authorized for that purpose in writing by the Chairman or the President,and subject O = to such limitation as the Chairman or the President may prescribe,shall appoint such attomeys-in-fact,as may be necessary to act in behalf of the Corporation to make,execute,seal, O S acknowledge and deliver as surety any and all undertakings,bonds,recognizances and other surety obligations. Such attomeys-in-fact;subject to the limitations set forth in their respective : E powers of attorney,shall have full power to bind the Corporation by their signature:and execution of any such instruments and to attach thereto the seal of the Corporation. When so er L. executed,such instruments shall be as binding as if signed by the President and attested to bythe Secretary.Any power or authority granted to any representative or attomey-in-fact under the provisions of this article may be revoked at any time by the Board,the Chairman,the President or by the officer or officers granting such power or authority. _IV N M r ARTICLE All—Execution of Contracts—SECTION 5,Surety Bonds and Undertakings.Any officer of the Company authorized for that purpose in writing by the chairman or the president, i and subject to such limitations as the chairman or the president may prescribe,shall appoint such attomeys-in-fact,as may be necessary to act in behalf of the Company to make,execute, O seal,acknowledge and deliver as surety any and all undertakings,bonds,recognizances and other surety obligations. Such`attomeys-in-fact subject to the limitations set forth in their C? Z v respective powers of attorney,shall have full power to bind the Company by their signature and execution of any such instruments and to attach thereto the seal of the Company. When so v o executed such instruments shall be as binding as if signed by the president and attested by the secretary. p Certificate of Designation—The President of the Company,acting pursuant to the Bylaws of the Company,authorizes David M.Carey,Assistant Secretary to appoint such attomeys-in- ~ fact as maybe necessary to act on behalf of the Company to make,execute,seal,acknowledge and deliver as surety any and all undertakings,bonds,recognizances and other surety obligations. Authorization—By unanimous consent of the Company's Board of Directors,the Company consents that facsimile or mechanically reproduced signature of any assistant secretary of the Company,wherever appearing upon a certified copy of any power of attorney issued by the Company in connection with surety bonds,shall be valid and binding upon the Company with the same force and effect as though manually affixed. I,Gregory W.Davenport,the undersigned,Assistant Secretary,of American Fire and Casualty Company,The Ohio Casualty Insurance Company,Liberty Mutual Insurance Company,and West American Insurance Company do hereby certify that the original power of attorney of which the foregoing is a full,true and correct copy of the Power ofAttomey executed by said Companies,is in full force and effect and has not been revoked. ,—lit i t n � IN TESTIMONY WHEREOF,I have hereunto set my hand and affixed the seals of said Companies this 3 r day of ��Y v ,20 �- s r�1 � j.mot s • y{ 9 lY �f� c/ l�. By: a. Gregory W.Davenport,Assistant Secretary r, LMS 12873`122013 24 of 100 Bond No. 022036911 006119-1 MAINTENANCE BOND Page I or3 1 SECTION 00 61 19 2 MAINTENANCE BOND 3 4 THE STATE OF TEXAS § 5 § KNOW ALL BY THESE PRESENTS: 6 COUNTY OF TARRANT § 7` 8 That we C.Green Scaping, LP _.— _ - --_- _.._.. known as 9 "Principal"herein and I West American Insurance_Company ,a corporate surety 10 (sureties,if more than one)duly authorized to do business in the State of Texas,known as 11 "Surety"herein(whether one.or more),are held and firmly bound unto the City of Fort Worth,a 12 municipal corporation created pursuant to the laws of the State of Texas,known as"City"herein, 13 in the sum of Ninety Eight,Thousand Four Hundred Ninety Two Dollars 14 (s 98,492.00 ),lawful money of the United States,to be paid in Fort Worth, 15 Tarrant County,Texas, for payment of which sum well and truly be made unto the City and its 16 successors,we bind ourselves,our heirs,executors,administrators,successors and assigns,jointly 17 and severally, firmly by these presents. 18 19 WHEREAS,the Principal has entered into a certain written contract with the City awarded 20 the 3rd day of February ,2015 .,which Contract is hereby 21 referred to and a made part hereof for all purposes as if fully set forth herein,to furnish all 22 materials,equipment labor and other accessories as defined by law,in the prosecution of the 23 Work,including any Work resulting from a duly authorized Change Order(collectively herein, 24 the"Work")as provided for in said contract and designated as Mary's Creek recycling Center 25 Tree Planting,City Project No.0.1239;and 26 27 WHEREAS,Principal binds itself to use such materials and to so construct the Work in 28 accordance with the plans,specifications and Contract Documents that the Work is and will 29 remain free from defects in materials or workmanship for and during the period of two(2)years 30 after the date of Final Acceptance of the Work by the City("Maintenance Period");and 31 32 WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part 33 upon receiving notice from the City of the need therefor at any time within the Maintenance 34 Period. OFFICIAL RECORD CITY OF FORT WORTH aty'S C,rc�k,Rccvcl' enter Trcc Planting STANDARD CONSTRUCTION SPECIFICATION'DOCUMENTS CI A � `�+ �55..`17�r3ltiji V Project No.01239 R"ised July 1,2011 i W00Hy TX 006119-2 MAINTENANCE BOND Pagc 2 or 3 l 2 NOW THEREFORE,the condition of this obligation is such that if Principal shall 3 remedy any defective Work,for which timely notice was provided by City,to a completion 4 satisfactory to the City,then this obligation shall become null and void;otherwise to remain in 5 full force and effect. 6 7 PROVIDED,HOWEVER, if Principal shall fail so to repair or reconstruct any timely 8 noticed defective Work,it is agreed that the City may cause any and all,such defective Work to 9 be repaired and/or reconstructed with all associated costs thereof being borne by the Principal and 10 the Surety under this Maintenance bond;and l 1. 12 PROVIDED FURTHER,that if any legal action be filed on this Bond, venue shall lie in 13, Tarrant County,Texas or the United States District Court for the Northem District of Texas,Fort 14 Worth Division;and 15 116 PROVIDED FURTHER,that this obligation shall be continuous in nature and 17 successive recoveries may be had hereon for successive breaches. 18 19 20 OFFICIAL RECORD CITY SECRETARY , 'I C"OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,20 11 006t N-1 MAINTENANCI BOND Page 3 ol`3 1 IN WITNESS WHEREOF,the Principal and the Suretyhave each SIGNED and SEALED this 2 instrument by duly authorized agents and officers on this the 3rd day of. 3 February ,20 . 4 - 3 P CZL: � 6 7 - - -_ - 8 - - g BY: 1:0 Signature 11 ATTEST: 12 , 13 �l 14 (Principal) ecretary Name and Title- , 15 �JG( 16 Address:2401 Handley Ederville fed. 17 Fort Worth TX 76118 18 19 - 20 Witness as to Principal T 21. SURETY: 22 West American Insurance Company 23 24 25 B 26 ignatur 27 28 Kylie Kelsoe-Attorney in Fact _ 29 AT Name and Title 30 ATTEST: 3:1 _ k-- Address: 320 Eagle Drive Ste 210 32 (Surety S retaryDenton, 33 34 _ 940-382 9691 _:kA� 35 W mess as to urety Telephone Number ___ 36 37 *Note: 1f signed by an officer of the Surety Company,there must be on-file a certified extract 38 from the by-laws showing:that this person:has authority to sign such obligation. If 39 Surety's physical address is different from its mailing address, both must.b.e provided. 40 The date of the bond shall not be prior to the.date the.Contract is awarded. 41 OFFICIAL RECORD C SECRETARY !IFT UIDM TX CITY OF FORT WORTH Mory's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,OW9 Revised July 1.,20.I 1 THIS POWER OF ATTORNEY IS NOT VALID UNLESS IT IS PRINTED ON RED BACKGROUND. This Power of Attorney limits the acts of those named herein,and they have no authority to bind the Company except in manner and to the extent herein stated. Certificate No."6849220 American Fire and Casualty Company Liberty Mutual Insurance Company The Ohio Casualty Insurance Company West American Insurance Company POWER OF ATTORNEY KNOWN ALL PERSONS BY THESE PRESENTS: That American Fire&Casualty Company and The Ohio Casualty Insurance Company are corporations duly organized under the laws of the State of New Hampshire,that Liberty Mutual Insurance Company is a corporation duly organized under the laws of the State of Massachusetts,and West American Insurance Company is a corporation duly organized under the laws of the State of Indiana(herein collectively called the°Companies°),pursuant to and by authority herein set forth,does hereby name,constitute and appoint, James E.King:Jeff P.King:KKie Kelsoe;Rachyl Mullins all of the city of Denton state of TX each individually if there be more than one named,its true and lawful attomey-in-fact to make,execute;seal,acknowledge and deliver,for and on its behalf as surety and as its act and deed,any and all undertakings,bonds,recognizances and other surety obligations,in pursuance of these presents and shall be as binding upon the Companies as if they have been duly signed by the president and attested by the secretary of the Companies in their own proper persons. IN WITNESS WHEREOF,this Power of Attorney has been subscribed by an authorized officer or official of the Companies and the corporate seals of the Companies have been affixed thereto this 27th day of January 2015 >, American Fire and Casualty Company The Ohio Casualty Insurance Company to 1 r Liberty Mutual Insurance Company aNi 3 West merican Insurance Company _ a0i - By >, = STATE OF PENNSYLVANIA ss David M.Care,Assistant Secretary COUNTY OF MONTGOMERY C _ O: d 0) On this 27th day of January 2015 , before me personally appeared David M. Carey,who acknowledged himself to be the Assistant Secretary of American Fire and v U y Casualty Company,Liberty Mutual Insurance Company,The Ohio Casualty Insurance Company,and West American Insurance Company,and that he,as such,being authorized so to do, �W p 2 execute the foregoing instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer. LC. ar> IN WITNESS WHEREOF,I have hereunto subscribed myname and affixed my notarial seal at Plymouth Meeting Pennsylvania,on the day and year first above written, 00. C g 6} & By: G " j Teresa Pastella,Notary Public 0 G ; . L 60 u a E; wr 02 tt ¢ C «c This Power of Attorney is made and executed pursuanf to and by"auihodtyof the following By-laws and Authorizations ofAmerican Fire and Casualty Company,The Ohio Casualty Insurance 0 p Company,Liberty Mutual Insurance Company,ana�WestAmerican Insurance Company which resolutions are now in full force and effect reading as follows: w co, N 4.. 4 tm ? W ARTICLE IV—OFFICERS—Section 12.Power ofAttomey.Any officer or other official of the Corporation authorized for that purpose in writing rting by the Chairman or the President,and subject O ' to such limitation as the Chairman or the President may prescribe,shall appoint such attomeys-in-fact,as may be necessary to act in behalf of the Corporation to make,execute,seal, O S acknowledge and deliver as surety any and all undertakings,bonds,recognizances and other surety obligations. Such attomeys-in-fact,subject to the limitations set forth in their respective 3; E ai powers of attorney,shall have full power to bind the Corporation by their signature and execution of any such instruments and to attach thereto the seal of the Corporation. When so q I- executed,such instruments shall be as binding as if signed by the President and attested to by the Secretary.Any power or authority granted to any representative or attomey-in-fact under >M: the provisions of this article may be revoked at any time by the Board,the Chairman,the President or by the officer or officers granting such power or authority. 4)0 C* ARTICLE XIII—Execution of Contracts—SECTION 5.Surety Bonds and Undertakings.Any officer of the Company authorized for that purpose in writing by the chairman or the president, E ao +>+ (2 and subject to such limitations as the chairman or the president may prescribe,shall appoint such attomeys-in-fact,as may be necessary to act in behalf of the Company to make,execute, �M O seal,acknowledge and deliver as surety any and all undertakings,bonds,recognizances and other surety obligations. Such attomeys-in-fact subject to the limitations set forth in their C oo Z v respective powers of attorney,shall have full power to bind the Company by their signature and execution of any such instruments and to attach thereto the seal of the Company.When so v C', executed such instruments shall be as binding as if signed by the president and attested by the secretary. o Certificate of Designation-The President of the Company,acting pursuant to the Bylaws of the Company,authorizes David M.Carey,Assistant Secretary to appoint such attomeys-rn- fact as may be necessary to act on behalf of the Company to make,execute,seal,acknowledge and deliver as surety any and all undertakings,bonds,recognizances and other surety obligations. Authorization—By unanimous consent of the Company's Board of Directors,the Company consents that facsimile or mechanically reproduced signature of any assistant secretary of the Company,wherever appearing upon a certified copy of any power of attorney issued by Company in connection with surety bonds,shall be valid and binding upon the Company with the same force and effect as though manually affixed. I,Gregory W.Davenport,the undersigned,Assistant Secretary;of American Fire and Casualty Company,The Ohio Casualty Insurance Company,.Liberty Mutual Insurance Company,and West American Insurance Company do hereby certify that the original power of attorney of which the foregoing is a full,true and correct copy of the Power of Attorney executed by said Companies,is in full force and effect and has not been revoked; ZA. IN TESTIMONY WHEREOF,I have hereunto set my hand and affixed the seals of said Companies this JY pit day of 20 r_3 . 1912 a i :'i } By: g Gregory W.Davenport,Assistant Secretary LMS 12873 122013 23 of 100 STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dxxxnlxr21,2012 STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT TABLE OF CONTENTS Page Article1 —Definitions and Terminology..........................................................................................................I 1.01 Defined Terms...............................................................................................................................1 1.02 Terminology..................................................................................................................................6 Article2—Preliminary Matters.........................................................................................................................7 2.01 Copies of Documents....................................................................................................................7 2.02 Commencement of Contract Time;Notice to Proceed................................................................7 2.03 Starting the Work..........................................................................................................................8 2.04 Before Starting Construction........................................................................................................8 2.05 Preconstruction Conference..........................................................................................................8 2.06 Public Meeting..............................................................................................................................8 2.07 Initial Acceptance of Schedules....................................................................................................8 Article 3 —Contract Documents: Intent, Amending, Reuse............................................................................8 3.01 Intent..............................................................................................................................................8 3.02 Reference Standards......................................................................................................................9 3.03 Reporting and Resolving Discrepancies.......................................................................................9 3.04 Amending and Supplementing Contract Documents................................................................. 10 3.05 Reuse of Documents...................................................................................................................10 3.06 Electronic Data............................................................................................................................11 Article 4—Availability of Lands; Subsurface and Physical Conditions; Hazardous Environmental Conditions; Reference Points...........................................................................................................11 4.01 Availability of Lands .................................................................................................................. 11 4.02 Subsurface and Physical Conditions ..........................................................................................12 4.03 Differing Subsurface or Physical Conditions.............................................................................12 4.04 Underground Facilities ...............................................................................................................13 4.05 Reference Points.........................................................................................................................14 4.06 Hazardous Environmental Condition at Site..............................................................................14 Article 5—Bonds and Insurance.....................................................................................................................16 5.01 Licensed Sureties and Insurers...................................................................................................16 5.02 Performance,Payment, and Maintenance Bonds.......................................................................16 5.03 Certificates of Insurance.............................................................................................................16 5.04 Contractor's Insurance................................................................................................................18 5.05 Acceptance of Bonds and Insurance; Option to Replace...........................................................19 Article 6—Contractor's Responsibilities........................................................................................................19 6.01 Supervision and Superintendence...............................................................................................19 CRY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dewnber21,2012 6.02 Labor; Working Hours................................................................................................................20 6.03 Services,Materials, and Equipment...........................................................................................20 6.04 Project Schedule..........................................................................................................................21 6.05 Substitutes and"Or-Equals".......................................................................................................21 6.06 Concerning Subcontractors, Suppliers,and Others....................................................................24 6.07 Wage Rates..................................................................................................................................25 6.08 Patent Fees and Royalties...........................................................................................................26 6.09 Permits and Utilities....................................................................................................................27 6.10 Laws and Regulations.................................................................................................................27 6.11 Taxes ...........................................................................................................................................28 6.12 Use of Site and Other Areas.......................................................................................................28 6.13 Record Documents......................................................................................................................29 6.14 Safety and Protection..................................................................................................................29 6.15 Safety Representative..................................................................................................................30 6.16 Hazard Communication Programs .............................................................................................30 6.17 Emergencies and/or Rectification...............................................................................................30 6.18 Submittals....................................................................................................................................31 6.19 Continuing the Work...................................................................................................................32 6.20 Contractor's General Warranty and Guarantee..........................................................................32 6.21 Indemnification.........................................................................................................................33 6.22 Delegation of Professional Design Services ..............................................................................34 6.23 Right to Audit..............................................................................................................................34 6.24 Nondiscrimination.......................................................................................................................35 Article7-Other Work at the Site...................................................................................................................35 7.01 Related Work at Site...................................................................................................................35 7.02 Coordination................................................................................................................................36 Article8-City's Responsibilities...................................................................................................................36 8.01 Communications to Contractor...................................................................................................36 8.02 Furnish Data................................................................................................................................36 8.03 Pay When Due............................................................................................................................36 8.04 Lands and Easements; Reports and Tests...................................................................................36 8.05 Change Orders.............................................................................................................................36 8.06 Inspections,Tests, and Approvals..............................................................................................36 8.07 Limitations on City's Responsibilities.......................................................................................37 8.08 Undisclosed Hazardous Environmental Condition....................................................................37 8.09 Compliance with Safety Program...............................................................................................37 Article 9-City's Observation Status During Construction...........................................................................37 9.01 City's Project Representative.....................................................................................................37 9.02 Visits to Site................................................................................................................................37 9.03 Authorized Variations in Work..................................................................................................38 9.04 Rejecting Defective Work..........................................................................................................38 9.05 Determinations for Work Performed..........................................................................................38 9.06 Decisions on Requirements of Contract Documents and Acceptability of Work.....................38 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:D:xxm xT21,2012 Article 10 Changes in the Work;Claims; Extra Work................................................................................38 10.01 Authorized Changes in the Work...............................................................................................38 10.02 Unauthorized Changes in the Work ...........................................................................................39 10.03 Execution of Change Orders.......................................................................................................39 10.04 Extra Work..................................................................................................................................39 10.05 Notification to Surety..................................................................................................................39 10.06 Contract Claims Process.............................................................................................................40 Article I I -Cost of the Work; Allowances; Unit Price Work; Plans Quantity Measurement......................41 11.01 Cost of the Work.........................................................................................................................41 11.02 Allowances..................................................................................................................................43 11.03 Unit Price Work..........................................................................................................................44 11.04 Plans Quantity Measurement......................................................................................................45 Article 12-Change of Contract Price;Change of Contract Time.................................................................46 12.01 Change of Contract Price............................................................................................................46 12.02 Change of Contract Time............................................................................................................47 12.03 Delays..........................................................................................................................................47 Article 13-Tests and Inspections; Correction, Removal or Acceptance of Defective Work......................48 13.01 Notice of Defects ........................................................................................................................48 13.02 Access to Work...........................................................................................................................48 13.03 Tests and Inspections..................................................................................................................48 13.04 Uncovering Work........................................................................................................................49 13.05 City May Stop the Work.............................................................................................................49 13.06 Correction or Removal of Defective Work................................................................................50 13.07 Correction Period........................................................................................................................50 13.08 Acceptance of Defective Work...................................................................................................51 13.09 City May Correct Defective Work.............................................................................................51 Article 14-Payments to Contractor and Completion....................................................................................52 14.01 Schedule of Values......................................................................................................................52 14.02 Progress Payments......................................................................................................................52 14.03 Contractor's Warranty of Title...................................................................................................54 14.04 Partial Utilization........................................................................................................................55 14.05 Final Inspection...........................................................................................................................55 14.06 Final Acceptance.........................................................................................................................55 14.07 Final Payment..............................................................................................................................56 14.08 Final Completion Delayed and Partial Retainage Release........................................................56 14.09 Waiver of Claims........................................................................................................................57 Article 15 -- Suspension of Work and Termination........................................................................................57 15.01 City May Suspend Work.............................................................................................................57 15.02 City May Terminate for Cause...................................................................................................58 15.03 City May Terminate For Convenience.......................................................................................60 Article16 Dispute Resolution......................................................................................................................61 16.01 Methods and Procedures.............................................................................................................61 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dc=nbcx21,2012 Article17 Miscellaneous..............................................................................................................................62 17.01 Giving Notice..............................................................................................................................62 17.02 Computation of Times................................................................................................................62 17.03 Cumulative Remedies.................................................................................................................62 17.04 Survival of Obligations...............................................................................................................63 17.05 Headings......................................................................................................................................63 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dncanbe21,2012 UU 72 OU•I General Conditions Pagel of b3 ARTICLE 1—DEFINITIONS AND TERMINOLOGY 1.01 Defined Teims A. Wherever used in these General Conditions or in other Contract Documents, the terms listed below have the meanings indicated which are applicable to both the singular and plural thereof, and words denoting gender shall include the masculine, feminine and neuter. Said terms are generally capitalized or written in italics, but not always. When used in a context consistent with the definition of a listed-defined term, the term shall have a meaning as defined below whether capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Addenda—Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the proposed Contract Documents. 2. Agreement—The written instrument which is evidence of the agreement between City and Contractor covering the Work. 3. Application for Payment—The form acceptable to City which is to be used by Contractor during the course of the Work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract Documents. 4. Asbestos—Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 5. Awaid—Authorization by the City Council for the City to enter into an Agreement. 6. Bid—The offer or proposal of a Bidder submitted on the prescribed form setting forth the prices for the Work to be performed. 7. Bidder-- The individual or entity who submits a Bid directly to City. 8. Bidding Documents--The Bidding Requirements and the proposed Contract Documents (including all Addenda). 9. Bidding Requirements--The advertisement or Invitation to Bid, Instructions to Bidders, Bid security of acceptable form, if any, and the Bid Form with any supplements. 10. Business Day — A business day is defined as a day that the City conducts normal business, generally Monday through Friday, except for federal or state holidays observed by the City. 11. Buzz-saw—City's on-line,electronic document management and collaboration system. 12. Calendar Day—A day consisting of 24 hours measured from midnight to the next midnight. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:D=nibLr21.2012 U0 72 00-t General Conditions Page 2 of 63 13. Change Order--A document, which is prepared and approved by the City, which is signed by Contractor and City and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 14. City— The City of Fort Worth, Texas, a home-rule municipal corporation, authorized and chartered under the Texas State Statutes, acting by its governing body through its City Manager, his designee, or agents authorized under his behalf, each of which is required by Charter to perform specific duties with responsibility for final enforcement of the contracts involving the City of Fort Worth is by Charter vested in the City Manager and is the entity with whom Contractor has entered into the Agreement and for whom the Work is to be performed. 15. City Attorney - The officially appointed City Attorney of the City of Fort Worth, Texas, or his duly authorized representative. 16. City Council - The duly elected and qualified governing body of the City of Fort Worth, Texas. 17. City Manager The officially appointed and authorized City Manager of the City of Fort Worth,Texas,or his duly authorized representative. 18. Contract Claim--A demand or assertion by City or Contractor seeking an adjustment of Contract Price or Contract Time, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Contract Claim. 19. Contract--The entire and integrated written document between the City and Contractor concerning the Work. The Contract contains the Agreement and all Contract Documents and supersedes prior negotiations,representations, or agreements, whether written or oral. 20. Contract Documents--Those items so designated in the Agreement. All items listed in the Agreement are Contract Documents. Approved Submittals, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. 21. Contract Price-The moneys payable by City to Contractor for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of Paragraph 11.03 in the case of Unit Price Work). 22. Contract Time---The number of days or the dates stated in the Agreement to: (i) achieve Milestones, if any and(ii)complete the Work so that it is ready for Final Acceptance. 23. Contractor--The individual or entity with whom City has entered into the Agreement. 24. Cost of the War*--See Paragraph 11.01 of these General Conditions for definition. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dwa l=21,2012 0072OU-1 General Conditions Page 3 of 63 25. Damage Claims — A demand for money or services arising from the Project or Site from a third party,City or Contractor exclusive of a Contract Claim. 26. Day or day--A day, unless otherwise defined, shall mean a Calendar Day. 27. Director of Aviationr — The officially appointed Director of the Aviation Department of the City of Fort Worth,Texas, or his duly appointed representative, assistant, or agents. 28. Director of Par Jos and Community Services— The officially appointed Director of the Parks and Community Services Department of the City of Fort Worth, Texas, or his duly appointed representative, assistant,or agents. 29. Director of Planning and Development — The officially appointed Director of the Planning and Development Department of the City of Fort Worth, Texas, or his duly appointed representative, assistant,or agents. 30. Director of Transportation Public Works — The officially appointed Director of the Transportation Public Works Department of the City of Fort Worth, Texas, or his duly appointed representative, assistant,or agents. 31. Director of Water Department -- The officially appointed Director of the Water Department of the City of Fort Worth, Texas,or his duly appointed representative, assistant,or agents. 32. Drawings--That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Submittals are not Drawings as so defined. 33. Effective Date of the Agreement—The date indicated in the Agreement on which it becomes effective, but if no such date is indicated, it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver. 34. Engineer—The licensed professional engineer or engineering firm registered in the State of Texas performing professional services for the City. 35. Extra Work Additional work made necessary by changes or alterations of the Contract Documents or of quantities or for other reasons for which no prices are provided in the Contract Documents. Extra work shall be part of the Work. 36.Field Order---A written order issued by City which requires changes in the Work but which does not involve a change in the Contract Price, Contract Time, or the intent of the Engineer. Field Orders are paid from Field Order Allowances incorporated into the Contract by funded work type at the time of award. 37. Final Acceptance — The written notice given by the City to the Contractor that the Work specified in the Contract Documents has been completed to the satisfaction of the City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision;De=rba21,2012 00 72 UU-I General Conditions Page 4 or63 38. Final Inspection — Inspection carried out by the City to verify that the Contractor has completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in conformance with the Contract Documents. 39. General Requirements—Sections of Division 1 of the Contract Documents. 40. Hazardous Environmental Condition—The presence at the Site of Asbestos, PCBs, Petroleum, Hazardous Waste, Radioactive Material, or other materials in such quantities or circumstances that may present a substantial danger to persons or property exposed thereto. 41. Hazardous Waste—Hazardous waste is defined as any solid waste listed as hazardous or possesses one or more hazardous characteristics as defined in the federal waste regulations, as amended from time to time. 42. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 43. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 44. Major Item An Item of work included in the Contract Documents that has a total cost equal to or greater than 5%of the original Contract Price or$25,000 whichever is less. 45. Milestone---A principal event specified in the Contract Documents relating to an intermediate Contract Time prior to Final Acceptance of the Work. 46. Notice of Award----The written notice by City to the Successful Bidder stating that upon timely compliance by the Successful Bidder with the conditions precedent listed therein, City will sign and deliver the Agreement. 47. Notice to Proceed---A written notice given by City to Contractor fixing the date on which the Contract Time will commence to run and on which Contractor shall start to perform the Work specified in Contract Documents. 48.PCBs—Polychlorinated biphenyls. 49. Petroleum- Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with other non-Hazardous Waste and crude oils. 50. Plans--See definition of Drawings. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dwerntxr2l,2012 00 71 U0.1 General Conditions Page 5 of 63 51. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with the General Requirements, describing the sequence and duration of the activities comprising the Contractor's plan to accomplish the Work within the Contract Time. 52. Project—The Work to be performed under the Contract Documents. 53. Project Representative—The authorized representative of the City who will be assigned to the Site. 54. Public Meeting — An announced meeting conducted by the City to facilitate public participation and to assist the public in gaining an informed view of the Project. 55. Radioactive Material—Source, special nuclear, or byproduct material as defined by the Atomic Energy Act of 1954 (42 USC Section 2011 et seq.) as amended from time to time. 56. Regular Working Hours Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday thru Friday(excluding legal holidays). 57. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged. 58. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities. 59. Schedule of Values—A schedule, prepared and maintained by Contractor, allocating portions of the Contract Price to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment. 60. Site—Lands or areas indicated in the Contract Documents as being furnished by City upon which the Work is to be performed, including rights-of-way, permits, and easements for access thereto, and such other lands furnished by City which are designated for the use of Contractor. 61. Specifications—That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto. Specifications may be specifically made a part of the Contract Documents by attachment or, if not attached, may be incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each Project. 62, Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site. cny Or f ORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:De=nba2t,2012 00 7100-1 General Conditions Page 6 of 63 63. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. 64. Successful Bidder—The Bidder submitting the lowest and most responsive Bid to whom City makes an Award. 65. Superintendent The representative of the Contractor who is available at all times and able to receive instructions from the City and to act for the Contractor. 66. Supplementary Conditions----That part of the Contract Documents which amends or supplements these General Conditions. 67. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor. 68. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including but not limited to, those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water,wastewater,storm water, other liquids or chemicals,or traffic or other control systems. 69. Unit Price Work—See Paragraph 11.03 of these General Conditions for definition. 70. Weekend Working Hours— Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday, Sunday or legal holiday, as approved in advance by the City. 71. Work—The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction including any Change Order or Field Order, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents. 72. Working Day— A working day is defined as a day, not including Saturdays, Sundays, or legal holidays authorized by the City for contract purposes, in which weather or other conditions not under the control of the Contractor will permit the performance of the principal unit of work underway for a continuous period of not less than 7 hours between 7 a.m. and 6 p.m. 1.02 Tei-minology A. The words and terms discussed in Paragraph 1.02.B through E are not defined but, when used in the Bidding Requirements or Contract Documents,have the indicated meaning. B. Intent of Certain Ternis or Adjectives: CrrY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Da xmiber2l,2012 UU7200-1 General Conditions Page 9 of 63 1. The Contract Documents include the terms "as alIowed," "as approved," "as ordered," "as directed" or teens of like effect or import to authorize an exercise of judgment by City. In addition, the adjectives "reasonable," "suitable," "acceptable," "proper," "satisfactory," or adjectives of like effect or import are used to describe an action or determination of City as to the Work. It is intended that such exercise of professional judgment, action, or determination will be solely to evaluate, in general, the Work for compliance with the information in the Contract Documents and with the design concept of the Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). C. Defective: 1. The word "defective," when modifying the word "Work," refers to Work that is unsatisfactory, faulty,or deficient in that it: a. does not conform to the Contract Documents; or b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or c. has been damaged prior to City's written acceptance. D. Furnish, Install, Perform, Provide: 1. The word "Furnish" or the word "Install" or the word "Perform" or the word "Provide" or the word "Supply," or any combination or similar directive Or usage thereof, shall mean furnishing and incorporating in the Work including all necessary labor, materials, equipment, and everything necessary to perform the Work indicated, unless specifically limited in the context used. E. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning. ARTICLE 2—PRELIMINARY MATTERS 2.01 Copies of Documents City shall furnish to Contractor one (1) original executed copy and one (1) electronic copy of the Contract Documents, and four (4) additional copies of the Drawings. Additional copies will be furnished upon request at the cost of reproduction. 2.02 Commencement of Contract Time;Notice to Proceed The Contract Time will commence to run on the day indicated in the Notice to Proceed. A Notice to Proceed may be given at anytime within 14 days after the Effective Date of the Agreement. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Do=nbcr21,2012 007LOO-1 General Conditions Page 8 of 63 2.03 Starting the Work Contractor shall start to perform the Work on the date when the Contract Time commences to run. No Work shall be done at the Site prior to the date on which the Contract Time commences to run. 2.04 Before Starting Construction Baseline Schedules: Submit in accordance with the Contract Documents, and prior to starting the Work. 2.05 Pr-econstrttction Conference Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as specified in the Contract Documents. 2.06 Public Meeting Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor attending the Public Meeting as scheduled by the City. 2.07 Initial Acceptance of Schedules No progress payment shall be made to Contractor until acceptable schedules are submitted to City in accordance with the Schedule Specification as provided in the Contract Documents. ARTICLE 3—CONTRACT DOCUMENTS: INTENT,AMENDING,REUSE 3.01 Intent A. The Contract Documents are complementary; what is required by one is as binding as if required by all. B. It is the intent of the Contract Documents to describe a functionally complete project (or part thereof) to be constructed in accordance with the Contract Documents. Any labor, documentation, services, materials, or equipment that reasonably may be inferred from the Contract Documents or from prevailing custom or trade usage as being required to produce the indicated result will be provided whether or not specifically called for, at no additional cost to City. C. Clarifications and interpretations of the Contract Documents shall be issued by City. D. The Specifications may vary in form, format and style. Some Specification sections may be written in varying degrees of streamlined or declarative style and some sections may be relatively narrative by comparison. Omission of such words and phrases as "the Contractor shall," "in conformity with," "as shown," or "as specified" are intentional in streamlined sections. Omitted words and phrases shall be supplied by inference. Similar types of provisions may appear in various parts of a section or articles within a part depending on the format of the CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:De21>2012 00T200-1 General Conditions Page 4 of 63 section. The Contractor shall not take advantage of any variation of form, format or style in making Contract Claims. E. The cross referencing of specification sections under the subparagraph heading "Related Sections include but are not necessarily limited to:" and elsewhere within each Specification section is provided as an aid and convenience to the Contractor. The Contractor shall not rely on the cross referencing provided and shall be responsible to coordinate the entire Work under the Contract Documents and provide a complete Project whether or not the cross referencing is provided in each section or whether or not the cross referencing is complete. 3.02 Reference Slandar ds A. Standards, Specifications, Codes,Laws, and Regulations 1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. 2. No provision of any such standard, specification, manual, or code, or any instruction of a Supplier, shall be effective to change the duties or responsibilities of City, Contractor, or any of their subcontractors, consultants, agents, or employees, from those set forth in the Contract Documents. No such provision or instruction shall be effective to assign to City, or any of its officers, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.03 Reporting and Resolving Discrepancies A. Reporting Discrepancies: 1. Conntraclor's Review of Contract Documents Before Slarling Wok: Before undertaking each part of the Work, Contractor shall carefully study and compare the Contract Documents and check and verify pertinent figures therein against all applicable field measurements and conditions. Contractor shall promptly report in writing to City any conflict, error, ambiguity, or discrepancy which Contractor discovers, or has actual knowledge of, and shall obtain a written interpretation or clarification from City before proceeding with any Work affected thereby. 2. Contractor's Revieev of Contract Documents During Performance of Wok: If, during the performance of the Work, Contractor discovers any conflict, error, ambiguity, or discrepancy within the Contract Documents, or between the Contract Documents and (a) any applicable Law or Regulation , (b) any standard, specification, manual, or code, or(c) any instruction of any Supplier, then Contractor shall promptly report it to City in writing. Contractor shall not proceed with the Work affected thereby (except in an emergency as required by Paragraph CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision;Dwwiber2l,2012 0072W-I General Conditions Page 10 of 63 6.17.A) until an amendment or supplement to the Contract Documents has been issued by one of the methods indicated in Paragraph 3.04. 3. Contractor shall not be liable to City for failure to report any conflict, error, ambiguity, or discrepancy in the Contract Documents unless Contractor had actual knowledge thereof. B. Resolving Discrepancies: 1. Except as may be otherwise specifically stated in the Contract Documents, the provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity, or discrepancy between the provisions of the Contract Documents and the provisions of any standard, specification, manual, or the instruction of any Supplier(whether or not specifically incorporated by reference in the Contract Documents). 2. In case of discrepancies, figured dimensions shall govern over scaled dimensions, Plans shall govern over Specifications, Supplementary Conditions shall govern over General Conditions and Specifications, and quantities shown on the Plans shall govern over those shown in the proposal. 3.04 Antending and Supplementing Contract Documents A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by a Change Order. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work not involving a change in Contract Price or Contract Time, may be authorized,by one or more of the following ways: 1. A Field Order; 2. City's review of a Submittal (subject to the provisions of Paragraph 6.18.C); or 3. City's written interpretation or clarification. 3.05 Reuse of Documents A. Contractor and any Subcontractor or Supplier shall not: 1. have or acquire any title to or ownership rights in any of the Drawings, Specifications, or other documents (or copies of any thereof) prepared by or bearing the seal of Engineer, including electronic media editions; or 2. reuse any such Drawings, Specifications, other documents, or copies thereof on extensions of the Project or any other project without written consent of City and specific written verification or adaptation by Engineer. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dea mber2l,2012 01173 ou-1 General Conditions Page I of63 B. The prohibitions of this Paragraph 3.05 will survive final payment, or termination of the Contract. Nothing herein shall preclude Contractor from retaining copies of the Contract Documents for record purposes. 3.06 Electronic Data A. Unless otherwise stated in the Supplementary Conditions, the data furnished by City or Engineer to Contractor, or by Contractor to City or Engineer, that may be relied upon are limited to the printed copies included in the Contract Documents (also known as hard copies) and other Specifications referenced and located on the City's Buzzsaw site. Files in electronic media format of text, data, graphics, or other types are furnished only for the convenience of the receiving party. Any conclusion or information obtained or derived from such electronic files will be at the user's sole risk. If there is a discrepancy between the electronic files and the hard copies,the hard copies govern. B. When transferring documents in electronic media format, the transferring party makes no representations as to long term compatibility, usability, or readability of documents resulting from the use of software application packages, operating systems, or computer hardware differing from those used by the data's creator. ARTICLE 4—AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; HAZARDOUS ENVIRONMENTAL CONDITIONS; REFERENCE POINTS 4.01 Availability of Lauds A. City shall furnish the Site. City shall notify Contractor of any encumbrances or restrictions not of general application but specifically related to use of the Site with which Contractor must comply in performing the Work. City will obtain in a timely manner and pay for easements for permanent structures or permanent changes in existing facilities. 1. The City has obtained or anticipates acquisition of and/or access to right-of-way, and/or easements. Any outstanding right-of-way and/or easements are anticipated to be acquired in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding right-of-way, and/or easements. 2. The City has or anticipates removing and/or relocating utilities, and obstructions to the Site. Any outstanding removal or relocation of utilities or obstructions is anticipated in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding utilities or obstructions to be removed,adjusted, and/or relocated by others. B. Upon reasonable written request, City shall furnish Contractor with a current statement of record legal title and legal description of the lands upon which the Work is to be performed. C n Y OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision Dwwba2l,2012 0072W-I General Conditions Page 12 of 63 C. Contractor shall provide for all additional lands and access thereto that may be required for construction facilities or storage of materials and equipment. 4.02 Subsurface and Physical Conditions A. Repa-ts and Drawings: The Supplementary Conditions identify: 1. those reports known to City of explorations and tests of subsurface conditions at or contiguous to the Site; and 2. those drawings known to City of physical conditions relating to existing surface or subsurface structures at the Site(except Underground Facilities). B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely,upon the accuracy of the "technical data" contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such "technical data" is identified in the Supplementary Conditions. Contractor may not make any Contract Claim against City, or any of their officers, directors,members,partners, employees, agents, consultants,or subcontractors with respect to: 1. the completeness of such reports and drawings for Contractor's purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, and safety precautions and programs incident thereto; or 2. other data, interpretations, opinions, and information contained in such reports or shown or indicated in such drawings; or 3. any Contractor interpretation of or conclusion drawn from any "technical data" or any such other data, interpretations,opinions, or information. 4.03 Differing Subsun face or-Physical Conditions A. Notice: If Contractor believes that any subsurface or physical condition that is uncovered or revealed either: 1. is of such a nature as to establish that any "technical data"on which Contractor is entitled to rely as provided in Paragraph 4.02 is materially inaccurate; or 2. is of such a nature as to require a change in the Contract Documents; or 3. differs materially from that shown or indicated in the Contract Documents; or 4, is of an unusual nature, and differs materially from conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents; CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Do=nbLT21,2012 00 72 00-1 General Conditions Page 13 of 63 then Contractor shall, promptly after becoming aware thereof and before further disturbing the subsurface or physical conditions or performing any Work in connection therewith (except in an emergency as required by Paragraph 6.17.A), notify City in writing about such condition. B. Possible Price and Time Adjustments Contractor shall not be entitled to any adjustment in the Contract Price or Contract Time if 1. Contractor knew of the existence of such conditions at the time Contractor made a final commitment to City with respect to Contract Price and Contract Time by the submission of a Bid or becoming bound under a negotiated contract; or 2. the existence of such condition could reasonably have been discovered or revealed as a result of the examination of the Contract Documents or the Site; or 3. Contractor failed to give the written notice as required by Paragraph 4.03.A. 4.04 Underground Facilities A. Shown o1•Indicated. The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the Site is based on information and data furnished to City or Engineer by the owners of such Underground Facilities, including City, or by others. Unless it is otherwise expressly provided in the Supplementary Conditions: I. City and Engineer shall not be responsible for the accuracy or completeness of any such information or data provided by others; and 2. the cost of all of the following will be included in the Contract Price, and Contractor shall have full responsibility for: a. reviewing and checking all such information and data; b. locating all Underground Facilities shown or indicated in the Contract Documents; c. coordination and adjustment of the Work with the owners of such Underground Facilities, including City, during construction; and d. the safety and protection of all such Underground Facilities and repairing any damage thereto resulting from the Work. B. Not Shown or Indicated- 1. If an Underground Facility which conflicts with the Work is uncovered or revealed at or contiguous to the Site which was not shown or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Doeeabea21,2012 00 72 00-1 General Conditions Page 14 of63 Work in connection therewith (except in an emergency as required by Paragraph 6.17.A), identify the owner of such Underground Facility and give notice to that owner and to City. City will review the discovered Underground Facility and determine the extent, if any, to which a change may be required in the Contract Documents to reflect and document the consequences of the existence or location of the Underground Facility. Contractor shall be responsible for the safety and protection of such discovered Underground Facility. 2. If City concludes that a change in the Contract Documents is required, a Change Order may be issued to reflect and document such consequences. 3. Verification of existing utilities, structures, and service lines shall include notification of all utility companies a minimum of 48 hours in advance of construction including exploratory excavation if necessary. 4.05 Reference Points A. City shall provide engineering surveys to establish reference points for construction, which in City's judgment are necessary to enable Contractor to proceed with the Work. City will provide construction stakes or other customary method of marking to establish line and grades for roadway and utility construction, centerlines and benchmarks for bridgework. Contractor shall protect and preserve the established reference points and property monuments,and shall make no changes or relocations. Contractor shall report to City whenever any reference point or property monument is lost or destroyed or requires relocation because of necessary changes in grades or locations. The City shall be responsible for the replacement or relocation of reference points or property monuments not carelessly or willfully destroyed by the Contractor. The Contractor shall notify City in advance and with sufficient time to avoid delays. B. Whenever, in the opinion of the City, any reference point or monument has been carelessly or willfully destroyed, disturbed, or removed by the Contractor or any of his employees, the full cost for replacing such points plus 25% will be charged against the Contractor, and the full amount will be deducted from payment due the Contractor. 4.06 Hazai does Environmental Condition at Site A. Repots and Drawings: The Supplementary Conditions identify those reports and drawings known to City relating to Hazardous Environmental Conditions that have been identified at the Site. B. Limited Reliance by Contractor on Technical Data Autho•ized: Contractor may rely upon the accuracy of the "technical data" contained in such reports and drawings, but such reports and drawings are not Contract Documents. Such "technical data" is identified in the Supplementary Conditions. Contractor may not make any Contract Claim against City, or any of their officers, directors, members,partners, employees,agents,consultants, or subcontractors with respect to: 1. the completeness of such reports and drawings for Contractor's purposes, including, but not limited to, any aspects of the means, methods, techniques, sequences and procedures of CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deeenb-T21,2012 UO72OU-I General Conditions Page 15 of 63 construction to be employed by Contractor and safety precautions and programs incident thereto; or 2. other data, interpretations, opinions and information contained in such reports or shown or indicated in such drawings; or 3. any Contractor interpretation of or conclusion drawn from any "technical data" or any such other data, interpretations,opinions or information. C. Contractor shall not be responsible for any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work. Contractor shall be responsible for a Hazardous Environmental Condition created with any materials brought to the Site by Contractor, Subcontractors, Suppliers,or anyone else for whom Contractor is responsible. D. If Contractor encounters a Hazardous Environmental Condition or if Contractor or anyone for whom Contractor is responsible creates a Hazardous Environmental Condition, Contractor shall immediately: (i) secure or otherwise isolate such condition; (ii) stop all Work in connection with such condition and in any area affected thereby (except in an emergency as required by Paragraph 6.I7.A); and (iii) notify City (and promptly thereafter confirm such notice in writing). City may consider the necessity to retain a qualified expert to evaluate such condition or take corrective action, if any. E. Contractor shall not be required to resume Work in connection with such condition or in any affected area until after City has obtained any required permits related thereto and delivered written notice to Contractor: (i) specifying that such condition and any affected area is or has been rendered suitable for the resumption of Work; or (ii) specifying any special conditions under which such Work may be resumed. F. If after receipt of such written notice Contractor does not agree to resume such Work based on a reasonable belief it is unsafe, or does not agree to resume such Work under such special conditions, then City may order the portion of the Work that is in the area affected by such condition to be deleted from the Work. City may have such deleted portion of the Work performed by City's own forces or others. G. To the f dlest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City,front and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resohrtion costs) arising out of or relating to a Hazardous Environmental Condition created by Contractor or by anyone for whom Contractor is responsible. Nothing in this Paragraph 4.06.G shall obligate Contractor to indeinnify ally individual or entity from and against the Consequences of that individual's or entity's own negligence. H. The provisions of Paragraphs 4.02, 4.03, and 4.04 do not apply to a Hazardous Environmental Condition uncovered or revealed at the Site. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decanbcr21,2012 UU 72 00-1 General Conditions Page 16 of 63 ARTICLE 5—BONDS AND INSURANCE 5.01 Licensed Sureties and Insurefs All bonds and insurance required by the Contract Documents to be purchased and maintained by Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the State of Texas to issue bonds or insurance policies for the limits and coverages so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided in the Supplementary Conditions. 5.02 Performance, Payment, and Maintenance Bonds A. Contractor shall furnish performance and payment bonds, in accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as security for the faithful performance and payment of all of Contractor's obligations under the Contract Documents. B. Contractor shall furnish maintenance bonds in an amount equal to the Contract Price as security to protect the City against any defects in any portion of the Work described in the Contract Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final Acceptance by the City. C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list of"Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney which shall show that it is effective on the date the agent or attorney-in-fact signed each bond. D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in the State of Texas or it ceases to meet the requirements of Paragraph 5.02.C, Contractor shall promptly notify City and shall, within 30 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 5.01 and 5.02.C. 5.03 Certificates of Insurance Contractor shall deliver to City, with copies to each additional insured and loss payee identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by City or any other additional insured)which Contractor is required to purchase and maintain. 1. The certificate of insurance shall document the City, and all identified entities named in the Supplementary Conditions as"Additional Insured"on all liability policies. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision;Doxmber2l,2012 0072 UtJ-1 General Conditions Page 17 of 63 2. The Contractor's general liability insurance shall include a, "per project" or "per location", endorsement,which shall be identified in the certificate of insurance provided to the City. 3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured, be complete in its entirety, and show complete insurance carrier names as listed in the current A.M.Best Property&Casualty Guide 4. The insurers for all policies must be licensed and/or approved to do business in the State of Texas. Except for workers' compensation, all insurers must have a minimum rating of A-: VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength and solvency to the satisfaction of Risk Management. If the rating is below that required,written approval of City is required. 5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of the City. In addition, the Contractor agrees to waive all rights of subrogation against the Engineer (if applicable), and each additional insured identified in the Supplementary Conditions 5. Failure of the City to demand such certificates or other evidence of full compliance with the insurance requirements or failure of the City to identify a deficiency from evidence that is provided shall not be construed as a waiver of Contractor's obligation to maintain such lines of insurance coverage. 7. If insurance policies are not written for specified coverage limits, an Umbrella or Excess Liability insurance for any differences is required. Excess Liability shall follow form of the primary coverage. 8. Unless otherwise stated, all required insurance shall be written on the "occurrence basis". If coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with or prior to the date of the effective date of the agreement and the certificate of insurance shall state that the coverage is claims-made and the retroactive date. The insurance coverage shall be maintained for the duration of the Contract and for three (3) years following Final Acceptance provided under the Contract Documents or for the warranty period, whichever is longer. An annual certificate of insurance submitted to the City shall evidence such insurance coverage. 9. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the required lines of coverage, nor decrease the limits of said coverage unless such endorsements are approved in writing by the City. In the event a Contract has been bid or executed and the exclusions are determined to be unacceptable or the City desires additional insurance coverage, and the City desires the contractor/engineer to obtain such coverage, the contract price shall be adjusted by the cost of the premium for such additional coverage plus 10%. 10. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance coverage shall be approved by the City in regards to asset value and stockholders' equity. In CFIY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dwmiba21,2012 UU 72 00-1 General Conditions Page 18 of 63 lieu of traditional insurance, alternative coverage maintained through insurance pools or risk retention groups, must also be approved by City. 11. Any deductible in excess of$5,000.00, for any policy that does not provide coverage on a first-dollar basis, must be acceptable to and approved by the City. 12. City, at its sole discretion, reserves the right to review the insurance requirements and to make reasonable adjustments to insurance coverage's and their limits when deemed necessary and prudent by the City based upon changes in statutory law, court decision or the claims history of the industry as well as of the contracting party to the City. The City shall be required to provide prior notice of 90 days, and the insurance adjustments shall be incorporated into the Work by Change Order. 13. City shall be entitled, upon written request and without expense, to receive copies of policies and endorsements thereto and may make any reasonable requests for deletion or revision or modifications of particular policy terms, conditions, limitations, or exclusions necessary to conform the policy and endorsements to the requirements of the Contract. Deletions, revisions, or modifications shall not be required where policy provisions are established by law or regulations binding upon either party or the underwriter on any such policies. 14. City shall not be responsible for the direct payment of insurance premium costs for Contractor's insurance. 5.04 Contractor's Insiu•ance A. Workers Compensations and Employers' Liability. Contractor shall purchase and maintain such insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers' Compensation Act (Texas Labor Code, Ch. 405, as amended), and minimum limits for Employers' Liability as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor's performance of the Work and Contractor's other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers' compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor's employees. B. Commercial General Liability. Coverage shall include but not be limited to covering liability (bodily injury or property damage) arising from: premises/operations, independent contractors, products/completed operations, personal injury, and liability under an insured contract. Insurance shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision,Dweunb r21,2012 00 72 00-1 General Conditions Page 19 or63 insurance or self-insurance programs afforded to the City. The Commercial General Liability policy, shall have no exclusions by endorsements that would alter of nullify premises/operations, products/completed operations, contractual, personal injury, or advertising injury, which are normally contained with the policy,unless the City approves such exclusions in writing. For construction projects that present a substantial completed operation exposure, the City may require the contractor to maintain completed operations coverage for a minimum of no less than three (3) years following the completion of the project (if identified in the Supplementary Conditions). C. Automobile Liability. A commercial business auto policy shall provide coverage on "any auto", defined as autos owned, hired and non-owned and provide indemnity for claims for damages because bodily injury or death of any person and or property damage arising out of the work, maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable. D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of railroad right-of-way, the Contractor shall comply with the requirements identified in the Supplementary Conditions. E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or other loss of insurance coverage. Contractor shall stop work until replacement insurance has been procured. There shall be no time credit for days not worked pursuant to this section. 5.05 Acceptance of Bonds and Insurance; Option to Replace If City has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the Contractor in accordance with Article S on the basis of non-conformance with the Contract Documents, the City shall so notify the Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor shall provide to the City such additional information in respect of insurance provided as the City may reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required by the Contract Documents, the City shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. ARTICLE 6—CONTRACTOR'S RESPONSIBILITIES 6.01 Supe7vision and Supe7•intendence A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. COPY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision,Dwun1xT21,?01? 0072 OU-1 General Conditions Page 20 of 63 B. At all times during the progress of the Work, Contractor shall assign a competent, English- speaking, Superintendent who shall not be replaced without written notice to City. The Superintendent will be Contractor's representative at the Site and shall have authority to act on behalf of Contractor. All communication given to or received from the Superintendent shall be binding on Contractor. C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction. 6.02 Labor; Working Hours A. Contractor shall provide competent, suitably qualified personnel to perform construction as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during Regular Working Hours. Contractor will not permit the performance of Work beyond Regular Working Hours or for Weekend Working Hours without City's written consent (which will not be unreasonably withheld). Written request (by letter or electronic communication) to perfonn Work: 1, for beyond Regular Working Hours request must be made by noon at least two (2) Business Days prior 2, for Weekend Working Hours request must be made by noon of the preceding Thursday 3. for legal holidays request must be made by noon two Business Days prior to the legal holiday. 6.03 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, Contractor required testing, start-up,and completion of the Work. B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of City. If required by City, Contractor shall fumish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Do niba2l,2012 007200-1 General Conditions Page 21 of 63 C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier,except as otherwise may be provided in the Contract Documents. D. All items of standard equipment to be incorporated into the Work shall be the latest model at the time of bid, unless otherwise specified. 6.04 Project Schedule A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.07 and the General Requirements as it may be adjusted from time to time as provided below. 1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.07 and the General Requirements) proposed adjustments in the Project Schedule that will not result in changing the Contract Time. Such adjustments will comply with any provisions of the General Requirements applicable thereto. 2. Contractor shall submit to City a monthly Project Schedule with a monthly progress payment for the duration of the Contract in accordance with the schedule specification 01 32 16. 3. Proposed adjustments in the Project Schedule that will change the Contract Time shall be submitted in accordance with the requirements of Article 12. Adjustments in Contract Time may only be made by a Change Order. 6.05 Substitutes and "Or-Equals" A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or"or-equal" item or no substitution is permitted, other items of material or equipment of other Suppliers may be submitted to City for review under the circumstances described below. 1. "O)=Equal"Items: If in City's sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by City as an "or-equal" item, in which case review and approval of the proposed item may, in City's sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 6.05.A.1, a proposed item of material or equipment will be considered functionally equal to an item so named if: a. the City determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength,and design characteristics; CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dwmnb v21,2012 UU72UU-t General Conditions Page 22 of 63 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; and 3) it has a proven record of performance and availability of responsive service; and b. Contractor certifies that, if approved and incorporated into the Work: 1) there will be no increase in cost to the City or increase in Contract Time; and 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. 2. Substitute Items: a. If in City's sole discretion an item of material or equipment proposed by Contractor does not qualify as an "or-equal" item under Paragraph 6.05.A.1, it may be submitted as a proposed substitute item. b. Contractor shall submit sufficient information as provided below to allow City to determine if the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by City from anyone other than Contractor. c. Contractor shall make written application to City for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application shall comply with Section 01 25 00 and: 1) shall certify that the proposed substitute item will: a) perform adequately the functions and achieve the results called for by the general design; b) be similar in substance to that specified; c) be suited to the same use as that specified; and 2) will state: a) the extent, if any, to which the use of the proposed substitute item will prejudice Contractor's achievement of final completion on time; b) whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for other work on the Project) to adapt the design to the proposed substitute item; CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Do n ber2l,2012 UU7200-1 General Conditions Page 23 of 63 c) whether incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty; and 3) will identify: a) all variations of the proposed substitute item from that specified; b) available engineering, sales, maintenance, repair, and replacement services; and 4) shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and Damage Claims of other contractors affected by any resulting change. B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by City. Contractor shall submit sufficient information to allow City, in City's sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. Contractor shall make written application to City for review in the same manner as those provided in Paragraph 6.05.A.2. C. City's Evaluation: City will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 6.05.A and 6.05.13. City may require Contractor to furnish additional data about the proposed substitute. City will be the sole judge of acceptability. No "or-equal" or substitute will be ordered, installed or utilized until City's review is complete, which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal for an "or-equal."City will advise Contractor in writing of its determination. D. Special Guarantee: City may require Contractor to furnish at Contractor's expense a special performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall indemnify and hold harmless City and anyone directly or indirectly employed by them fr-oin and against any and all claims, damages, losses and expenses (inchiding attorneys fees) arising out of the use of substituted niaterials or equipment. E. City's Cost Reinibiurseinent: City will record City's costs in evaluating a substitute proposed or submitted by Contractor pursuant to Paragraphs 6.05.A.2 and 6.05.13. Whether or not City approves a substitute so proposed or submitted by Contractor, Contractor may be required to reimburse City for evaluating each such proposed substitute. Contractor may also be required to reimburse City for the charges for making changes in the Contract Documents (or in the provisions of any other direct contract with City) resulting from the acceptance of each proposed substitute. F. Contractor's Expense: Contractor shall provide all data in support of any proposed substitute or "or-equal"at Contractor's expense. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Do=T&T21,2412 0072UU-t General Conditions Page 24 of 63 G. City Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute shall be incorporated to the Contract by Change Order. H. Time Extensions: No additional time will be granted for substitutions. 6.06 Concerning Subcontractors, Suppliers, and Others A. Contractor shall perform with his own organization, work of a value not less than 35% of the value embraced on the Contract,unless otherwise approved by the City., B. Contractor shall not employ any Subcontractor, Supplier, or other individual or entity, whether initially or as a replacement, against whom City may have reasonable objection. Contractor shall not be required to employ any Subcontractor, Supplier, or other individual or entity to furnish or perform any of the Work against whom Contractor has reasonable objection (excluding those acceptable to City as indicated in Paragraph 6.06.C). C. The City may from time to time require the use of certain Subcontractors, Suppliers, or other individuals or entities on the project, and will provide such requirements in the Supplementary Conditions. D. Business Diversity Enterprise Ordinance Compliance; It is City policy to ensure the full and equitable participation by Minority and Small Business Enterprises (MBE)(SBE) in the procurement of goods and services on a contractual basis. If the Contract Documents provide for a MBE and/or SBE goal, Contractor is required to comply with the intent of the City's Business Diversity Ordinance(as amended)by the following: 1. Contractor shall, upon request by the City, provide complete and accurate information regarding actual work performed by a MBE and/or SBE on the Contract and payment therefor. 2. Contractor will not make additions, deletions, or substitutions of accepted MBE without written consent of the City. Any unjustified change or deletion shall be a material breach of Contract and may result in debarment in accordance with the procedures outlined in the Ordinance. 3. Contractor shall, upon request by City, allow an audit and/or examination of any books, records, or files in the possession of the Contractor that will substantiate the actual work performed by an MBE and/or SBE. Material misrepresentation of any nature may be grounds for termination of the Contract in accordance with Paragraph 15.02.A. Any such misrepresentation may be grounds for disqualification of Contractor to bid an future contracts with the City for a period of not less than three years. E. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just as Contractor is responsible for Contractor's own acts and omissions. Nothing in the Contract Documents: CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Du eniba21.2412 0072W-I Genera!Conditions Page 25 of 63 1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between City and any such Subcontractor, Supplier or other individual or entity; nor 2. shall create any obligation on the part of City to pay or to see to the payment of any moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and Regulations. F. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor. G. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any of the Work shall communicate with City through Contractor. H. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate agreement between Contractor and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of the Contract Documents for the benefit of City. 6.07 Wage Rates A. Ditty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of Chapter 2258, Texas Government Code (as amended), including the payment of not less than the rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in accordance with Chapter 2258. Such prevailing wage rates are included in these Contract Documents. B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage shall, upon demand made by the City, pay to the City $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated in these contract documents. This penalty shall be retained by the City to offset its administrative costs,pursuant to Texas Government Code 2258.023. C. Complaints of Violations and City Determination of Good Cause. On receipt of information, including a complaint by a worker, concerning an alleged violation of 2258.023, Texas Government Code, by a Contractor or Subcontractor, the City shall make an initial determination, before the 31st day after the date the City receives the information, as to whether good cause exists to believe that the violation occurred. The City shall notify in writing the Contractor or Subcontractor and any affected worker of its initial determination. Upon the City's determination that there is good cause to believe the Contractor or Subcontractor has violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and wages due under the prevailing wage rates, such amounts being subtracted from successive progress payments pending a final determination of the violation. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:D=rba21,20 i 2 007l00- General Conditions Page 26 of 63 D. Arbitration Required if violation Not Resolved An issue relating to an alleged violation of Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker does not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to Paragraph C above. If the persons required to arbitrate under this section do not agree on an arbitrator before the 11 th day after the date that arbitration is required, a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the arbitration. The decision and award of the arbitrator is final and binding on all parties and may be enforced in any court of competent jurisdiction. E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3) years following the date of acceptance of the work, maintain records that show (i) the name and occupation of each worker employed by the Contractor in the construction of the Work provided for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right to Audit, shall pertain to this inspection. F. Progress Payments. With each progress payment or payroll period, whichever is less, the Contractor shall submit an affidavit stating that the Contractor has complied with the requirements of Chapter 2258,Texas Government Code. G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at all times. H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its Subcontractors to comply with Paragraphs A through G above. 6.08 Patent Fees and Royalties A. Contractor shall pay all license fees and royalties and assume all costs incident to the use in the performance of the Work or the incorporation in the Work of any invention, design, process, product, or device which is the subject of patent rights or copyrights held by others. If a particular invention, design, process, product, or device is specified in the Contract Documents for use in the performance of the Work and if, to the actual knowledge of City, its use is subject to patent rights or copyrights calling for the payment of any license fee or royalty to others, the existence of such rights shall be disclosed by City in the Contract Documents. Failure of the City to disclose such information does not relieve the Contractor from its obligations to pay for the use of said fees or royalties to others. B. To the fiullest extent permitted by Laivs and Regulations, Contractor shall indemnify and hold hanmless City,from and against all claims, costs, losses, and damages (inchuding but not limited to all fees and charges of engineers, architects, attonueys, and other professionals and all court or arbitration or other-dispute resolution costs) arising out of or relating to any infringement ringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision;Dxmiber21,2012 UU T2 till-1 General Conditions Page 27 of 63 the incorporation in the Work of any invention, design,process,product, or device not specified in the Contract Documents. 6.09 Permits and Utilities A. Contractor obtained permits and licenses. Contractor shall obtain and pay for all construction permits and licenses except those provided for in the Supplementary Conditions or Contract Documents. City shall assist Contractor, when necessary, in obtaining such permits and licenses. Contractor shall pay all governmental charges and inspection fees necessary for the prosecution of the Work which are applicable at the time of opening of Bids, or, if there are no Bids, on the Effective Date of the Agreement, except for permits provided by the City as specified in 6.09.B. City shall pay all charges of utility owners for connections for providing permanent service to the Work. B. City obtained permits and licenses. City will obtain and pay for all permits and licenses as provided for in the Supplementary Conditions or Contract Documents. it will be the Contractor's responsibility to carry out the provisions of the permit. If the Contractor initiates changes to the Contract and the City approves the changes, the Contractor is responsible for obtaining clearances and coordinating with the appropriate regulatory agency. The City will not reimburse the Contractor for any cost associated with these requirements of any City acquired permit. The following are permits the City will obtain if required: 1. Texas Department of Transportation Permits 2. U.S. Army Corps of Engineers Permits 3. Texas Commission on Environmental Quality Permits 4. Railroad Company Permits C. Outstanding permits and licenses. The City anticipates acquisition of and/or access to permits and licenses. Any outstanding permits and licenses are anticipated to be acquired in accordance with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by the Contractor in accordance with the Contract Documents must consider any outstanding permits and licenses. 6.10 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor's compliance with any Laws or Regulations. B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Da=nber2l,2012 U072W-1 General Conditions Page 28 or63 court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor's responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor's obligations under Paragraph 3.02. C. Changes in Laws or Regulations not known at the time of opening of Bids having an effect on the cost or time of performance of the Work may be the subject of an adjustment in Contract Price or Contract Time. 6.11 Taxes A. On a contract awarded by the City, an organization which qualifies for exemption pursuant to Texas Tax Code, Subchapter H, Sections 151.301-335 (as amended), the Contractor may purchase, rent or lease all materials, supplies and equipment used or consumed in the performance of this contract by issuing to his supplier an exemption certificate in lieu of the tax, said exemption certificate to comply with State Comptroller's Ruling .007. Any such exemption certificate issued to the Contractor in lieu of the tax shall be subject to and shall comply with the provision of State Comptroller's Ruling .011, and any other applicable rulings pertaining to the Texas Tax Code, Subchapter H. B. Texas Tax permits and information may be obtained from: 1. Comptroller of Public Accounts Sales Tax Division Capitol Station Austin,TX 78711;or 2. http://w,,vw.window,state.tx.us/taxinfa/taxform 93-forms.html 6.12 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas: 1. Contractor shall confine construction equipment, the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work. 2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is carrying on operations in a portion of a street, right-of-way, or easement greater than is necessary for proper execution of the Work, the City may require the Contractor to finish the section on which operations are in progress before work is commenced on any additional area of the Site. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS RuMsiont D=n dxx2l,2012 GU 72 00-I General Conditions Page 29 of 63 3. Should any Damage Claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim. 4. Pursuant to Paragraph 6.21, Contractor shall indemnify and hold harmless City,fr-onn and against all claims, costs, losses, and damages arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against City. B. Removal of Debris During Pei forniance of the Won*: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations. C. Site Maintenance Cleaning. 24 hours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the City, if the Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice (by letter or electronic communication), and the costs of such direct action, plus 25 % of such costs, shall be deducted from the monies due or to become due to the Contractor. D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and the Work and make it ready for utilization by City or adjacent property owner. At the completion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition or better all property disturbed by the Work. E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 6.13 Record Documents A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change Orders, Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon completion of the Work, these record documents, any operation and maintenance manuals, and Submittals will be delivered to City prior to Final Inspection. Contractor shall include accurate locations for buried and imbedded items. 6.14 Safety and Protection A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Such responsibility does not relieve Subcontractors of their responsibility for the safety of persons or property in the performance of their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision;Decmiber21,2012 OU72UU-1 General Conditions Page 30 of 63 take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal,relocation,or replacement in the course of construction. B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal,relocation,and replacement of their property. C. Contractor shall comply with the applicable requirements of City's safety programs, if any. D. Contractor shall inform City of the specific requirements of Contractor's safety program, if any, with which City's employees and representatives must comply while at the Site. E. All damage, injury, or loss to any property referred to in Paragraph 6.14.A.2 or 6.14.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor. F. Contractor's duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and City has accepted the Work. 6.15 Safety RepJ-esentative Contractor shall inform City in writing of Contractor's designated safety representative at the Site. 6.16 Hazai-d Communication PJ'OgJ'ains Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers in accordance with Laws or Regulations. 6.17 Erne,gencies andloi-Rectification A. In emergencies affecting the safety or protection of persons or the Work or property at the Site or adjacent thereto, Contractor is obligated to act to prevent threatened damage, injury, or loss. Contractor shall give City prompt written notice if Contractor believes that any significant CnY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deow bex2l,2012 00 72 00-1 General Conditions Page 31 of 63 changes in the Work or variations from the Contract Documents have been caused thereby or are required as a result thereof. If City determines that a change in the Contract Documents is required because of the action taken by Contractor in response to such an emergency, a Change Order may be issued. B. Should the Contractor fail to respond to a request from the City to rectify any discrepancies, omissions, or correction necessary to conform with the requirements of the Contract Documents, the City shall give the Contractor written notice that such work or changes are to be performed. The written,notice shall direct attention to the discrepant condition and request the Contractor to take remedial action to correct the condition. In the event the Contractor does not take positive steps to fulfill this written request, or does not show just cause for not taking the proper action, within 24 hours, the City may take such remedial action with City forces or by contract. The City shall deduct an amount equal to the entire costs for such remedial action, plus 25%, from any funds due or become due the Contractor on the Project. 6.18 Submittals A. Contractor shall submit required Submittals to City for review and acceptance in accordance with the accepted Schedule of Submittals(as required by Paragraph 2.07). Each submittal will be identified as City may require. 1. Submit number of copies specified in the General Requirements. 2. Data shown on the Submittals will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show City the services, materials, and equipment Contractor proposes to provide and to enable City to review the information for the limited purposes required by Paragraph 6.18.C. 3. Submittals submitted as herein provided by Contractor and reviewed by City for conformance with the design concept shall be executed in conformity with the Contract Documents unless otherwise required by City. 4. When Submittals are submitted for the purpose of showing the installation in greater detail, their review shall not excuse Contractor from requirements shown on the Drawings and Specifications. 5. For-Information-Only submittals upon which the City is not expected to conduct review or take responsive action may be so identified in the Contract Documents. 6. Submit required number of Samples specified in the Specifications. 7. Clearly identify each Sample as to material, Supplier,pertinent data such as catalog numbers, the use for which intended and other data as City may require to enable City to review the submittal for the limited purposes required by Paragraph 6.18.C. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision;Decanber21.2012 0072W-I General Conditions Page 32 or 63 B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to City's review and acceptance of the pertinent submittal will be at the sole expense and responsibility of Contractor. C. City's Review: 1. City will provide timely review of required Submittals in accordance with the Schedule of Submittals acceptable to City. City's review and acceptance will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. 2. City's review and acceptance will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and acceptance of a separate item as such will not indicate approval of the assembly in which the item functions. 3. City's review and acceptance shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Section 01 33 00 and City has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Submittal. City's review and acceptance shall not relieve Contractor from responsibility for complying with the requirements of the Contract Documents. 6.19 Continuing the Work Except as otherwise provided, Contractor shall carry on the Work and adhere to the Project Schedule during all disputes or disagreements with City. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as City and Contractor may otherwise agree in writing. 6.20 Contractor's General Warranty and Guarantee A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract Documents and will not be defective. City and its officers, directors, members, partners, employees, agents, consultants, and subcontractors shall be entitled to rely on representation of Contractor's warranty and guarantee. B. Contractor's warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse, modification, or improper maintenance or operation by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or CITY OF FORT WORTH STANDARD CONSTRUCI`!ON SPECIFCATION DOCUMENTS Revision:Dwern=2l,2012 00 72 00-1 General Conditions Page 33 of 63 2. normal wear and tear under normal usage. C. Contractor's obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor's obligation to perform the Work in accordance with the Contract Documents: I. observations by City; 2. recommendation or payment by City of any progress or final payment; 3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by City; 4. use or occupancy of the Work or any part thereof by City; 5. any review and acceptance of Submittal by City; 6. any inspection, test,or approval by others; or 7. any correction of defective Work by City. D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other work or property resulting therefrom which shall appear within a period of two (2) years from the date of Final Acceptance of the Work unless a longer period is specified and shall furnish a good and sufficient maintenance bond, complying with the requirements of Article 5.02.13. The City will give notice of observed defects with reasonable promptness. 6.21 Indemnification A. Contractor covenants and agrees. to indemnify, hold harmless and defend, at its own expense, the City, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licenses or invitees under this Contract. THIS INDEMNIFICATION_PROVISION IS SPECIFICAL.L.Y INTENDED TO OPERATE AND BE EFFECTIVE EVEN-IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED IN WHOLE OR IN PART, BY ANY AC]:. OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the City in defending against such claims and causes of actions. B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the City, arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees under this Contract. THIS INDF, NMEICATIQN PROVISION IS CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dxe of a21,2012 UU7'2OU-1 General Conditions Page 34 of 63 SPF.CISCALLY INTEMED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART. BY ANY ACT. OMISSION OR NEGLIGENCE OF THE CITY. 6.22 Delegation of Professional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such services are required to carry out Contractor's responsibilities for construction means, methods, techniques, sequences and procedures. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, City will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, and Submittals prepared by such professional. Submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional's written approval when submitted to City. C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided City has specified to Contractor performance and design criteria that such services must satisfy. D. Pursuant to this Paragraph 6.22, City's review and acceptance of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. City's review and acceptance of Submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 6.18.C. 6.23 Right to Audit A. The Contractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents,papers, and records of the Contractor involving transactions relating to this Contract. Contractor agrees that the City shall have access during Regular Working Hours to all necessary Contractor facilities and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Contractor reasonable advance notice of intended audits. B. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the subcontractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of such Subcontractor, involving transactions to the subcontract, and further, that City shall have access during Regular Working Hours to all cn-Y OP FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deeenber21,2012 00 72f 00-t Gencral Conditions Page 35 of 63 Subcontractor facilities, and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Subcontractor reasonable advance notice of intended audits. C. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published in the Texas Administrative Code in effect as of the time copying is performed. 6.24 Nondiscrimination A. The City is responsible for operating Public Transportation Programs and implementing transit- related projects, which are funded in part with Federal financial assistance awarded by the U.S. Department of Transportation and the Federal Transit Administration (FTA), without discriminating against any person in the United States on the basis of race, color, or national origin. B. Title VI, Civil Rights Act of 1964 as amended. Contractor shall comply with the requirements of the Act and the Regulations as further defined in the Supplementary Conditions for any project receiving Federal assistance. ARTICLE 7—OTHER WORK AT THE SITE 7.01 Related Woi k at Site A. City may perform other work related to the Project at the Site with City's employees, or other City contractors, or through other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Contract Documents, then written notice thereof will be given to Contractor prior to starting any such other work; and B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner, and City, if City is performing other work with City's employees or other City contractors, proper and safe access to the Site, provide a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering such work; provided, however, that Contractor may cut or alter others' work with the written consent of City and the others whose work will be affected. C. If the proper execution or results of any part of Contractor's Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor's Work. Contractor's failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor's Work except for latent defects in the work provided by others. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS RuMsion:Dowrbir21,2012 0072W-I General Conditions Page 36 of 63 7.02 Cow-dination A. If City intends to contract with others for the performance of other work on the Project at the Site, the following will be set forth in Supplementary Conditions: 1. the individual or entity who will have authority and responsibility for coordination of the activities among the various contractors will be identified; 2. the specific matters to be covered by such authority and responsibility will be itemized; and 3. the extent of such authority and responsibilities will be provided. B. Unless otherwise provided in the Supplementary Conditions, City shall have authority for such coordination. ARTICLE 8—CITY'S RESPONSIBILITIES 8.01 Communications to Contmelot' Except as otherwise provided in the Supplementary Conditions, City shall issue all communications to Contractor. 8.02 Fin-nish Data City shall timely furnish the data required under the Contract Documents. 8.03 Pay When Due City shall make payments to Contractor in accordance with Article 14. 8.04 Lands and Easements;Repons and Tests City's duties with respect to providing lands and easements and providing engineering surveys to establish reference points are set forth in Paragraphs 4.01 and 4.05. Paragraph 4.02 refers to City's identifying and making available to Contractor copies of reports of explorations and tests of subsurface conditions and drawings of physical conditions relating to existing surface or subsurface structures at or contiguous to the Site that have been utilized by City in preparing the Contract Documents. 8.05 Change Otzleis City shall execute Change Orders in accordance with Paragraph 10.03. 8.06 Inspection's, Tests, and Approvals City's responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph 13.03. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dwunba2l,2012 00 72 00-1 General Conditions Page 37 of 63 8.07 Limitations on City's Responsibilities A. The City shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor's means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. City will not be responsible for Contractor's failure to perform the Work in accordance with the Contract Documents. B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 6.14. 8.08 Undisclosed Hazardous Environmental Condition City's responsibility with respect to an undisclosed Hazardous Environmental Condition is set forth in Paragraph 4.06, 8.09 Compliance with Safety Program While at the Site, City's employees and representatives shall comply with the specific applicable requirements of Contractor's safety programs of which City has been informed pursuant to Paragraph 6.14. ARTICLE 9—CITY'S OBSERVATION STATUS DURING CONSTRUCTION 9.01 City's Project Representative City will provide one or more Project Representative(s) during the construction period. The duties and responsibilities and the limitations of authority of City's representative during construction are set forth in the Contract Documents. The Project Representative(s) will be as provided in the Supplementary Conditions. 9.02 Visits to Site A. City's Project Representative will make visits to the Site at intervals appropriate to the various stages of construction as City deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor's executed Work. Based on information obtained during such visits and observations, City's Project Representative will determine, in general, if the Work is proceeding in accordance with the Contract Documents. City's Project Representative will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. City's Project Representative's efforts will be directed toward providing City a greater degree of confidence that the completed Work will conform generally to the Contract Documents. B. City's Project Representative's visits and observations are subject to all the limitations on authority and responsibility in the Contract Documents including those set forth in Paragraph 8.07. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision;Deo=ber2l,2012 UO72W-I General Conditions Page 38 of 63 9.03 Authorized Variations in Work City's Project Representative may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on City and also on Contractor,who shall perform the Work involved promptly. 9.04 Rejecting Defective Work City will have authority to reject Work which City's Project Representative believes to be defective, or will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. City will have authority to conduct special inspection or testing of the Work as provided in Article 13, whether or not the Work is fabricated, installed, or completed. 9.05 Determinations foi• Work Performed Contractor will determine the actual quantities and classifications of Work performed. City's Project Representative will review with Contractor the preliminary determinations on such matters before rendering a written recommendation. City's written decision will be final (except as modified to reflect changed factual conditions or more accurate data). f 9.06 Decisions ort Requirements ofContract Documents arrd Acceptability of Work A. City will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder. B. City will render a written decision on any issue referred. C. City's written decision on the issue referred will be final and binding on the Contractor, subject to the provisions of Paragraph 10.06. ARTICLE 10—CHANGES IN THE WORK; CLAIMS; EXTRA WORK 10.01 Autlrorized Clianges in the Work A. Without invalidating the Contract and without notice to any surety, City may, at any time or from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). Extra Work shall be memorialized by a Change Order which may or may not precede an order of Extra work. B. For minor changes of Work not requiring changes to Contract Time or Contract Price, a Field Order may be issued by the City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision,Dwanbx2l,2012 00720U-I General Conditions Page 39 of63 10.02 Unauthorized Changes in the Woi k Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Time with respect to any work performed that is not required by the Contract Documents as amended, modified, or supplemented as provided in Paragraph 3.04, except in the case of an emergency as provided in Paragraph 6.17. 10.03 Execution of Change Orders A. City and Contractor shall execute appropriate Change Orders covering: 1. changes in the Work which are: (i) ordered by City pursuant to Paragraph 10.01.A, (ii) required because of acceptance of defective Work under Paragraph 13.08 or City's correction of defective Work under Paragraph 13.09,or(iii)agreed to by the parties; 2. changes in the Contract Price or Contract Time which are agreed to by the parties, including any undisputed sum or amount of time for Work actually performed. 10.04 Exti-a Work A. Should a difference arise as to what does or does not constitute Extra Work, or as to the payment thereof, and the City insists upon its performance, the Contractor shall proceed with the work after making written request for written orders and shall keep accurate account of the actual reasonable cost thereof. Contract Claims regarding Extra Work shall be made pursuant to Paragraph 10.06. B. The Contractor shall furnish the City such installation records of all deviations from the original Contract Documents as may be necessary to enable the City to prepare for permanent record a corrected set of plans showing the actual installation. C. The compensation agreed upon for Extra Work whether or not initiated by a Change Order shall be a full, complete and final payment for all costs Contractor incurs as a result or relating to the change or Extra Work, whether said costs are known, unknown, foreseen or unforeseen at that time, including without limitation, any costs for delay, extended overhead, ripple or impact cost, or any other effect on changed or unchanged work as a result of the change or Extra Work. 10.05 Notification to Surety If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time), the giving of any such notice will be Contractor's responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any such change. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dr2l,20l2 W71W-I General Conditions Pate 40 of 63 10.06 Conti-act Claims Process A. City's Decision Required: All Contract Claims, except those waived pursuant to Paragraph 14.09, shall be referred to the City for decision. A decision by City shall be required as a condition precedent to any exercise by Contractor of any rights or remedies he may otherwise have under the Contract Documents or by Laws and Regulations in respect of such Contract Claims. B. Notice: 1. Written notice stating the general nature of each Contract Claim shall be delivered by the Contractor to City no later than 15 days after the start of the event giving.rise thereto. The responsibility to substantiate a Contract Claim shall rest with the party making the Contract Claim. 2. Notice of the amount or extent of the Contract Claim, with supporting data shall be delivered to the City on or before 45 days from the start of the event giving rise thereto (unless the City allows additional time for Contractor to submit additional or more accurate data in support of such Contract Claim). 3. A Contract Claim for an adjustment in Contract Price shall be prepared in accordance with the provisions of Paragraph 12.01. 4. A Contract Claim for an adjustment in Contract Time shall be prepared in accordance with the provisions of Paragraph 12.02. 5. Each Contract Claim shall be accompanied by Contractor's written statement that the adjustment claimed is the entire adjustment to which the Contractor believes it is entitled as a result of said event. 6. The City shall submit any response to the Contractor within 30 days after receipt of the claimant's last submittal (unless Contract allows additional time). C. City's Action: City will review each Contract Claim and, within 30 days after receipt of the last submittal of the Contractor, if any, take one of the following actions in writing: 1. deny the Contract Claim in whole or in part; 2. approve the Contract Claim; or 3. notify the Contractor that the City is unable to resolve the Contract Claim if, in the City's sole discretion, it would be inappropriate for the City to do so. For purposes of further resolution of the Contract Claim, such notice shall be deemed a denial. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dxarber21,2012 00 72 OU-I General Conditions Page 41 of 63 D. City's written action under Paragraph 10.06.0 will be final and binding, unless City or Contractor invoke the dispute resolution procedure set forth in Article 16 within 30 days of such action or denial. E. No Contract Claim for an adjustment in Contract Price or Contract Time will be valid if not submitted in accordance with this Paragraph 10.06. ARTICLE I1 —COST OF.THE WORK;ALLOWANCES; UNIT PRICE WORK; PLANS QUANTITY MEASUREMENT 11.01 Cost of the Work— A. Costs Included. The term Cost of the Work means the sum of all costs, except those excluded in Paragraph 11.01.13, necessarily incurred and paid by Contractor in the proper performance of the Work. When the value of any Work covered by a Change Order, the costs to be reimbursed to Contractor will be only those additional or incremental costs required because of the change in the Work. Such costs shall not include any of the costs itemized in Paragraph 11.01.13, and shall include but not be limited to the following items: 1. Payroll costs for employees in the direct employ of Contractor in the performance of the Work under schedules of job classifications agreed upon by City and Contractor. Such employees shall include, without limitation, superintendents, foremen, and other personnel employed full time on the Work. Payroll costs for employees not employed full time on the Work shall be apportioned on the basis of their time spent on the Work. Payroll costs shall include•, a. salaries with a 55%markup, or b. salaries and wages plus the cost of fringe benefits, which shall include social security contributions, unemployment, excise, and payroll taxes, workers' compensation, health and retirement benefits, bonuses, sick leave, vacation and holiday pay applicable thereto. The expenses of performing Work outside of Regular Working Hours, Weekend Working Hours, or legal holidays, shall be included in the above to the extent authorized by City. 2. Cost of all materials and equipment furnished and incorporated in the Work, including costs of transportation and storage thereof, and Suppliers' field services required in connection therewith. . Rentals of all construction equipment and machinery, and the parts thereof whether rented from Contractor or others in accordance with rental agreements approved by City, and the costs of transportation, loading, unloading, assembly, dismantling, and removal thereof. All such costs shall be in accordance with the terms of said rental agreements. The rental of any such equipment, machinery, or parts shall cease when the use thereof is no longer necessary for the Work. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Ikt=nbtT21,2012 00 72 00-1 General Conditions Page 42 of 63 4. Payments made by Contractor to Subcontractors for Work performed by Subcontractors. If required by City, Contractor shall obtain competitive bids from subcontractors acceptable to City and Contractor and shall deliver such bids to City, who will then determine, which bids, if any, will be acceptable. If any subcontract provides that the Subcontractor is to be paid on the basis of Cost of the Work plus a fee, the Subcontractor's Cost of the Work and fee shall be determined in the same manner as Contractor's Cost of the Work and fee as provided in this Paragraph 11.01. 5. Costs of special consultants (including but not limited to engineers, architects, testing laboratories, surveyors, attorneys, and accountants) employed for services specifically related to the Work. 6. Supplemental costs including the following: a. The proportion of necessary transportation, travel, and subsistence expenses of Contractor's employees incurred in discharge of duties connected with the Work. b. Cost, including transportation and maintenance, of all materials, supplies, equipment, machinery, appliances, office, and temporary facilities at the Site, and hand tools not owned by the workers, which are consumed in the performance of the Work, and cost, less market value, of such items used but not consumed which remain the property of Contractor. c. Sales, consumer, use, and other similar taxes related to the Work, and for which Contractor is liable not covered under Paragraph 6.11, as imposed by Laws and Regulations. d. Deposits lost for causes other than negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, and royalty payments and fees for permits and licenses. e. Losses and damages (and related expenses) caused by damage to the Work, not compensated by insurance or otherwise, sustained by Contractor in connection with the performance of the Work, provided such losses and damages have resulted from causes other than the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable. Such losses shall include settlements made with the written consent and approval of City. No such losses, damages, and expenses shall be included in the Cost of the Work for the purpose of determining Contractor's fee. £ The cost of utilities, fuel, and sanitary facilities at the Site. g. Minor expenses such as telegrams, long distance telephone calls, telephone and communication services at the Site, express and courier services, and similar petty cash items in connection with the Work. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:DL=mb r21,20I2 uu1200-1 General Conditions Page 43 of 63 h. The costs of premiums for all bonds and insurance Contractor is required by the Contract Documents to purchase and maintain. B. Costs Excluded:The term Cost of the Work shall not include any of the following items: 1. Payroll costs and other compensation of Contractor's officers, executives, principals (of partnerships and sole proprietorships), general managers, safety managers, engineers, architects, estimators, attorneys, auditors, accountants, purchasing and contracting agents, expediters, timekeepers, clerks, and other personnel employed by Contractor, whether at the Site or in Contractor's principal or branch office for general administration of the Work and not specifically included in the agreed upon schedule of job classifications referred to in Paragraph 11.01.A.1 or specifically covered by Paragraph 11.0I.A.4, all of which are to be considered administrative costs covered by the Contractor's fee. 2. Expenses of Contractor's principal and branch offices other than Contractor's office at the Site. 3. Any part of Contractor's capital expenses, including interest on Contractor's capital employed for the Work and charges against Contractor for delinquent payments. 4. Costs due to the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable, including but not limited to, the correction of defective Work, disposal of materials or equipment wrongly supplied,and making good any damage to property. S. Other overhead or general expense costs of any kind. C. Contractors Fee: When all the Work is performed on the basis of cost-plus, Contractor's fee shall be determined as set forth in the Agreement. When the value of any Work covered by a Change Order for an adjustment in Contract Price is determined on the basis of Cost of the Work, Contractor's fee shall be determined as set forth in Paragraph 12.01.C. D. Documentation: Whenever the Cost of the Work for any purpose is to be determined pursuant to Paragraphs 11.01.A and 11.01.13, Contractor will establish and maintain records thereof in accordance with generally accepted accounting practices and submit in a form acceptable to City an itemized cost breakdown together with supporting data. 11.02 Allowances A. Specified Allowance: It is understood that Contractor has included in the Contract Price all allowances so named in the Contract Documents and shall cause the Work so covered to be performed for such sums and by such persons or entities as may be acceptable to City. B. Pre-bid Allowances: 1. Contractor agrees that: CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dxentber2l,2012 UU72UU-1 General Conditions Page 44 of 63 a. the pre-bid allowances include the cost to Contractor of materials and equipment required by the allowances to be delivered at the Site, and all applicable taxes; and b. Contractor's costs for unloading and handling on the Site, labor, installation, overhead, profit,and other expenses contemplated for the pre-bid allowances have been included in the allowances, and no demand for additional payment on account of any of the foregoing will be valid. C. Contingency Allowance: Contractor agrees that a contingency allowance, if any, is for the sole use of City. D. Prior to final payment, an appropriate Change Order will be issued to reflect actual amounts due Contractor on account of Work covered by allowances, and the Contract Price shall be correspondingly adjusted. 11.03 Unit Price Work A. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to the sum of the unit price for each separately identified item of Unit Price Work times the estimated quantity of each item as indicated in the Agreement. B. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the purpose of comparison of Bids and determining an initial Contract Price. Determinations of the actual quantities and classifications of Unit Price Work performed by Contractor will be made by City subject to the provisions of Paragraph 9.05. C. Each unit price will be deemed to include an amount considered by Contractor to be adequate to cover Contractor's overhead and profit for each separately identified item. Work described in the Contract Documents, or reasonably inferred as required for a functionally complete installation, but not identified in the listing of unit price items shall be considered incidental to unit price work listed and the cost of incidental work included as part of the unit price. D. City may make an adjustment in the Contract Price in accordance with Paragraph 12.01 if. 1, the quantity of any item of Unit Price Work performed by Contractor differs materially and significantly from the estimated quantity of such item indicated in the Agreement; and 2. there is no corresponding adjustment with respect to any other item of Work. E. Increased or Decreased Quantities: The City reserves the right to order Extra Work in accordance with Paragraph 10.01. 1. If the changes in quantities or the alterations do not significantly change the character of work under the Contract Documents, the altered work will be paid for at the Contract unit price. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:De =btr2l,20)2 U07200=1 General Conditions Page 45 of 63 2. If the changes in quantities or alterations significantly change the character of work, the Contract will be amended by a Change Order. 3. If no unit prices exist, this will be considered Extra Work and the Contract will be amended by a Change Order in accordance with Article 12. 4. A significant change in the character of work occurs when: a. the character of work for any Item as altered differs materially in kind or nature from that in the Contract or b. a Major Item of work varies by more than 25%from the original Contract quantity. 5. When the quantity of work to be done under any Major Item of the Contract is more than 125% of the original quantity stated in the Contract, then either party to the Contract may request an adjustment to the unit price on the portion of the work that is above 125%. 6. When the quantity of work to be done under any Major Item of the Contract is less than 75% of the original quantity stated in the Contract, then either party to the Contract may request an adjustment to the unit price. 11.04 Plans Quantity Measurenient A. Plans quantities may or may not represent the exact quantity of work performed or material moved, handled, or placed during the execution of the Contract. The estimated bid quantities are designated as final payment quantities, unless revised by the governing Section or this Article. B. If the quantity measured as outlined under"Price and Payment Procedures" varies by more than 25% (or as stipulated under "Price and Payment Procedures" for specific Items) from the total estimated quantity for an individual Item originally shown in the Contract Documents, an adjustment may be made to the quantity of authorized work done for payment purposes. The party to the Contract requesting the adjustment will provide field measurements and calculations showing the final quantity for which payment will be made. Payment for revised quantity will be made at the unit price bid for that Item, except as provided for in Article 10. C. When quantities are revised by a change in design approved by the City, by Change Order, or to correct an error, or to correct an error on the plans, the plans quantity will be increased or decreased by the amount involved in the change, and the 25% variance will apply to the new plans quantity. O. If the total Contract quantity multiplied by the unit price bid for an individual Item is less than $250 and the Item is not originally a plans quantity Item, then the Item may be paid as a plans quantity Item if the City and Contractor agree in writing to fix the final quantity as a plans quantity. cny OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:De canber2l,2012 till 72 W-I General Conditions Page 46 of 63 E. For callout work or non-site specific Contracts, the plans quantity measurement requirements are not applicable. ARTICLE 12--CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME 12.01 Change of Conti-act Price A. The Contract Price may only be changed by a Change Order. B. The value of any Work covered by a Change Order will be determined as follows: 1. where the Work involved is covered by unit prices contained in the Contract Documents, by application of such unit prices to the quantities of the items involved (subject to the provisions of Paragraph 11.03); or 2. where the Work involved is not covered by unit prices contained in the Contract Documents, by a mutually agreed lump sum or unit price (which may include an allowance for overhead and profit not necessarily in accordance with Paragraph 12.01.C.2), and shall include the cost of any secondary impacts that are foreseeable at the time of pricing the cost of Extra Work; or 3. where the Work involved is not covered by unit prices contained in the Contract Documents and agreement to a lump sum or unit price is not reached under Paragraph 12.01.13.2, on the basis of the Cost of the Work (determined as provided in Paragraph 11.01) plus a Contractor's fee for overhead and profit(determined as provided in Paragraph 12.01.C). C. Contractor's Fee: The Contractor's additional fee for overhead and profit shall be determined as follows: 1. a mutually acceptable fixed fee; or 2. if a fixed fee is not agreed upon, then a fee based on the following percentages of the various portions of the Cost of the Work: a. for costs incurred under Paragraphs 11.01.A.1, 11.0l.A.2, and 11.01.A.3, the Contractor's additional fee shall be 15 percent except for: 1) rental fees for Contractor's own equipment using standard rental rates; 2) bonds and insurance; b. for costs incurred under Paragraph 11.01.A.4 and 11.01.A.5, the Contractor's fee shall be five percent (5%); 1) where one or more tiers of subcontracts are on the basis of Cost of the Work plus a fee and no fixed fee is agreed upon, the intent of Paragraphs 12.0l.C.2.a and 12.01.C.2.b is that the Subcontractor who actually performs the Work, at whatever CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dc mib r2l,2412 00 72 00-1 General Conditions Page 47 of 63 tier, will be paid a fee of 15 percent of the costs incurred by such Subcontractor under Paragraphs 11.0l.A.1 and 11.01.A.2 and that any higher tier Subcontractor and Contractor will each be paid a fee of five percent (5%) of the amount paid to the next lower tier Subcontractor, however in no case shall the cumulative total of fees paid be in excess of 25%; c. no fee shall be payable on the basis of costs itemized under Paragraphs 11.0l.A.6, and 11.01.13; d. the amount of credit to be allowed by Contractor to City for any change which results in a net decrease in cost will be the amount of the actual net decrease in cost plus a deduction in Contractor's fee by an amount equal to five percent (5%) of such net decrease. 12.02 Change of Conti-act Time A. The Contract Time may only be changed by a Change Order. B. No extension of the Contract Time will be allowed for Extra Work or for claimed delay unless the Extra Work contemplated or claimed delay is shown to be on the critical path of the Project Schedule or Contractor can show by Critical Path Method analysis how the Extra Work or claimed delay adversely affects the critical path. 12.03 Delays A. Where Contractor is reasonably delayed in the performance or completion of any part of the Work within the Contract Time due to delay beyond the control of Contractor, the Contract Time may be extended in an amount equal to the time lost due to such delay if a Contract Claim is made therefor. Delays beyond the control of Contractor shall include, but not be limited to, acts or neglect by City, acts or neglect of utility owners or other contractors performing other work as contemplated by Article 7, fires, floods, epidemics, abnormal weather conditions, or acts of God. Such an adjustment shall be Contractor's sole and exclusive remedy for the delays described in this Paragraph. B. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. C. Contractor shall not be entitled to an adjustment in Contract Price or Contract Time for delays within the control of Contractor. Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of Contractor. D. The Contractor shall receive no compensation for delays or hindrances to the Work, except when direct and unavoidable extra cost to the Contractor is caused by the failure of the City to provide information or material,if any, which is to be furnished by the City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATiON DOCUMENTS Revision:Dcxember2l,2012 OU71W-1 General Conditions Page 48 of 63 ARTICLE 13--TESTS AND INSPECTIONS; CORRECTION,REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 13.01 Notice of Defects Notice of all defective Work of which City has actual knowledge will be given to Contractor. Defective Work may be rejected, corrected,or accepted as provided in this Article 13. 13.02 Access to Work City, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor's safety procedures and programs so that they may comply therewith as applicable. 13.03 Tests and Inspections A. Contractor shall give City timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any of the Work (or part thereof} to be inspected, tested, or approved, Contractor shall assume full responsibility for arranging and obtaining such independent inspections, tests, retests or approvals, pay all costs in connection therewith, and furnish City the required certificates of inspection or approval; excepting, however, those fees specifically identified in the Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR) inspections, which shall be paid as described in the Supplementary Conditions. C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, re-tests, or approvals required for City's acceptance of materials or equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor's purchase thereof for incorporation in the Work. Such inspections, tests, re-tests, or approvals shall be performed by organizations acceptable to City. D. City may arrange for the services of an independent testing laboratory ("Testing Lab") to perform any inspections or tests ("Testing") for any part of the Work, as determined solely by City. 1. City will coordinate such Testing to the extent possible,with Contractor; 2. Should any Testing under this Section 13.03 D result in a "fail", "did not pass" or other similar negative result, the Contractor shall be responsible for paying for any and all retests. Contractor's cancellation without cause of City initiated Testing shall be deemed a negative result and require a retest. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:D=nbss21,Za E) UU 72 UU-1 General Conditions Page 49 orb3 3. Any amounts owed for any retest under this Section 13.03 D shall be paid directly to the Testing Lab by Contractor. City will forward all invoices for retests to Contractor. 4. If Contractor fails to pay the Testing Lab, City will not issue Final Payment until the Testing Lab is paid. E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of City, Contractor shall, if requested by City, uncover such Work for observation. F. Uncovering Work as provided in Paragraph 13.03.E shall be at Contractor's expense. G. Contractor shall have the right to make a Contract Claim regarding any retest or invoice issued under Section 13.03 D. 13.04 Uncovering Work A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it must, if requested by City, be uncovered for City's observation and replaced at Contractor's expense. B. If City considers it necessary or advisable that covered Work be observed by City or inspected or tested by others, Contractor, at City's request, shall uncover, expose, or otherwise make available for observation, inspection, or testing as City may require, that portion of the Work in question, furnishing all necessary labor, material, and equipment. 1. If it is found that the uncovered Work is defective, Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such uncovering, exposure, observation, inspection, and testing, and of satisfactory replacement or reconstruction (including but not limited to all costs of repair or replacement of work of others); or City shall be entitled to accept defective Work in accordance with Paragraph 13.08 in which case Contractor shall still be responsible for all costs associated with exposing, observing,and testing the defective Work. 2. If the uncovered Work is not found to be defective, Contractor shall be allowed an increase in the Contract Price or an extension of the Contract Time, or both, directly attributable to such uncovering, exposure,observation, inspection, testing, replacement, and reconstruction. 13.05 City May Stop the Wor k If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of City to stop the Work shall not give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision,Dxm ixr2l,2U12 007LW-1 General Conditions Page 50 of 63 Subcontractor, any Supplier, any other individual or entity,or any surety for, or employee or agent of any of them. 13.06 Correction ol•Removal of Defective Woi k A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has been rejected by City, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, additional testing, losses, and-damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others). Failure to require the removal of any defective Work shall not constitute acceptance of such Work. B. When correcting defective Work under the terms of this Paragraph 13.06 or Paragraph 13.07, Contractor shall take no action that would void or otherwise impair City's special warranty and guarantee, if any,on said Work. 13.07 Correction Period A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the terns of any applicable special guarantee required by the Contract Documents), any Work is found to be defective, or if the repair of any damages to the Iand or areas made available for Contractor's use by City or permitted by Laws and Regulations as contemplated in Paragraph 6.IO.A is found to be defective, Contractor shall promptly, without cost to City and in accordance with City's written instructions: 1, repair such defective land or areas; or 2, correct such defective Work; or 3. if the defective Work has been rejected by City, remove it from the Project and replace it with Work that is not defective, and 4, satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of City's written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision;Dwernber2l,2012 007200-1 General Conditions Page51 of'63 C. In special circumstances where a particular item of equipment is placed in continuous service before Final Acceptance of all the Work, the correction period for that item may start to run from an earlier date if so provided in the Contract Documents. D. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 13.07, the correction period hereunder with respect to such Work may be required to be extended for an additional period of one year after the end of the initial correction period. City shall provide 30 days written notice to Contractor should such additional warranty coverage be required. Contractor may dispute this requirement by filing a Contract Claim,pursuant to Paragraph 10.06. E. Contractor's obligations under this Paragraph 13.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 13.07 shall not be construed as a substitute for, or a waiver of, the provisions of any applicable statute of limitation or repose. 13.08 Acceptance of Defective Woi k If, instead of requiring correction or removal and replacement of defective Work, City prefers to accept it, City may do so. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) attributable to City's evaluation of and determination to accept such defective Work and for the diminished value of the Work to the extent not otherwise paid by Contractor. If any such acceptance occurs prior to Final Acceptance, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and City shall be entitled to an appropriate decrease in the Contract Price, reflecting the diminished value of Work so accepted. 13.09 City May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from City to correct defective Work, or to remove and replace rejected Work as required by City in accordance with Paragraph 13,06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven(7) days written notice to Contractor, correct, or remedy any such deficiency. B. In exercising the rights and remedies under this Paragraph 13.09, City shall proceed expeditiously. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor's services related thereto, and incorporate in the Work all materials and equipment incorporated in the Work, stored at the Site or for which City has paid Contractor but which are stored elsewhere. Contractor shall allow City, City's representatives, agents, consultants, employees, and City's other contractors, access to the Site to enable City to exercise the rights and remedies under this Paragraph. C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deom ba2f,2012 UG 72 W.I General Conditions Page 52 of 63 costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph 13.09 will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price. D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the performance of the Work attributable to the exercise of City's rights and remedies under this Paragraph 13.09. ARTICLE 14—PAYMENTS TO CONTRACTOR AND COMPLETION 14.01 Schedule of Vahces The Schedule of Values for lump sum contracts established as provided in Paragraph 2.07 will serve as the basis for progress payments and will be incorporated into a form Of Application for Payment acceptable to City. Progress payments on account of Unit Price Work will be based on the number of units completed. 14.02 Progress Payments A. Applications for Payments: 1. Contractor is responsible for providing all information as required to become a vendor of the City. 2. At least 20 days before the date established in the General Requirements for each progress payment, Contractor shall submit to City for review an Application for Payment filled out and signed by Contractor covering the Work completed as of the date of the Application and accompanied by such supporting documentation as is required by the Contract Documents. 3. If payment is requested on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the Site or at another location agreed to in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice, or other documentation warranting that City has received the materials and equipment free and clear of all Liens and evidence that the materials and equipment are covered by appropriate insurance or other arrangements to protect City's interest therein, all of which must be satisfactory to City. 4. Beginning with the second Application for Payment, each Application shall include an affidavit of Contractor stating that previous progress payments received on account of the Work have been applied on account to discharge Contractor's legitimate obligations associated with prior Applications for Payment. 5. The amount of retainage with respect to progress payments will be as stipulated in the Contract Documents. cny OF PORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Do ►nba21,2012 0072W•I General Conditions Page 53 of 63 B. Review of applications.• 1. City will, after receipt of each Application for Payment, either indicate in writing a recommendation of payment or return the Application to Contractor indicating reasons for refusing payment. In the latter case, Contractor may make the necessary corrections and resubmit the Application. 2. City's processing of any payment requested in an Application for Payment will be based on City's observations of the executed Work, and on City's review of the Application for Payment and the accompanying data and schedules,that to the best of City's knowledge: a. the Work has progressed to the point indicated; b. the quality of the Work is generally in accordance with the Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Final Acceptance, the results of any subsequent tests called for in the Contract Documents, a final determination of quantities and classifications for Work performed under Paragraph 9.05, and any other qualifications stated in the recommendation). 3. Processing any such payment will not thereby be deemed to have represented that: a. inspections made to check the quality or the quantity of the Work as it has been performed have been exhaustive, extended to every aspect of the Work in progress, or involved detailed inspections of the Work beyond the responsibilities specifically assigned to City in the Contract Documents;or b. there may not be other matters or issues between the parties that might entitle Contractor to be paid additionally by City or entitle City to withhold payment to Contractor, or c. Contractor has complied with Laws and Regulations applicable to Contractor's performance of the Work. 4. City may refuse to process the whole or any part of any payment because of subsequently discovered evidence or the results of subsequent inspections or tests, and revise or revoke any such payment previously made, to such extent as may be necessary to protect City from loss because: a. the Work is defective, or the completed Work has been damaged by the Contractor or his subcontractors, requiring correction or replacement; b. discrepancies in quantities contained in previous applications for payment; c. the Contract Price has been reduced by Change Orders; d. City has been required to correct defective Work or complete Work in accordance with Paragraph 13.09;or CrrY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decemba2l,2012 0071U0-1 General Conditions Page 54 of63 e. City has actual knowledge of the occurrence of any of the events enumerated in Paragraph I5.02.A. C. Retai►tage: 1. For contracts less than $400,000 at the time of execution, retainage shall be ten percent (10%). 2. For contracts greater than $400,000 at the time of execution, retainage shall be five percent (5%)• D. Liquidated Damages. For each calendar day that any work shall remain uncompleted after the time specified in the Contract Documents, the sum per day specified in the Agreement, will be deducted from the monies due the Contractor, not as a penalty, but as liquidated damages suffered by the City. E. Payment: Contractor will be paid pursuant to the requirements of this Article 14 and payment will become due in accordance with the Contract Documents. F. Reduction in Payment: 1. City may refuse to make payment of the amount requested because: a. Liens have been filed in connection with the Work, except where Contractor has delivered a specific bond satisfactory to City to secure the satisfaction and discharge of such Liens; b. there are other items entitling City to a set-off against the amount recommended; or c. City has actual knowledge of the occurrence of any of the events enumerated in Paragraphs 14.02.B.4.a through 14.02.B.4.e or Paragraph 15.02.A. 2. If City refuses to make payment of the amount requested, City will give Contractor written notice stating the reasons for such action and pay Contractor any amount remaining after deduction of the amount so withheld. City shall pay Contractor the amount so withheld, or any adjustment thereto agreed to by City and Contractor, when Contractor remedies the reasons for such action. 14.03 Conti-actor's Warranty of Title Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment, whether incorporated in the Project or not, will pass to City no later than the time of payment free and clear of all Liens. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision.Dmanba21,2012 0072UU-I General Conditions Page 55 of 63 14.04 Partial Utilization A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which City, determines constitutes a separately functioning and usable part of the Work that can be used by City for its intended purpose without significant interference with Contractor's performance of the remainder of the Work. City at any time may notify Contractor in writing to permit City to use or occupy any such part of the Work which City determines to be ready for its intended use, subject to the following conditions: 1. Contractor at any time may notify City in writing that Contractor considers any such part of the Work ready for its intended use. 2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and Contractor shall make an inspection of that part of the Work to determine its status of completion. If City does not consider that part of the Work to be substantially complete, City will notify Contractor in writing giving the reasons therefor. 3. Partial Utilization will not constitute Final Acceptance by City. 14.05 Final Inspection A. Upon written notice from Contractor that the entire Work is complete in accordance with the Contract Documents: 1. within 10 days, City will schedule a Final Inspection with Contractor. 2. City will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. B. No time charge will be made against the Contractor between said date of notification of the City and the date of Final Inspection. Should the City determine that the Work is not ready for Final Inspection, City will notify the Contractor in writing of the reasons and Contract Time will resume. 14.06 Final Acceptance Upon completion by Contractor to City's satisfaction, of any additional Work identified in the Final Inspection, City will issue to Contractor a letter of Final Acceptance. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Deamlxx2l,2012 0U 72 0U•1 General Conditions Page 56 of 63 14,07 Final Payment A. Application for Payment: 1. Upon Final Acceptance, and in the opinion of City, Contractor may make an application for final payment following the procedure for progress payments in accordance with the Contract Documents. 2. The final Application for Payment shall be accompanied(except as previously delivered) by: a. all documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.03; b. consent of the surety, if any, to final payment; c. a list of all pending or released Damage Claims against City that Contractor believes are unsettled; and d. affidavits of payments and complete and legally effective releases or waivers (satisfactory to City) of all Lien rights arising out of or Liens filed in connection with the Work. B. Payment Becomes Due: 1. After City's acceptance of the Application for Payment and accompanying documentation, requested by Contractor, less previous payments made and any sum City is entitled, including but not limited to liquidated damages, will become due and payable. 2. After all Damage Claims have been resolved: a. directly by the Contractor or; b. Contractor'provides evidence that the Damage Claim has been reported to Contractor's insurance provider for resolution. 3. The making of the final payment by the City shall not relieve the Contractor of any guarantees or other requirements of the Contract Documents which specifically continue thereafter. 14.08 Final Completion Delayed and Partial Retainage Release A. 1f final completion of the Work is significantly delayed, and if City so confirms, City may, upon receipt of Contractor's final Application for Payment, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance to be held by City for Work not fully completed or corrected is less than the retainage stipulated in Paragraph 14.02.C, and if bonds have been furnished as required in Paragraph 5.02, the written consent of the surety to the payment of the balance due for that CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision;D=ber21,2012 UU 72 00-1 General Conditions Page 57 of 63 portion of the Work fully completed and accepted shall be submitted by Contractor to City with the Application for such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of Contract Claims. B. Pai-lial Retainage Release. For a Contract that provides for a separate vegetative establishment and maintenance, and test and performance periods following the completion of all other construction in the Contract Documents for all Work locations, the City may release a portion of the amount retained provided that all other work is completed as determined by the City. Before the release, all submittals and final quantities must be completed and accepted for all other work. An amount sufficient to ensure Contract compliance will be retained. 14.09 Waiver-of Claims The acceptance of final payment will constitute a release of the City from all claims or liabilities under the Contract for anything done or furnished or relating to the work under the Contract Documents or any act or neglect of City related to or connected with the Contract. ARTICLE 15—SUSPENSION OF WORK AND TERMINATION 15.01 City May Suspend Wor k A. At any time and without cause, City may suspend the Work or any portion thereof by written notice to Contractor and which may fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. During temporary suspension of the Work covered by these,Contract Documents, for any reason, the City will make no extra payment for stand-by time of construction equipment and/or construction crews. B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the control of and without the fault or negligence of the Contractor, and should it be determined by mutual consent of the Contractor and City that a solution to allow construction to proceed is not available within a reasonable period of time, Contractor may request an extension in Contract Time, directly attributable to any such suspension. C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall store all materials in such a manner that they will not obstruct or impede the public unnecessarily nor become damaged in any way, and he shall take every precaution to prevent damage or deterioration of the work performed; he shall provide suitable drainage about the work, and erect temporary structures where necessary. D. Contractor may be reimbursed for the cost of moving his equipment off the job and returning the necessary equipment to the job when it is determined by the City that construction may be resumed. Such reimbursement shall be based on actual cost to the Contractor of moving the equipment and no profit will be allowed. Reimbursement may not be allowed if the equipment is moved to another construction project for the City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dxcnbx21,2012 UU72ou-! General Conditions Page 58 of 63 15.02 City May Ter ndnate for Cause A. The occurrence of any one or more of the following events by way of example, but not of limitation,may justify termination for cause: 1. Contractor's persistent failure to perform the Work in accordance with the Contract Documents (including, but not limited to, failure to supply sufficient skilled workers or suitable materials or equipment, failure to adhere to the Project Schedule established under Paragraph 2.07 as adjusted from time to time pursuant to Paragraph 6.04, or failure to adhere to the City's Business Diversity Enterprise Ordinance #20020-12-201lestablished under Paragraph 6.06.D); 2. Contractor's disregard of Laws or Regulations of any public body having jurisdiction; 3. Contractor's repeated disregard of the authority of City;or 4. Contractor's violation in any substantial way of any provisions of the Contract Documents; or 5. Contractor's failure to promptly make good any defect in materials or workmanship, or defects of any nature, the correction of which has been directed in writing by the City; or 6. Substantial indication that the Contractor has made an unauthorized assignment of the Contract or any funds due therefrom for the benefit of any creditor or for any other,purpose; or 7. Substantial evidence that the Contractor has become insolvent or bankrupt, or otherwise financially unable to carry on the Work satisfactorily; or 8. Contractor commences legal action in a court of competent jurisdiction against the City. B. If one or more of the events identified in Paragraph 15.02A. occur, City will provide written notice to Contractor and Surety to arrange a conference with Contractor and Surety to address Contractor's failure to perform the Work. Conference shall be held not later than 15 days, after receipt of notice. 1. If the City, the Contractor, and the Surety do not agree to allow the Contractor to proceed to perform the construction Contract, the City may, to the extent permitted by Laws and Regulations, declare a Contractor default and formally terminate the Contractor's right to complete the Contract. Contractor default shall not be declared earlier than 20 days after the Contractor and Surety have received notice of conference to address Contractor's failure to perform the Work. 2. If Contractor's services are terminated, Surety shall be obligated to take over and perform the Work. If Surety does not commence performance thereof within 15 consecutive calendar days after date of an additional written notice demanding Surety's performance of its CITY OF FORT WORTH STANDARD CONSTRUCTION SP)CIFCATION DOCUMENTS Revision,Da=ntxs2l,2012 OU 710U-l General Conditions Page 59 or63 obligations, then City, without process or action at law, may take over any portion of the Work and complete it as described below. a. If City completes the Work, City may exclude Contractor and Surety from the site and take possession of the Work, and all materials and equipment incorporated into the Work stored at the Site or for which City has paid Contractor or Surety but which are stored elsewhere, and finish the Work as City may deem expedient. 3. Whether City or Surety completes the Work, Contractor shall not be entitled to receive any further payment until the Work is finished. If the unpaid balance of the Contract Price exceeds all claims, costs, losses and damages sustained by City arising out of or resulting from completing the Work, such excess will be paid to Contractor. If such claims, costs, losses and damages exceed such unpaid balance, Contractor shall pay the difference to City. Such claims, costs, losses and damages incurred by City will be incorporated in a Change Order, provided that when exercising any rights or remedies under this Paragraph, City shall not be required to obtain the lowest price for the Work performed. 4. Neither City, nor any of its respective consultants, agents, officers, directors or employees shall be in any way liable or accountable to Contractor or Surety for the method by which the completion of the said Work, or any portion thereof, may be accomplished or for the price paid therefor. 5. City, notwithstanding the method used in completing the Contract, shall not forfeit the right to recover damages from Contractor or Surety for Contractor's failure to timely complete the entire Contract. Contractor shall not be entitled to any claim on account of the method used by City in completing the Contract. 6. Maintenance of the Work shall continue to be Contractor's and Surety's responsibilities as provided for in the bond requirements of the Contract Documents or any special guarantees provided for under the Contract Documents or any other obligations otherwise prescribed by law. C. Notwithstanding Paragraphs 15.023, Contractor's services will not be terminated if Contractor begins within seven days of receipt of notice of intent to terminate to correct its failure to perform and proceeds diligently to cure such failure within no more than 30 days of receipt of said notice. D. Where Contractor's services have been so terminated by City, the termination will not affect any rights or remedies of City against Contractor then existing or which may thereafter accrue. Any retention or payment of moneys due Contractor by City will not release Contractor from liability. E. If and to the extent that Contractor has provided a performance bond under the provisions of Paragraph 5.02, the termination procedures of that bond shall not supersede the provisions of this Article. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision;Dc=nbr21,20I2 UU 12 UU.I General Conditions Page 60 of 63 15.03 City May Terminate For Convenience A. City may, without cause and without prejudice to any other right or remedy of City, terminate the Contract. Any termination shall be effected by mailing a notice of the termination to the Contractor specifying the extent to which performance of Work under the contract is terminated, and the date upon which such termination becomes effective. Receipt of the notice shall be deemed conclusively presumed and established when the letter is placed in the United States Postal Service Mail by the City. Further, it shall be deemed conclusively presumed and established that such termination is made with just cause as therein stated; and no proof in any claim,demand or suit shall be required of the City regarding such discretionary action. B. After receipt of a notice of termination, and except as otherwise directed by the City, the Contractor shall: 1. Stop work under the Contract on the date and to the extent specified in the notice of termination; 2, place no further orders or subcontracts for materials, services or facilities except as may be necessary for completion of such portion of the Work under the Contract as is not terminated; 3. terminate all orders and subcontracts to the extent that they relate to the performance of the Work terminated by notice of termination; 4. transfer title to the City and deliver in the manner, at the times, and to the extent, if any, directed by the City: a. the fabricated or unfabricated parts, Work in progress, completed Work, supplies and other material produced as a part of, or acquired in connection with the performance of, the Work terminated by the notice of the termination; and b. the completed, or partially completed plans, drawings, information and other property which, if the Contract had been completed, would have been required to be furnished to the City. 5. complete performance of such Work as shall not have been terminated by the notice of termination; and 5. take such action as may be necessary, or as the City may direct, for the protection and preservation of the property related to its contract which is in the possession of the Contractor and in which the owner has or may acquire the rest. C. At a time not later than 30 days after the termination date specified in the notice of termination, the Contractor may submit to the City a list, certified as to quantity and quality, of any or all items of termination inventory not previously disposed of, exclusive of items the disposition of which has been directed or authorized by City. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Decc nber2l,2012 VU/L UU- General Conditions Page 61 of 63 D. Not later than 15 days thereafter, the City shall accept title to such items provided, that the list submitted shall be subject to verification by the City upon removal of the items or, if the items are stored, within 45 days from the date of submission of the list, and any necessary adjustments to correct the list as submitted, shall be made prior to final settlement. E. Not later than 60 days after the notice of termination, the Contractor shall submit his termination claim to the City in the form and with the certification prescribed by the City. Unless an extension is made in writing within such 60 day period by the Contractor, and granted by the City,any and all such claims shall be conclusively deemed waived. F. In such case,Contractor shall be paid for(without duplication of any items): 1. completed and acceptable Work executed in accordance with the Contract Documents prior to the effective date of termination, including fair and reasonable sums for overhead and profit on such Work; 2. expenses sustained prior to the effective date of termination in perfon-ring services and furnishing labor, materials, or equipment as required by the Contract Documents in connection with uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses; and 3. reasonable expenses directly attributable to termination. G. In the event of the failure of the Contractor and City to agree upon the whole amount to be paid to the Contractor by reason of the termination of the Work, the City shall determine, on the basis of information available to it, the amount, if any, due to the Contractor by reason of the termination and shall pay to the Contractor the amounts determined. Contractor shall not be paid on account of loss of anticipated profits or revenue or other economic loss arising out of or resulting from such termination. ARTICLE 16—DISPUTE RESOLUTION 16.01 Methods and Piocedu-es A. Either City or Contractor may request mediation of any Contract Claim submitted for a decision under Paragraph 10.06 before such decision becomes final and binding. The request for mediation shall be submitted to the other party to the Contract. Timely submission of the request shall stay the effect of Paragraph 10.06.E. B. City and Contractor shall participate in the mediation process in good faith. The process shall be commenced within 60 days of filing of the request. C. If the Contract Claim is not resolved by mediation, City's action under Paragraph 10.06.0 or a denial pursuant to Paragraphs 10.06.C.3 or 10.06.13 shall become final and binding 30 days after termination of the mediation unless, within that time period,City or Contractor: CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision;Doccrrhy2l,2012 UU/L uu-1 Genera!Conditions Page 62 of 63 1. elects in writing to invoke any other dispute resolution process provided for in the Supplementary Conditions; or 2. agrees with the other party to submit the Contract Claim to another dispute resolution process; or 3. gives written notice to the other party of the intent to submit the Contract Claim to a court of competent jurisdiction. ARTICLE 17—MISCELLANEOUS 17.01 Giving Notice A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if: 1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended; or 2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. B. Business address changes must be promptly made in writing to the other party. C. Whenever the Contract Documents specifies giving notice by electronic means such electronic notice shall be deemed sufficient upon confirmation of receipt by the receiving party. 17.02 Computation of Times When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day of the period. 17.03 Cumulative Remedies The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. CnYOF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Dwe nb x21,2012 UU 72 UU-I General Conditions Page 63 of 63 17.04 Survival of Obligations All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor. 17.05 Headings Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFCATION DOCUMENTS Revision:Uecen txr2l,2012 00 73 00.1 SUPPLEMENTARY CONDITIONS Pagel of 5 1 SECTION 00 73 00 2 SUPPLEMENTARY CONDITIONS 3 TO 4 GENERAL CONDITIONS 5 6 Supplementary Conditions 7 8 These Supplementary Conditions modify and supplement Section 00 72 00-General Conditions,and other 9 provisions of the Contract Documents as indicated below. All provisions of the General Conditions that are 10 modified or supplemented remain in full force and effect as so modified or supplemented. All provisions 1 I of the General Conditions which are not so modified or supplemented remain in full force and effect. 12 13 Defined Terms I4 15 The terms used in these Supplementary Conditions which are defined in the General Conditions have the 16 meaning assigned to them in the General Conditions,unless specifically noted herein. I7 I8 Modifications and Supplements 19 20 The following are instructions that modify or supplement specific paragraphs in the General Conditions and 21 other Contract Documents. 22 23 SC-3.03B.2,"Resolving Discrepancies" 24 25 Plans govern over Specifications. 26 27 SC-4.01A 28 29 Easement limits shown on the Drawing are approximate and were provided to establish a basis for bidding. 30 Upon receiving the final easements descriptions,Contractor shall compare them to the lines shown on the 31 Contract Drawings. 32 33 SC4.01A.1.,"Availability of Lands" 34 35 The following is a list of known outstanding right-of-way,and/or easements to be acquired,if any as of 36 October 28,2014 37 38 Outstanding Right-Of-Way,and/or Easements to Be Acquired PARCEL OWNER TARGET DATE NUMBER OF POSSESSION NONE 39 The Contractor understands and agrees that the dates listed above are estimates only, are not guaranteed, 40 and do not bind the City. 41 42 If Contractor considers the final easements provided to differ materially from the representations on the 43 Contract Drawings, Contractor shall within five (5) Business Days and before proceeding with the Work, 44 notify City in writing associated with the differing easement line locations. 45 46 SC4.01A.2,"Availability of Lands" 47 48 Utilities or obstructions to be removed,adjusted,and/or relocated CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised April 1,2013 007300.2 SUPPLEMENTARY CONDITIONS Page 2 of 5 1 2 The following is list of utilities and/or obstructions that have not been removed,adjusted,and/or relocated 3 as of October 28,2014 4 EXPECTED UTILITY AND LOCATION TARGET DATE OF OWNER ADJUSTMENT NONE 5 The Contractor understands and agrees that the dates listed above are estimates only,are not guaranteed, 6 and do not bind the City. 7 8 SC4.02A.,"Subsurface and Physical Conditions" 9 10 The following are reports of explorations and tests of subsurface conditions at the site of the Work: it 12 NONE 13 14 The following are drawings of physical conditions in or relating to existing surface and subsurface 15 structures(except Underground Facilities)which are at or contiguous to the site of the Work: 16 NONE 17 18 SC4.06A.,"Hazardous Environmental Conditions at Site" 19 20 The following are reports and drawings of existing hazardous environmental conditions known to the City: 21 NONE 22 23 SC-5.03A.,"Certificates of Insurance" 24 25 The entities listed below are"additional insureds as their interest may appear" including their respective 26 officers,directors,agents and employees. 27 28 (1) City 29 (2) Consultant: NONE 30 (3) Other: NONE 31 32 SC-5.04A.,"Contractor's Insurance" 33 34 The limits of liability for the insurance required by Paragraph GC-5.04 shall provide the following 35 coverages for not less than the following amounts or greater where required by laws and regulations: 36 37 5.04A.Workers'Compensation,under Paragraph GC-5.04A. 38 39 Statutory limits 40 Employer's liability 41 $100,000 each accident/occurrence 42 $100,000 Disease-each employee 43 $500,000 Disease-policy limit 44 45 SC-5.04B.,"Contractor's insurance" 46 47 5.04B.Commercial General Liability,under Paragraph GC-5.0413. Contractor's Liability Insurance 48 under Paragraph GC-5.04B.,which shall be on a per project basis covering the Contractor with 49 minimum limits of: CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised April 1,2013 007300-3 SUPPLEMENTARY CONDITIONS Page 3 of 5 1 2 $1,000,000 each occurrence 3 $2,000,000 aggregate limit 4 5 The policy must have an endorsement(Amendment v Aggregate Limits of Insurance)making the 6 General Aggregate Limits apply separately to each job site. 7 8 The Commercial General Liability Insurance policies shall provide"X","C",and"U"coverage's. 9 Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance. 10 11 SC 5.04C.,"Contractor's Insurance" 12 5.04C. Automobile Liability,under Paragraph GC-5.04C.Contractor's Liability Insurance under 13 Paragraph GC-5.04C., which shall be in an amount not less than the following amounts: 14 15 (1) Automobile Liability-a commercial business policy shall provide coverage on"Any Auto", 16 defined as autos owned,hired and non-owned. 17 18 $1,000,000 each accident on a combined single limit basis. Split limits are acceptable if limits are at 19 least: 20 21 $250,000 Bodily Injury per person f 22 $500,000 Bodily Injury per accident t 23 $100,000 Property Damage 24 25 SC-5.04D.,"Contractor's Insurance" 26 27 The Contractor's construction activities will require its employees,agents,subcontractors,equipment,and 28 material deliveries to cross railroad properties and tracks NONE 29 30 The Contractor shall conduct its operations on railroad properties in such a manner as not to interfere with, 31 hinder,or obstruct the railroad company in any manner whatsoever in the use or operation of its/their trains 32 or other property. Such operations on railroad properties may require that Contractor to execute a"Right of 33 Entry Agreement"with the particular railroad company or companies involved,and to this end the 34 Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute 35 the right-of-entry(if any)required by a railroad company.The requirements specified herein likewise relate 36 to the Contractor's use of private and/or construction access roads crossing said railroad company's 37 properties. 38 39 The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide 40 coverage for not less than the following amounts, issued by companies satisfactory to the City and to the 41 Railroad Company for a term that continues for so long as the Contractor's operations and work cross, 42 occupy,or touch railroad property: 43 44 (1) General Aggregate: 45 46 (2) Each Occurrence: 47 48 -,.,_Required for this Contract X Not required for this Contract 49 50 With respect to the above outlined insurance requirements,the following shall govern: 51 52 1. Where a single railroad company is involved,the Contractor shall provide one insurance policy in 53 the name of the railroad company. However, if more than one grade separation or at-grade 54 crossing is affected by the Project at entirely separate locations on the line or lines of the same 55 railroad company,separate coverage may be required,each in the amount stated above. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised April 1,2013 007300-4 SUPPLEMENTARY CONDITIONS Page 4 of 5 I 2 2. Where more than one railroad company is operating on the same right-of-way or where several 3 railroad companies are involved and operated on their own separate rights-of-way, the Contractor 4 may be required to provide separate insurance policies in the name of each railroad company. 5 6 3. If,in addition to a grade separation or an at-grade crossing,other work or activity is proposed on a 7 railroad company's right-of-way at a location entirely separate from the grade separation or at- 8 grade crossing,insurance coverage for this work must be included in the policy covering the grade 9 separation. 10 11 4. If no grade separation is involved but other work is proposed on a railroad company's right-of- 12 way,all such other work may be covered in a single policy for that railroad,even though the work 13 may be at two or more separate locations. 14 15 No work or activities on a railroad company's property to be performed by the Contractor shall be 16 commenced until the Contractor has furnished the City with an original policy or policies of the insurance 17 for each railroad company named,as required above. All such insurance must be approved by the City and 18 each affected Railroad Company prior to the Contractor's beginning work. 19 20 The insurance specified above must be carried until all Work to be performed on the railroad right-of-way 21 has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition, 22 insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way. 23 Such insurance must name the railroad company as the insured,together with any tenant or lessee of the 24 railroad company operating over tracks involved in the Project. 25 26 SC-6.04.,"Project Schedule" 27 28 Project schedule shall be tier 2 for the project. 29 30 SC-6.07.,"Wage Rates" 31 32 The following is the prevailing wage rate table(s)applicable to this project and is provided in the 33 Appendixes: 34 GC 6.07 Wage Rates 35 36 SC-6.09.,"Permits and Utilities" 37 38 SC-6.09A.,"Contractor obtained permits and licenses" 39 The following are known permits and/or licenses required by the Contract to be acquired by the Contractor: 40 NONE 41 42 SC-6.09B."City obtained permits and licenses" 43 The following are known permits and/or licenses required by the Contract to be acquired by the City: 44 NONE 45 46 SC-6.09C."Outstanding permits and licenses" 47 48 The following is a list of known outstanding permits and/or licenses to be acquired,if any as of October 28, 49 2014 50 51 52 53 54 55 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised April 1,2013 007300-5 SUPPLEMENTARY CONDITIONS Page 5 of 5 1 Outstanding Permits and/or Licenses to Be Acquired OWNER PERMIT OR LICENSE AND LOCATION TARGET DATE OF POSSESSION NONE 2 3 4 SC-7.02.,"Coordination" 5 6 The individuals or entities listed below have contracts with the City for the performance of other work at 7 the Site: 8 Vendor Scope of Work Coordination Authority NONE 9 10 I I SC-8.01,"Communications to Contractor" I2 13 1. The contractor shall take special note the pre-bid item for Associated Well Services. The 14 contractor shall contract Associated Well Services for the rehabilitation of the existing well. 15 No other well service company will be allowed to service or rehabilitate the existing well. 16 17 SC-9.01.,"City's Project Representative" 18 19 The following firm is a consultant to the City responsible for construction management of this Project: 20 21 NONE 22 23 SC-13.03C.,"Tests and Inspections" 24 25 1. The City shall perform a test of the irrigation system prior to acceptance of the project 26 2. The City's Parks Department shall inspect and approve the tree planting prior toe acceptance of 27 the project. 28 29 SCA6.01C.1,"Methods and Procedures" 30 31 NONE 32 33 34 35 END OF SECTION CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised April 1,2013 011100-1 SUMMARY OF WORK Page 1 of 3 I SECTION 011100 2 SUMMARY OF WORK 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Summary of Work to be performed in accordance with the Contract Documents 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0- Bidding Requirements, Contract Forms,and Conditions of the Contract 11 2. Division I -General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES (NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Work Covered by Contract Documents 19 1. Work is to include furnishing all labor, materials, and equipment, and performing 20 all Work necessary for this construction project as detailed in the Drawings and 21 Specifications. 22 B. Subsidiary Work 23 1. Any and all Work specifically governed by documentary requirements for the 24 project,such as conditions imposed by the Drawings or Contract Documents in 25 which no specific item for bid has been provided for in the Proposal and the item is 26 not a typical unit bid item included on the standard bid item list,then the item shall 27 be considered as a subsidiary item of Work,the cost of which shall be included in 28 the price bid in the Proposal for various bid items. 29 C. Use of Premises 30 1. Coordinate uses of premises under direction of the City. 31 2. Assume full responsibility for protection and safekeeping of materials and 32 equipment stored on the Site. 33 3. Use and occupy only portions of the public streets and alleys,or other public places 34 or other rights-of-way as provided for in the ordinances of the City,as shown in the 35 Contract Documents,or as may be specifically authorized in writing by the City. 36 a. A reasonable amount of tools,materials,and equipment for construction 37 purposes may be stored in such space,but no more than is necessary to avoid 38 delay in the construction operations. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Pmjcct No,01239 Revised December 20,2012 01 1100-2 SUMMARY OF WORK Page 2 of 3 1 b. Excavated and waste materials shall be stored in such a way as not to interfere 2 with the use of spaces that may be designated to be left free and unobstructed 3 and so as not to inconvenience occupants of adjacent property. 4 c. If the street is occupied by railroad tracks, the Work shall be carried on in such 5 manner as not to interfere with the operation of the railroad. 6 1) All Work shall be in accordance with railroad requirements set forth in 7 Division 0 as well as the railroad permit. 8 D. Work within Easements 9 1. Do not enter upon private property for any purpose without having previously 10 obtained permission from the owner of such property. 11 2. Do not store equipment or material on private property unless and until the 12 specified approval of the property owner has been secured in writing by the 13 Contractor and a copy furnished to the City. 14 3. Unless specifically provided otherwise,clear all rights-of-way or easements of 15 obstructions which must be removed to make possible proper prosecution of the 16 Work as a part of the project construction operations. 17 4. Preserve and use every precaution to prevent damage to, all trees,shrubbery, plants, 18 lawns, fences,culverts,curbing,and all other types of structures or improvements, 19 to all water, sewer,and gas lines,to all conduits,overhead pole lines, or 20 appurtenances thereof, including the construction of temporary fences and to all 21 other public or private property adjacent to the Work. 22 5. Notify the proper representatives of the owners or occupants of the public or private 23 lands of interest in lands which might be affected by the Work. 24 a. Such notice shall be made at least 48 hours in advance of the beginning of the 25 Work. 26 b. Notices shall be applicable to both public and private utility companies and any 27 corporation,company, individual, or other,either as owners or occupants, 28 whose land or interest in land might be affected by the Work. 29 c. Be responsible for all damage or injury to property of any character resulting 30 from any act,omission,neglect,or misconduct in the manner or method or 31 execution of the Work,or at any time due to defective work, material,or 32 equipment. 33 6. Fence 34 a. Restore all fences encountered and removed during construction of the Project 35 to the original or a better than original condition. 36 b. Erect temporary fencing in place of the fencing removed whenever the Work is 37 not in progress and when the site is vacated overnight, and/or at all times to 38 provide site security. 39 c. The cost for all fence work within easements, including removal, temporary 40 closures and replacement,shall be subsidiary to the various items bid in the 41 project proposal,unless a bid item is specifically provided in the proposal. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 011100-3 SUMMARY OF WORK Page 3 of 3 I 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 7 1.11 FIELD [SITE] CONDITIONS [NOT USED[ 8 1.12 WARRANTY [NOT USED] 9 PART 2- PRODUCTS [NOT USED] 10 PART 3- EXECUTION [NOT USED[ 1 1 END OF SECTION 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 CITY OF FORT WORTH Marys Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 01 25 00-1 SUBSTITUTION PROCEDURES Page I of 5 1 SECTION 0125 00 2 SUBSTITUTION PROCEDURES 3 PARTI - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 I. The procedure for requesting the approval of substitution of a product that is not 7 equivalent to a product which is specified by descriptive or performance criteria or 8 defined by reference to I or more of the following: 9 a. Name of manufacturer 10 b. Name of vendor I 1 c. Trade name 12 d. Catalog number 13 2. Substitutions are not"or-equals". 14 B. Deviations from this City of Fort Worth Standard Specification 15 1. None, 16 C. Related Specification Sections include,but are not necessarily limited to: 17 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 18 2. Division 1 —General Requirements 19 1.2 PRICE AND PAYMENT PROCEDURES 20 A. Measurement and Payment 21 1. Work associated with this Item is considered subsidiary to the various items bid. 22 No separate payment will be allowed for this Item. 23 1.3 REFERENCES [NOT USED] 24 1.4 ADMINISTRATIVE REQUIREMENTS 25 A. Request for Substitution-General 26 1. Within 30 days after award of Contract(unless noted otherwise),the City will 27 consider formal requests from Contractor for substitution of products in place of 28 those specified. 29 2. Certain types of equipment and kinds of material are described in Specifications by 30 means of references to names of manufacturers and vendors, trade names,or 31 catalog numbers. 32 a. When this method of specifying is used, it is not intended to exclude from 33 consideration other products bearing other manufacturer's or vendor's names, 34 trade names,or catalog numbers,provided said products are"or-equals,"as 35 determined by City. 36 3. Other types of equipment and kinds of material may be acceptable substitutions 37 under the following conditions: 38 a. Or-equals are unavailable due to strike,discontinued production of products 39 meeting specified requirements,or other factors beyond control of Contractor; 40 or, CrrY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 25 00-2 SUBSTITUTION PROCEDURES Page 2 of 5 I b. Contractor proposes a cost and/or time reduction incentive to the City. 2 1.5 SUBMITTALS 3 A. See Request for Substitution Form(attached) 4 B. Procedure for Requesting Substitution 5 1. Substitution shall be considered only: 6 a. After award of Contract 7 b. Under the conditions stated herein 8 2. Submit 3 copies of each written request for substitution, including: 9 a. Documentation 10 1) Complete data substantiating compliance of proposed substitution with I 1 Contract Documents 12 2) Data relating to changes in construction schedule,when a reduction is 13 proposed 14 3) Data relating to changes in cost 15 b. For products 16 1) Product identification 17 a) Manufacturer's name 18 b) Telephone number and representative contact name 19 c) Specification Section or Drawing reference of originally specified 20 product,including discrete name or tag number assigned to original 21 product in the Contract Documents 22 2) Manufacturer's literature clearly marked to show compliance of proposed 23 product with Contract Documents 24 3) Itemized comparison of original and proposed product addressing product 25 characteristics including, but not necessarily limited to: 26 a) Size 27 b) Composition or materials of construction 28 c) Weight 29 d) Electrical or mechanical requirements 30 4) Product experience 31 a) Location of past projects utilizing product 32 b) Name and telephone number of persons associated with referenced 33 projects knowledgeable concerning proposed product 34 c) Available field data and reports associated with proposed product 35 5) Samples 36 a) Provide at request of City. 37 b) Samples become the property of the City. 38 c. For construction methods: 39 1) Detailed description of proposed method 40 2) Illustration drawings 41 C. Approval or Rejection 42 1. Written approval or rejection of substitution given by the City 43 2. City reserves the right to require proposed product to comply with color and pattern 44 of specified product if necessary to secure design intent. 45 3. In the event the substitution is approved,the resulting cost and/or time reduction 46 will be documented by Change Order in accordance with the General Conditions. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July I,2011 012500-3 SUBSTITUTION PROCEDURES Page 3 of 5 1 4. No additional contract time will be given for substitution. 2 5. Substitution will be rejected if- 3 a. Submittal is not through the Contractor with his stamp of approval 4 b. Request is not made in accordance with this Specification Section 5 c. In the City's opinion, acceptance will require substantial revision of the original 6 design 7 d. In the City's opinion, substitution will not perform adequately the function 8 consistent with the design intent 9 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 10 1.7 CLOSEOUT SUBMITTALS [NOT USED] 11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 12 1.9 QUALITY ASSURANCE 13 A. In making request for substitution or in using an approved product, the Contractor 14 represents that the Contractor: 15 1. Has investigated proposed product, and has determined that it is adequate or 16 superior in all respects to that specified,and that it will perform function for which 17 it is intended I8 2. Will provide same guarantee for substitute item as for product specified 19 3. Will coordinate installation of accepted substitution into Work,to include building 20 modifications if necessary, making such changes as may be required for Work to be 21 complete in all respects 22 4. Waives all claims for additional costs related to substitution which subsequently 23 arise 24 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 25 1.11 FIELD [SITE] CONDITIONS [NOT USED] 26 1.12 WARRANTY [NOT USED] 27 PART 2- PRODUCTS [NOT USED] 28 PART 3- EXECUTION [NOT USED] 29 END OF SECTION 30 Revision Log DATE NAME SUMMARY OF CHANGE 31 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 2500-4 SUBSTITUTION PROCEDURES Page 4 of 5 1 EXHIBIT A 2 REQUEST FOR SUBSTITUTION FORM: 3 4 TO: 5 PROJECT: DATE: - 6 We hereby submit for your consideration the following product instead of the specified item for 7 the above project: 8 SECTION PARAGRAPH SPECIFIED 9 ITEM 10 11 12 Proposed Substitution: 13 Reason for Substitution: 14 Include complete information on changes to Drawings and/or Specifications which proposed 15 substitution will require for its proper installation. 16 17 Fill in Blanks Below: 18 A. Will the undersigned contractor pay for changes to the building design, including 19 engineering and detailing costs caused by the requested substitution? 20 21 22 B. What effect does substitution have on other trades? 23 24 25 C. Differences between proposed substitution and specified item? 26 27 28 D. Differences in product cost or product delivery time? 29 30 31 E. Manufacturer's guarantees of the proposed and specified items are: 32 33 Equal Better (explain on attachment) 34 The undersigned states that the function, appearance and quality are equivalent or superior to 35 the specified item. 36 Submitted By: For Use by City 37 38 Signature Recommended Recommended 39 as noted 40 41 Firm Not recommended ,Received late 42 Address BY 43 Date 44 Date Remarks 45 Telephone 46 47 For Use by City: 48 49 Approved Rejected CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised July 1,2011 01 2500-5 SUBSTITUTION PROCEDURES Page 5 of 5 i City Date CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised July 1,2011 0131 t9-1 PRECONSTRUCTION MEETING Page 1 of 3 1 SECTION 01 31 19 2 PRECONSTRUCTION MEETING 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Provisions for the preconstruction meeting to be held prior to the start of Work to 7 clarify construction contract administration procedures 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. None. 10 C. Related Specification Sections include,but are not necessarily limited to: I 1 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 12 2. Division 1 —General Requirements 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Work associated with this Item is considered subsidiary to the various items bid. 16 No separate payment will be allowed for this Item. 17 1.3 REFERENCES [NOT USED] 18 1.4 ADMINISTRATIVE REQUIREMENTS 19 A. Coordination 20 1. Attend preconstruction meeting. 21 2. Representatives of Contractor,subcontractors and suppliers attending meetings 22 shall be qualified and authorized to act on behalf of the entity each represents. 23 3. Meeting administered by City may be tape recorded. 24 a. if recorded,tapes will be used to prepare minutes and retained by City for 25 future reference. 26 B. Preconstruction Meeting 27 1. A preconstruction meeting will be held within 14 days after the execution of the 28 Agreement and before Work is started. 29 a. The meeting will be scheduled and administered by the City. 30 2. The Project Representative will preside at the meeting,prepare the notes of the 31 meeting and distribute copies of same to all participants who so request by fully 32 completing the attendance form to be circulated at the beginning of the meeting. 33 3. Attendance shall include: 34 a. Project Representative 35 b. Contractor's project manager 36 c. Contractor's superintendent 37 d. Any subcontractor or supplier representatives whom the Contractor may desire 38 to invite or the City may request CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised August 17,2012 01 31 19-2 PRECONSTRUCTION MEETING Page 2 of 3 I e. Other City representatives 2 f. Others as appropriate 3 4. Construction Schedule 4 a. Prepare baseline construction schedule in accordance with Section 0132 16 and 5 provide at Preconstruction Meeting. 6 b. City will notify Contractor of any schedule changes upon Notice of 7 Preconstruction Meeting. 8 5. Preliminary Agenda may include: 9 a. Introduction of Project Personnel 10 b. General Description of Project I 1 c. Status of right-of-way, utility clearances,easements or other pertinent permits 12 d. Contractor's work plan and schedule 13 e. Contract Time 14 f. Notice to Proceed 15 g. Construction Staking 16 h. Progress Payments 17 i. Extra Work and Change Order Procedures 18 j. Field Orders 19 k. Disposal Site Letter for Waste Material 20 1. Insurance Renewals 21 m. Payroll Certification 22 n. Material Certifications and Quality Control Testing 23 o. Public Safety and Convenience 24 p. Documentation of Pre-Construction Conditions 25 q. Weekend Work Notification 26 r. Legal Holidays 27 s. Trench Safety Plans 28 t. Confined Space Entry Standards 29 u. Coordination with the City's representative for operations of existing water 30 systems 31 v. Storm Water Pollution Prevention Plan 32 w. Coordination with other Contractors 33 x. Early Warning System 34 y. Contractor Evaluation 35 z. Special Conditions applicable to the project 36 aa. Damages Claims 37 bb. Submittal Procedures 38 cc. Substitution Procedures 39 dd. Correspondence Routing 40 ee. Record Drawings 41 ff. Temporary construction facilities 42 gg. M/WBE or MBE/SBE procedures 43 hh. Final Acceptance 44 ii. Final Payment 45 jj. Questions or Comments CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised August 17,2012 0131 19-3 PRECONSTRUCTION MEETING Page 3 of 1 1.5 SUBMITTALS INOT USEDI 2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS (NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 7 1.11 FIELD [SITE] CONDITIONS INOT USED] 8 1.12 WARRANTY [NOT USEDI 9 PART 2- PRODUCTS [NOT USED] 10 PART 3- EXECUTION [NOT USED] 11 END OF SECTION 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 CITY OF FORT WORTH Mary's Cm-ek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised August 17,2012 013120-1 PROJECT MEETINGS Paget of 3 1 SECTION 01 31 20 2 PROJECT MEETINGS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Provisions for project meetings throughout the construction period to enable orderly 7 review of the progress of the Work and to provide for systematic discussion of 8 potential problems 9 B. Deviations this City of Fort Worth Standard Specification 10 1. None. 11 C. Related Specification Sections include,but are not necessarily limited to: 12 1. Division 0 Bidding Requirements,Contract Forms and Conditions of the Contract 13 2. Division 1 —General Requirements 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Work associated with this Item is considered subsidiary to the various items bid. 17 No separate payment will be allowed for this Item. 18 1.3 REFERENCES [NOT USED] 19 1.4 ADMINISTRATIVE REQUIREMENTS 20 A. Coordination 21 1. Schedule, attend and administer as specified,periodic progress meetings,and 22 specially called meetings throughout progress of the Work. 23 2. Representatives of Contractor,subcontractors and suppliers attending meetings 24 shall be qualified and authorized to act on behalf of the entity each represents. 25 3. Meetings administered by City may be tape recorded. 26 a. If recorded,tapes will be used to prepare minutes and retained by City for 27 future reference. 28 4. Meetings, in addition to those specified in this Section,may be held when requested 29 by the City, Engineer or Contractor. 30 B. Pre-Construction Neighborhood Meeting 31 1. After the execution of the Agreement,but before construction is allowed to begin, 32 attend l Public Meeting with affected residents to: 33 a. Present projected schedule, including construction start date 34 b. Answer any construction related questions 35 2. Meeting Location 36 a. Location of meeting to be determined by the City. 37 3. Attendees 38 a. Contractor CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 013120-2 PROJECT MEETINGS Page 2 of 3 1 b. Project Representative 2 c. Other City representatives 3 4. Meeting Schedule 4 a. In general,the neighborhood meeting will occur within the 2 weeks following 5 the pre-construction conference. 6 b. In no case will construction be allowed to begin until this meeting is held. 7 C. Progress Meetings 8 1. Formal project coordination meetings will be held periodically. Meetings will be 9 scheduled and administered by Project Representative. 10 2. Additional progress meetings to discuss specific topics will be conducted on an as- I 1 'needed basis. Such additional meetings shall include,but not be limited to: 12 a. Coordinating shutdowns 13 b. Installation of piping and equipment 14 c. Coordination between other construction projects 15 d. Resolution of construction issues 16 e. Equipment approval 17 3. The Project Representative will preside at progress meetings,prepare the notes of 18 the meeting and distribute copies of the same to all participants who so request by 19 fully completing the attendance form to be circulated at the beginning of each 20 meeting. 21 4. Attendance shall include: 22 a. Contractor's project manager 23 b. Contractor's superintendent 24 c. Any subcontractor or supplier representatives whom the Contractor may desire 25 to invite or the City may request 26 d. Engineer's representatives 27 e. City's representatives 28 f. Others,as requested by the Project Representative 29 5. Preliminary Agenda may include: 30 a. Review of Work progress since previous meeting 31 b. Field observations,problems,conflicts 32 c. Items which impede construction schedule 33 d. Review of off-site fabrication, delivery schedules 34 e. Review of construction interfacing and sequencing requirements with other 35 construction contracts 36 f. Corrective measures and procedures to regain projected schedule 37 g. Revisions to construction schedule 38 h. Progress,schedule,during succeeding Work period 39 i. Coordination of schedules 40 j. Review submittal schedules 41 k. Maintenance of quality standards 42 1. Pending changes and substitutions 43 m. Review proposed changes for: 44 1) Effect on construction schedule and on completion date 45 2) Effect on other contracts of the Project 46 n. Review Record Documents 47 o. Review monthly pay request 48 p. Review status of Requests for Information CITY OF FORT WORTH Mary's Cruck Recycling Center Trcc Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 013120-3 PROJECT MEETINGS Page 3 of 3 1 6. Meeting Schedule 2 a. Progress meetings will be held periodically as determined by the Project 3 Representative. 4 1) Additional meetings may be held at the request of the: 5 a) City 6 b) Engineer 7 c) Contractor 8 7. Meeting Location 9 a. The City will establish a meeting location. 10 1) To the extent practicable, meetings will be held at the Site. 11 1.5 SUBMITTALS [NOT USED] 12 1.6 ACTION SUBMITTALSlINFORMATIONAL SUBMITTALS [NOT USED] 13 1.7 CLOSEOUT SUBMITTALS [NOT USED] 14 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 15 1.9 QUALITY ASSURANCE [NOT USED] 16 1.10 DELIVERY,STORAGE,AND HANDLING ]NOT USED] 17 1.11 FIELD [SITE] CONDITIONS [NOT USED) 18 1.12 WARRANTY [NOT USED] 19 PART 2» PRODUCTS [NOT USED] 20 PART 3- EXECUTION [NOT USED] 21 END OF SECTION 22 Revision Log DATE NAME SUMMARY OF CHANGE 23 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1.2011 013216-1 CONSTRUCTION PROGRESS SCHEDULE Page 1 of 5 I SECTION 0132 16 2 CONSTRUCTION PROGRESS SCHEDULE 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. General requirements for the preparation,submittal,updating,status reporting and 7 management of the Construction Progress Schedule 8 2. Specific requirements are presented in the City of Fort Worth Schedule Guidance 9 Document 10 B. Deviations from this City of Fort Worth Standard Specification 11 1. None. 12 C. Related Specification Sections include,but are not necessarily limited to: 13 1. Division 0 u Bidding Requirements,Contract Forms and Conditions of the Contract 14 2. Division 1 —General Requirements 15 1.2 PRICE AND PAYMENT PROCEDURES 16 A. Measurement and Payment 17 1. Work associated with this Item is considered subsidiary to the various items bid. 18 No separate payment will be allowed for this Item. 19 1.3 REFERENCES 20 A. Definitions 21 1. Schedule Tiers 22 a. Tier 1 -No schedule submittal required by contract. Small,brief duration 23 projects 24 b. Tier 2 -No schedule submittal required by contract,but will require some 25 milestone dates. Small,brief duration projects 26 c. Tier 3 - Schedule submittal required by contract as described in the 27 Specification and herein. Majority of City projects, including all bond program 28 projects 29 d. Tier 4-Schedule submittal required by contract as described in the 30 Specification and herein. Large and/or complex projects with long durations 31 1) Examples: Iarge water pump station project and associated pipeline with 32 interconnection to another governmental entity 33 e. Tier 5-Schedule submittal required by contract as described in the 34 Specification and herein. Large and/or very complex projects with long 35 durations, high public visibility 36 1) Examples might include a water or wastewater treatment plant 37 2. Baseline Schedule- Initial schedule submitted before work begins that will serve 38 as the baseline for measuring progress and departures from the schedule. 39 3. Progress Schedule-Monthly submittal of a progress schedule documenting 40 progress on the project and any changes anticipated. CITY OF FORT WORTH Mary's Creck Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 32 16.2 CONSTRUCTION PROGRESS SCHEDULE Page 2 of 5 1 4. Schedule Narrative-Concise narrative of the schedule including schedule 2 changes,expected delays,key schedule issues,critical path items,etc 3 B. Reference Standards 4 1. City of Fort Worth Schedule Guidance Document 5 1.4 ADMINISTRATIVE REQUIREMENTS 6 A. Baseline Schedule 7 1. General 8 a. Prepare a cost-loaded baseline Schedule using approved software and the 9 Critical Path Method(CPM) as required in the City of Fort Worth Schedule 10 Guidance Document. I I b. Review the draft cost-loaded baseline Schedule with the City to demonstrate 12 understanding of the work to be performed and known issues and constraints 13 related to the schedule. 14 c. Designate an authorized representative(Project Scheduler)responsible for 15 developing and updating the schedule and preparing reports. 16 B. Progress Schedule 17 1. Update the progress Schedule monthly as required in the City of Fort Worth 18 Schedule Guidance Document. 19 2. Prepare the Schedule Narrative to accompany the monthly progress Schedule. 20 3. Change Orders 21 a. Incorporate approved change orders,resulting in a change of contract time, in 22 the baseline Schedule in accordance with City of Fort Worth Schedule 23 Guidance Document. 24 C. Responsibility for Schedule Compliance 25 1. Whenever it becomes apparent from the current progress Schedule and CPM Status 26 Report that delays to the critical path have resulted and the Contract completion 27 date will not be met,or when so directed by the City,make some Or all of the 28 fallowing actions at no additional cost to the City 29 a. Submit a Recovery Plan to the City for approval revised baseline Schedule 30 outlining: 31 1) A written statement of the steps intended to take to remove or arrest the 32 delay to the critical path in the approved schedule 33 2) Increase construction manpower in such quantities and crafts as will 34 substantially eliminate the backlog of work and return current Schedule to 35 meet projected baseline completion dates 36 3) Increase the number of working hours per shift,shifts per day, working 37 days per week,the amount of construction equipment,or any combination 38 of the foregoing,sufficiently to substantially eliminate the backlog of work 39 4) Reschedule activities to achieve maximum practical concurrency of 40 accomplishment of activities, and comply with the revised schedule 41 2. If no written statement of the steps intended to take is submitted when so requested 42 by the City,the City may direct the Contractor to increase the level of effort in 43 manpower(trades),equipment and work schedule(overtime,weekend and holiday 44 work,etc.)to be employed by the Contractor in order to remove or arrest the delay 45 to the critical path in the approved schedule. 46 a. No additional cost for such work will be considered. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 32 16-3 CONSTRUCTION PROGRESS SCHEDULE Page 3 of 5 1 D. The Contract completion time will be adjusted only for causes specified in this 2 Contract. 3 a. Requests for an extension of any Contract completion date must be 4 supplemented with the following: 5 1) Furnish justification and supporting evidence as the City may deem 6 necessary to determine whether the requested extension of time is entitled 7 under the provisions of this Contract. 8 a) The City will,after receipt of such justification and supporting 9 evidence,make findings of fact and will advise the Contractor, in 10 writing thereof. 11 2) If the City finds that the requested extension of time is entitled,the City's 12 determination as to the total number of days allowed for the extensions 13 shall be based upon the approved total baseline schedule and on all data 14 relevant to the extension. 15 a) Such data shall be included in the next updating of the Progress 16 schedule. 17 b) Actual delays in activities which, according to the Baseline schedule, 18 do not affect any Contract completion date shown by the critical path in 19 the network will not be the basis for a change therein. 20 2. Submit each request for change in Contract completion date to the City within 30 21 days after the beginning of the delay for which a time extension is requested but 22 before the date of final payment under this Contract. 23 a. No time extension will be granted for requests which are not submitted within 24 the foregoing time limit. 25 b. From time to time, it may be necessary for the Contract schedule or completion 26 time to be adjusted by the City to reflect the effects of job conditions,weather, 27 technical difficulties,strikes,unavoidable delays on the part of the City or its 28 representatives,and other unforeseeable conditions which may indicate 29 schedule adjustments or completion time extensions. 30 1) Under such conditions,the City will direct the Contractor to reschedule the 31 work or Contract completion time to reflect the changed conditions and the 32 Contractor shall revise his schedule accordingly. 33 a) No additional compensation will be made to the Contractor for such 34 schedule changes except for unavoidable overall contract time 35 extensions beyond the actual completion of unaffected work, in which 36 case the Contractor shall take all possible action to minimize any time 37 extension and any additional cost to the City. 38 b) Available float time in the Baseline schedule may be used by the City 39 as well as by the Contractor. 40 3. Float or slack titne is defined as the amount of time between the earliest start date 41 and the latest start date or between the earliest finish date and the latest finish date 42 of a chain of activities on the Baseline Schedule. 43 a. Float or slack time is not for the exclusive use or benefit of either the 44 Contractor or the City. 45 b. Proceed with work according to early start dates,and the City shall have the 46 right to reserve and apportion float time according to the needs of the project. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 32 16-4 CONSTRUCTION PROGRESS SCHEDULE Page 4 of 5 1 c. Acknowledge and agree that actual delays, affecting paths of activities 2 containing float time,will not have any effect upon contract completion times, 3 providing that the actual delay does not exceed the float time associated with 4 those activities. 5 E. Coordinating Schedule with Other Contract Schedules 6 1. Where work is to be performed under this Contract concurrently with or contingent 7 upon work performed on the same facilities or area under other contracts,the 8 Baseline Schedule shall be coordinated with the schedules of the other contracts. 9 a. Obtain the schedules of the other appropriate contracts from the City for the 10 preparation and updating of Baseline schedule and make the required changes 11 in his schedule when indicated by changes in corresponding schedules. 12 2. In case of interference between the operations of different contractors,the City will 13 determine the work priority of each contractor and the sequence of work necessary 14 to expedite the completion of the entire Project. 15 a. In such cases,the decision of the City shall be accepted as final. 16 b. The temporary delay of any work due to such circumstances shall not be 17 considered as justification for claims for additional compensation. 18 1.5 SUBMITTALS 19 A. Baseline Schedule 20 1. Submit Schedule in native file format and pdf format as required in the City of Fort 21 Worth Schedule Guidance Document. 22 a. Native file format includes: 23 1) Primavera(P6 or Primavera Contractor) 24 2. Submit draft baseline Schedule to City prior to the pre-construction meeting and 25 bring in hard copy to the meeting for review and discussion. 26 B. Progress Schedule 27 1. Submit progress Schedule in native file format and pdf format as required in the 28 City of Fort Worth Schedule Guidance Document. 29 2. Submit progress Schedule monthly no later than the last day of the month. 30 C. Schedule Narrative 31 I. Submit the schedule narrative in pdf format as required in the City of Fort Worth 32 Schedule Guidance Document. 33 2. Submit schedule narrative monthly no later than the last day of the month. 34 D. Submittal Process 35 1. The City administers and manages schedules through Buzzsaw. 36 2. Contractor shall submit documents as required in the City of Fort Worth Schedule 37 Guidance Document. 38 3. Once the project has been completed and Final Acceptance has been issued by the 39 City, no further progress schedules are required. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July I,2011 01 32 16-5 CONSTRUCTION PROGRESS SCHEDULE Page 5 of 5 1 1.6 ACTION SUBMITTALSJINFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED[ 4 1.9 QUALITY ASSURANCE 5 A. The person preparing and revising the construction Progress Schedule shall be 6 experienced in the preparation of schedules of similar complexity. 7 B. Schedule and supporting documents addressed in this Specification shall be prepared, 8 updated and revised to accurately reflect the performance of the construction. 9 C. Contractor is responsible for the quality of all submittals in this section meeting the 10 standard of care for the construction industry for similar projects. 11 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 12 1.11 FIELD (SITE] CONDITIONS [NOT USED] 13 1.12 WARRANTY [NOT USED[ 14 PART 2- PRODUCTS [NOT USED) 15 PART 3- EXECUTION [NOT USED] 16 END OF SECTION 17 Revision Log DATE NAME SUMMARY OF CHANGE 18 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 32 33-1 PRECONSTRUCTION VIDEO Page I of 2 1 SECTION 0132 33 2 PRECONSTRUCTION VIDEO 3 PART ] - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Administrative and procedural requirements for: 7 a. Preconstruction Videos 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. None. 10 C. Related Specification Sections include, but are not necessarily limited to: 11 1. Division 0 m Bidding Requirements, Contract Forms and Conditions of the Contract 12 2. Division 1 —General Requirements 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Work associated with this Item is considered subsidiary to the various items bid. 16 No separate payment will be allowed for this Item. 17 1.3 REFERENCES [NOT USED] 18 1.4 ADMINISTRATIVE REQUIREMENTS 19 A. Preconstruction Video 20 1. Produce a preconstruction video of the site/alignment, including all areas in the 21 vicinity of and to be affected by construction. 22 a. Provide digital copy of video upon request by the City. 23 2. Retain a copy of the preconstruction video until the end of the maintenance surety 24 period. 25 1.5 SUBMITTALS [NOT USED] 26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 27 1.7 CLOSEOUT SUBMITTALS [NOT USED] 28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29 1.9 QUALITY ASSURANCE [NOT USED] 30 1.10 DELIVERY, STORAGE,AND HANDLING [NOT USED] 31 1.11 FIELD [SITE] CONDITIONS [NOT USED] 32 1.12 WARRANTY [NOT USED) 33 PART 2- PRODUCTS [NOT USED] CITY OF FORT WORTH Mary's Creels Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 013233-2 PRECONS'IRUCTION VIDEO Page 2 of 2 I PART 3- EXECUTION (NOT USED] 2 END OF SECTION 3 Revision Log DATE NAME SUMMARY OF CHANGE 4 CITY OF FORT WORTH Mary's Creek.Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1>2011 01 33 00-1 SUBMITTALS Page 1 of 8 1 SECTION 0133 00 2 SUBMITTALS 3 PARTI - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. General methods and requirements of submissions applicable to the following 7 Work-related submittals: 8 a. Shop Drawings 9 b. Product Data(including Standard Product List submittals) 10 c. Samples 11 d. Mock Ups 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include,but are not necessarily limited to: 15 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 16 2. Division 1 —General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED[ 22 1.4 ADMINISTRATIVE REQUIREMENTS 23 A. Coordination 24 1. Notify the City in writing,at the time of submittal,of any deviations in the 25 submittals from the requirements of the Contract Documents. 26 2. Coordination of Submittal Times 27 a. Prepare,prioritize and transmit each submittal sufficiently in advance of 28 performing the related Work or other applicable activities,or within the time 29 specified in the individual Work Sections,of the Specifications. 30 b. Contractor is responsible such that the installation will not be delayed by 31 processing times including,but not limited to: 32 a) Disapproval and resubmittal(if required) 33 b) Coordination with other submittals 34 c) Testing 35 d) Purchasing 36 e) Fabrication 37 f) Delivery 38 g) Similar sequenced activities 39 c. No extension of time will be authorized because of the Contractor's failure to 40 transmit submittals sufficiently in advance of the Work. CITY OF PORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 013300-2 SUBMITTALS Page 2 of 8 1 d. Make submittals promptly in accordance with approved schedule,and in such 2 sequence as to cause no delay in the Work or in the work of any other 3 contractor. 4 B. Submittal Numbering 5 1. When submitting shop drawings or samples,utilize a 9-character submittal cross- 6 reference identification numbering system in the following manner: 7 a. Use the first 6 digits of the applicable Specification Section Number. 8 b. For the next 2 digits number use numbers 01-99 to sequentially number each 9 initial separate item or drawing submitted under each specific Section number. 10 c. Last use a letter,A-Z, indicating the resubmission of the same drawing(i.e. 11 A=2nd submission, B3rd submission,C=4th submission, etc.). A typical 12 submittal number would be as follows: 13 14 03 30 00-08-B 15 16 1) 03 30 00 is the Specification Section for Concrete 17 2) 08 is the eighth initial submittal under this Specification Section 18 3) B is the third submission(second resubmission)of that particular shop 19 drawing 20 C. Contractor Certification 21 1. Review shop drawings, product data and samples,including those by 22 subcontractors,prior to submission to determine and verify the following: 23 a. Field measurements 24 b. Field construction criteria 25 c. Catalog numbers and similar data 26 d. Conformance with the Contract Documents 27 2. Provide each shop drawing,sample and product data submitted by the Contractor 28 with a Certification Statement affixed including: 29 a. The Contractor's Company name 30 b. Signature of submittal reviewer 31 c. Certification Statement 32 1) "By this submittal, I hereby represent that I have determined and verified 33 field measurements, field construction criteria,materials,dimensions, 34 catalog numbers and similar data and I have checked and coordinated each 35 item with other applicable approved shop drawings." 36 D. Submittal Format 37 1. Fold shop drawings larger than 8 %:inches x 11 inches to 8 % inches x 11 inches. 38 2. Bind shop drawings and product data sheets together. 39 3. Order 40 a. Cover Sheet 41 1) Description of Packet 42 2) Contractor Certification 43 b. List of items/Table of Contents 44 c. Product Data/Shop Drawings/Samples/Calculations 45 E. Submittal Content 46 1. The date of submission and the dates of any previous submissions CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 013300-3 SUBMITTALS Page 3 of 8 1 2. The Project title and number 2 3. Contractor identification 3 4. The names of 4 a. Contractor 5 b. Supplier 6 c. Manufacturer 7 5. Identification of the product,with the Specification Section number,page and 8 paragraph(s) 9 6. Field dimensions,clearly identified as such 10 7. Relation to adjacent or critical features of the Work or materials 11 8. Applicable standards, such as ASTM or Federal Specification numbers 12 9. Identification by highlighting of deviations from Contract Documents 13 10. Identification by highlighting of revisions on resubmittals 14 It. An 8-inch x 3-inch blank space for Contractor and City stamps 15 F. Shop Drawings 16 1. As specified in individual Work Sections includes,but is not necessarily limited to: 17 a. Custom-prepared data such as fabrication and erection/installation (working) 18 drawings 19 b. Scheduled information 20 c. Setting diagrams 21 d. Actual shopwork manufacturing instructions 22 e. Custom templates 23 f. Special wiring diagrams 24 g. Coordination drawings 25 h. Individual system or equipment inspection and test reports including: 26 1) Performance curves and certifications 27 i. As applicable to the Work 28 2, Details 29 a. Relation of the various parts to the main members and lines of the structure 30 b. Where correct fabrication of the Work depends upon field measurements 31 1) Provide such measurements and note on the drawings prior to submitting 32 for approval. 33 G. Product Data 34 1. For submittals of product data for products included on the City's Standard Product 35 List,clearly identify each item selected for use on the Project. 36 2. For submittals of product data for products not included on the City's Standard 37 Product List, submittal data may include,but is not necessarily limited to: 38 a. Standard prepared data for manufactured products(sometimes referred to as 39 catalog data) 40 1) Such as the manufacturer's product specification and installation 41 instructions 42 2) Availability of colors and patterns 43 3) Manufacturer's printed statements of compliances and applicability 44 4) Roughing-in diagrams and templates 45 5) Catalog cuts 46 6) Product photographs CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised December 20.2012 013300-4 SUBMITTALS Page 4 of 8 1 7) Standard wiring diagrams 2 8) Printed performance curves and operational-range diagrams 3 9) Production or quality control inspection and test reports and certifications 4 10) Mill reports 5 11) Product operating and maintenance instructions and recommended 6 spare-parts listing and printed product warranties 7 12) As applicable to the Work 8 H. Samples 9 1. As specified in individual Sections, include,but are not necessarily limited to: 10 a. Physical examples of the Work such as: 11 1) Sections of manufactured or fabricated Work 12 2) Small cuts or containers of materials 13 3) Complete units of repetitively used products color/texture/pattern swatches 14 and range sets 15 4) Specimens for coordination of visual effect 16 5) Graphic symbols and units of Work to be used by the City for independent 17 inspection and testing,as applicable to the Work 18 I. Do not start Work requiring a shop drawing,sample or product data nor any material to 19 be fabricated or installed prior to the approval or qualified approval of such item. 20 1. Fabrication performed,materials purchased or on-site construction accomplished 21 which does not conform to approved shop drawings and data is at the Contractor's 22 risk. 23 2. The City will not be liable for any expense or delay due to corrections or remedies 24 required to accomplish conformity. 25 3. Complete project Work,materials, fabrication,and installations in conformance 26 with approved shop drawings, applicable samples, and product data. 27 J. Submittal Distribution 28 1. Electronic Distribution 29 a. Confirm development of Project directory for electronic submittals to be 30 uploaded to City's Buzzsaw site,or another external FTP site approved by the 31 City. 32 b. Shop Drawings 33 1) Upload submittal to designated project directory and notify appropriate 34 City representatives via email of submittal posting. 35 2) Hard Copies 36 a) 3 copies for all submittals 37 b) If Contractor requires more than 1 hard copy of Shop Drawings 38 returned,Contractor shall submit more than the number of copies listed 39 above. 40 c. Product Data 41 1) Upload submittal to designated project directory and notify appropriate 42 City representatives via email of submittal posting. 43 2) Hard Copies 44 a) 3 copies for all submittals 45 d. Samples 46 1) Distributed to the Project Representative 47 2. Hard Copy Distribution(if required in lieu of electronic distribution) CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 013300-5 SUBMITTALS Page 5 of 8 1 a. Shop Drawings 2 1) Distributed to the City 3 2) Copies 4 a) 8 copies for mechanical submittals 5 b) 7 copies for all other submittals 6 c) If Contractor requires more than 3 copies of Shop Drawings returned, 7 Contractor shall submit more than the number of copies listed above. 8 b. Product Data 9 1) Distributed to the City 10 2) Copies 11 a) 4 copies 12 c. Samples 13 1) Distributed to the Project Representative 14 2) Copies 15 a) Submit the number stated in the respective Specification Sections. 16 3. Distribute reproductions of approved shop drawings and copies of approved 17 product data and samples,where required,to the job site file and elsewhere as 18 directed by the City. 19 a. Provide number of copies as directed by the City but not exceeding the number 20 previously specified. 21 K. Submittal Review 22 1. The review of shop drawings,data and samples will be for general conformance 23 with the design concept and Contract Documents. This is not to be construed as: 24 a. Permitting any departure from the Contract requirements 25 b. Relieving the Contractor of responsibility for any errors, including details, 26 dimensions,and materials 27 c. Approving departures from details furnished by the City, except as otherwise 28 provided herein 29 2. The review and approval of shop drawings,samples or product data by the City 30 does not relieve the Contractor from his/her responsibility with regard to the 31 fulfillment of the terms of the Contract. 32 a. All risks of error and omission are assumed by the Contractor,and the City will 33 have no responsibility therefore. 34 3. The Contractor remains responsible for details and accuracy, for coordinating the 35 Work with all other associated work and trades, for selecting fabrication processes, 36 for techniques of assembly and for performing Work in a safe manner. 37 4. If the shop drawings,data or samples as submitted describe variations and show a 38 departure from the Contract requirements which City finds to be in the interest of 39 the City and to be so minor as not to involve a change in Contract Price or time for 40 performance, the City may return the reviewed drawings without noting an 41 exception. 42 5. Submittals will be returned to the Contractor under 1 of the following codes: 43 a. Code 1 44 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or 45 comments on the submittal. 46 a) When returned under this code the Contractor may release the 47 equipment and/or material for manufacture. 48 b. Code 2 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 013300-6 SUBMITTALS Page 6 of 8 1 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of 2 the notations and comments IS NOT required by the Contractor. 3 a) The Contractor may release the equipment or material for manufacture; 4 however,all notations and comments must be incorporated into the 5 final product. 6 c. Code 3 7 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is 8 assigned when notations and comments are extensive enough to require a 9 resubmittal of the package. 10 a) The Contractor may release the equipment or material for manufacture; 11 however,all notations and comments must be incorporated into the 12 final product. 13 b) This resubmittal is to address all comments,omissions and 14 non-conforming items that were noted. 15 c) Resubmittal is to be received by the City within 15 Calendar Days of 16 the date of the City's transmittal requiring the resubmittal. 17 d. Code 4 18 1) "NOT APPROVED" is assigned when the submittal does not meet the 19 intent of the Contract Documents. 20 a) The Contractor must resubmit the entire package revised to bring the 21 submittal into conformance. 22 b) It may be necessary to resubmit using a different manufacturer/vendor 23 to meet the Contract Documents. 24 6. Resubmittals 25 a. Handled in the same manner as first submittals 26 1) Corrections other than requested by the City 27 2) Marked with revision triangle or other similar method 28 a) At Contractor's risk if not marked 29 b. Submittals for each item will be reviewed no more than twice at the City's 30 expense. 31 1) All subsequent reviews will be performed at times convenient to the City 32 and at the Contractor's expense,based on the City's or City 33 Representative's then prevailing rates. 34 2) Provide Contractor reimbursement to the City within 30 Calendar Days for 35 all such fees invoiced by the City. 36 c. The need for more than 1 resubmission or any other delay in obtaining City's 37 review of submittals,will not entitle the Contractor to an extension of Contract 38 Time. 39 7. Partial Submittals 40 a. City reserves the right to not review submittals deemed partial, at the City's 41 discretion. 42 b. Submittals deemed by the City to be not complete will be returned to the 43 Contractor,and will be considered "Not Approved"until resubmitted. 44 e. The City may at its option provide a list or mark the submittal directing the 45 Contractor to the areas that are incomplete. 46 8. If the Contractor considers any correction indicated on the shop drawings to 47 constitute a change to the Contract Documents,then written notice must be 48 provided thereof to the City at least 7 Calendar Days prior to release for 49 manufacture. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENT'S City Project No.01239 Revised December 20,2012 013300-7 SUBMITTALS Page 7 of 8 1 9. When the shop drawings have been completed to the satisfaction of the City, the 2 Contractor may carry out the construction in accordance therewith and no further 3 changes therein except upon written instructions from the City. 4 10. Each submittal,appropriately coded,will be returned within 30 Calendar Days 5 following receipt of submittal by the City. 6 L. Mock ups 7 1. Mock Up units as specified in individual Sections, include,but are not necessarily 8 limited to,complete units of the standard of acceptance for that type of Work to be 9 used on the Project. Remove at the completion of the Work or when directed. 10 M. Qualifications 11 1. if specifically required in other Sections of these Specifications,submit a F.E. 12 Certification for each item required. 13 N. Request for Information(RFI) 14 1. Contractor Request for additional information 15 a. Clarification or interpretation of the contract documents 16 b. When the Contractor believes there is a conflict between Contract Documents 17 c. When the Contractor believes there is a conflict between the Drawings and 18 Specifications 19 1) Identify the conflict and request clarification 20 2. Use the Request for Information(RFI) form provided by the City. 21 3. Numbering of RFI 22 a. Prefix with"RFI"followed by series number,"-xxx",beginning with"01"and 23 increasing sequentially with each additional transmittal. 24 4. Sufficient information shall be attached to permit a written response without further 25 information. 26 5. The City will log each request and will review the request. 27 a. If review of the project information request indicates that a change to the 28 Contract Documents is required,the City will issue a Field Order or Change 29 Order,as appropriate. 30 1.5 SUBMITTALS [NOT USED] 31 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 32 1.7 CLOSEOUT SUBMITTALS [NOT USED] 33 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 34 1.9 QUALITY ASSURANCE [NOT USED] 35 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 36 1.11 FIELD [SITE] CONDITIONS [NOT USED] 37 1.12 WARRANTY [NOT USED] CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 013300-8 SUBMITTALS Page 8 of 8 PART 2- PRODUCTS [NOT USED] 2 PART 3- EXECUTION [NOT USED] 3 END OF SECTION 4 Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D.Johnson I.4.K.8.Working Days modified to Calendar Days 5 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 013513-1 SPECIAL PROJECT PROCEDURES Page I of 8 1 SECTION 0135 13 2 SPECIAL PROJECT PROCEDURES 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedures for special project circumstances that includes, but is not limited to: 7 a. Coordination with the Texas Department of Transportation 8 b. Work near High Voltage Lines 9 c. Confined Space Entry Program 10 d. Air Pollution Watch Days I I e. Use of Explosives, Drop Weight, Etc. 12 f. Water Department Notification 13 g. Public Notification Prior to Beginning Construction 14 h. Coordination with United States Army Corps of Engineers 15 i. Coordination within Railroad permits areas 16 j. Dust Control 17 k. Employee Parking 18 B. Deviations from this City of Fort Worth Standard Specification 19 1. None. 20 C. Related Specification Sections include,but are not necessarily limited to: 21 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 22 2. Division 1 —General Requirements 23 3. Section 33 12 25 Connection to Existing Water Mains 24 1.2 PRICE AND PAYMENT PROCEDURES 25 A. Measurement and Payment 26 1. Coordination within Railroad permit areas 27 a. Measurement 28 1) Measurement for this Item will be by lump sum. 29 b. Payment 30 1) The work performed and materials furnished in accordance with this Item 31 will be paid for at the lump sum price bid for Railroad Coordination. 32 c. The price bid shall include: 33 1) Mobilization 34 2) Inspection 35 3) Safety training 36 4) Additional Insurance 37 5) Insurance Certificates 38 6) Other requirements associated with general coordination with Railroad, 39 including additional employees required to protect the right-of-way and 40 property of the Railroad from damage arising out of and/or from the 41 construction of the Project. 42 2. Railroad Flagmen CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 0135 13-2 SPECIAL PROJECT PROCEDURES Page 2 of 8 1 a. Measurement 2 1) Measurement for this Item will be per working day. 3 b. Payment 4 1) The work performed and materials furnished in accordance with this Item 5 will be paid for each working day that Railroad Flagmen are present at the 6 Site. 7 c. The price bid shall include: 8 1) Coordination for scheduling flagmen 9 2) Flagmen 10 3) Other requirements associated with Railroad 11 3. All other items 12 a. Work associated with these Items is considered subsidiary to the various Items 13 bid. No separate payment will be allowed for this Item. 14 1.3 REFERENCES 15 A. Reference Standards 16 1. Reference standards cited in this Specification refer to the current reference 17 standard published at the time of the latest revision date logged at the end of this 18 Specification,unless a date is specifically cited. 19 2. Health and Safety Code,Title 9. Safety, Subtitle A. Public Safety, Chapter 752. 20 High Voltage Overhead Lines. 21 3. North Central Texas Council of Governments(NCTCOG)—Clean Construction 22 Specification 23 1.4 ADMINISTRATIVE REQUIREMENTS 24 A. Coordination with the Texas Department of Transportation 25 1. When work in the right-of-way which is under the jurisdiction of the Texas 26 Department of Transportation(TxDOT): 27 a. Notify the Texas Department of Transportation prior to commencing any work 28 therein in accordance with the provisions of the permit 29 b. All work performed in the TxDOT right-of-way shall be perforated in 30 compliance with and subject to approval from the Texas Department of 31 Transportation 32 B. Work near High Voltage Lines 33 1. Regulatory Requirements 34 a. All Work near High Voltage Lines(more than 600 volts measured between 35 conductors or between a conductor and the ground)shall be in accordance with 36 Health and Safety Code,Title 9, Subtitle A,Chapter 752. 37 2. Warning sign 38 a. Provide sign of sufficient size meeting all OSHA requirements. 39 3. Equipment operating within 10 feet of high voltage lines will require the following 40 safety features 41 a. Insulating cage-type of guard about the boom or arm 42 b. Insulator links on the lift hook connections for back hoes or dippers 43 c. Equipment must meet the safety requirements as set forth by OSHA and the 44 safety requirements of the owner of the high voltage lines 45 4. Work within 6 feet of high voltage electric lines CITY OF FORT WORTH Mary's Creek Recycling Center Trcc Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 0133 t3-3 SPECIAL PROJECT PROCEDURES Page 3 of 8 a. Notification shall be given to: 2 1) The power company(example: ONCOR) 3 a) Maintain an accurate log of all such calls to power company and record 4 action taken in each case. 5 b. Coordination with power company 6 1) After notification coordinate with the power company to: 7 a) Erect temporary mechanical barriers,de-energize the lines,or raise or 8 lower the lines 9 c. No personnel may work within 6 feet of a high voltage line before the above 10 requirements have been met. 11 C. Confined Space Entry Program t2 1. Provide and follow approved Confined Space Entry Program in accordance with 1.3 OSHA requirements. 14 2. Confined Spaces include: 15 a. Manholes 16 b. All other confined spaces in accordance with OSHA's Permit Required for 17 Confined Spaces 18 D. Air Pollution Watch Days 19 1. General 20 a. Observe the following guidelines relating to working on City construction sites 21 on days designated as"AIR POLLUTION WATCH DAYS". 22 b. Typical Ozone Season ,23 1) May I through October 31. 24 c. Critical Emission Time 25 1) 6:00 a.m. to 10:00 a.m. 26 2. Watch Days 27 a. The Texas Commission on Environmental Quality(TCEQ), in coordination 28 with the National Weather Service, will issue the Air Pollution Watch by 3:00 29 p.m. on the afternoon prior to the WATCH day. 30 b. Requirements 31 1) Begin work after 10:00 a.m. whenever construction phasing requires the 32 use of motorized equipment for periods in excess of 1 hour. 33 2) However,the Contractor may begin work prior to 10:00 a.m. if: 34 a) Use of motorized equipment is less than 1 hour,or 35 b) If equipment is new and certified by EPA as "Low Emitting",or 36 equipment burns Ultra Low Sulfur Diesel (ULSD), diesel emulsions,or 37 alternative fuels such as CNG. 38 E. TCEQ Air Permit 39 1. Obtain TCEQ Air Permit for construction activities per requirements of TCEQ. 40 F. Use of Explosives, Drop Weight, Etc. 41 1. When Contract Documents permit on the project the following will apply: 42 a. Public Notification 43 1) Submit notice to City and proof of adequate insurance coverage, 24 hours 44 prior to commencing. 45 2) Minimum 24 hour public notification in accordance with Section 0131 13 46 G. Water Department Coordination CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 0135 13-4 SPECIAL PROJECT PROCEDURES Page 4 of 8 1 I. During the construction of this project, it will be necessary to deactivate,for a 2 period of time,existing lines. The Contractor shall be required to coordinate with 3 the Water Department to determine the best times for deactivating and activating 4 those lines. 5 2. Coordinate any event that will require connecting to or the operation of an existing 6 City water line system with the City's representative. 7 a. Coordination shall be in accordance with Section 33 12 25. 8 b. If needed,obtain a hydrant water meter from the Water Department for use 9 during the life of named project. 10 c. In the event that a water valve on an existing live system be turned off and on 11 to accommodate the construction of the project is required,coordinate this 12 activity through the appropriate City representative. 13 1) Do not operate water line valves of existing water system. 14 a) Failure to comply will render the Contractor in violation of Texas Penal 15 Code Title 7, Chapter 28.03 (Criminal Mischieo and the Contractor 16 will be prosecuted to the full extent of the law. 17 b) In addition,the Contractor will assume all liabilities and 18 responsibilities as a result of these actions. 19 H. Public Notification Prior to Beginning Construction 20 1. Prior to beginning construction on any black in the project, on a block by black 21 basis, prepare and deliver a notice or flyer of the pending construction to the front 22 door of each residence or business that will be impacted by construction.The notice 23 shall be prepared as follows: 24 a. Post notice or flyer 7 days prior to beginning any construction activity on each 25 block in the project area. 26 1) Prepare flyer on the Contractor's letterhead and include the following 27 information: 28 a) Name of Project 29 b) City Project No(CPN) 30 c) Scope of Project(i.e. type of construction activity) 31 d) Actual construction duration within the block 32 e) Name of the contractor's foreman and phone number 33 f) Name of the City's inspector and phone number 34 g) City's after-hours phone number 35 2) A sample of the `pre-construction notification' flyer is attached as Exhibit 36 A. 37 3) Submit schedule showing the construction start.and finish time for each 38 block of the project to the inspector. 39 4) Deliver flyer to the City Inspector for review prior to distribution. 40 b. No construction will be allowed to begin on any block until the flyer is 41 delivered to all residents of the block. 42 I. Public Notification of Temporary Water Service Interruption during Construction 43 1. In the event it becomes necessary to temporarily shut down water service to 44 residents or businesses during construction,prepare and deliver a notice or flyer of 45 the pending interruption to the front door of each affected resident. 46 2. Prepared notice as follows: 47 a. The notification or flyer shall be posted 24 hours prior to the temporary 48 interruption. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised Dmetnbcr 20,2012 0135 13-5 SPECIAL PROJECT PROCEDURES Page 5 of 8 I b. Prepare flyer on the contractor's letterhead and include the following 2 information: 3 1) Name of the project 4 2) City Project Number 5 3) Date of the interruption of service 6 4) Period the interruption will take place 7 5) Name of the contractor's foreman and phone number 8 6) Name of the City's inspector and phone number 9 c. A sample of the temporary water service interruption notification is attached as 10 Exhibit B. 11 d. Deliver a copy of the temporary interruption notification to the City inspector 12 for review prior to being distributed. 13 e. No interruption of water service can occur until the flyer has been delivered to 14 all affected residents and businesses. 15 f. Electronic versions of the sample flyers can be obtained from the Project 16 Construction Inspector. 17 J. Coordination with United States Army Corps of Engineers(USACE) 18 1. At locations in the Project where construction activities occur in areas where 19 USACE permits are required, meet all requirements set forth in each designated 20 permit. 21 K. Coordination within Railroad Permit Areas 22 1. At locations in the project where construction activities occur in areas where 23 railroad permits are required, meet all requirements set forth in each designated 24 railroad permit. This includes,but is not limited to,provisions for: 25 a. Flagmen 26 b. Inspectors 27 c. Safety training 28 d. Additional insurance 29 e. Insurance certificates 30 f. Other employees required to protect the right-of-way and property of the 31 Railroad Company from damage arising out of and/or from the construction of 32 the project. Proper utility clearance procedures shall be used in accordance 33 with the permit guidelines. 34 2. Obtain any supplemental information needed to comply with the railroad's 35 requirements. 36 3. Railroad Flagmen 37 a. Submit receipts to City for verification of working days that railroad flagmen 38 were present on Site. 39 L. Dust Control 40 1. Use acceptable measures to control dust at the Site. 41 a. If water is used to control dust,capture and properly dispose of waste water. 42 b. If wet saw cutting is performed,capture and properly dispose of slurry. 43 M. Employee Parking 44 1. Provide parking for employees at locations approved by the City. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 013513.6 SPECIAL PROJECT PROCEDURES Page 6 of 8 1 1.5 SUBMITTALS [NOT USED] 2 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 5 1.9 QUALITY ASSURANCE [NOT USED] 6 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 7 1.11 FIELD [SITE] CONDITIONS [NOT USED] 8 1.12 WARRANTY [NOT USED] 9 PART 2- PRODUCTS [NOT USED] 10 PART 3- EXECUTION [NOT USED] I i END OF SECTION 12 Revision Log DATE NAME SUMMARY OF CHANGE 1.4.13—Added requirement of compliance with Health and Safety Code,Title 9. 8/3112012 D.Johnson Safety,Subtitle A.Public Safety,Chapter 752.High Voltage Overhead Lines. 1.4.E—Added Contractor responsibility for obtaining a TCEQ Air Permit 13 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 0135 13-7 SPECLkL PROJECT PROCEDURES Page 7 of 8 1 EXHIBIT A 2 (To be printed on Contractor's Letterhead) 3 4 5 6 Date: 7 8 CPN No.: 9 Project Name: 10 Mapsco Location: i I Limits of Construction: 12 13 14 15 16 17 THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT 18 WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR 19 PROPERTY. 20 21 CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE 22 OF THIS NOTICE. 23 24 IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER 25 ISSUE, PLEASE CALL: 26 27 28 Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.> 29 30 OR 31 32 Mr. <CITY INSPECTOR> AT <TELEPHONE NO.> 33 34 AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306 35 36 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL 37 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 013513.8 SPECIAL PROJECT PROCEDURES Page 8 of 8 I EXHIBIT B 2 FFORT WORTH �g>Kfl.IGII.IK]L NOTICE OF TEMPORARY WATER SERVICE INTERRUPTION DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR WATER SERVICE WILL BE INTERRUPTED ON BETWEEN THE HOURS OF AND IF YOU HAVE QUESTIONS ABOUT THIS SHUT-OUT,PLEASE CALL: MR. AT (CONTRACTORS SUPERINTENDENT) (TELEPHONE NUMBER) OR MR. AT (CITY INSPECTOR) (TELEPHONE NUMBER) THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE. THANK YOU, .CONTRACTOR CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised December 20,2012 0135 13-8 SPECIAL PROJECT PROCEDURES Page 8 of 8 EXHIBIT B FORT WORTH DOE Ito.Xj= pmJ"t : NOTICE OF TEMPORARY WATER SERVICE INTERRUPTION DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR WATER SERVICE WILL BE INTERRUPTED ON BETWEEN THE HOURS OF AND IF YOU HAVE QUESTIONS ABOUT THIS SHUT-OUT,PLEASE CALL: M R. AT (CONTRACTORS SUPERINTENDENT) (TELEPHONE NUMBER) OR MR. AT (CITY INSPECTOR) (TELEPHONE NUMBER) THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE. THANK YOU, CONTRACTOR 4 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 01 45 23-1 TESTING AND INSPECTION SERVICES Pagel of 2 I SECTION 0145 23 2 TESTING AND INSPECTION SERVICES 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Testing and inspection services procedures and coordination 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division 1 General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various Items bid. 15 No separate payment will be allowed for this Item. 16 a. Contractor is responsible for performing,coordinating,and payment of all 17 Quality Control testing. 18 b. City is responsible for performing and payment for first set of Quality 19 Assurance testing. 20 1) If the first Quality Assurance test performed by the City fails,the 21 Contractor is responsible for payment of subsequent Quality Assurance 22 testing until a passing test occurs. 23 a) Final acceptance will not be issued by City until all required payments 24 for testing by Contractor have been paid in full. 25 1.3 REFERENCES [NOT USED] 26 1.4 ADMINISTRATIVE REQUIREMENTS 27 A. Testing 28 1. Complete testing in accordance with the Contract Documents. 29 2. Coordination 30 a. When testing is required to be performed by the City, notify City, sufficiently 31 in advance,when testing is needed. 32 b. When testing is required to be completed by the Contractor, notify City, 33 sufficiently in advance, that testing will be performed. 34 3. Distribution of Testing Reports 35 a. Electronic Distribution 36 1) Confirm development of Project directory for electronic submittals to be 37 uploaded to City's Buzzsaw site,or another external FTP site approved by 38 the City. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 014523.2 TESTING AND INSPECTION SERVICES Page 2 of 2 1 2) Upload test reports to designated project directory and notify appropriate 2 City representatives via email of submittal posting. 3 3) Hard Copies 4 a) I copy for all submittals submitted to the Project Representative 5 b. Hard Copy Distribution(if required in lieu of electronic distribution) 6 1) Tests performed by City 7 a) Distribute 1 hard copy to the Contractor 8 2) Tests performed by the Contractor 9 a) Distribute 3 hard copies to City's Project Representative 10 4. Provide City's Project Representative with trip tickets for each delivered load of 1 I Concrete or Lime material including the following information: 12 a. Name of pit 13 b. Date of delivery 14 c. Material delivered 15 B. Inspection 16 1. Inspection or lack of inspection does not relieve the Contractor from obligation to 17 perform work in accordance with the Contract Documents. 18 1.5 SUBMITTALS [NOT USED] 19 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 20 1.7 CLOSEOUT SUBMITTALS (NOT USED] 21 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 22 1.9 QUALITY ASSURANCE [NOT USED) 23 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 24 1.11 FIELD [SITE] CONDITIONS [NOT USED] 25 1.12 WARRANTY [NOT USED] 26 PART 2- PRODUCTS [NOT USED] 27 PART 3- EXECUTION [NOT USED] 28 END OF SECTION 29 Revision Log DATE NAME SUMMARY OF CHANGE 30 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 50 00-1 TEMPORARY FACILITIES AND CONTROLS Pagel of 4 I SECTION 0150 00 2 TEMPORARY FACILITIES AND CONTROLS 3 PARTI - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 I. Provide temporary facilities and controls needed for the Work including,but not 7 necessarily limited to: 8 a. Temporary utilities 9 b. Sanitary facilities 10 c. Storage Sheds and Buildings I l d. Dust control 12 e. Temporary fencing of the construction site 13 B. Deviations from this City of Fort Worth Standard Specification 14 1. None. 15 C. Related Specification Sections include, but are not necessarily limited to: 16 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 17 2. Division 1 —General Requirements 18 1.2 PRICE AND PAYMENT PROCEDURES 19 A. Measurement and Payment 20 1. Work associated with this Item is considered subsidiary to the various Items bid. 21 No separate payment will be allowed for this Item. 22 1.3 REFERENCES [NOT USED] 23 1.4 ADMINISTRATIVE REQUIREMENTS 24 A. Temporary Utilities 25 1. Obtaining Temporary Service 26 a. Make arrangements with utility service companies for temporary services. 27 b. Abide by rules and regulations of utility service companies or authorities 28 having jurisdiction. 29 c. Be responsible for utility service costs until Work is approved for Final 30 Acceptance. 31 1) Included are fuel,power, light,heat and other utility services necessary for 32 execution,completion,testing and initial operation of Work. 33 2. Water 34 a. Contractor to provide water required for and in connection with Work to be 35 performed and for specified tests of piping,equipment,devices or other use as 36 required for the completion of the Work. 37 b. Provide and maintain adequate supply of potable water for domestic 38 consumption by Contractor personnel and City's Project Representatives. 39 c. Coordination 40 1) Contact City 1 week before water for construction is desired CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised July 1.2011 01 50 00-2 TEMPORARY FACILITIES AND CONTROLS Page 2 of 4 1 d. Contractor Payment for Construction Water 2 1) Obtain construction water meter from City for payment as billed by City's 3 established rates. 4 3. Electricity and Lighting 5 a. Provide and pay for electric powered service as required for Work, including 6 testing of Work. 7 1) Provide power for lighting,operation of equipment,or other use. 8 b. Electric power service includes temporary power service or generator to 9 maintain operations during scheduled shutdown. 10 4. Telephone 11 a. Provide emergency telephone service at Site for use by Contractor personnel 12 and others performing work or furnishing services at Site. 13 5. Temporary Heat and Ventilation 14 a. Provide temporary heat as necessary for protection or completion of Work. 15 b. Provide temporary heat and ventilation to assure safe working conditions. 16 B. Sanitary Facilities 17 1. Provide and maintain sanitary facilities for persons on Site. 18 a. Comply with regulations of State and local departments of health. 19 2. Enforce use of sanitary facilities by construction personnel at job site. 20 a. Enclose and anchor sanitary facilities. 21 b. No discharge will be allowed from these facilities. 22 c. Collect and store sewage and waste so as not to cause nuisance or health 23 problem. 24 d. Haul sewage and waste off-site at no less than weekly intervals and properly 25 dispose in accordance with applicable regulation. 26 3. Locate facilities near Work Site and keep clean and maintained throughout Project. 27 4. Remove facilities at completion of Project 28 C. Storage Sheds and Buildings 29 1. Provide adequately ventilated,watertight,weatherproof storage facilities with floor 30 above ground level for materials and equipment susceptible to weather damage. 31 2. Storage of materials not susceptible to weather damage may be on blocks off 32 ground. 33 3. Store materials in a neat and orderly manner. 34 a. Place materials and equipment to permit easy access for identification, 35 inspection and inventory. 36 4. Equip building with lockable doors and lighting, and provide electrical service for 37 equipment space heaters and heating or ventilation as necessary to provide storage 38 environments acceptable to specified manufacturers. 39 5. Fill and grade site for temporary structures to provide drainage away from 40 temporary and existing buildings. 41 6. Remove building from site prior to Final Acceptance. 42 D. Temporary Fencing 43 1. Provide and maintain for the duration or construction when required in contract 44 documents 45 E. Dust Control CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 5000-3 TEMPORARY FACILITIES AND CONTROLS Page 3 of 4 1 1. Contractor is responsible for maintaining dust control through the duration of the 2 project. 3 a. Contractor remains on-call at all times 4 b. Must respond in a timely manner 5 F. Temporary Protection of Construction 6 1. Contractor or subcontractors are responsible for protecting Work from damage due 7 to weather. 8 1.5 SUBMITTALS [NOT USED] 9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 10 1.7 CLOSEOUT SUBMITTALS [NOT USED] 11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 12 1.9 QUALITY ASSURANCE [NOT USED] 13 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 14 1.11 FIELD [SITE) CONDITIONS [NOT USED) 15 1.12 WARRANTY [NOT USED] 16 PART 2- PRODUCTS [NOT USED] 17 PART 3- EXECUTION [NOT USED] 18 3.1 INSTALLERS [NOT USED] 19 3.2 EXAMINATION [NOT USED] 20 3.3 PREPARATION [NOT USED] 21 3.4 INSTALLATION 22 A. Temporary Facilities 23 1. Maintain all temporary facilities for duration of construction activities as needed. 24 3.5 [REPAIR]/ [RESTORATION] 25 3.6 RE-INSTALLATION 26 3.7 FIELD 10R) SITE QUALITY CONTROL [NOT USED] 27 3.8 SYSTEM STARTUP[NOT USED] 28 3.9 ADJUSTING [NOT USED] 29 3.10 CLEANING [NOT USED] 30 3.11 CLOSEOUT ACTIVITIES 31 A. Temporary Facilities CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revjsed July 1.2011 01 5000-4 TEMPORARY FACILITIES AND CONTROLS Page 4 of 4 1 1. Remove all temporary facilities and restore area after completion of the Work,to a 2 condition equal to or better than prior to start of Work. 3 3.12 PROTECTION [NOT USED] 4 3.13 MAINTENANCE [NOT USED] 5 3.14 ATTACHMENTS [NOT USED] 6 END OF SECTION 7 Revision Log DATE NAME SUMMARY OF CHANGE 8 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 33 26-I STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL. Page I of 3 I SECTION 0155 26 2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL. 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Administrative procedures for: 7 a. Street Use Permit 8 b. Modification of approved traffic control 9 c. Removal of Street Signs 10 B. Deviations from this City of Fort Worth Standard Specification I 1 1. None. 12 C. Related Specification Sections include,but are not necessarily limited to: 13 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 14 2. Division 1 —General Requirements 15 3. Section 34 71 13 Traffic Control 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 I. Work associated with this Item is considered subsidiary to the various Items bid. 19 No separate payment will be allowed for this Item. 20 1.3 REFERENCES 21 A. Reference Standards 22 1. Reference standards cited in this specification refer to the current reference standard 23 published at the time of the latest revision date logged at the end of this 24 specification,unless a date is specifically cited. 25 2. Texas Manual on Uniform Traffic Control Devices(TMUTCD). 26 1.4 ADMINISTRATIVE REQUIREMENTS 27 A. Traffic Control 28 1. General 29 a. When traffic control plans are included in the Drawings,provide Traffic 30 Control in accordance with Drawings and Section 34 71 13. 31 b. When traffic control plans are not included in the Drawings, prepare traffic 32 control plans in accordance with Section 34 71 13 and submit to City for 33 review. 34 1) Allow minimum 10 working days for review of proposed Traffic Control. 35 B. Street Use Permit 36 1. Prior to installation of Traffic Control,a City Street Use Permit is required. 37 a. To obtain Street Use Permit,submit Traffic Control Plans to City 38 Transportation and Public Works Department. CITY OF FORT WORTH Mary's Cm-ck Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 5526-2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 2 of 3 1 1) Allow a minimum of 5 working days for permit review. 2 2) Contractor's responsibility to coordinate review of Traffic Control plans for 3 Street Use Permit,such that construction is not delayed. 4 C. Modification to Approved Traffic Control 5 1. Prior to installation traffic control: 6 a. Submit revised traffic control plans to City Department Transportation and 7 Public Works Department. 8 1) Revise Traffic Control plans in accordance with Section 34 71 13. 9 2) Allow minimum 5 working days for review of revised Traffic Control. 10 3) It is the Contractor's responsibility to coordinate review of Traffic Control 11 plans for Street Use Permit, such that construction is not delayed. 12 D. Removal of Street Sign 13 1. If it is determined that a street sign must be removed for construction, then contact 14 City Transportation and Public Works Department, Signs and Markings Division to 15 remove the sign. 16 E. Temporary Signage 17 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting 18 requirements of the latest edition of the Texas Manual on Uniform Traffic Control 19 Devices(MUTCD). 20 2. Install temporary sign before the removal of permanent sign. 21 3. When construction is complete, to the extent that the permanent sign can be 22 reinstalled,contact the City Transportation and Public Works Department, Signs 23 and Markings Division,to reinstall the permanent sign. 24 F. Traffic Control Standards 25 1. Traffic Control Standards can be found on the City's Buzzsaw website. 26 1.5 SUBMITTALS [NOT USED] 27 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 28 1.7 CLOSEOUT SUBMITTALS [NOT USED] 29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 30 19 QUALITY ASSURANCE [NOT USED] 31 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 32 1.11 FIELD [SITE] CONDITIONS [NOT USED) 33 1.12 WARRANTY [NOT USED] 34 PART 2- PRODUCTS [NOT USED] 35 PART 3- EXECUTION [NOT USED] 36 END OF SECTION CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised July 1,2011 01 55 26-3 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 3 of 3 1 Revision Log DATE NAME SUMMARY OF CHANGE 2 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 Ot 57 13-1 STORM WATER POLLUTION PREVENTION Page I of 3 1 SECTION 0157 13 2 STORM WATER POLLUTION PREVENTION 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Procedures for Storm Water Pollution Prevention Plans 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None, 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0— Bidding Requirements,Contract Forms and Conditions of the I I Contract 12 2. Division 1 General Requirements 13 3. Section 3125 00—Erosion and Sediment Control 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Construction Activities resulting in less than 1 acre of disturbance 17 a. Work associated with this Item is considered subsidiary to the various Items 18 bid. No separate payment will be allowed for this Item. 19 2. Construction Activities resulting in greater than 1 acre of disturbance 20 a. Measurement and Payment shall be in accordance with Section 3125 00. 21 1.3 REFERENCES 22 A. Abbreviations and Acronyms 23 1. Notice of Intent: NOI 24 2. Notice of Termination: NOT 25 3. Storm Water Pollution Prevention Plan: SWPPP 26 4. Texas Commission on Environmental Quality:TCEQ 27 5. Notice of Change: NOC 28 A. Reference Standards 29 1. Reference standards cited in this Specification refer to the current reference 30 standard published at the time of the latest revision date logged at the end of this 31 Specification,unless a date is specifically cited. 32 2. Integrated Storm Management(iSWM)Technical Manual for Construction 33 Controls 34 1.4 ADMINISTRATIVE REQUIREMENTS 35 A. General 36 1. Contractor is responsible for resolution and payment of any fines issued associated 37 with compliance to Stormwater Pollution Prevention Plan. CrrY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 0157 13-2 STORM WATER POLLUTION PREVENTION Page 2 of 1 B. Construction Activities resulting in: 2 1. Less than 1 acre of disturbance 3 a. Provide erosion and sediment control in accordance with Section 3125 00 and 4 Drawings. 5 2. 1 to less than 5 acres of disturbance 6 a. Texas Pollutant Discharge Elimination System(TPDES)General Construction 7 Permit is required 8 b. Complete SWPPP in accordance with TCEQ requirements 9 1) TCEQ Small Construction Site Notice Required under general permit 10 TXRI 50000 11 a) Sign and post at job site 12 b) Prior to Preconstruction Meeting,send 1 copy to City Department of 13 Transportation and Public Works, Environmental Division,(817)392- 14 6088. 15 2) Provide erosion and sediment control in accordance with: 16 a) Section 3125 00 17 b) The Drawings 18 c) TXR150000 General Permit 19 d) SWPPP 20 e) TCEQ requirements 21 3. 5 acres or more of Disturbance 22 a. Texas Pollutant Discharge Elimination System(TPDES)General Construction 23 Permit is required 24 b. Complete SWPPP in accordance with TCEQ requirements 25 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee 26 a) Sign and post at job site 27 b) Send copy to City Department of Transportation and Public Works, 28 Environmental Division,(817)392-6088. 29 2) TCEQ Notice of Change required if making changes or updates to NOI 30 3) Provide erosion and sediment control in accordance with: 31 a) Section 3125 00 32 b) The Drawings 33 c) TXR150000 General Permit 34 d) SWPPP 35 e) TCEQ requirements 36 4) Once the project has been completed and all the closeout requirements of 37 TCEQ have been met a TCEQ Notice of Termination can be submitted. 38 a) Send copy to City Department of Transportation and Public Works, 39 Environmental Division,(817)392-6088. 40 1.5 SUBMITTALS 41 A. SWPPP 42 1. Submit in accordance with Section 0133 00,except as stated herein. 43 a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City 44 as follows: 45 1) 1 copy to the City Project Manager 46 a) City Project Manager will forward to the City Department of 47 Transportation and Public Works, Environmental Division for review CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 0157 13-3 STORM WATER POLLUTION PREVENTION Page 3 of 3 1 B. Modified SWPPP 2 1. If the SWPPP is revised during construction,resubmit modified SWPPP to the City 3 in accordance with Section 0133 00. 4 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED) 5 1.7 CLOSEOUT SUBMITTALS (NOT USED] 6 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 7 1.9 QUALITY ASSURANCE [NOT USED] 8 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED) 9 1.11 FIELD [SITE] CONDITIONS [NOT USED] 10 1.12 WARRANTY [NOT USED] I I PART 2- PRODUCTS [NOT USED] 12 PART 3- EXECUTION [NOT USED] 13 END OF SECTION I4 Revision Log DATE NAME SUMMARY OF CHANGE 15 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 015813-1 TEMPORARY PROJECT SIGNAGE Page I of 3 I SECTION 01 5813 2 TEMPORARY PROJECT SIGNAGE 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Temporary Project Signage Requirements 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0— Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division I General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various Items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 18 1.5 SUBMITTALS [NOT USED] 19 1.6 ACTION SUBMITTALSIINFORMATIONAL SUBMITTALS [NOT USED] 20 1.7 CLOSEOUT SUBMITTALS [NOT USED] 21 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 22 1.9 QUALITY ASSURANCE [NOT USED[ 23 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 24 1.11 FIELD [SITE] CONDITIONS [NOT USED] 25 1.12 WARRANTY [NOT USED] 26 PART 2- PRODUCTS 27 2.1 OWNER-FURNISHED loR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 28 2.2 EQUIPMENT,PRODUCT TYPES,AND MATERIALS 29 A. Design Criteria 30 1. Provide free standing Project Designation Sign in accordance with City's Standard 31 Details for project signs. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 0158 13-2 TEMPORARY PROJECT SIGNAGE Page 2 of 3 1 B. Materials 2 1. Sign 3 a. Constructed of 3/4-inch fir plywood,grade A-C(exterior)or better 4 2.3 ACCESSORIES [NOT USED] 5 2.4 SOURCE QUALITY CONTROL[NOT USED] 6 PART 3- EXECUTION 7 3.1 INSTALLERS [NOT USED] 8 3.2 EXAMINATION [NOT USED] 9 3.3 PREPARATION [NOT USED] 10 3.4 INSTALLATION 11 A. General 12 1. Provide vertical installation at extents of project. 13 2. Relocate sign as needed, upon request of the City. 14 B. Mounting options 15 a. Skids 16 b. Pasts 17 c. Barricade 18 3.5 REPAIR/RESTORATION [NOT USED] 19 3.6 RE-INSTALLATION [NOT USED[ 20 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 21 3.8 SYSTEM STARTUP [NOT USED] 22 3.9 ADJUSTING [NOT USED] 23 3.10 CLEANING [NOT USED] 24 3.11 CLOSEOUT ACTIVITIES [NOT USED] 25 3.12 PROTECTION [NOT USED[ 26 3.13 MAINTENANCE 27 A. General 28 1. Maintenance will include painting and repairs as needed or directed by the City. 29 3.14 ATTACHMENTS [NOT USED] 30 END OF SECTION 31 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 015813-3 TEMPORARY PROJECT SIGNAGE Page 3 of 3 1 Revision Lag DATE NAME SUMMARY OF CHANGE 2 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July I,2011 01 60 00-1 PRODUCT REQUIREMENTS Page I or2 1 SECTION 0160 00 2 PRODUCT REQUIREMENTS 3 PARTI - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. References for Product Requirements and City Standard Products List 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 Bidding Requirements,Contract Forms and Conditions Of the Contract 11 2. Division 1 -- General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES [NOT USED] 13 1.3 REFERENCES [NOT USED] 14 1.4 ADMINISTRATIVE REQUIREMENTS 15 A. A list of City approved products for use is located on Buzzsaw as follows: 16 1. Resources\02 -Construction DocumentslStandard Products List 17 B. Only products specifically included on City's Standard Product List in these Contract 18 Documents shall be allowed for use on the Project. 19 1. Any subsequently approved products will only be allowed for use upon specific 20 approval by the City. 21 C. Any specific product requirements in the Contract Documents supersede similar 22 products included on the City's Standard Product List. 23 1. The City reserves the right to not allow products to be used for certain projects even 24 though the product is listed on the City's Standard Product List. 25 D. Although a specific product is included on City's Standard Product List,not all 26 products from that manufacturer are approved for use,including but not limited to,that 27 manufacturer's standard product. 28 E. See Section 0133 00 for submittal requirements of Product Data included on City's 29 Standard Product List. 30 1.5 SUBMITTALS [NOT USED] 31 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 32 1.7 CLOSEOUT SUBMITTALS [NOT USED] 33 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED[ 34 1.9 QUALITY ASSURANCE [NOT USED] CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 01 6000-2 PRODUCT REQUIREMENTS Page 2 of 2 1 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 2 1.11 FIELD [SITE] CONDITIONS [NOT USED] 3 1.12 WARRANTY [NOT USED] 4 PART 2- PRODUCTS [NOT USED] S PART 3- EXECUTION [NOT USED] 6 END OF SECTION 7 Revision Log DATE NAME SUMMARY OF CHANGE 10112/12 D.Johnson Modified Location ofCity's Standard Product List 8 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 01 66 00-1 PRODUCT STORAGE AND HANDLING REQUMMENTS Page I of 1 SECTION 0166 00 2 PRODUCT STORAGE AND HANDLING REQUIREMENTS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Scheduling of product delivery 7 2. Packaging of products for delivery 8 3. Protection of products against damage from: 9 a. Handling 10 b. Exposure to elements or harsh environments 11 B. Deviations from this City of Fort Worth Standard Specification 12 1. None. 13 C. Related Specification Sections include,but are not necessarily limited to: 14 1. Division 0— Bidding Requirements,Contract Forms and Conditions of the Contract 15 2. Division 1 General Requirements 16 1.2 PRICE AND PAYMENT PROCEDURES I7 A. Measurement and Payment 18 1. Work associated with this Item is considered subsidiary to the various Items bid. 19 No separate payment will be allowed for this Item. 20 1.3 REFERENCES [NOT USED] 21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 22 1.5 SUBMITTALS [NOT USED] 23 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED] 24 1.7 CLOSEOUT SUBMITTALS [NOT USED] 25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 26 1.9 QUALITY ASSURANCE [NOT USED] 27 1.10 DELIVERY AND HANDLING 28 A. Delivery Requirements 29 1. Schedule delivery of products or equipment as required to allow timely installation 30 and to avoid prolonged storage. 31 2. Provide appropriate personnel and equipment to receive deliveries. 32 3. Delivery trucks will not be permitted to wait extended periods of time on the Site 33 for personnel or equipment to receive the delivery. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 6600-2 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 2 of 4 1 4. Deliver products or equipment in manufacturer's original unbroken cartons or other 2 containers designed and constructed to protect the contents from physical or 3 environmental damage. 4 5. Clearly and fully mark and identify as to manufacturer, item and installation 5 location. 6 6. Provide manufacturer's instructions for storage and handling. 7 B. Handling Requirements 8 1. Handle products or equipment in accordance with these Contract Documents and 9 manufacturer's recommendations and instructions. 10 C. Storage Requirements 11 1. Store materials in accordance with manufacturer's recommendations and 12 requirements of these Specifications. 13 2. Make necessary provisions for safe storage of materials and equipment. 14 a. Place loose soil materials and materials to be incorporated into Work to prevent 15 damage to any part of Work or existing facilities and to maintain free access at 16 all times to all parts of Work and to utility service company installations in 17 vicinity of Work. 18 3. Keep materials and equipment neatly and compactly stored in locations that will 19 cause minimum inconvenience to other contractors,public travel, adjoining owners, 20 tenants and occupants. 21 a. Arrange storage to provide easy access for inspection. 22 4. Restrict storage to areas available on construction site for storage of material and 23 equipment as shown on Drawings, or approved by City's Project Representative. 24 5. Provide off-site storage and protection when on-site storage is not adequate. 25 a. Provide addresses of and access to off-site storage locations for inspection by 26 City's Project Representative. 27 6. Do not use lawns,grass plots or other private property for storage purposes without 28 written permission of owner or other person in possession or control of premises. 29 7. Store in manufacturers' unopened containers. 30 8. Neatly, safely and compactly stack materials delivered and stored along line of 31 Work to avoid inconvenience and damage to property owners and general public 32 and maintain at least 3 feet from fire hydrant. 33 9. Keep public and private driveways and street crossings open. 34 10. Repair or replace damaged lawns,sidewalks, streets or other improvements to 35 satisfaction of City's Project Representative. 36 a. Total length which materials may be distributed along route of construction at 37 one time is 1,000 linear feet, unless otherwise approved in writing by City's 38 Project Representative. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 016600-3 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 3 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS (NOT USED] 4 PART 3- EXECUTION 5 3.1 INSTALLERS [NOT USEDI 6 3.2 EXAMINATION [NOT USED] 7 3.3 PREPARATION [NOT USED] 8 3.4 ERECTION ]NOT USEDI 9 3.5 REPAIR/RESTORATION [NOT USED] 10 3.6 RE-INSTALLATION [NOT USED] 11 3.7 FIELD lotz] SITE QUALITY CONTROL 12 A. Tests and Inspections 13 1. Inspect all products or equipment delivered to the site prior to unloading. 14 B. Non-Conforming Work 15 1. Reject all products or equipment that are damaged, used or in any other way 16 unsatisfactory for use on the project. 17 3.8 SYSTEM STARTUP [NOT USED] 18 3.9 ADJUSTING [NOT USED] 19 3.10 CLEANING [NOT USED] 20 3.11 CLOSEOUT ACTIVITIES INOT USED] 21 3.12 PROTECTION 22 A. Protect all products or equipment in accordance with manufacturer's written directions. 23 B. Store products or equipment in location to avoid physical damage to items while in 24 storage. 25 C. Protect equipment from exposure to elements and keep thoroughly dry if required by 26 the manufacturer. 27 3.13 MAINTENANCE [NOT USEDI 28 3.14 ATTACHMENTS [NOT USED] 29 END OF SECTION 30 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July I,2011 01 6600-4 PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 4 of 4 Revision Log DATE NAME SUMMARY OF CHANGE I CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised July 1,2011 01 70 00-1 MOBILIZATION AND REMOBILIZATION Page l of 1 SECTION 0170 00 2 MOBILIZATION AND REMOBILIZATION 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Mobilization and Demobilization 7 a. Mobilization 8 1) Transportation of Contractor's personnel,equipment,and operating supplies 9 to the Site 10 2) Establishment of necessary general facilities for the Contractor's operation I 1 at the Site 12 3) Premiums paid for performance and payment bonds 13 4) Transportation of Contractor's personnel,equipment, and operating supplies 14 to another location within the designated Site 15 5) Relocation of necessary general facilities for the Contractor's operation 16 from I location to another location on the Site. 17 b. Demobilization 18 1) Transportation of Contractor's personnel,equipment, and operating supplies 19 away from the Site including disassembly 20 2) Site Clean-up 21 3) Removal of all buildings and/or other facilities assembled at the Site for this 22 Contract 23 c. Mobilization and Demobilization do not include activities for specific items of 24 work that are for which payment is provided elsewhere in the contract. 25 2. Remobilization 26 a. Remobilization for Suspension of Work specifically required in the Contract 27 Documents or as required by City includes: 28 1) Demobilization 29 a) Transportation of Contractor's personnel,equipment, and operating 30 supplies from the Site including disassembly or temporarily securing 31 equipment,supplies,and other facilities as designated by the Contract 32 Documents necessary to suspend the Work. 33 b) Site Clean-up as designated in the Contract Documents 34 2) Remobilization 35 a) Transportation of Contractor's personnel,equipment, and operating 36 supplies to the Site necessary to resume the Work. 37 b) Establishment of necessary general facilities for the Contractor's 38 operation at the Site necessary to resume the Work. 39 3) No Payments will be made for: 40 a) Mobilization and Demobilization from one location to another on the 41 Site in the normal progress of performing the Work. 42 b) Stand-by or idle time 43 c) Lost profits 44 3. Mobilizations and Demobilization for Miscellaneous Projects 45 a. Mobilization and Demobilization CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Pmject No.01239 Revised December 20,2012 01 7000-2 MOBILIZATION AND REMOBILIZATION Page 2 of A 1 1) Mobilization shall consist of the activities and cost on a Work Order basis 2 necessary for: 3 a) Transportation of Contractor's personnel,equipment, and operating 4 supplies to the Site for the issued Work Order. 5 b) Establishment of necessary general facilities for the Contractor's 6 operation at the Site for the issued Work Order 7 2) Demobilization shall consist of the activities and cost necessary for: 8 a) Transportation of Contractor's personnel,equipment,and operating 9 supplies from the Site including disassembly for each issued Work 10 Order 1 I b) Site Clean-up for each issued Work Order 12 c) Removal of all buildings or other facilities assembled at the Site for 13 each Work Oder 14 b. Mobilization and Demobilization do not include activities for specific items of 15 work for which payment is provided elsewhere in the contract. 16 4. Emergency Mobilizations and Demobilization for Miscellaneous Projects 17 a. A Mobilization for Miscellaneous Projects when directed by the City and the 18 mobilization occurs within 24 hours of the issuance of the Work Order. 19 B. Deviations from this City of Fort Worth Standard Specification 20 1. None. 21 C. Related Specification Sections include,but are not necessarily limited to: 22 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 23 2. Division 1 —General Requirements 24 1.2 PRICE AND PAYMENT PROCEDURES 25 A. Measurement and Payment 26 1. Mobilization and Demobilization 27 a. Measure 28 1) This Item is considered subsidiary to the various Items bid. 29 b. Payment 30 1) The work performed and materials furnished in accordance with this Item 31 are subsidiary to the various Items bid and no other compensation will be 32 allowed. 33 2. Remobilization for suspension of Work as specifically required in the Contract 34 Documents 35 a. Measurement 36 1) Measurement for this Item shall be per each remobilization performed. 37 b. Payment 38 1) The work performed and materials furnished in accordance with this Item 39 and measured as provided under"Measurement"will be paid for at the unit 40 price per each"Specified Remobilization"in accordance with Contract 41 Documents. 42 c. The price shall include: 43 1) Demobilization as described in Section 1.1.A.2.a.1) 44 2) Remobilization as described in Section 1.1.A.2.a.2) 45 d. No payments will be made for standby, idle time,or lost profits associated this 46 Item. CITY OF FORT WORTH Mary's Creck Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 01 70 00-3 MOBILIZATION AND REMOBILIZATION Page 3 of 4 1 3. Remobilization for suspension of Work as required by City 2 a. Measurement and Payment 3 1) This shall be submitted as a Contract Claim in accordance with Article 10 4 of Section 00 72 00. 5 2) No payments will be made for standby, idle time,or Iost profits associated 6 with this Item. 7 4. Mobilizations and Demobilizations for Miscellaneous Projects 8 a. Measurement 9 l) Measurement for this Item shall be for each Mobilization and 10 Demobilization required by the Contract Documents I b. Payment 12 1) The Work performed and materials furnished in accordance with this Item 13 and measured as provided under"Measurement"will be paid for at the unit 14 price per each"Work Order Mobilization" in accordance with Contract 15 Documents. Demobilization shall be considered subsidiary to mobilization 16 and shall not be paid for separately. 17 c. The price shall include: 18 1) Mobilization as described in Section 1.1.A.3.a.1) 19 2) Demobilization as described in Section 1.1.A.3.a.2) 20 d. No payments will be made for standby, idle time, or lost profits associated this 21 Item. 22 5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects 23 a. Measurement 24 1) Measurement for this Item shall be for each Mobilization and 25 Demobilization required by the Contract Documents 26 b. Payment 27 1) The Work performed and materials furnished in accordance with this Item 28 and measured as provided under"Measurement"will be paid for at the unit 29 price per each"Work Order Emergency Mobilization"in accordance with 30 Contract Documents. Demobilization shall be considered subsidiary to 31 mobilization and shall not be paid for separately. 32 c. The price shall include 33 1) Mobilization as described in Section 1.1.A.4.a) 34 2) Demobilization as described in Section l.l.A.3.a.2) 35 d. No payments will be made for standby, idle time, or lost profits associated this 36 Item. 37 1.3 REFERENCES [NOT USED] 38 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 39 1.5 SUBMITTALS [NOT USED] 40 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 41 1.7 CLOSEOUT SUBMITTALS [NOT USED] 42 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 43 1.9 QUALITY ASSURANCE [NOT USED] 44 1.10 DELIVERY,STORAGE,AND HANDLING[NOT USED] CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 0l 7000-4 MOBILIZATION AND REMOBILIZATION Page 4 of 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3- EXECUTION [NOT USED] 5 END OF SECTION 6 Revision Log DATE NAME SUMMARY OF CHANGE 7 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 017123-1 CONSTRUCTION STAKING AND SURVEY Page 1 of 4 1 SECTION 01 71 23 2 CONSTRUCTION STAKING AND SURVEY 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Requirements for construction staking and construction survey 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0-- Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division 1 General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Construction Staking 15 a. Measurement 16 1) This Item is considered subsidiary to the various Items bid. 17 b. Payment 18 1) The work performed and the materials furnished in accordance with this 19 Item are subsidiary to the various Items bid and no other compensation will 20 be allowed. 21 2. Construction Survey 22 a. Measurement 23 1) This Item is considered subsidiary to the various Items bid. 24 b. Payment 25 1) The work performed and the materials furnished in accordance with this 26 Item are subsidiary to the various Items bid and no other compensation will 27 be allowed. 28 1.3 REFERENCES [NOT USED] 29 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 30 1.5 SUBMITTALS 31 A. Submittals, if required,shall be in accordance with Section 0133 00. 32 B. All submittals shall be approved by the City prior to delivery. 33 1.6 ACTION SUBMITTALSANFORMATIONAL SUBMITTALS 34 A. Certificates 35 1. Provide certificate certifying that elevations and locations of improvements are in 36 conformance or non-conformance with requirements of the Contract Documents. 37 a. Certificate must be sealed by a registered professional land surveyor in the 38 State of Texas. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 01 71 23-2 CONSTRUCTION STAKING AND SURVEY Page 2 of 4 1 B. Field Quality Control Submittals 2 1. Documentation verifying accuracy of field engineering work. 3 1.7 CLOSEOUT SUBMITTALS [NOT USED] 4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED) 5 1.9 QUALITY ASSURANCE 6 A. Construction Staking 7 1. Construction staking will be performed by the City. 8 2. Coordination 9 a. Contact City's Project Representative at least 2 weeks in advance for 10 scheduling of Construction Staking. I 1 b. It is the Contractor's responsibility to coordinate staking such that construction 12 activities are not delayed or negatively impacted. 13 3. General 14 a. Contractor is responsible for preserving and maintaining stakes furnished by is City. 16 b. If in the opinion of the City,a sufficient number of stakes or markings have 17 been lost,destroyed or disturbed,by Contractor's neglect,such that the 18 contracted Work cannot take place,then the Contractor will be required to pay 19 the City for new staking with a 25 percent markup.The cost for staking will be 20 deducted from the payment due to the Contractor for the Project. 21 B. Construction Survey 22 1. Construction Survey will be performed by the City. 23 2. Coordination 24 a. Contractor to verify that control data established in the design survey remains 25 intact. 26 b. Coordinate with the City prior to field investigation to determine which 27 horizontal and vertical control data will be required for construction survey. 28 c. It is the Contractor's responsibility to coordinate Construction Survey such that 29 construction activities are not delayed or negatively impacted. 30 d. Notify City if any control data needs to be restored or replaced due to damage 31 caused during construction operations. 32 1) City shall perform replacements and/or restorations. 33 3. General 34 a. Construction survey will be performed in order to maintain complete and 35 accurate logs of control and survey work as it progresses for Project Records. 36 b. The Contractor will need to ensure coordination is maintained with the City to 37 perform construction survey to obtain construction features, including but not 38 limited to the following: 39 1) All Utility Lines 40. a) Rim and flowline elevations and coordinates for each manhole or 41 junction structure 42 2) Water Lines 43 a) Top of pipe elevations and coordinates for waterlines at the following 44 locations: 45 (1) Every 250 linear feet CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 01 71 23-3 CONSTRUCTION STAKING AND SURVEY Page 3 of 4 1 (2) Horizontal and vertical points of inflection,curvature,etc. (All 2 Fittings) 3 (3) Cathodic protection test stations 4 (4) Sampling stations 5 (5) Meter boxes/vaults(All sizes) 6 (6) Fire lines 7 (7) Fire hydrants 8 (8) Gate valves 9 (9) Plugs,stubouts, dead-end lines 10 (10) Air Release valves(Manhole rim and vent pipe) 1 I (11) Blow off valves(Manhole rim and valve lid) 12 (12) Pressure plane valves 13 (13) Cleaning wyes 14 (14) Casing pipe(each end) 15 b) Storm Sewer 16 (1) Tap of pipe elevations and coordinates at the following locations: 17 (a) Every 250 linear feet 18 (b) Horizontal and vertical points of inflection,curvature,etc. 19 c) Sanitary Sewer 20 (1) Top of pipe elevations and coordinates for sanitary sewer lines at 21 the following locations: 22 (a) Every 250 linear feet 23 (b) Horizontal and vertical points of inflection, curvature,etc. 24 (c) Cleanouts 25 c. Construction survey will be performed in order to maintain complete and 26 accurate logs of control and survey work associated with meeting or exceeding 27 the line and grade required by these Specifications. 28 d. The Contractor will need to ensure coordination is maintained with the City to 29 perform construction survey and to verify control data,including but not 30 limited to the following: 31 1) Established benchmarks and control points provided for the Contractor's 32 use are accurate 33 2) Benchmarks were used to furnish and maintain all reference lines and 34 grades for tunneling 35 3) Lines and grades were used to establish the location of the pipe 36 4) Submit to the City copies of field notes used to establish all lines and 37 grades and allow the City to check guidance system setup prior to 38 beginning each tunneling drive. 39 5) Provide access for the City to verify the guidance system and the line and 40 grade of the carrier pipe on a daily basis. 41 6) The Contractor remains fully responsible for the accuracy of the work and 42 the correction of it,as required. 43 7) Monitor line and grade continuously during construction. 44 8) Record deviation with respect to design line and grade once at each pipe 45 joint and submit daily records to City. 46 9) If the installation does not meet the specified tolerances, immediately notify 47 the City and correct the installation in accordance with the Contract 48 Documents, 49 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 017123-4 CONSTRUCTION STAKING AND SURVEY Page of 1 1.11 FIELD [SITE[ CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3- EXECUTION 5 3.1 INSTALLERS [NOT USED] 6 3.2 EXAMINATION [NOT USED] 7 3.3 PREPARATION [NOT USED] 8 3.4 APPLICATION 9 3.5 REPAIR/RESTORATION [NOT USED] 10 3.6 RE-INSTALLATION [NOT USED] 11 3.7 FIELD [OR] SITE QUALITY CONTROL 12 A. It is the Contractor's responsibility to maintain all stakes and control data placed by the 13 City in accordance with this Specification. 14 B. Do not change or relocate stakes or control data without approval from the City. 15 3.8 SYSTEM STARTUP [NOT USED) 16 3.9 ADJUSTING [NOT USED] 17 3.10 CLEANING [NOT USED] 18 3.11 CLOSEOUT ACTIVITIES ]NOT USED] 19 3.12 PROTECTION [NOT USED] 20 3.13 MAINTENANCE [NOT USED] 21 3.14 ATTACHMENTS [NOT USED] 22 END OF SECTION 23 Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D.7ohnson 24 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 01 74 23-l CLEANING Page I of 4 1 SECTION 0174 23 2 CLEANING 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Intermediate and final cleaning for Work not including special cleaning of closed 7 systems specified elsewhere 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. None. 10 C. Related Specification Sections include,but are not necessarily limited to: I 1 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 12 2. Division 1 —General Requirements 13 3. Section 32 92 13 —Hydro-Mulching,Seeding and Sodding 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Work associated with this Item is considered subsidiary to the various items bid. 17 No separate payment will be allowed for this Item. 18 1.3 REFERENCES [NOT USED) 19 1.4 ADMINISTRATIVE REQUIREMENTS 20 A. Scheduling 21 1. Schedule cleaning operations so that dust and other contaminants disturbed by 22 cleaning process will not fall on newly painted surfaces. 23 2. Schedule final cleaning upon completion of Work and immediately prior to final 24 inspection. 25 1.5 SUBMITTALS [NOT USED] 26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS (NOT USED] 27 1.7 CLOSEOUT SUBMITTALS [NOT USED] 28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29 1.9 QUALITY ASSURANCE [NOT USED] 30 1.10 STORAGE,AND HANDLING 31 A. Storage and Handling Requirements 32 1. Store cleaning products and cleaning wastes in containers specifically designed for 33 those materials. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 017423-2 CLEANING Page 2 of 4 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED[ 3 PART 2- PRODUCTS 4 2.1 OWNER-FURNISHED loa] OWNER-SUPPLIEDPRODUCTS [NOT USED] 5 2.2 MATERIALS 6 A. Cleaning Agents 7 1. Compatible with surface being cleaned 8 2. New and uncontaminated 9 3. For manufactured surfaces 10 a. Material recommended by manufacturer 11 2.3 ACCESSORIES [NOT USED] 12 2.4 SOURCE QUALITY CONTROL [NOT USED] 13 PART 3- EXECUTION 14 3.1 INSTALLERS [NOT USED] 15 3.2 EXAMINATION [NOT USED) 16 3.3 PREPARATION [NOT USED] 17 3.4 APPLICATION [NOT USED] 18 3.5 REPAIR/RESTORATION [NOT USED] 19 3.6 RE-INSTALLATION [NOT USED[ 20 3.7 FIELD Ion] SITE QUALITY CONTROL(NOT USED] 21 3.8 SYSTEM STARTUP [NOT USED] 22 3.9 ADJUSTING [NOT USED] 23 3.10 CLEANING 24 A. General 25 1. Prevent accumulation of wastes that create hazardous conditions. 26 2. Conduct cleaning and disposal operations to comply with laws and safety orders of 27 governing authorities. 28 3. Do not dispose of volatile wastes such as mineral spirits,oil or paint thinner in 29 storm or sanitary drains or sewers. 30 4. Dispose of degradable debris at an approved solid waste disposal site. 31 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an 32 alternate manner approved by City and regulatory agencies. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 74 23-3 CLEANING Page 3 of 4 1 6. Handle materials in a controlled manner with as few handlings as possible. 2 7. Thoroughly clean,sweep,wash and polish all Work and equipment associated with 3 this project. 4 8. Remove all signs of temporary construction and activities incidental to construction 5 of required permanent Work. 6 9. If project is not cleaned to the satisfaction of the City,the City reserves the right to 7 have the cleaning completed at the expense of the Contractor. 8 10. Do not burn on-site. 9 B. Intermediate Cleaning during Construction 10 1. Keep Work areas clean so as not to hinder health,safety or convenience of 11 personnel in existing facility operations. 12 2. At maximum weekly intervals,dispose of waste materials,debris and rubbish. 13 3. Confine construction debris daily in strategically located container(s): 14 a. Cover to prevent blowing by wind 15 b. Store debris away from construction or operational activities 16 c. Haul from site at a minimum of once per week 17 4. Vacuum clean interior areas when ready to receive finish painting. 18 a. Continue vacuum cleaning on an as-needed basis,until Final Acceptance. 19 5. Prior to storm events,thoroughly clean site of all loose or unsecured items,which 20 may become airborne or transported by flowing water during the storm. 21 C. Interior Final Cleaning 22 1. Remove grease, mastic,adhesives,dust,dirt,stains, fingerprints, labels and other 23 foreign materials from sight-exposed surfaces. 24 2. Wipe all lighting fixture reflectors, lenses, lamps and trims clean. 25 3. Wash and shine glazing and mirrors. 26 4. Polish glossy surfaces to a clear shine. 27 5. Ventilating systems 28 a. Clean permanent filters and replace disposable filters if units were operated 29 during construction. 30 b. Clean ducts,blowers and coils if units were operated without filters during 31 construction. 32 6. Replace all burned out lamps. 33 7. Broom clean process area floors. 34 8. Mop office and control room floors. 35 D. Exterior(Site or Right of Way) Final Cleaning 36 1. Remove trash and debris containers from site. 37 a. Re-seed areas disturbed by location of trash and debris containers in accordance 38 with Section 32 92 13. 39 2. Sweep roadway to remove all rocks,pieces of asphalt,concrete or any other object 40 that may hinder or disrupt the flow of traffic along the roadway. 41 3. Clean any interior areas including, but not limited to, vaults, manholes,structures, 42 junction boxes and inlets. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 017423-4 CLEANING Page 4 of 4 1 4. If no longer required for maintenance of erosion facilities,and upon approval by 2 City,remove erosion control from site. 3 5. Clean signs, lights,signals, etc. 4 3.11 CLOSEOUT ACTIVITIES INOT USED] 5 3.12 PROTECTION [NOT USED] 6 3.13 MAINTENANCE [NOT USED] 7 3.14 ATTACHMENTS [NOT USEDI 8 END OF SECTION 9 Revision Log DATE NAME SUMMARY OF CHANGE to CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 7719-1 CLOSEOUT REQUIREMENTS Page I of 3 1 SECTION 017719 2 CLOSEOUT REQUIREMENTS 3 PARTI- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedure for closing out a contract 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0--Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 —General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various Items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES ]NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Guarantees, Bands and Affidavits 19 1. No application for final payment will be accepted until all guarantees, bonds, 20 certificates,licenses and affidavits required for Work or equipment as specified are 21 satisfactorily filed with the City. 22 B. Release of Liens or Claims 23 1. No application for final payment will be accepted until satisfactory evidence of 24 release of liens has been submitted to the City. 25 1.5 SUBMITTALS 26 A. Submit all required documentation to City's Project Representative. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,7011 01 77 19-2 CLOSEOUT REQUIREMENTS Page 2 of 3 1 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 PART 2- PRODUCTS [NOT USED] 4 PART 3- EXECUTION 5 3.1 INSTALLERS [NOT USED] 6 3.2 EXAMINATION [NOT USED] 7 3.3 PREPARATION [NOT USED] 8 3.4 CLOSEOUT PROCEDURE 9 A. Prior to requesting Final Inspection,submit: 10 1. Project Record Documents in accordance with Section 0178 39 11 2. Operation and Maintenance Data, if required,in accordance with Section 01 78 23 12 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section 13 01 74 23. 14 C. Final Inspection 15 1. After final cleaning,provide notice to the City Project Representative that the Work 16 is completed. 17 a. The City will make an initial Final Inspection with the Contractor present. 18 b. Upon completion of this inspection, the City will notify the Contractor, in 19 writing within 10 business days,of any particulars in which this inspection 20 reveals that the Work is defective or incomplete. 21 2. Upon receiving written notice from the City, immediately undertake the Work 22 required to remedy deficiencies and complete the Work to the satisfaction of the 23 City. 24 3. Upon completion of Work associated with the items listed in the City's written 25 notice,inform the City, that the required Work has been completed. Upon receipt 26 of this notice,the City,in the presence of the Contractor,will make a subsequent 27 Final Inspection of the project. 28 4. Provide all special accessories required to place each item of equipment in full 29 operation. These special accessory items include,but are not limited to: 30 a. Specified spare parts 31 b. Adequate oil and grease as required for the first lubrication of the equipment 32 c. Initial fill up of all chemical tanks and fuel tanks 33 d. Light bulbs 34 e. Fuses 35 f. Vault keys 36 g. Handwheels 37 h. Other expendable items as required for initial start-up and operation of all 38 equipment 39 D. Notice of Project Completion CITY OF FORT WORTH Mary's Creek Recycling Center Trcc Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised July 1,2011 01 77 19-3 CLOSEOUT REQUIREMENTS Page 3 of 3 1 1. Once the City Project Representative finds the Work subsequent to Final Inspection 2 to be satisfactory, the City will issue a Notice of Project Completion(Green Sheet). 3 E. Supporting Documentation 4 1. Coordinate with the City Project Representative to complete the following 5 additional forms: 6 a. Final Payment Request 7 b. Statement of Contract Time 8 e. Affidavit of Payment and Release of Liens 9 d. Consent of Surety to Final Payment 10 e. Pipe Report(if required) 1 I f. Contractor's Evaluation of City 12 g. Performance Evaluation of Contractor 13 F. Letter of Final Acceptance 14 1. Upon review and acceptance of Notice of Project Completion and Supporting 15 Documentation, in accordance with General Conditions, City will issue Letter of 16 Final Acceptance and release the Final Payment Request for payment. 17 3.5 REPAIR/RESTORATION [NOT USED] 18 3.6 RE-INSTALLATION [NOT USED) 19 3.7 FIELD lotz] SITE QUALITY CONTROL [NOT USED] 20 3.8 SYSTEM STARTUP[NOT USED] 21 3.9 ADJUSTING [NOT USED[ 22 3.10 CLEANING [NOT USED] 23 3.11 CLOSEOUT ACTIVITIES [NOT USED] 24 3.12 PROTECTION [NOT USED] 25 3.13 MAINTENANCE [NOT USED) 26 3.14 ATTACHMENTS [NOT USED] 27 END OF SECTION 28 Revision Log DATE NAME SUMMARY OF CHANGE 29 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 017823-1 OPERATION AND MAINTENANCE DATA Page I of 5 I SECTION 0178 23 2 OPERATION AND MAINTENANCE DATA 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Product data and related information appropriate for City's maintenance and 7 operation of products furnished under Contract 8 2. Such products may include,but are not limited to: 9 a. Traffic Controllers t0 b. Irrigation Controllers(to be operated by the City) l l c. Butterfly Valves 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include, but are not necessarily limited to: 15 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 16 2. Division 1 —General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various Items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS 23 A. Schedule 24 1. Submit manuals in final form to the City within 30 calendar days of product 25 shipment to the project site. 26 1.5 SUBMITTALS 27 A. Submittals shall be in accordance with Section 0133 00 . All submittals shall be 28 approved by the City prior to delivery. 29 1.6 INFORMATIONAL SUBMITTALS 30 A. Submittal Form 31 1. Prepare data in form of an instructional manual for use by City personnel. 32 2. Format 33 a. Size: 8 V2 inches x I I inches 34 b. Paper 35 1) 40 pound minimum,white, for typed pages 36 2) Holes reinforced with plastic,cloth or metal 37 C. Text: Manufacturer's printed data,or neatly typewritten CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 Ol1823-2 OPERATION AND MAINTENANCE DATA Page 2 of 5 1 d. Drawings 2 1) Provide reinforced punched binder tab,bind in with text 3 2) Reduce larger drawings and fold to size of text pages. 4 e. Provide fly-leaf for each separate product,or each piece of operating 5 equipment. 6 1) Provide typed description of product,and major component parts of 7 equipment. 8 2) Provide indexed tabs. 9 f. Cover 10 1) Identify each volume with typed or printed title"OPERATING AND I I MAINTENANCE INSTRUCTIONS". 12 2) List: 13 a) Title of Project 14 b) Identity of separate structure as applicable 15 c) Identity of general subject matter covered in the manual 16 3. Binders 17 a. Commercial quality 3-ring binders with durable and cleanable plastic covers 18 b. When multiple binders are used,correlate the data into related consistent 19 groupings. 20 4. If available,provide an electronic form of the O&M Manual. 21 B. Manual Content 22 1. Neatly typewritten table of contents for each volume,arranged in systematic order 23 a. Contractor,name of responsible principal,address and telephone number 24 b. A list of each product required to be included,indexed to content of the volume 25 c. List,with each product: 26 1) The name, address and telephone number of the subcontractor or installer 27 2) A list of each product required to be included, indexed to content of the 28 volume 29 3) Identify area of responsibility of each 30 4) Local source of supply for parts and replacement 31 d. Identify each product by product name and other identifying symbols as set 32 forth in Contract Documents. 33 2. Product Data 34 a. Include only those sheets which are pertinent to the specific product. 35 b. Annotate each sheet to: 36 1) Clearly identify specific product or part installed 37 2) Clearly identify data applicable to installation 38 3) Delete references to inapplicable information 39 3. Drawings 40 a. Supplement product data with drawings as necessary to clearly illustrate: 41 1) Relations of component parts of equipment and systems 42 2) Control and flow diagrams 43 b. Coordinate drawings with information in Project Record Documents to assure 44 correct illustration of completed installation. 45 c. Do not use Project Record Drawings as maintenance drawings. 46 4. Written text, as required to supplement product data for the particular installation: 47 a. Organize in consistent format under separate headings for different procedures. 48 b. Provide logical sequence of instructions of each procedure. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 01 78 23-3 OPERATION AND MAINTENANCE DATA Page 3 of 5 1 5. Copy of each warranty,bond and service contract issued 2 a. Provide information sheet for City personnel giving: 3 1) Proper procedures in event of failure 4 2) Instances which might affect validity of warranties or bonds 5 C. Manual for Materials and Finishes 6 1. Submit 5 copies of complete manual in final farm. 7 2. Content, for architectural products,applied materials and finishes: 8 a. Manufacturer's data,giving full information on products 9 1) Catalog number,size,composition 10 2) Color and texture designations 11 3) Information required for reordering special manufactured products 12 b. Instructions for care and maintenance 13 1) Manufacturer's recommendation for types of cleaning agents and methods 14 2) Cautions against cleaning agents and methods which are detrimental to 15 product 16 3) Recommended schedule for cleaning and maintenance 17 3. Content, for moisture protection and weather exposure products: 18 a. Manufacturer's data,giving full information on products 19 1) Applicable standards 20 2) Chemical composition 21 3) Details of installation 22 b. Instructions for inspection, maintenance and repair 23 D. Manual for Equipment and Systems 24 1. Submit 5 copies of complete manual in final form. 25 2. Content, for each unit of equipment and system, as appropriate: 26 a. Description of unit and component parts 27 1) Function, normal operating characteristics and limiting conditions 28 2) Performance curves, engineering data and tests 29 3) Complete nomenclature and commercial number of replaceable parts 30 b. Operating procedures 31 1) Start-up,break-in,routine and normal operating instructions 32 2) Regulation,control,stopping,shut-down and emergency instructions 33 3) Summer and winter operating instructions 34 4) Special operating instructions 35 c. Maintenance procedures 36 1) Routine operations 37 2) Guide to "trouble shooting" 38 3) Disassembly,repair and reassembly 39 4) Alignment,adjusting and checking 40 d. Servicing and lubrication schedule 41 1) List of lubricants required 42 e. Manufacturer's printed operating and maintenance'instructions 43 f. Description of sequence of operation by control manufacturer 44 1) Predicted life of parts subject to wear 45 2) Items recommended to be stocked as spare parts 46 g. As installed control diagrams by controls manufacturer 47 h. Each contractor's coordination drawings 48 1) As installed color coded piping diagrams CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 01 78 23.4 OPERATION AND MAINTENANCE DATA Page 4 of 5 1 i. Charts of valve tag numbers,with location and function of each valve 2 j. List of original manufacturer's spare parts,manufacturer's current prices,and 3 recommended quantities to be maintained in storage 4 k. Other data as required under pertinent Sections of Specifications 5 3. Content, for each electric and electronic system,as appropriate: 6 a. Description of system and component parts 7 1) Function,normal operating characteristics,and limiting conditions 8 2) Performance curves,engineering data and tests 9 3) Complete nomenclature and commercial number of replaceable parts 10 b. Circuit directories of panelboards 11 1) Electrical service 12 2) Controls 13 3) Communications 14 c. As installed color coded wiring diagrams 15 d. Operating procedures 16 1) Routine and normal operating instructions 17 2) Sequences required 18 3) Special operating instructions 19 e. Maintenance procedures 20 1) Routine operations 21 2) Guide to"trouble shooting" 22 3) Disassembly,repair and reassembly 23 4) Adjustment and checking 24 f. Manufacturer's printed operating and maintenance instructions 25 g. List of original manufacturer's spare parts,manufacturer's current prices,and 26 recommended quantities to be maintained in storage 27 h. Other data as required under pertinent Sections of Specifications 28 4. Prepare and include additional data when the need for such data becomes apparent 29 during instruction of City's personnel. 30 1.7 CLOSEOUT SUBMITTALS [NOT USED] 31 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 32 1.9 QUALITY ASSURANCE 33 A. Provide operation and maintenance data by personnel with the following criteria: 34 1. Trained and experienced in maintenance and operation of described products 35 2. Skilled as technical writer to the extent required to communicate essential data 36 3. Skilled as draftsman competent to prepare required drawings CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 01 78 23-5 OPERATION AND MAINTENANCE DATA Page 5 of 5 1 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 2 1.11 FIELD [SITE] CONDITIONS [NOT USED] 3 1.12 WARRANTY [NOT USED] 4 PART 2- PRODUCTS [NOT USED] 5 PART 3- EXECUTION [NOT USED] 6 END OF SECTION 7 Revision Log DATE NAME SUMMARY OF CHANGE 813112012 D.Johnson 1.5.A.1 title of section removed 8 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revises!December 20,2012 01 78 39.1 PROJECT RECORD DOCUMENTS Page 1 of 4 1 SECTION 0178 39 2 PROJECT RECORD DOCUMENTS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Work associated with the documenting the project and recording changes to project 7 documents,including: 8 a. Record Drawings 9 b. Water Meter Service Reports 10 c. Sanitary Sewer Service Reports I I d. Large Water Meter Reports 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include,but are not necessarily limited to: 15 1. Division 0—Bidding Requirements, Contract Forms and Conditions of the Contract 16 2. Division l General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various Items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 23 1.5 SUBMITTALS 24 A. Prior to submitting a request for Final Inspection,deliver Project Record Documents to 25 City's Project Representative. 26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 27 1.7 CLOSEOUT SUBMITTALS [NOT USED] 28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29 1.9 QUALITY ASSURANCE 30 A. Accuracy of Records 31 1. Thoroughly coordinate changes within the Record Documents,making adequate 32 and proper entries on each page of Specifications and each sheet of Drawings and 33 other Documents where such entry is required to show the change properly. 34 2. Accuracy of records shall be such that future search for items shown in the Contract 35 Documents may rely reasonably on information obtained from the approved Project 36 Record Documents. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 01 7839-2 PROJECT RECORD DOCUMENTS Page 2 of 4 1 3. To facilitate accuracy of records, make entries within 24 hours after receipt of 2 information that the change has occurred. 3 4. Provide factual information regarding all aspects of the Work,both concealed and 4 visible,to enable future modification of the Work to proceed without lengthy and 5 expensive site measurement, investigation and examination. 6 1.10 STORAGE AND HANDLING 7 A. Storage and Handling Requirements 8 1. Maintain the job set of Record Documents completely protected from deterioration 9 and from loss and damage until completion of the Work and transfer of all recorded 10 data to the final Project Record Documents. 11 2. In the event of loss of recorded data, use means necessary to again secure the data 12 to the City's approval. 13 a. In such case,provide replacements to the standards originally required by the 14 Contract Documents, 15 1.11 FIELD [SITE] CONDITIONS [NOT USED] 16 1.12 WARRANTY [NOT USED] 17 PART 2- PRODUCTS 18 2.1 OWNER-FURNISHED IoR] OWNER-SUPPLIED PRODUCTS [NOT USED] 19 2.2 RECORD DOCUMENTS 20 A. Job set 21 1. Promptly following receipt of the Notice to Proceed,secure from the City, at no 22 charge to the Contractor, 1 complete set of all Documents comprising the Contract. 23 B. Final Record Documents 24 1. At a time nearing the completion of the Work and prior to Final Inspection, provide 25 the City 1 complete set of all Final Record Drawings in the Contract. 26 2.3 ACCESSORIES [NOT USED] 27 2.4 SOURCE QUALITY CONTROL [NOT USED] 28 PART 3- EXECUTION 29 3.1 INSTALLERS [NOT USED] 30 3.2 EXAMINATION [NOT USED] 31 3.3 PREPARATION [NOT USED] 32 3.4 MAINTENANCE DOCUMENTS 33 A. Maintenance of Job Set 34 1. Immediately upon receipt of the job set, identify each of the Documents with the 35 title, "RECORD DOCUMENTS-JOB SET". CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 017839.3 PROJECT RECORD DOCUMENTS Page 3 of 4 1 2. Preservation 2 a. Considering the Contract completion time,the probable number of occasions 3 upon which the job set must be taken out for new entries and for examination, 4 and the conditions under which these activities will be performed,devise a 5 suitable method for protecting the job set. 6 b. Do not use the job set for any purpose except entry of new data and for review 7 by the City,until start of transfer of data to final Project Record Documents. 8 c. Maintain the job set at the site of work. 9 3. Coordination with Construction Survey 10 a. At a minimum, in accordance with the intervals set forth in Section 01 71 23, 11 clearly mark any deviations from Contract Documents associated with 12 installation of the infrastructure. 13 4. Making entries on Drawings 14 a. Record any deviations from Contract Documents. 15 b. Use an erasable colored pencil (not ink or indelible pencil),clearly describe the 16 change by graphic line and note as required. 17 c. Date all entries. 18 d. Call attention to the entry by a "cloud"drawn around the area or areas affected. 19 e. In the event of overlapping changes,use different colors for the overlapping 20 changes. 21 5. Conversion of schematic layouts 22 a. In some cases on the Drawings,arrangements of conduits,circuits,piping, 23 ducts,and similar items, are shown schematically and are not intended to 24 portray precise physical layout. 25 1) Final physical arrangement is determined by the Contractor,subject to the 26 City's approval. 27 2) However,design of future modifications of the facility may require 28 accurate information as to the final physical layout of items which are 29 shown only schematically on the Drawings. 30 b. Show on the job set of Record Drawings,by dimension accurate to within 1 31 inch,the centerline of each run of items. 32 1) Final physical arrangement is determined by the Contractor,subject to the 33 City's approval. 34 2) Show,by symbol or note,the vertical location of the Item("under slab","in 35 ceiling plenum", "exposed",and the like). 36 3) Make all identification sufficiently descriptive that it may be related 37 reliably to the Specifications. 38 c. The City may waive the requirements for conversion of schematic layouts 39 where, in the City's judgment,conversion serves no useful purpose. However, 40 do not rely upon waivers being issued except as specifically issued in writing 41 by the City. 42 B. Final Project Record Documents 43 1. Transfer of data to.Drawings 44 a. Carefully transfer change data shown on the job set of Record Drawings to the 45 corresponding final documents,coordinating the changes as required. 46 b. Clearly indicate at each affected detail and other Drawing a full description of 47 changes made during construction, and the actual location of items. CITY OF PORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,20)1 01 78 39-4 PROJECT RECORD DOCUMENTS Page 4 of 4 1 c. Call attention to each entry by drawing a"cloud" around the area or areas 2 affected. 3 d. Make changes neatly,consistently and with the proper media to assure 4 longevity and clear reproduction. 5 2. Transfer of data to other Documents 6 a. If the Documents,other than Drawings,have been kept clean during progress of 7 the Work,and if entries thereon have been orderly to the approval of the City, 8 the job set of those Documents,other than Drawings,will be accepted as final 9 Record Documents. 10 b. If any such Document is not so approved by the City,secure a new copy of that 1 i Document from the City at the City's usual charge for reproduction and 12 handling,and carefully transfer the change data to the new copy to the approval 13 of the City. 14 3.5 REPAIR/RESTORATION [NOT USED] 15 3.6 RE-INSTALLATION [NOT USED] 16 3.7 FIELD (oa] SITE QUALITY CONTROL (NOT USED] 17 3.8 SYSTEM STARTUP [NOT USED] 18 3.9 ADJUSTING [NOT USED] 19 3.10 CLEANING [NOT USED] 20 3.11 CLOSEOUT ACTIVITIES [NOT USED] 21 3.12 PROTECTION [NOT USED] 22 3.13 MAINTENANCE ]NOT USED] 23 3.14 ATTACHMENTS [NOT USED] 24 END OF SECTION 25 Revision Log DATE NAME SUMMARY OF CHANGE 26 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised July 1,2011 Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 1 of 16 SECTION 32 90 10 LANDSCAPE IRRIGATION SYSTEM PART 1 -GENERAL 1.1 SCOPE OF WORK: A. The objective of these plans and specifications is to provide an assembled and installed automatic irrigation system.The work covered by these plans and specifications consists of providing all labor, material, equipment and services required for all work as described in the plans and specifications.The plans and specifications are intended to include everything necessary for proper completion of the project, whether each item is mentioned herein or not, and the Contractor shall provide for the same. B. Well drilling, Water storage tank installation and all related work and equipment for well and water storage tank shall be provided by others. 1.2 GENERAL DESCRIPTION OF PROJECT: A. This project consists of supplying an automatically controlled irrigation system by means of: 1. Installing a booster pump system as specified. 2. Installing an automatic control system as specified including a central control panel, master shut-off and Dbl. check valves, electric zone control valves, lightning arrestors, and wiring for power supply and low-voltage valve wiring. 3. Installing all piping as shown on plans. 4. Installing dripperline,quick coupling valves and brass diaphragm valves as shown on plans. 5. Installing isolation gate valves as shown on plans. 6. Conducting all field testing and pressurizing of system to full operating capacity. 7. Posting warning signs in locations approved by City of Fort Worth Water Department Inspector. B. The irrigation system is designed to supply 6.5 inches of precipitation monthly to all areas to be covered. 1.3 LANDSCAPE IRRIGATOR LICENSE: A. Installation of the irrigation system shall be under the supervision of a superintendent or foreman currently licensed as a Landscape Irrigator in the State of Texas. 1.4 EQUAL MATERIALS: A. It is not the intent of these specifications to limit materials to the product of any particular manufacturer.Where definite materials, equipment and/or fixtures have been specified by name, manufacturer or catalog number, it has been done to set a definite standard and a reference as to quality, application, physical conformity and other characteristics. It is not the Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 2 of 16 intention to discriminate against or prevent any dealer,jobber or manufacturer from furnishing materials,equipment,and/or fixtures that meet or exceed the characteristics of the specified items. Substitution of materials shall not be made without prior written approval from the Owner or his designated representative. B. Design criteria and water pressure must be carefully considered when selecting equipment. Only equipment that performs as specified will be considered. 1.5 LOCATION OF AND DAMAGE TO EXISTING UTILITIES: A. The Irrigation Contractor is responsible for locating underground obstacles. It is not represented that the drawings show all sewers,water lines, gas lines, telephone lines and other underground obstacles.The Contractor shall exercise caution to prevent damage to existing facilities during the progress of the construction work, taking care to locate same, where possible, in advance of the actual work.The Owner will render all assistance possible to the Irrigation Contractor in the matter of determining the location of existing utilities by making available such maps, records and other information as may be accessible to him,when requested to do so, but the accuracy of such information will not be guaranteed.The Irrigation Contractor shall make good all damage to existing utilities resulting from his operations. Should the Irrigation Contractor, in the layout of his work, encounter any pipe, underground utility, or structure, the location of which has not been furnished to him by the Owner, he shall bring such conditions to the attention of the Owner and make arrangements to bypass such obstructions. 1.6 WATER SUPPLY: A. Connections shall be made to the existing water line at the location shown on the drawings. Contractor shall provide connections downstream of the domestic water meter. All connections shall be made in accordance with City Of Fort Worth Plumbing Code. 1.7 WORKMANSHIP: A. Equipment shall be installed in accordance with the recommendations of the manufacturer and the best standard practice for this type of work. Care must be taken to keep the inside of the pipes clean and free of dirt, rock, cuttings, etc. 1.8 CODES AND PERMITS: A. All work shall be installed according to applicable codes and ordinances of the City of Fort Worth and National Electrical Code.Any permits required shall be obtained by the Irrigation Contractor. B. The misplacement, addition or omission of any letter word, punctuation mark, or drawing symbol is not to damage the true spirit, intent or meaning of these plans and specifications 1.9 WEATHER PROTECTION: A. The Irrigation Contractor shall provide protection against weather so as to protect all work, materials and fixtures from injury or damages.All new work likely to be damaged shall be covered or otherwise protected as required. B. All electrical equipment shall be provided with adequate surge and lightning protection as per manufacturers recommendations. Specifically, all controller(s)are to be protected before power or signal pulse wires are connected. 1.10 MEASUREMENT: Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 3 of 16 A. Before ordering any material or doing any work, the Irrigation Contractor shall verify all measurements of any existing and new work and shall be responsible for their correctness. Any differences which may be found shall be submitted to the Owner for consideration before proceeding with the work. No extra compensation will be allowed because of differences between actual dimensions and measurements indicated on the drawings. 1.11 PROTECTION: A. The Irrigation Contractor shall send proper notices, make all necessary arrangements and perform all other services required for the care, protection and maintenance of all public utilities, both above and below ground, assuming all responsibility and paying all costs for the repair of any damages to such utilities. B. The Irrigation Contractor shall construct and maintain all necessary temporary drainage and do all pumping necessary to keep excavations free of water. C. The Irrigation Contractor shall provide all shoring, bracing and sheeting as required for safety and for the proper execution of the work; and have same removed when the work is completed. D. Fires shall not be built on the premises except by the express consent of the Owner and City Fire Marshal. E. All work shall be performed in accordance with the national"Occupational Safety and Health Standards." 1.12 SHOP DRAWINGS AND SAMPLES: A. After checking and verifying all field measurements,the Irrigation Contractor will submit to the Owner for approval a mylar transparency and 5 prints of each shop drawing.These Will be reviewed and checked for design and materials only, and then the mylar shall be returned to the Irrigation Contractor. The prints will be retained as record copies. If resubmission is required, the mylar shall be corrected as indicated and the same procedure shall be followed.When approval is received, the Irrigation Contractor shall make sufficient prints,from the mylar to meet the needs of the Owner and the work. Not less than one such print shall be in the file of the Irrigation Contractor's Representative at the job. 1.13 IRRIGATION CONTRACTOR'S RESPONSIBILITY: A. The irrigation Contractor shall coordinate this work with the other trades so that all phases of the work may be properly coordinated without delays or damage to any parts of the work. 1.14 CHANGES IN THE WORK: A. The owner may,without invalidating the contract,order additional work or alterations to the contract. B. Any changes shall be requested in writing and the contract sum shall be adjusted according to the unit cost bid submitted by the Contractor. Any extension of time shall only be granted by change order. C. Minor changes, such as subsurface emitter tubing locations,valve and controller locations,which do not involve extra cost and are consistent with the purpose of the work Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 4 of 16 may be ordered by the Owner and no claim for an addition to the contract sum will be considered. 1.15 FINAL INSPECTION: A. A qualified person duly authorized in writing to represent the Irrigation Contractor shall be present at the final inspection to demonstrate the systems and prove the performance of the equipment. Prior to this inspection, all work under this division shall have been completed, tested, balanced and adjusted and in final operating condition. 1.16 GUARANTEE: A. The Irrigation Contractor shall guarantee the satisfactory operation of the entire system, to the extent possible under the scope of work included in this contract, and the workmanship performed by him.The entire system on which work is to be performed shall be guaranteed to be complete and work properly for a period of one year from date of acceptance, and he hereby agrees to repair or replace any defects occurring within that year free of expense to the Owner only on that work performed by him and covering materials furnished by him. 1.17 SERVICES OF IRRIGATION CONTRACTOR: A. The Irrigation Contractor shall school at least two of the Owner's employees,who will be responsible for the maintenance and operation of the irrigation system. They will include the operation of the booster pump system, controllers, valves and subsurface drip emitter tubing, and how to most effectively use the system, maintenance on all equipment including the removal and replacement of valve and controller components. S. The Irrigation Contractor shall provide,one extra complete control valve of each size used, one quick coupling valve, four quick coupling valve keys,curb stop valve key, and all special tools and equipment needed to operate and maintain the system.This equipment shall be turned over to the Owner at the completion of the job. C. The Irrigation Contractor shall provide the Owner a minimum of two copies of the parts list and manufacturer's catalog showing performance, weight,quality and functions of each item of equipment and each important system component which he furnishes under this specification,e.g.,controllers, valves, pipe, check valve,wire,tubing and double check valve assembly. 1.18 MATERIAL AND EQUIPMENT STORAGE: A. The Irrigation Contractor shall be permitted to store equipment and materials on the site, in a location designated by the Owner.The Irrigation Contractor will be completely responsible for all damages and/or losses to the irrigation materials and equipment stored on the site. Security for such materials and equipment will be furnished by the Irrigation Contractor. PART 2-MATERIALS 2.1 GENERAL: A. All materials and accessories shall be of new and unused material.Any section of pipe found to be defective before or after laying shall be replaced with new pipe.All new sprinkler irrigation equipment shall be essentially the standard product of the manufacturer.All new equipment furnished shall have in-service performance records Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 5 of 16 sufficient to verify published capabilities. Irrigation equipment shall be designed to operate efficiently at the pressure, flow and coverage indicated on the drawings. 2.2 GATE VALVES: A. Gate valves 3"and larger shall be M &H Model 4067, resilient seated w/2"operator nut or an approved equal and have bell or spigot ends,flanges or other joints as required for the piping in which they are installed.All gate valves shall be manufactured of Class D cast iron or brass conforming to the AWWA Standard C-509,or to Federal Specification WW- V-58, Class A. Gate valves shall be designed for a minimum water working pressure of 150 psi.Gate valves shall have a clear waterway equal to the full nominal diameter of the valve and shall be opened by turning counterclockwise. B. Valves 2-1/2 inches and smaller shall be NIBCO T-113 all bronze gate valve or an approved equal;and shall conform to Federal Specification MSS-5P80. 2.3 PVC PIPE AND FITTINGS: A. All main line pipe shall be Class 200 unplasticized polyvinyl chloride,Type 1, Grade 1. violet colored pipe marked continuously with the wording"CAUTION NON-POTABLE WATER". Buried Line Warning and Detectable Tape: Shall be minimum 5.5 mil composition film containing metalized layer laminated between two layers of inert plastic.Tape to contain the continuous message"CAUTION NON-POTABLE WATER LINE BURIED BELOW"; three-inch minimum width. Use with all buried pipe and place 6 inches above pipe. B. All lateral pipe 3"and larger shall be class 160 unplasticized polyvinyl chloride, Type 1, Grade 1. All 1-1/4"-1-1/2"pipe shall be Class 160 unplasticized polyvinyl chloride,Type 1, Grade 1.All 34'"-1"pipe shall be Class 200 unplasticized polyvinyl chloride, Type 1, Grade 1.All 1/2"pipe shall be Class 315 unplasticized polyvinyl chloride,Type 1, Grade 1.All plastic pipe shall be manufactured by one of the following manufacturers,or an approved equal: 1. Can-Tex Industries. 2. Certain-Teed Products Corporation 3. Ethyl Corporation 4. Gifford-Hill&Company, Incorporated 5. Johns-Manville C. 3"and larger pipe shall utilize belled ends or belled couplings using rubber gaskets in 20 foot laying lengths. Pipe sized less than 3"may be solvent welded. D. Dead end pipe that pipe not tied into a loop at both ends, shall be solvent weld type. E. All fittings to be used on 2"or smaller PVC pipe shall be Schedule 40,Type 1, Grade 1, PVC of the same domestic manufacturer.All 2"fittings shall be solvent welded. 2"pipe couplings shall utilize rubber gaskets. All fittings to be used on 3"or larger PVC pipe shall be Harco Deep Bell Ductile Iron fittings, Grade 65-45-12 or an approved equal. Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 6 of 16 F. Nipples for sprinkler heads shall be Schedule 80 PVC, threaded both ends, of the same manufacturer as the Schedule 40 fittings. Elbows shall be Schedule 40 PVC. All swing joints for quick coupling valves shall be Schedule 80, swing joint assemblies with"0" ring seals.All connections shall be watertight using methods as approved by manufacturer. Street ells are not to be used. G. All stub-outs shall extend a minimum of 18"from main pipe and they shall be capped. H. Solvent used on PVC pipe shall be of a type approved by both the manufacturer of the pipe and the manufacturer of the fittings. I. Purple colored primer used on PVC pipe and fittings shall be of a type approved by both the manufacturer of the pipe and the manufacturer of the fittings. J. All exposed PVC pipe shall be freeze protected and insulated using Urecon Pre-Insulated Pipe process or an approved equal. Insulation of associated joints,fittings and accessories shall be as per Urecon's recommendations, depending on the size and type involved.All exposed ends of insulation shall be coated with an approved waterproofing sealant prior to, leaving the factory. The product shall be manufactured in accordance to ISO-9001-2001 standards or an approved. 2.4 CONTROL SYSTEM: A. The irrigation central control system shall be the Rain Master Eagle PlusTm Central System with iCord remote receiver as manufactured by Rain Master Irrigation Systems, Inc., Part numbers shall be SA-RM2-24 for controller, EV-CAB-SEN for sensor cable, and FSMV-150P for 1-1/2" Flow sensor. Contact John Deere Greene Tech representative: Bill Rosser at 214-283-2851 for additional information. B. The central system shall consist of the following general components: 1. Evolution Central software. 2. Evolution DX2 satellite controllers. 3. Evolution flow,moisture, and weather sensing devices. 4. Evolution communication hardware. 5. Personal computer utilizing a Windows="' 95, 98, or NT operating system. C. The Evolution Central Software shall be available in Standard, International (metric), and Central-Lite versions. The Central-Lite version is identical to the Standard version but limited to fifteen satellite controllers and a single weather station.All versions shall include RolaidTm communication software for remote access to the central computer. D. The Evolution Central Software shall be available with two optional modules, Advanced ET and Advanced Irrigation Management(AIM). E. The Evolution Central Software shall have the following general features: 1. Employ an easy to use Graphic User Interface(GUI). 2. Capability to operate up to one thousand satellite controllers. 3. Remotely perform all satellite keystroke operations from the central computer. 4. Provide automatic and timely notification of system malfunctions. 5. Display, print, annotate, and save over fifty report formats. 6. Provide mixed communication modes including hardwire, phone or radio. 7. Support multiple weather stations and microclimates for rain,wind, and ET. 8. Offer two methods of ET based water management, Basic or Advanced ET. 9. Activate pump by program ( Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 7 of 16 10. Provide flow management for optimizing flow distribution and runtimes. 11. Allow for global programming and scheduling changes. 12. Display drawings and maps utilizing an optional AutoCAD-LTTM feature. Part 2.4.1 -Programming Features A. The Evolution Central System shall allow for the programming of each satellite controller. Each controller shall have twelve programs. Programs may be either irrigation or non- irrigation. Non-irrigation programs shall be for lighting, security, etc. Non-irrigation programs are independent of rain and wind shutdown modes. B. Each program shall have the following setup options: 1. Specified start times(1-8)or a continuous cycle. 2. Hour/minute or minute/second runtime format. 3. Irrigation program, yes or no. 4. Omit by date effect,on or off. 5. Overlap protection, on or off. 6. Over water limit, give warning or stop water. 7. Inter-station time delay(0-255 sec). 8. Either of two normally closed master valves, or one normally open master valve. 9. Master valve time delay(0-600 sec). 10. Pump operation,on or off. C. Each program shall have two options for setting water days. Programmed days within either a 14-day calendar or a 31-day schedule. Either option shall allow for up to eight start times per program. D. The central system shall allow for the programming up to forty-eight stations per satellite controller. Stations may be assigned to more than one program. Station runtimes may range from 1 second to 24 hours. A 'Quick Station' function shall allow for the programming of a block of stations all with the same runtime. E. Each program shall have a percentage adjustment feature (water budget). This feature shall allow all station runtimes within a program to be adjusted from 0 and 999% of their programmed runtimes that are defaulted at 100%. F. The central system shall provide an automated ET (evapotranspiration) driven water management capability utilizing user-defined base watering schedules. ET data for this function may be obtained automatically from a Rain Master Weather Station or entered manually by the user. A global ET percentage adjustment (0-999%) feature allows the user to make corrections for site differences. G. The central system shall allow the user to enter base schedules and establish a reference ET from which all calculations are derived. On a daily basis, the software will automatically adjust run times for all stations dependent upon daily ET. H. The central system includes a 'View All' function. This feature shall allow the user to review all programmed data within a satellite controller on a single screen. Following are the View All options: 1. Start times-Shows all eight start times for all twelve programs. 2. Station run times-Shows all station run times across all twelve programs. 3. Program run times-Shows adjusted program runtimes accounting for ET for all Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 8 of 16 twelve programs. 4. Master/pump-Shows operations across all twelve programs. 5. Start/end time utility - Calculates and displays all program start and end times for all satellites in a system considering adjusted ET station runtimes, program percent, inter-station delay,and global ET percent. I. The central system shall provide the capability to upload and download programs between the central computer and the satellite controllers. Programs may be automatically downloaded at times set by the user. Programs may be downloaded by type: all valid programs, all modified programs, or all programs. Programs may be uploaded and downloaded manually at anytime. 2.5 REMOTE CONTROL VALVES: The remote control valves shall be Hunter ICV series plastic electric diaphragm valve, or an approved equal.. The valve shall be a normally closed, electronically-actuated, diaphragm-operated, remote-control valve. The valve will be capable of operating between 20 and 220 PSI with a flow range of between 0.1 and 300 GPM. Pressure loss shall be 17.7 PSI maximum at 200 GPM. The valve shall be available in a globe configuration with 1-,1-1/2- or 2-inch Female National Pipe Thread (FNPT) inlet and outlet. When specified, the valve shall be configured with British Standard Pipe threads. The valve shall be equipped with a flow control mechanism with removable handle that will regulate flow from full on to completely off. The body and bonnet shall be molded of non-corrodible, glass-reinforced nylon, rated to 220 PSI. The body of the valve shall have brass inserts, with through-holes, which will accept the bonnet bolts. The bonnet bolts shall be serviceable with a slotted screwdriver, Phillips screwdriver, or a hex wrench, and shall be held captive in the bonnet when the bonnet is removed from the valve body. The diaphragm assembly shall be of molded construction, reinforced with nylon fabric and have a thermoplastic elastomer seating material. The valve shall be equipped with an internal filter as well as a self-cleaning metering rod, so only clean water can enter the solenoid chamber. An optional filter cleaning system, that cleans a stainless steel filter each time the valve opens and closes, shall be available. All metal parts internal to the valve shall be manufactured from corrosion-resistant stainless steel. The valve shall be available with an optional adjustable pressure regulating device with a calibrated dial for setting of the outlet pressure. (The regulator shall be capable of adjusting the outlet pressure from between 20 and 100 PSI when inlet pressure is 15 PSI or greater than regulated outlet pressure.) The regulated downstream pressure shall remain constant regardless of variations in upstream pressure. The regulation shall be maintained when valve is manually operated with use of internal bleed valve. The regulator should be capable of regulating upstream pressures from 35 psi to 220 psi. The standard solenoid shall be a 24 VAC unit with a 370mA inrush current and 190mA holding current at 60 cycles and a 475 mA inrush current and 230 mA holding current at 50 cycles. When specified, the unit shall be equipped with a DC latching solenoid for use with battery-operated controllers. The solenoid shall be an encapsulated, one-piece unit with captive plunger. It shall be equipped with manual internal bleed capability to release the upper chamber water to the downstream piping, allowing the valve to open. The valve shall carry a five-year, exchange warranty(not prorated). The valve shall be manufactured by Hunter Industries Incorporated, San Marcos, California,or an approved equal. 2.6 120 VOLT WIRING: A. All 120 volt wiring shall be of solid copper wire type, minimum size of 14 AWG.Wire for power supply to satellites shall be as sized to allow a voltage drop of not more than 12 Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 9 of 16 volts under maximum power requirement. All wire shall be installed according to local electrical codes and must be insulated with PVC and bear UL approval(Type UF)for direct underground burial. B. All wire connections and/or splicing shall be made using"Scotch-Loks"connectors or an approved equal. 2.7 VALVE BOXES: A. Valve boxes for gate valves and automatic control valves shall be cast iron and may have height adjustment.All valve boxes shall utilize locking covers and color-coded for"NON- POTABLE"water. B. Valve box for double check valve assembly shall be precast concrete, Brooks or equal, and sized as per City's specifications. Covers shall be cast iron, locking and color-coded for"NON-POTABLE"water.. C. All Valve boxes and/or vaults shall be installed in accordance with the Fort Worth Plumbing codes. 2.8 QUICK COUPLING SPRINKLER VALVES: A. All quick coupling sprinkler valves shall be a one piece, 1"in size, single lug brass or bronze unit with a self-closing rubber cover and color-coded for"NON-POTABLE"water. Valves shall be guaranteed to withstand 150 psi pressure without leaking. Valves shall be Toro 474-01, or an approved equal. 2.9 AIR AND VACUUM RELEASE VALVES: A. Install per manufacturer's recommendations. 2.10 BACKFLOW PREVENTER: A. Backflow Prevention Devices: Shall be reduced pressure principle device(RPZ)with city of Fort Worth,TX and/or TCEQ's approval and shall be a USC Foundation approved device. Devices shall be equipped with double shutoff valves and manufactured by Febco, or an approved equal. Febco's Model 860 RPZ Valve shall be used,or an equivalent model, and approved by the City Cross-Connection Inspector. Provide a galvanized 3/16 inch general- purpose carbon shell chain, lock and keys to secure the valve handles on units 4 inches and larger. 2.11 BOOSTER PUMP: Part 1 -General Manufacturer. The pumping system shall be manufactured by John Deere Green Tech or equal as approved by the purchaser prior to bid opening. The manufacturer shall closely adhere to the following specifications. Part 2-Mechanical Scope. The pump station shall be completed skid-mounted, with an enclosure, manufactured by a single manufacturer. All equipment including but not limited to, pumps, motors, piping, valves and controls shalt be mounted on a common steel base to form a complete operation pumping system. Station Base. The pump system station base shall be designed and fabricated to provide Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 10 of 16 proper structural support for all attached equipment. Pump station base shall be manufactured from 14 gauge carbon steel.The base shall have pre-cut holes for the inlet and discharge of the pumping system. Systems requiring inlets and discharges to be outside the enclosure will not be accepted. Piping. Pump inlet and discharge piping shall be schedule 40 galvanized steel. All bolts used in the assembly shall be SAE J429 Grade 5 unichrome plated to retard corrosion. Enclosure. The pumping system enclosure shall be weather resistant. The lid shall have a bullet style double hinge for removal from the base. The enclosure shall also have a single latch for use with any type of padlock to prevent unauthorized entry.The enclosure shall be manufactured from marine grade aluminum with pre-punched louvers for proper heat dissipation from the motor. Coating. The station base shall be powder coated to a thickness of 0.5 mils and be black in color Pumps. Pumps shall be horizontal, end-suction centrifugal and be of the back pull-out design to allow access to the impeller without disturbing the piping arrangement. The pump casing/volute shall be manufactured of ASTM A48, class 25-25 close-grained cast iron precision machined to modern hydraulic standards. Motors. Motors shall be NEMA JM, JP or C face ODP design with 200 degree, C-rated, high efficiency, moisture resistant copper windings impregnated with high-temperature polyester insulation resin. Motors shall have locked shaft end bearings for longer life and positive end play control. Valves.A discharge isolation valve shall be installed inside the cover to isolate the system from the irrigation system. Pressure Gauge.A discharge pressure gauge shall be installed. Gauge shall be silicon filled to reduce wear from vibration and shall be accurate to within 2%. Disconnect.A three-polemain disconnect switch shall be mounted in the enclosure to completely disconnect the incoming power. Variable Frequency Drive.All control shall be through the VFD including set point pressure control. Skid Wiring.All station wiring shall be completed by the pump system manufacturer. All other wiring including incoming power and external irrigation control wiring shall be the responsibility of the owner or contractor. Run Testing. Each system shall be fully run tested by the manufacturer to meet exact specified performance. 2.12 TECHLINE: A. Techline: Continuously Self-Flushing, Pressure-Compensating Dripperline: The dripperline shall consist of nominal sized one-half inch low density, linear polyethylene tubing,housing internal pressure compensating,continuously self- flushing, integral drip emitters. The tubing shall be brown in color and conform to an outside diameter(O.D.)of 0.67 inches, and an inside diameter(I.D.)of 0.57 inches. The emitters shall have the ability to independently regulate discharge rates, with an output pressure of seven (7)to seventy(70)psi,at a constant flow and with a coefficient of variability(Cv)of 0.03. The emitter discharge rate shall be either 0.61 gallons per hour(gph),or 0.92 gallons per hour(gph), utilizing a Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 11 of 16 combination turbulent flow/reduced pressure compensation cell mechanism and a diaphragm to maintain uniform discharge rates. The emitters shall continuously clean themselves while in operation. The dripperline shall be available in 12 inch, 18 inch, or 24 inch spacing between emitters. 1. Techline 17 mm (0.57") Fittings: All Techline connections shall be made with approved Techline 17 mm (0.57")insert fittings. 2. Line Flushing Valves: All Techline systems shall utilize Netafim Automatic Line Flushing Valves at the end of each independent zone or dripperline(maximum flow per valve; 15 gpm). This valve shall be capable of flushing one gallon of water at the beginning of each irrigation cycle. The valves shall be either Netafim model TL050MFV-1,with 1/2" MPT connection,or Netafim model TLFV-1 with Techline connection. 3. Air/Vacuum Relief Valves: Each independent irrigation zone shall utilize a Techline AirNacuum Relief Valve, model TLARV, at the zone's highest point(s). The purpose of the valve is to evacuate air from the zone at start-up,and to relieve vacuum at zone shut down. 3. Pressure Regulator: The pressure regulator shall be a Netafim piston-type unit with an externally accessible regulation unit that can be serviced without removing the valve from the system. The pressure regulator shall have a built in indicator that shows when the proper outlet pressure has been reached. It shall respond immediately to any inlet pressure variation. The pressure regulator shall be capable of regulating downstream pressure from 15 psi to 50 psi using interchangeable, color-coded regulating springs. Maximum upstream pressure shall not exceed 120 psi. The pressure regulating valve shall be a Netafim model PRV075HF35. 4. Disc Filter: The filter shall be a multiple disc filter with color-coded filter elements indicating the mesh size of the element being used. The discs shall be constructed of chemical resistant thermoplastic for corrosion resistance. The filter shall be a Netafim model DF075-120—or DF100- 120,with a maximum flow of 18 gpm and a maximum pressure loss of 3.40 psi. PART 3-EXECUTION 3.1 GENERAL: A. Unless otherwise specified or shown on the drawings, the construction of sprinkler lines shall include excavation and backfill,the furnishing, installing and testing of sprinkler pipe and fittings, and electrical conductors and all other work in accordance with the plans and specifications.All irrigation installation shall be coordinated with the construction of the facility and the landscaping. 3.2 AUTOMATIC CONTROLLERS: A. Controller(s)shall be installed at locations shown on the drawings. Controller shall be installed on concrete pad and pedestal as shown in the details on the drawings. Excavation for proper construction of concrete slab shall be unclassified. Contractor shall dress and clean up around slab upon completion of unit. B. The controller shall be installed at the location shown on the plan and as approved by Owner's Representative. All wiring above ground to control module shall be installed in conduit of sufficient size. C. Concrete for the base shall develop a minimum psi of 2,500 after curing. Portland cement shall confirm to ASTM C-150-53,Type 1.Aggregate shall conform in general to ASTM C- 33, Class A. Water used in mixing shall be clean,fresh from city mains. Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 12 of 16 D. All electrical wiring shall be installed according to the City and National Codes. 3.3 120 VAC POWER WIRE: A. All power and signal pulse wiring shall be installed,routed and sized in accordance with manufacturers specifications.All wires in a common trench shall be bundled and taped together every 10 feet.All wire shall be consistently color coded through the system with a different color for each wire.An explanation of the color code shall be included on the as- built plan upon completion of the project. 3.4 WIRE SPLICES: A. Splices shall be in strict accordance with the kit manufacturer's recommendations.Wires shall be cleaned before splices are made. Splices at control valves shall be left exposed in the valve boxes. 3.5 PVC PIPE: A. PVC pipe,coupling and fittings shall be handled and installed in accordance with the manufacturer's recommendations. Each pipe length shall be properly spaced in jointing to allow for expansion and contraction. Piping will be snaked in trench as shown in the trenching details. If necessary, stakes are to be used to make pipe snake in trench.All stakes are to be removed after trench is backfilled. B. Install concrete thrust blocks as necessary at direction changes, sizes changes, terminations and valves. Blocking shall be a minimum of 1.5 C.F. each. Set concrete blocking against undisturbed earth. C. The interior of the pipe shall be thoroughly cleaned of all foreign matter before lowered into the trench, and shall be kept clean during laying operations by means of plugs or other approved methods.The pipe shall not be laid in water,or when trench or weather conditions are unsuitable for the work. Water shall be kept out of the trench until the joints are completed.When work is not in progress, open ends of pipe and fittings shall be securely closed so that no trench water, earth or other substance will enter the pipes or fittings.Any pipe that has the grade or joint disturbed after laying shall be taken up and re- laid. Fittings at bends in the pipe line and at ends of lines shall be firmly wedged against the vertical face of the trench by means of concrete thrust blocks. D. Joints in all screwed fittings shall be made by applying Teflon tape on male threads. E. After installation,the lines will be flushed until they are free of rocks, dirt, debris,etc., before the heads are installed. F. Pipes and/or sleeves placed underground and not immediately connected to shall be capped or plugged to prevent water and dirt from entering the pipe. 3.6 VALVES: A. Install all new valves as indicated on the plans or as may be required for the proper- control of the piping systems in which they are incorporated. Valves shall be buried deep enough so that the valve box lid will not protrude above the ground.Valves shall be set vertically. B. Control valves shall be set to give the correct pressure for proper zone operation. C. Teflon tape is to be used on all male threads when installing valves. Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 13 of 16 3.7 QUICK COUPLING SPRINKLER VALVES: A. Quick coupling sprinkler valves shall be Installed in a vertical position as shown in the details and at locations shown on the drawings or as designated by Inspector. All swing joints shall be fitted with Schedule 80 nipples and Schedule 40 threaded elbows. Street ells are not to be used. 3.8 DRIPPER LINE: A. Dripperline Installation: 1. Techline is designed for use in surface and sub-surface applications utilizing a grid design, the result being a complete wetted area within the grid. it can also be installed as a single or"snaked"lines where grids are not justified. The most uniform way to install Techline is sub-surface at a uniform depth as specified. 2. Techline is available in dripper flow rates of 0.61 gallons per hour(gph) and 0.92 gallons per hour(gph)with drippers spaced at 12 inch, 18 inch or 24 inch intervals.The drippers are designed to regulate flow at the specified output from 7 psi to 70 psi with maximum recommended pressure of 45 psi when using unclamped Techline insert fittings. 3. The choice of dripper spacing, Techline lateral spacing and depth is dependent on the soil type and plants being used. The following chart gives spacing recommendations for both turf and landscape applications GENERAL SPACING GUIDELINES FOR TECHLINE DRIPPERLINE FOR FOR LANDSCAPE AND TURF APPLICATIONS Trees,Shrub Beds and Ground Cover Applications Clay Soil Loamy Soil Sandy Soil Flow 0.61 GPH 1.92 GPH 0.92 GPH Dripper Interval 24" 18" 12" ;Techline Lateral Spa • DepthBurial Application to + • . of g x h, . Dripper • Dripper DepthBurial + •• • hr 1 •8 Time to + • • of 39 min. 15 min. 1 4. It is necessary to use Techline insert fittings for all Techline connections Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 14 of 16 to ensure the integrity of the connection. Techline dripperline has an ID of 0.57", or 17 mm, which differs from most other polyethylene tubing dimensions and improperly sized fittings will cause leaks. 5. Techline can be installed by: a. Trenching, b. Laying it out on a sub-grade lower than finished grade and backfilling to the specified grade depth, C. Vibratory plow, or Surface installation using Techline staples (TLS6)to hold it in place along with a four(4)to six(6)inch shredded bark mulch cover. B. Drip Tubing: Install all drip tubing as detailed on drawings or specifications. Use only Teflon tape on all threaded connections. 3.9 SLEEVES: A. All pipe installed under hard surfaced walks. service roads etc., must be in Sch.40 PVC sleeves and must be of sufficient size to easily accept the designed size pipe. A separate sleeve may be provided for the electrical wires. It must also be of Sch 40 PVC and of sufficient size to easily accept the required amount of materials as designed. 3.10 ISOLATION VALVES: A. Gate valves must be installed as shown on plan and as recommended by the manufacturer and be placed in suitable valve boxes of proper size for easy access to the valve. 3.11 TRENCH EXCAVATION AND BACKFILL: A. The Contractor shall perform all excavation to the depth indicated in these specifications and drawings.All excavated materials not required for fill or backfill shall be removed and wasted as directed by the inspector. The banks of trenches shall be kept as nearly vertical as practicable. Trenches shall be wide enough to permit proper placing of pipe.Where rock excavation is required,or where stones are encountered in the bottom of the trench that would create a concentrated pressure on the pipe, the rock or stones shall be removed to a depth of 4"minimum below the trench depth indicated.The over depth rock excavation and all excess trench excavation shall be backfilled with loose, moist earth or sand, thoroughly tamped. Whenever wet or otherwise unstable soil that is incapable of supporting the pipe is encountered in the trench bottom, such soil shall be removed to a depth and length required and the trench backfilled to trench bottom grade as hereinafter specified,with coarse sand,fine gravel or other suitable material. B. Bottom of trench grade shall be continued past ground surface deviations to avoid air pockets and low collection points in line.The minimum cover specifications shall govern regardless of variations in ground surface profile and the occasional deeper excavation required at banks and other field conditions. Excavation shall be such that a uniform trench grade variation will occur in all cases where variations are necessary. In no case shall the angle of deflection from one pipe length to another exceed 5 degrees. C. Trench excavation shall comprise the satisfactory removal and disposition of all materials, and shall include all shoring and sheeting required to protect the excavation and to safeguard employees. D. During excavation materials suitable for backfilling shall be stockpiled in an orderly manner a sufficient distance back from edge of trenches to avoid overloading and prevent slides or cave-ins. Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 15 of 16 E. The trenches shall be carefully backfilled with the excavated materials approved for backfilling, consisting of earth, loam, sandy clay, sand or other approved materials,free from large clods of earth or stone. Rock, broken concrete or pavement and large boulders shall not be used as backfill material.The backfill shall be thoroughly compacted and evened off with the adjacent soil level. Any materials not suitable for backfill shall be removed from the site and disposed of. F. Selected fill dirt or sand shall be used if soil conditions are rocky. In rocky areas the trenching depth shall be four inches below normal trench depths to allow for this bedding. The fill dirt or sand shall be used in filling four inches above the pipe or wires.The remainder of the backfill shall contain no lumps or rocks larger than one inch.The top six inches of backfill shall be free of rocks, subsoil or trash. G. Backfill shall be placed in layers; the thickness of the layers shall depend on the nature of the material and the method of compaction used. Compaction shall be accomplished in such a manner as to assure that there will be no future subsidence. H. Any trenches improperly backfilled, or where settlement occurs, shall be reopened to the depth required for compaction, then refilled and compacted with the surface restored to the required grade and left in a completed surface condition as described above. I. All excavation and backfill shall be unclassified and covered in the basic bid. No additional fees will be allowed for rock encountered. 3.12 LEAK TEST: A. When the main line or sections of the main line, laterals, swing joints, quick couplers and valves have been installed,the system (or section)will be thoroughly flushed.The system (or section)will then be pressurized during a 24 hour period to the operating pressure. B. Any leakage found will be repaired and retested for another 24 hour period before any backfilling occurs.This procedure shall be repeated until all leaks are eliminated. 3.13 CLEANING AND FLUSHING SYSTEM: A. After pipe,fittings, and valves have been installed and connections made to the water source,flush pipes several times until free of all rocks, dirt, trash, pipe shavings or debris before installing heads.After the pipe has been thoroughly flushed start installing the dripper tubing, flush valves, air/vacuum release valves, etc. After the heads have been installed, the system is to be used several times before final inspection.The dripper zones shall flushed as many times as necessary to remove all debris before final inspection. 3.14 CLEANUP: A. The Contractor shall make final cleanup of all parts of the work before final acceptance. This cleanup shall include removal of all construction materials and equipment, and in general preparing the site in an orderly and finished appearance. A. The Contractor shall also remove fro the site any rock or extra dirt that resulted from this contract and he shall restore the site to its original condition. PART 4-METHOD OF MEASUREMENT MEASUREMENT: Landscape Irrigation Systems described in this section will be paid for on a lump sum basis wherein no measurement will be made. Section 32-90-10 LANDSCAPE IRRIGATON SYSTEM Page 16 of 16 PART 5--BASIS OF PAYMENT PAYMENT: A. Landscape Irrigation Systems will be paid for at the Contract lump sum, which price will be full compensation for furnishing and installing equipment; shop drawings; providing all submittals and warranties; furnishing all labor, materials, tools, equipment; and incidentals necessary to complete the work as described in this section and related other sections of these Specifications and plans,as well as maintenance until final acceptance. B. Payment will be made under: Pay Item NUMBER PAY ITEM PAY UNIT Landscape Irrigation System Lump Sum END OF SECTION G r 03 r � v:t .0 S1 c`�i 0 71 ' a `. � r a u d � C r - .c om c a ° c w LL � 0 � Q ' r Ea� � S � m � Y � Tj a a U a;q �± a to o n dg i n Q tn Fcma Ln 0:cc ty4m N 7 +p N� .y �N JOB NO. P202090168 Section 32-90-10 MARY'S CREEK RECYCLING CENTER LANDSCAPE IRRIGATON SYSTEM Page 1 of i ATTACHMENT `C' Warning Sign for NON-POTABLE Water UJ F- W Z Z 3291 19-1 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS Page 1 of 3 1 SECTION 32 9119 2 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Furnish and place topsoil to the depths and on the areas shown on the Drawings. 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include but are not necessarily limited to 10 1. Division 0-Bidding Requirements,Contract Forms,and Conditions of the Contract 11 2. Division 1 -General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Measurement 15 a. Measurement for this Item shall be by cubic yard of Topsoil in place. 16 2. Payment 17 a. The work performed and materials furnished in accordance with this Item and 18 measured as provided under"Measurement"will be paid for at the unit price 19 bid per cubic yard of Topsoil. 20 b. All excavation required by this Item in cut sections shall be measured in 21 accordance with provisions for the various excavation items involved with the 22 provision that excavation will be measured and paid for once,regardless of the 23 manipulations involved. 24 3. The price bid shall include: 25 a. Furnishing Topsoil 26 b. Loading 27 c. Hauling 28 d. Placing 29 1.3 REFERENCES [NOT USED] 30 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 31 1.5 ACTION SUBMITTALS [NOT USED] 32 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 33 1.7 CLOSEOUT SUBMITTALS [NOT USED] 34 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 35 1.9 QUALITY ASSURANCE [NOT USED] 36 1.10 DELIVERY,STORAGE,AND HANDLING [NOT USED] 37 1.11 FIELD [SITE] CONDITIONS [NOT USED] 38 1.12 WARRANTY [NOT USED] CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 3291 19-2 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS Page 2 of 3 I PART 2- PRODUCTS 2 2.1 OWNER-FURNISHED loR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 3 2.2 MATERIALS 4 A. Topsoil 5 1. Use easily cultivated, fertile topsoil that: 6 a. Is free from objectionable material including subsoil,weeds,clay lumps, non- 7 soil materials,roots,stumps or stones larger than 1.5 inches 8 b. Has a high resistance to erosion 9 c. Is able to support plant growth 10 2. Secure topsoil from approved sources. 11 3. Topsoil is subject to testing by the City. 12 4. pH: 5.5 to 8.5. 13 5. Liquid Limit: 50 or less 14 6. Plasticity Index: 20 or less 15 7. Gradation: maximum of 10 percent passing No. 200 sieve 16 B. Water: Clean and free of industrial wastes and other substances harmful to the growth 17 of vegetation 18 2.3 ACCESSORIES [NOT USED) 19 2.4 SOURCE QUALITY CONTROL [NOT USEDI 20 PART 3- EXECUTION 21 3.1 INSTALLERS INOT USED] 22 3.2 EXAMINATION [NOT USED] 23 3.3 PREPARATION [NOT USED] 24 3.4 INSTALLATION 25 A. Finishing of Parkways 26 1. Smoothly shape parkways,shoulders,slopes, and ditches. 27 2. Cut parkways to finish grade prior to the placing of any improvements in or 28 adjacent to the roadway. 29 3. In the event that unsuitable material for parkways is encountered,extend the depth 30 of excavation in the parkways 6 inches and backfill with top soil. 31 4. Make standard parkway grade perpendicular to and draining to the curb line. 32 a. Minimum: I/4 inch per foot 33 b. Maximum:4:1 34 c. City may approve variations from these requirements in special cases. 35 5. Whenever the adjacent property is lower than the design curb grade and runoff 36 drains away from the street,the parkway grade must be set level with the top of the 37 curb. 38 6. The design grade from the parkway extends to the back of the walk line. 39 7. From that point(behind the walk),the grade may slope up or down at maximum 40 slope of 4:1. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 3291 19.3 TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS Page 3 of 3 1 B. Placing of Topsoil 2 1. Spread the topsoil to a uniform loose cover at the thickness specified. 3 2. Place and shape the topsoil as directed. 4 3. Hand rake finish a minimum of 5 feet from all flatwork. 5 4. Tamp the topsoil with a light roller or other suitable equipment. 6 3.5 REPAIR/RESTORATION] [NOT USED] 7 3.6 RE-INSTALLATION [NOT USED] 8 3.7 FIELD QUALITY CONTROL [NOT USED] 9 3.8 SYSTEM STARTUP[NOT USED] 10 3.9 ADJUSTING ]NOT USED] 11 3.10 CLEANING [NOT USED] 12 3.11 CLOSEOUT ACTIVITIES [NOT USED] 13 3.12 PROTECTION [NOT USED] 14 3.13 MAINTENANCE ]NOT USED) 15 3.14 ATTACHMENTS [NOT USED) 16 END OF SECTION 17 Revision Log DATE NAME SUMMARY OF CHANGE 18 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 339343-1 TREES AND SHRUBS Pagel of 8 1 SECTION 32 93 43 2 TREES AND SHRUBS 3 PART1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Tree and shrub planting and maintenance within street right-of-way and easements. 7 2. Tree removal and transplant is to be performed in accordance with Section 31 10 00 8 B. Deviations from this City of Fort Worth Standard Specification 9 1. None. 10 C. Related Specification Sections include,but are not necessarily limited to: I I 1. Division 0-Bidding Requirements,Contract Forms, and Conditions of the Contract 12 2. Division 1 -General Requirements 13 3. Section 31 10 00—Site Clearing 14 4. Section 32 92 13 -Hydromulching, Seeding and Sodding 15 5. Section 32 91 19-Topsoil Placement and Finishing of Parkways 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Plant Tree 19 a. Measurement 20 1) Measurement for this Item shall be per each by caliper inch. 21 b. Payment 22 1) The work performed and materials furnished in accordance with this Item 23 and measured as provided under"Measurement"will be paid for at the unit 24 price bid per each tree to be Planted by caliper inch. 25 c. The price bid shall include: 26 1) Furnishing and installing trees 27 2) Hauling 28 3) Grading and backfilling 29 4) Excavation 30 5) Fertilization 31 6) Water 32 7) Removing and disposing of surplus material 33 1.3 REFERENCES 34 A. Reference Standards 35 I. Reference standards cited in this specification refer to the current reference standard 36 published at the time of the latest revision date logged at the end of this 37 specification, unless a date is specifically cited. 38 2. American National Standards Institute(ANSI): 39 a. ANSI Z60.1,American Standard for Nursery Stock 40 3. Hortus Third,The Staff of the L.H. Bailey Hortorium. 1976. MacMillan Publishing 41 Co.,New York. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 329343-2 TREES AND SHRUBS Page 2 of 8 1 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 2 1.5 ACTION SUBMITTALS [NOT USED] 3 1.6 INFORMATIONAL SUBMITTALS 4 A. Tree data: Submit certification from supplier that each type of tree conforms to 5 specification requirements. 6 1.7 CLOSEOUT SUBMITTALS [NOT USED] 7 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 8 1.9 QUALITY ASSURANCE 9 A. Coordination 10 1. Coordinate with City Forester prior to beginning construction activities adjacent to I I or that will impact existing trees and shrubs. 12 B. Qualifications 13 1. Landscaper specialized in landscape and planting work 14 C. Substitutions 15 1. Not permitted unless approved by City when specified planting material is not 16 obtainable 17 a. Submit proof of non-availability together with proposal for use of equivalent 18 material. 19 b. Substitutions of larger size or better grade than specified will be allowed upon 20 approval by City Forester,but with no increase in unit price. 21 1.10 DELIVERY,STORAGE,AND HANDLING 22 A. Do not remove container grown stock from containers before time of planting. 23 B. Delivery and Acceptance Requirements 24 1. Ship trees with Certificates of Inspection as required by governing authorities. 25 2. Label each tree and shrub with securely attached waterproof tag bearing legible 26 designation of botanical and common name. 27 3. Use protective covering during delivery. 28 4. Deliver packaged materials in fully labeled original containers showing weight, 29 analysis and name of manufacturer. 30 C. Storage and Handling Requirements 31 1. Protect materials from deterioration during delivery, and while stored at Site. 32 2. Do not prune prior to installation. 33 3. Do not bend or bind-tie trees or shrubs in such manner as to damage bark,break 34 branches,or destroy natural shape. 35 1.11 FIELD CONDITIONS [NOT USED] 36 1.12 WARRANTY 37 A. Warranty Period: 12 months after job acceptance 38 B. Warrant trees against defects including: 39 1. Death CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 329343-3 TREES AND SHRUBS Page 3 of 8 1 2. Unsatisfactory growth 2 3. Loss of shape due to improper pruning, maintenance,or weather conditions 3 C. Plumb leaning trees during warranty period. 4 D. Remove and replace trees found to be dead during warranty period. 5 E. Remove and replace trees which are in doubtful condition at end of warranty period,or 6 when approved by City,extend warranty period for trees for full growing season. 7 PART 2- PRODUCTS 8 2.1 OWNER-FURNISHED PRODUCTS [NOT USED] 9 2.2 MATERIALS 10 1. General 11 a. Plants shall be true to species and variety specified, grown under climatic 12 conditions similar to those in the locality of the project for at least 2 years and 13 have been freshly dug during the most recent favorable harvest season. 14 b. All plant names and descriptions are as defined in Hortcrs Third. 15 c. All plants are to be grown and harvested in accordance with the Anrericalt 16 Standard for Nursery Stock. 17 d. Unless approved by the City Forester,plants shall have been grown in a latitude 18 not more than 200 miles north or south of the latitude of the project unless the 19 provenance of the plant can be documented to be compatible with the latitude 20 and cold hardiness zone of the planting location. 21 2. Trees 22 a. Provide container grown trees which are straight and symmetrical and have 23 persistently preferred main leader. 24 b. Mark the tree's north orientation in the nursery for all deciduous trees grown in 25 the field with a I-inch diameter spot of white paint on the tree trunk within the 26 bottom twelve inches of the trunk. 27 c. Crown shall be in good overall proportion to entire height of tree with 28 branching configuration as recommended by ANSI Z60.1 for type and species 29 specified. 30 d. Trees designated as balled and burlapped(B&B) shall be properly dug with 31 firm,natural balls of soil retaining as many fibrous roots as possible,in sizes 32 and shapes as specified in the American Standard for Nursery Stock. Balls shall 33 be firmly wrapped with nonsynthetic,rottable burlap and secured with nails and 34 heavy,nonsynthetic,rottable twine.The root collar shall be apparent at surface 35 of ball.Trees with loose,broken,processed, or manufactured root balls will not 36 be accepted,except with special written approval before planting. 37 e. Where clump is specified, furnish plant having minimum of three stems 38 originating from common base at ground line. 39 f Measure trees by average caliper of trunk as follows: 40 1) For trunks up to 4 inches or less in diameter,measure caliper 6 inches 41 above top of root ball. 42 2) For trunks more than 4 inches,measure caliper 12 inches above top of root 43 ball. 44 3) Caliper measurements 45 a) By diameter tape measure CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 329343.4 TREES AND SHRUBS Page 4 of 8 I b) Indicated calipers on Drawings are minimum 2 c) Averaging of plant caliber: not permitted 3 g. Trees shall conform to following requirements: 4 1) Healthy 5 2) Vigorous stock 6 3) Grown in recognized nursery 7 4) , Free of: 8 a) Disease 9 b) Insects 10 c) Eggs 11 d) Larvae 12 e) Defects such as: 13 (1) Knots 14 (2) Sun-scald 15 (3) Injuries 16 (4) Abrasions 17 (5) Disfigurement 18 (6) Borers and infestations 19 3. Soil Products 20 a. Topsoil: See 32 91 19. 21 b. Peat moss,mulch and fertilizer: Use material recommended by City Forester 22 for establishment of healthy stock after replanting. 23 4. Stakes and Guys 24 a. Provide minimum 8-foot long steel T-stakes and 1 inch wide plastic tree chains. 25 b. Where applicable for anchoring trees,use wood deadmen: 26 l) Minimum: 2-inch by 4-inch stock 27 2) Minimum: 36 inches long and buried 3 feet. 28 3) Provide white surveyor's plastic tape for flagging tree guys. 29 5. Tree Wrap,Twine and Seal 30 a. Wrap 31 1) First quality 32 2) Bituminous impregnated tape 33 3) Corrugated or crepe paper,specifically manufactured for tree wrapping and 34 having qualities to resist insect infestation 35 b. Twine 36 1) Lightly tarred,medium-coarse sisal(lath)yarn 37 2) Do not use nails or staples to fasten wrapping 38 c. Seal: Commercially available tree wound dressing specifically produced for use 39 in sealing tree cuts and wounds 40 6. Water: clean and free of industrial wastes or other substances harmful to the growth 41 of the tree 42 2.3 ACCESSORIES [NOT USED] 43 2.4 SOURCE QUALITY CONTROL 44 A. Notify City,prior to installation,of location where trees that have been selected for 45 planting may be inspected. 46 B. Plant material will be inspected for compliance with following requirements. 47 1. Genus, species,variety, size and quality CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 329343-5 TREES AND SHRUBS Pagc 5 oP8 1 2. Size and condition of balls and root systems, insects, injuries and latent defects 2 PART 3- EXECUTION [NOT USED) 3 3.1 INSTALLERS [NOT USED] 4 3.2 EXAMINATION [NOT USED] 5 3.3 PREPARATION 6 A. General 7 1. Schedule work so that planting can proceed rapidly as portions of site become 8 available. 9 2. Plant trees after final grades are established and prior to seeding or sodding. 10 3. When planting of trees occurs after seeding work,protect seeded areas and I 1 promptly repair damage to seeded areas resulting from tree planting operations in 12 compliance with requirements of Section 32 92 13. 13 4. Layout individual trees at locations shown on Drawings. 14 5. In case of conflicts,notify City before proceeding with work. 15 6. Stake trees for City approval. 16 B. Preparation of Planting Soil 17 1. Before mixing,clean topsoil of roots,plants,sod,stones,clay lumps,and other 18 extraneous materials harmful or toxic to plant growth. 19 2. Strip and utilize 4 inch layer of top soil from existing ground. 20 3. Decay mixing of fertilizer when planting will not follow placing of planting soil 21 within 48 hours. 22 4. Incorporate amendments into soil as part of soil preparation process prior to fine 23 grading, fertilizing,and planting. 24 5. Broadcast or spread amendments evenly at specified rate over planting area. 25 6. Thoroughly incorporate amendments into top 3 or 4 inches of soil until 26 amendments are pulverized and have become homogeneous layer of topsoil ready 27 for planting. 28 3.4 INSTALLATION 29 A. Planting 30 1. Excavate pits,beds,or trenches with vertical sides and with bottom of excavation 31 raised minimum of 6 inches at center for proper drainage. 32 2. Provide following minimum widths: 33 a. 15 gallon containers or larger,2 feet wider than diameter of root ball 34 b. 1 and 5 gallon containers,6 inches wider than diameter of root ball 35 3. When conditions detrimental to plant growth are encountered,such as 36 unsatisfactory soil,obstructions,or adverse drainage conditions,notify City before 37 planting. 38 4. Deliver trees after preparations for planting have been completed and plant 39 immediately. 40 5. When planting is delayed more than 6 hours after delivery 41 a. Set trees and shrubs in shade. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 329343-6 TREES AND SHRUBS Pagc 6 of 8 1 b. Protect from weather and mechanical damage. 2 c. Keep roots moist by covering with mulch,burlap,or other acceptable means of 3 retaining moisture,and water as needed. 4 6. Lift plants only from the bottom of the root balls or with belts or lifting harnesses of 5 sufficient width not to damage the root balls. Do not lift trees by their trunk as a 6 lever in positioning or moving the tree in the planting area. 7 7. Remove plastic,paper,or fibrous pots from the containerized plant material. Pull 8 roots out of the root mat,and cut circling roots with a sharp knife. Loosen the 9 potting medium and shake away from the root mat. Immediately after removing the 10 container, install the plant such that the roots do not dry out. Pack planting mix 1 I around the exposed roots while planting. 12 8. Cut ropes or strings from the top of root balls and trees after plant has been set. 13 Remove burlap or cloth wrapping and any wire baskets from around top half of 14 balls. Do not turn under and bury portions of burlap at top of ball. Set balled and 15 burlapped trees in the hole with the north marker facing north. 16 9. Set root ball on undisturbed soil in center of pit or trench and plumb plant. 17 10. Place plants at level that,after settlement, natural relationship of plant crown with 18 ground surface will be established. 19 11. When set,place additional backfill around base and sides of ball,and work each 20 layer to settle backfill and eliminate voids and air pockets. 21 12. When excavation is approximately 2/3 full,water thoroughly before placing 22 remainder of backfill. 23 13. Repeat watering until no more water is absorbed. 24 14. Dish top of backfill to allow for mulching. 25 15. Mulch pits,trenches and planted areas. 26 a. All trees, shrubs and other plantings will be mulched with mulch previously 27 approved by the City Forester.The mulch on trees and shrubs shall be to the 28 depths shown on the drawing. Mulch must not be placed within 3 inches of the 29 trunks of trees and shrubs. 30 16. Provide 2 to 4 inch thickness of mulch,work into top of backfill,and finish level 31 with adjacent finish grades. 32 17. Cover entire root ball. 33 18. Prune 34 a. Plants shall not be heavily pruned at the time of planting. Pruning is required at 35 planting to correct defects in the tree structure, including removal of injured 36 branches,double leaders,watersprouts,suckers,and interfering branches. 37 Healthy lower branches and interior small twigs should not be removed except 38 as necessary to clear walks and roads. In no case should more than 1/4 of the 39 branching structure be removed. Retain the normal shape of the plant. 40 b. All pruning shall be completed using clean sharp tools. All cuts shall be clean 41 and smooth,with the bark intact with no rough edges or tears. 42 c. Except in circumstances dictated by the needs of specific pruning practices, tree 43 paint shall not be used. The use of tree paint shall be only upon approval of the 44 City Forester.Tree paint,when required,shall be paint specifically formulated 45 and manufactured for horticultural use. 46 19. Prune trees to retain required height and spread. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised December 20,2012 329343-7 TREES AND SHRUBS Page 7 of 8 1 20. Do not cut tree leaders, and remove only injured and dead branches from flowering 2 trees. 3 21. Remove and replace excessively pruned or misformed stock resulting from 4 improper pruning. 5 22. Inspect tree trunks for injury,improper pruning and insect infestation and take 6 corrective measures. 7 23. Guy and stake trees immediately after planting. 8 B. Moving Existing Trees 9 1. Coordinate tree moving and replanting with City Forester during dormant growth 10 season. 11 2. Provide tree spade of adequate size as directed by City Forester. 12 3.5 REPAIRIRESTORATION [NOT USED] 13 3.6 RE-INSTALLATION [NOT USED] 14 3.7 FIELD QUALITY CONTROL 15 A. City may reject unsatisfactory or defective material at anytime during progress of work. 16 B. Remove rejected trees immediately from site and replace with specified materials. 17 C. Plant material not installed in accordance with these Specifications will be rejected. 18 D. An inspection to determine final acceptance will be conducted by City at end of 12 19 month maintenance period. 20 E. Warranty periods provided for in paragraph 1.12A. 21 3.8 SYSTEM STARTUP [NOT USED] 22 3.9 ADJUSTING[NOT USED[ 23 3.10 CLEANING 24 A. During planting work,keep pavements clean and work area in orderly condition. 25 B. Dispose of excess soil and waste in approved location. 26 C. Waste Material Disposal: On-site burning of combustible cleared materials shall not be 27 permitted. 28 3.11 CLOSEOUT ACTIVITIES [NOT USED] 29 3.12 PROTECTION 30 A. Protect planting work and materials from damage due to planting operations. 31 B. Maintain protection during installation and maintenance period. 32 C. Treat,repair,or replace damaged planting work. 33 3.13 MAINTENANCE 34 A. Maintenance Period shall be 12 months after final acceptance. 35 B. During the maintenance period if a work schedule and frequency are not shown on the 36 Drawings,perform the minimum requirements shown below: 37 1. Water trees to full depth a minimum of once each week or as required to maintain 38 healthy,vigorous growth. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised December 20,2012 329343-8 '[BEES AND SHRUBS Page 8 of 8 i 2. Prune,cultivate,and weed as required for healthy growth. 2 3. Restore planting saucers. 3 4. Tighten and repair stake and guy supports,and reset trees and shrubs to proper 4 grades or vertical position as required. 5 5. Restore or replace damaged wrappings. 6 6. Spray as required to keep trees and shrubs free of insects and disease. 7 7. Contractor shall replace any plant that does not survive. It shall be replaced as soon 8 as it is determined no longer alive. Contractor is to maintain new plants as 9 described above until growth is established and maintenance period expires unless 10 waived by the City. 11 3.14 ATTACHMENTS [NOT USED] 12 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 1.LA-Payment Items removed for tree removal and transplantation;these Items are to be performed in accordance with Section 31 10 00. 1 2120/20 1 2 D.Johnson 3.13.A-modified maintenance period to begin 12 months after final acceptance 3.13.E-Modified maintenance period requirements 13 14 15 16 17 18 19 20 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised December 20,2012 34 4l 30-1 ALUMINUM SIGNS AND SIGN POSTS Page 1 of 9 1 SECTION 34 4130 2 ALUMINUM SIGNS AND SIGN POSTS 3 PART1- GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. Aluminum signs installed on mast arms,signal poles,or steel posts. 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include,but are not necessarily limited to: 10 1. Division 0—Bidding Requirements,Contract Forms and Conditions of the Contract 11 2. Division 1 —General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 I. Furnishing and Installing Mast Arm or Signal Pole Mounted Aluminum Signs 15 a. Measurement 16 1) Measurement for this Item shall be per each sign installed. 17 b. Payment 18 1) The work performed and materials furnished in accordance with this Item 19 shall be paid for at the unit price bid per each"Furnish/Install Alum Sign 20 Mast Arm Mount"installed for: 21 a) Various types 22 c. The price bid shall include: 23 1) Fabricating the aluminum sign 24 2) Treatment of sign panels required before application of background 25 materials 26 3) Application of the background materials and messages to the sign panels 27 4) Furnishing and fabricating frames,windbeams,stiffeners,or required joint 28 backing strips 29 5) Furnishing bolts,rivets,screws, fasteners,clamps,brackets,and sign 30 support connections 31 6) Assembling and erecting the signs 32 7) Preparing and cleaning the signs 33 2. Installing Mast Arm or Signal/Street Light Pole Mounted Aluminum Signs 34 a. Measurement 35 1) Measurement for this Item shall be per each sign installed. 36 b. Payment 37 1) The work performed and materials furnished in accordance with this Item 38 shall be paid for at the unit price bid for each"Install Alum Sign Mast Arm 39 Mount"installed. 40 c. The price bid shall include: 41 1) Installing each Aluminum Sign CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 12,2013 344130-2 ALUMINUM SIGNS AND SIGN POSTS Page 2 or9 1 2) Furnishing and fabricating frames,windbeams, stiffeners,or required joint 2 backing strips 3 3) Furnishing bolts,rivets,screws, fasteners,clamps,brackets,and sign 4 support connections 5 4) Assembling and erecting the signs 6 5) Preparing and cleaning the signs 7 3. Furnishing and Installing Ground Mounted Aluminum Sign and Post Assemblies 8 a. Measurement 9 1) Measurement for this Item shall be per each assembly furnished and 10 installed. 11 b. Payment 12 1) The work performed and materials furnished in accordance with this Item 13 shall be paid for at the unit price bid for each"Furnish/Install Alum Sign 14 Ground Mount"installed for: 15 a) Various types 16 c. The price bid shall include: 17 1) Fabrication of signs and posts 18 2) Treatment of sign panels required before application of background 19 materials 20 3) Application of the background materials and messages to the sign panels 21 4) Scheduling utility line locates 22 5) Furnishing and fabricating frames,windbeams, stiffeners,or required joint 23 backing strips 24 6) Furnishing bolts,rivets,screws, fasteners, clamps,brackets,and sign 25 support connections 26 7) Assembling and erecting the signs and posts 27 8) Preparing and cleaning the signs 28 4. Installing Ground Mounted Aluminum Sign and Post Assemblies 29 a. Measurement 30 1) Measurement for this Item shall be per each assembly installed. 31 b. Payment 32 1) The work performed and materials furnished in accordance with this Item 33 shall be paid for at the unit price bid for each"Install Alum Sign Ground 34 Mount"installed. 35 c. The price bid shall include: 36 1) Scheduling utility line locates 37 2) Assembling and erecting the signs and posts 38 3) Preparing and cleaning the signs 39 5. Furnishing and Installing Aluminum Signs Mounted on Existing Poles 40 a. Measurement 41 1) Measurement for this Item shall be per each sign furnished and installed. 42 b. Payment 43 1) The work performed and materials furnished in accordance with this Item 44 shall be paid for at the unit price bid per each"Furnish/Install Alum Sign 45 Ex.Pole Mount"furnished and installed. 46 c. The price bid shall include: 47 1) Furnishing and installing the aluminum sign 48 2) Furnishing and fabricating frames,windbeams, stiffeners,or required joint 49 backing stops CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 12,2013 34 41 30.3 ALUMINUM SIGNS AND SIGN POSTS Page 3 of 9 1 3) Furnishing bolts,rivets, screws, fasteners,clamps,brackets, and sign 2 support connections 3 4) Assembling and erecting the signs 4 5) Preparing and cleaning the signs 5 6. Installing Aluminum Signs Mounted on Existing Poles 6 a. Measurement 7 1) Measurement for this Item shall be per each sign installed. 8 b. Payment 9 1) The work performed and materials furnished in accordance with this Item 10 shall be paid for at the unit price bid per each"Install Alum Sign Ex. Pole 1 I Mount"installed. 12 c. The price bid shall include: 13 1) Fabricating the aluminum sign 14 2) Furnishing and fabricating frames,windbeams,stiffeners,or required joint 15 backing strips 16 3) Furnishing bolts,rivets,screws, fasteners,clamps, brackets, and sign 17 support connections 18 4) Assembling and erecting the signs 19 5) Preparing and cleaning the signs 20 7. Removal of Signs 21 a. Measurement 22 1) Measurement for this Item shall be per each sign panel removed, each sign 23 panel and post removed, and each sign panel and post removed and 24 reinstalled. 25 b. Payment 26 1) The work performed and materials furnished in accordance with this Item 27 shall be paid for at the unit price bid per each"Remove Sign" for: 28 a) Various types 29 b) Various configurations 30 c. The price bid shall include: 31 1) Removal of sign panel and post 32 2) Removal of sign panel 33 3) Backfill 34 4) Excavation 35 5) Returning materials to the City as specified in the plans 36 6) Cleaning sign panel if sign is to be reinstalled 37 1.3 REFERENCES 38 A. Reference Standards 39 1. Reference standards cited in this Specification refer to the current reference 40 standard published at the time of the latest revision date logged at the end of this 41 Specification,unless a date is specifically cited. 42 2. American Standard Testing Materials(ASTM) 43 a. ASTM B209-07 "Standard Specification for Aluminum and Aluminum-Alloy 44 Sheet and Plate". 45 b. ASTM D4956-y 09e1 —"Standard Specification for Retroreflective Sheeting for 46 Traffic Control". CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 12,2013 344130.4 ALUMINUM SIGNS AND SIGN POSTS Page 4 of 9 1 c. ASTM A1011 /A1011- 10 "Standard Specification for Steel, Sheet and Strip, 2 Hot-Rolled, Carbon, Structural, High-Strength Low-Alloy,High-Strength Low- 3 Alloy with Improved Formability,and Ultra-High Strength". 4 d. ASTM B117-09—"Standard Practice for Operating Salt Spray(Fog) 5 Apparatus". 6 e. AASHTO M 120-08 —"Standard Specification for Zinc". 7 3. Texas Manual on Uniform Traffic Control Devices 8 4. Item 644, Small Roadside Sign Supports and Assemblies,Texas Department of 9 Transportation,Standard Specifications for Constniction and Maintenance of 10 Highways, Streets, and Bridges. 11 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 12 1.5 SUBMITTALS 13 A. Submittals shall be in accordance with Section 0133 00. 14 B. All submittals shall be approved by the City prior to delivery and/or fabrication for 15 specials. 16 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 17 A. Shop Drawings 18 1. Submit 5 sets of sign shop drawings to City Traffic Services Department for 19 approval prior to fabrication. 20 1.7 CLOSEOUT SUBMITTALS [NOT USED] 21 1.8 MAINTENANCE MATERIAL SUBMITTALS ]NOT USED) 22 1.9 QUALITY ASSURANCE [NOT USED] 23 1.10 DELIVERY,STORAGE,AND HANDLING 24 A. Delivery and Acceptance Requirements 25 1. Signs and parts shall be properly protected so that no damage or deterioration 26 occurs during a prolonged delay from the time of shipment until installation. 27 2. The Contractor shall secure and maintain a location to store the material in 28 accordance with Section 0150 00. 29 B. Storage and Handling 30 1. Ship,handle, and store completed sign blanks and completed signs so that corners, 31 edges, and faces are not damaged. 32 2. Damage to the sign face that is not visible when viewed at a distance of 50 feet, 33 night and day,will be acceptable. 34 3. Replace unacceptable signs. 35 4. Store all finished signs off the ground and in a vertical position until erected. 36 5. Store finished signs 60 inches x 60 inches or smaller in a weatherproof building. 37 6. Larger signs may be stored outside. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No,01239 Revised November 12,2013 344130-5 ALUMINUM SIGNS AND SIGN POSTS Page 5 of 9 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USEDI 3 PART 2- PRODUCTS 4 2.1 PRODUCTS TO BE PURCHASED FROM THE CITY 5 A. Refer to Drawings and Contract Documents to determine if any Items are to be 6 purchased from the City and installed by the Contractor. 7 B. Items eligible for purchase from the City include: 8 1. Aluminum Signs 9 2.2 MATERIALS 10 A. Manufacturers 11 1. Only the manufacturers as listed in the City's Standard Products List will be 12 considered as shown in Section 0160 00. 13 a. The manufacturer must comply with this Specification and related Sections. 14 2. Any product that is not listed on the Standard Products List is considered a 15 substitution and shall be submitted in accordance with Section 0125 00. 16 B. Sign blanks 17 1. Sign blanks shall be new,unweathered, milled,rolled and finished aluminum alloy 18 meeting Specifications for 50521438 as outlined in ASTM B 209—02a. 19 2. Sign blanks shall be free of buckle,crevice,warp,dent,cockles,burrs,corrosion, 20 dirt,grease, oil,white rust, fingerprints and/or other irregularities. 21 3. Sign blanks shall be degreased and etched according to industry standards and shall 22 have an alodined finish applied per MIL-05541 Class IA. 23 4. The thickness of each sign blank shall be uniform throughout. 24 C. Sign sheeting 25 1. Acrylic overlay film 26 a. This film shall be applied to Type I,Type II,Type IV,Type IX,and other 27 retroreflective sheeting for permanent signing. 28 b. The film shall be equal to or better than 3M Scotchlite ElectroCut Film Series 29 1170. 30 c. Film shall be: 31 1) Durable 32 2) Transparent 33 3) Acrylic 34 4) Electronic-cuttable 35 5) Coated with a transparent,pressure sensitive adhesive 36 6) Have a removable synthetic liner—paper liner is not acceptable 37 d. Film colors can include yellow,green,blue,brown,red,and orange. 38 2. Non-reflective vinyl film 39 a. This film shall be applied to Type IV,Type XI(DG3)retroreflective sheeting 40 for permanent signing. The film shall be equal to or better than 3M Scotchcal 41 ElectroCut Film Series 7725. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 12,2013 34 41 30-6. ALUMINUM SIGNS AND SIGN POSTS Page 6 of 9 1 b. Film shall be: 2 1) Durable 3 2) 2 mil opaque cast vinyl 4 3) Coated with a transparent,pressure-sensitive adhesive 5 4) Have a removable synthetic liner—paper line is not acceptable 6 c. Film colors can include yellow, green,blue,brown, red,and orange. 7 3. High intensity prismatic retroreflective sheeting with adhesive backing shall: 8 a. Be combined with other components for permanent signing 9 b. Typically be an unmetallized microprismatic lens retroreflective element 10 material 11 c. Have a smooth outer surface that essentially has the property of the 12 retroreflector over its entire surface 13 1) The adhesive backing shall be pressure-sensitive, require no heat,solvent or 14 other preparation for the adhesion to smooth,clean surfaces. 15 d. Be equal to or better than 3M Series 3930 16 e. Be of colors including white,yellow,green,red,blue,and brown 17 4. Super-high efficiency full cube retroreflective sheeting with pressure sensitive 18 adhesive shall: 19 a. Be combined with other components for permanent signing 20 b. Be a super-high efficiency, full cube retroreflective sheeting having the highest 21 retroreflectivity characteristics at medium and short road distances. 22 c. Typically be a microprismatic retroreflective element material 23 d. Have a smooth outer surface that essentially has the property of retroreflector 24 over its entire surface 25 1) The adhesive backing shall be pressure-sensitive,require no heat,solvent or 26 other preparation for adhesion to smooth,clean surfaces. 27 e. Be equal to or better than 3M Series 4000 28 f. Be of colors including white,yellow,green,red,blue,brown, fluorescent 29 yellow, fluorescent yellow green, and fluorescent orange 30 D. Telescoping Steel Sign Post 31 1. Posts and anchors shall conform to the Standard Specifications for Hot Rolled 32 Carbon Sheet Steel,Structural Quality ASTM designation A 10 11 /A1011- 10. 33 2. Posts and anchors shall carry minimum certifiable 60,000 psi yield strength. 34 3. All posts and anchors shall be manufactured from raw steel,formed and welded on 35 the corner prior to receiving a triple coat protection of inline hot-dipped,galvanized 36 zinc per AASHTO M-120-08(0.8 ounces per square foot) followed by a chromate 37 conversion coating and a cross-linked polyurethane acrylic exterior coating. 38 4. The interior shall receive a double coat of zinc based organic coating, tested in 39 accordance with ASTM B-117-09. 40 E. Hardware 41 1. Use galvanized steel,stainless steel,or dichromate-sealed aluminum for bolts,nuts, 42 washers, lock washers, screws, and other sign assembly hardware. 43 2. Use plastic or nylon washers to avoid tearing the reflective sheeting. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 12,2013 3441 30-7 ALUMINUM SIGNS AND SIGN POSTS Page 7 of 9 1 2.3 ACCESSORIES [NOT USED] 2 2.4 SOURCE QUALITY CONTROL [NOT USED] 3 PART 3- EXECUTION 4 3.1 INSTALLERS [NOT USED] 5 3.2 EXAMINATION [NOT USED] 6 3.3 PREPARATION [NOT USED] 7 3.4 FABRICATION 8 A. Sign blanks 9 1. Furnish sign blanks to the sizes and shapes shown on the Drawings and that are free 10 of buckles,warps,burrs,dents,cockles,or other defects. 11 2. Do not splice individual extruded aluminum panel. 12 3. Complete the fabrication of sign blanks, including the cutting and drilling or 13 punching of holes,before cleaning and degreasing. 14 4. After cleaning and degreasing, ensure that the substrate does not come into contact 15 with grease,oils,or other contaminants before the application of the reflective 16 sheeting. 17 B. Sign sheeting 18 1. Use reflective sheeting from the same manufacturer for the entire face of a sign. 19 2. Apply sheeting to sign blanks in conformance with the recommended procedures of 20 the sheeting manufacturer. 2I 3. Clean and prepare the outside surface of extruded aluminum flanges in the same 22 manner as the sign panel face. 23 4. Minimize the number of splices in the sheeting. 24 5. Overlap the lap-splices by at least 1/4 inch. 25 6. Provide a 1-foot minimum dimension for any piece of sheeting. 26 7. Do not splice sheeting for signs fabricated with transparent screen inks or colored 27 transparent films. 28 C. Sign messages 29 1. Fabricate sign messages to the sizes, types,and colors shown on the Drawings. 30 2. Use sign message material from the same manufacturer for the entire message of a 31 sign. 32 3. Ensure that the screened messages have clean,sharp edges and exhibit uniform 33 color and reflectivity. 34 4. Prevent runs,sags,and voids. 35 D. Telescoping steel sign posts 36 1. Permissible variation in straightness is 1116 inch in 3 feet. 37 2. Tolerances are on the outside size. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 12,2013 3441 30-8 ALUMINUM SIGNS AND SIGN POSTS Pagc 8 of 9 l Measurements for outside dimensions shall be made at least 2 inches from end of 2 tube. 3 Nominal Outside Outside Tolerance Dimensions at all Side Corners inches inches 1 '/2 X 1 '/2 ±0.006 1 '/ X 1 '/ t0.008 2 X 2 ±0.008 2 'i X 2 'i ±0.010 2 '%X 2 '/2 +0.010 4 5 3. Permissible variation in wall thickness is plus 0.011 inches,minus 0.008 inches. 6 4. Measured in the center of the flat side tolerance is 0.01 inch applied to the 7 specific size determined at the corner. 8 5. Squareness of Sides and Twist 9 10 !t Nominal Squareness Twist Permissible in 3 Outside Tolerance inches Lengths Dimensions inches (inches) (inches) 1 '/2 X 1 '/2 ±0.009 0.050 1 '/ X 1 '/ :E0.010 0,062 2 X 2 t0.012 0.062 2 '/ X 2 '/ t0.014 0.062 2 '/2 X 2 '/2 k0.0I 5 0.075 12 13 6. All top posts must be capable of fracturing at the point of connection with a single 14 anchor,when impacted, in such a manner that the piece inside of the anchor can be 15 removed so as to allow the anchor to receive a new top post. 16 7. The shape of all posts and anchors shall be square and straight with smooth tubing 17 welded in one corner with a tolerance that permits telescoping of the next larger or 18 small size, in '/-inch increments. 19 8. All anchors shall be 12 gauge with holes that are fully perforated 7I16-inch 20 diameter on 1-inch centers for at least the top 4 inches of the anchor while being 21 truly aligned in the center of the section. CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 12,2013 344130-9 ALUMINUM SIGNS AND SIGN POSTS Page 9 of 9 1 9. All top posts shall be 14 gauge with holes that are die embossed knockouts on 1- 2 inch centers for the entire length of the post and truly aligned in the center of 3 section. 4 5 3.5 REPAIR/RESTORATION [NOT USED] 6 3.6 RE-INSTALLATION [NOT USED] 7 3.7 FIELD loa] SITE QUALITY CONTROL[NOT USED] 8 3.8 SYSTEM STARTUP [NOT USED) 9 3.9 ADJUSTING [NOT USED] 10 3.10 CLEANING l l A. Wash completed signs with a biodegradable cleaning solution acceptable to the 12 manufacturers of the sheeting,colored transparent film, and screen ink to remove 13 grease,oil,dirt,smears,streaks, finger marks, and other foreign material. 14 B. Wash again before final inspection after erection. 15 3.11 CLOSEOUT ACTIVITIES [NOT USED[ 16 3.12 PROTECTION [NOT USED] 17 3.13 MAINTENANCE [NOT USED] 18 3.14 ATTACHMENTS [NOT USED] 19 END OF SECTION 20 Revision Log DATE NAME SUMMARY OF CHANGE 11/22/13 S.Arnold Changes to vinyl film,added sign removal bid item 21 CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised November 12,2013 APPENDIX GG 4.06 t..i,,zar-,ous EHN,i»tame.}.. Gendition at Site GC-6.06.D Minority and Women Owned Business Enterprise Compliance GC-6.07 Wage Rates CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 GC-6.06.1) Minority and Women Owned Business Enterprise Compliance THIS PAGE LEFT INTENTIONALLY BLANK CITY OF FORT WORTH Marys Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 FORT WORTH City of Fort Worth Minority Business Enterprise Specifications SPECIAL INSTRUCTIONS FOR BIDDERS APPLICATION OF POLICY If the total dollar value of the contract is greater than$50,000,then a MBE subcontracting goal may be applicable. If the total dollar value of the contract is$50,000 or less,then an MBE subcontracting goal is not applicable. POLICY STATEMENT It is the policy of the City of Fort Worth to ensure the full and equitable participation by Minority Business Enterprises (MBE) in the procurement of all goods and services. All requirements and regulations stated in the City's current Business Diversity Enterprise Ordinance applies to this bid. MBE PROJECT GOALS The City's MBE goal on this project is 10 %of the total bid(Base bid applies to Parks and community services). Note: If both MBE and SBE subcontracting goals are established for this project,then an Offeror must submit both a MBE Utilization Form and a SBE Utilization Form to be deemed responsive. COMPLIANCE TO BID SPECIFICATIONS On City contracts greater than $50,000 where a MBE subcontracting goal is applied, bidders are required to comply with the intent of the City's Business Diversity Enterprise Ordinance by one of the following: 1. Meet or exceed the above stated MBE goat through MBE subcontracting participation,or 2. Meet or exceed the above stated MBE goal through MBE Joint Venture participation,or; 3. Good Faith Effort documentation,or; 4. Waiver documentation. SUBMITTAL OF REQUIRED DOCUMENTATION The applicable documents must be received by the Managing Department,within the following times allocated, in order for the entire bid to be considered responsive to the specifications. The t fferorshali deliver the MBE documentation i person to the appropriate employee of the managing iepartment and obtain a'datehimt3 receipt. Such receipt shall be' evidencs;that the„,City received documentation in tFre.tinteallocated_ Afaxed copy not be accepted; 1. Subcontractor Utilization Form,If goal is received by 5:00 p.m., five (5) City business days after the bid met or exceeded: opening date,exclusive of the bid opening date. 2. Good Faith Effort and Subcontractor received by 5:00 p.m., five (5) City business days after the bid Utilization Form,if participation is less than opening date,exclusive of the bid opening date. statedgoal: 3. Good Faith Effort and Subcontractor received by 5:00 p.m., five (5) City business days after the bid Utilization Form, if no MBE participation: opening date,exclusive of the bid 02ening date. 4. Prime Contractor Waiver Form,if you will received by 5:00 p.m., five (5) City business days after the bid perform all subcontractin /su lier work: opening date,exclusive of the bid opening date. S. Joint Venture Form,if utilize a joint venture received by 5:00 p.m., five (5) City business days after the bid to met or exceed goal. opening date,exclusive of the bid opening date. FAILURE TO COMPLY WITH THE CITY'S BUSINESS DIVERSITY ENTERPRISE ORDINANCE,WILL RESULT IN THE BID BEING CONSIDERED NON-RESPONSIVE TO SPECIFICATIONS Any questions,pleass contact the M1WBE Office at(817)212-2674. Rev.5/30/12 ATTACHMENT 1A Page 1 of 4 FORT WORTH City of Fort Worth MBE Subcontractors/SuAA tiers Utilization Form PRIME COMPANY NAME: Check applicable block to describe prime PROJECT NAME: M/W/OBE0 NON•MrJWOBE Marys Creek Recycling Center Tree Planting and Irrigation BID DATE City's MBE Project Goal: Prime's MBE Project Commitment: PROJECT NUMBER 10 % I ago 101239 Identify all subcontractors/suppliers you will use on this project Failure to complete this form, in its entirety with requested documentation, and received by the Managing Department on or before 5:00 p.m.five(5) City business days after bid opening, exclusive of bid opening date, will result in the bid being considered non-responsive to bid specifications. The undersigned Offeror agrees to enter into a formal agreement with the MBE firm(s) listed in this utilization schedule, conditioned upon execution of a contract with the City of Fort Worth. The intentional and/or knowing misrepresentation of facts is grounds for consideration of disqualification and will result in the bid being considered non-responsive to bid specifications MBEs listed toward meeting the project goal must be located in the six(6) county marketplace at the time of bid. Marketplace is the geographic area of Tarrant, Dallas, Denton, Johnson, Parker, and Wise counties. Identify each Tier level. Tier is the level of subcontracting below the prime contractor, i.e., a direct payment from the prime contractor to a subcontractor is considered 1st tier, a payment by a subcontractor to its supplier is considered 2"d tier ALL MBEs MUST BE CERTIFIED BEFORE CONTRACT AWARD. Certification means those firms, located within the Marketplace, that have been determined to be a bondafide minority business enterprise by the North Central Texas Regional Certification Agency(NCTRCA) or other certifying agencies that the City may deem appropriate and accepted by the City of Fort Worth. If hauling services are utilized, the prime will be given credit as long as the MBE listed owns and operates at least one fully licensed and operational truck to be used on the contract. The MBE may lease trucks from another MBE firm, including MBE owner-operators, and receive full MBE credit. The MBE may lease trucks from non-MBEs, including owner-operators, but will only receive credit for the fees and commissions earned by the MBE as outlined in the lease agreement. Rev.6130112 FORT IVORTH ATTACHMENT 1A Page 2 of 4 Primes are required to identify ALL subcontractors/suppliers,regardless of status;i.e., Minority and non-MBEs. MBE firms are to be listed first,use additional sheets if necessary. If a subcontractor/supplier is identified as an SBE,please attach a copy of the firm's SBE certification if they have not previously registered with the City's M/WBE Office,which may be contacted for verification. Please note that onIv cert!ried MBEs will be counted to meet an MBE goal. Attach N NCTRCA Certificate ° SUBCONTRACTOR/SUPPLIER T n Detail Detail Company Name I Subcontracting Supplies Dollar Amount Address e M w S M Work Purchased Telephone/Fax r B B B B E E E E 1:1 El _r F-1 El ❑ ❑ Rev.6/30/12 FORTIVORTH ATTACHMENT IA Page 3 of 4 Primes are required to identify ALL subcontractors/suppliers,regardless of status;i.e.,Minority and non-MBEs. Please list MBE firm's first,use additional sheets if necessary. If a subcontractor/supplier is identified as an SBE,please attach a copy of the firms SBE certification if they have not previously registered with the City's M/WBE Office which may be contacted for verification. Please note that only certified MBEs will be counted to meet an MBE goal. Attach N NCTRCA Certificate SUBCONTRACTORISUPPLIER T n Detail Detail Company Name i Subcontracting Supplies Dollar Amount Address e M W S M Work Purchased Telephone/Fax r B B B B E E E E F] LJ El El 1:1 Rev.5/30/12 ATTACHMENT 1A FORT WORTH Page 4 of 4 Total Dollar Amount of MBE Subcontractors/Suppliers $ Total Dollar Amount of Non-MBE Subcontractors/Suppliers $ TOTAL DOLLAR AMOUNT OF ALL SUBCONTRACTORS/SUPPLIERS $ . ................... . ......_ The Contractor will not make additions, deletions, or substitutions to this certified list without the prior approval' of the Minority and Women Business Enterprise Office through the submittal of a Request for Approval o ChangelAddition form. Any unjustified change or deletion shall be a material breach of contract and may result in debarment in accord with the procedures outlined in the ordinance. The contractor shall submit a detailed explanation of how the requested change/addition or deletion will affect the committed MBE goal. If the detail explanation is not submitted, it will affect the final compliance determination. By affixing a signature to this form, the Offeror further agrees to provide, directly to the City upon request, complete and accurate information regarding actual work performed by all subcontractors, including MBE(s) and any special arrangements with MBEs. The Offeror also agrees to allow an audit and/or examination of any books, records and files held by their company. The bidder agrees to allow the transmission of interviews with owners, principals, officers, employees and applicable subcontractors/suppliers participating on the contract that will substantiate the actual work performed by the MBE(s) on this contract, by an authorized officer or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract or debarment from City work for a period of not less than three (3) years and for initiating action under Federal, State or Local laws concerning false statements. Any failure to comply with this ordinance creates a material breach of the contract and may result in a determination of an irresponsible Offeror and debarment from participating in City work for a period of time not less than one(1)year. Authorized Signature Printed Signature Title Contact NameMtle(if different) Company Name Telephone andfor Fax Address E-mail Address City/State/Zip Date Rev.5/30112 ATTACHMENT 1B FORT WORTH Page 1 of 1 City of Fort Worth Prime Contractor Waiver Form PRIME COMPANY NAME: Check applicable block to describe prime PROJECT NAME: M/W/DBE11 NON-M//WDBE Marys Creek Recycling Center Tree Planting and Irrigation BID DATE City's MBE Project Goal: Prime's MBE Project Commitment: PROJECT NUMBER 10 % I % 101239 If both answers to this form are YES, do not complete ATTACHMENT 1C (Good Faith Effort Form). All questions on this form must be completed and a detailed explanation provided, if applicable. If the answer to either question is NO,then you must complete ATTACHMENT 1C. This form is only applicable if both answers are yes. Failure to complete this form in Its entirety and be received by the Manartina Department on or before 5:00 a.m.,five(5)city business days after bid'openina exclusive of the bid opening date,will result in the bid being considered non-responsive to bid specifications. Will you perform this entire contract without subcontractors? YES If yes, please provide a detailed explanation that proves based on the size and scope of this NO project,this is your normal business practice and provide an operational profile of your business. Will you perform this entire contract without suppliers? YES If yes, please provide a detailed explanation that proves based on the size and scope of this project, this is your normal business practice and provide an inventory profile of your business. NO The bidder further agrees to provide, directly to the City upon request, complete and accurate information regarding actual work performed by all subcontractors, including MBE(s) on this contract, the payment therefore and any proposed changes to the original MBE(s) arrangements submitted with this bid. The bidder also agrees to allow an audit and/or examination of any books, records and files held by their company that will substantiate the actual work performed by the MBEs on this contract, by an authorized officer or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract or debarment from City work for a period of not less than three (3) years and for initiating action under Federal, State or Local laws concerning false statements. Any failure to comply with this ordinance creates a material breach of contract may result in a determination of an irresponsible offeror and barred from participating in City work for a period of time not less than one(1)year. Authorized Signature Printed Signature Title Contact Name(if different) Company Name Phone Number Fax Number Address Email Address City/State/Zip Date Rev.5/30112 ATTACHMENT 1C Pagel of 3 FORT WORTH City of Fort Worth MBE Good Faith Effort Form PRIME COMPANY NAME: Check applicable block to describe prime ` PROJECT NAME: 11 MNWDBE NON-M//WDBE Marys Creek Recycling Center Tree Planting and Irrigation BID DATE City's MBE Project Goal: Prime's MBE Project Commitment: PROJECT NUMBER 10 % % 101239 If the Offeror did not meet or exceed the MBE subcontracting goal for this project, the Offeror must complete this form. If the Offeror's method of compliance with the MBE goat is based upon demonstration of a "good faith effort", the Offeror will have the burden of correctly and accurately preparing and submitting the documentation required by the City. Compliance with each item, 1 thru 11 below, shall satisfy the Good Faith Effort requirement absent proof of fraud, intentional and/or knowing misrepresentation of the facts or intentional discrimination by the Offeror. Failure to complete this form,In its entirety with supporting documentation, and It being submitted to and received by the Managing Department on or before 5:00 p.m.five(5)City business days after bid opening, exclusive of bid opening date,will result in the bid being considered non-responsive to bid specifications. 1.) Please list each and every subcontracting and/or supplier opportunity for the completion of this project, regardless of whether it is to be provided by a MBE or non-MBE. (DO NOT LIST NAMES OF FIRMS) On all projects, the Offeror must list each subcontracting and or supplier opportunity regardless of tier. (Use additional sheets, if necessary) List of Subcontracting Opportunities List of Supplier Opportunities Rev.5130/12 ATTACHMENT I Page 2 of 3 2.) Obtain a current(not more than two(2)months old from the bid open date) list of MBE subcontractors and/or suppliers from the City's M/WBE Office or the City's website. Yes Date of listing No 3.) Did you solicit bids from MBE firms,within the subcontracting and/or supplier areas previously listed, at least ten calendar days prior to bid opening by mail, exclusive of the day the bids are opened? Yes (if yes,attach MBE mail listing to include name of firm and address and a aced copy of letter mailed.) _LLNo 4.) Did you solicit bids from MBE firms,within the subcontracting and/or supplier areas previously listed, at least ten calendar days prior to bid opening by telephone, exclusive of the day the bids are opened? El Yes (if yes,attach list to include name of MBE firm,Person contacted,phone number and date and time of contact.) No 5.) Did you solicit bids from MBE firms,within the subcontracting and/or supplier areas previously listed, at least ten calendar days prior to bid opening by facsimile(fax),exclusive of the day the bids are opened? _aYes (If yes,attach list to include name of MBE firm,fax number and date and time of contact. In addition,if the fax is returned as undeliverable,then that"undeliverable confirmation"received must be printed directly from the facsimile for proper documentation. Failure to submit confirmation and/or"undeliverable confirmation" documentation may render the GFE non-responsive.) F No 6.) Did you solicit bids from MBE firms,within the subcontracting and/or supplier areas previously listed, at least ten calendar days prior to bid opening by email,exclusive of the day the bids are opened? _Yes (if yes,attach email confirmation to include name of MBE firm,date and time.In addition,if an email is returned as undeliverable,then that"undeliverable message"receipt must be printed directly from the email system for proper documentation. Failure to submit confirmation and/or"undeliverable message"documentation may render the __allo GFE non-responsive.) NOTE: The four methods identified above are acceptable for soliciting bids, and each selected method must be applied to the applicable contract. The Offeror must document that either at least two attempts were made using two of the four methods or that at least one successful contact was made using one of the four methods in order to be deemed responsive to the Good Faith Effort requirement. NOTE: The Offeror must contact the entire MBE list specific to each subcontracting and supplier opportunity to be In compliance with questions 3 through 6. 7.) Did you provide plans and specifications to potential MBEs? Yes No 8.) Did you provide the information regarding the location of plans and specifications in order to assist the MBEs? Yes No Rev.5/30112 ATTACHMENT 1C Page 3 of 3 9. Did you prepare a quotation for the MBEs to bid on goods/services specific to their skill set? Yes (If yes,attach all copies of quotations.) No 10. Was the contact Information on any of the listings not valid? Yes (if yes,attach the information that was not valid In order for the MfWBE Office to address the corrections ,_❑_No needed.) 11.)Submit documentation If MBE quotes were rejected. The documentation submitted should be in the forms of an affidavit, include a detailed explanation of why the MBE was rejected and any supporting documentation the Offeror wishes to be considered by the City. In the event of a bona fide dispute concerning quotes,the Offeror will provide for confidential In-camera access to and inspection of any relevant documentation by City personnel. Please use additional sheets,if necessary,and attach. ComEany Name Telephone Contact Person Scope of Work Reason for Rejection ADDITIONAL INFORMATION: Please provide additional information you feel will further explain your good and honest efforts to obtain MBE participation on this project. The Offeror further agrees to provide, directly to the City upon request, complete and accurate information regarding actual work performed on this contract, the payment thereof and any proposed changes to the original arrangements submitted with this bid. The Offeror also agrees to allow an audit and/or examination of any books, records and files held by their company that will substantiate the actual work performed on this contract, by an authorized officer or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract or debarment from City work for a period of not less than three {3) years and for initiating action under Federal, State or Local laws concerning false statements. Any failure to comply with this ordinance shall create a material breach of Rev.5/30/12 ATTACHMENT 1C Page 4 of 3 contract and may result in a determination of an irresponsible offeror and debarment from participating in City work for a period of time not less than one (1) year. The undersigned certifies that the information provided and the MBEs) listed was/were contacted in good faith. It is understood that any MBEs) listed in Attachment 1C will be contacted and the reasons for not using them will be verified by the City's M/WBE Office. Authorized Signature Printed Signature Title Contact Name and Title(if different) Company Name Phone Number Fax Number Address Email Address City/State/Zip Date Rev.5/30112 Joint Venture Page 1 of 3 FORT WORTH CITY OF FORT WORTH MBE Joint Venture Eligibility Form All questions must be answered;use"NIA"if nat applicable. Name of City project: Marys Creek Recycling Center Tree Planting and Irrigation A joint venture form must be completed on cac 11 project RFP/Bid/Purchasing Number: 1.Joint venture information: Joint Venture Name: Joint Venture Address: (If applicable) Telephone: Facsimile: E-mail address: Cellular: Identify the firms that comprise the joint venture: Please attach extra sheets if additional space is required to provide detailed explanations of work to be performed by each firm comprising the oint venture MBE firm Non-MBE firm name: name: Business Address: Business Address: City,State,Zip: City,State,Zip:. Telephone Facsimile E-mail Telephone Facsimile Cellular Cellular Certification Status: E-mail address Name of Certifying Agency: 2.Scope of work Rerformed by the Joint Venture: Describe the scope of work of the MBE: Describe the scope of work of the non-MBE: Rev.5/30/12 Joint Venture Page 2 of 3 3.What is the percentage of MBE participation on this joint venture that you wish to be counted toward meeting the project goat? 4.Attach a copy of the joint venture agreement. 5. List components of ownership of joint venture: (Do not complete if this information is described in joint venture agreentent) Profit and loss sharing: Capital contributions,including equipment: Other applicable ownership interests: 6. Identify by name,race,sex and firm those individuals(with titles)who are responsible for the day-to-day management and decision making of the joint venture: Financial decisions (to include Account Payable and Receivable): Management decisions: a. Estimating b. Marketing and Sales c. Hiring and Firing of management personnel d. Purchasing of major equipment and/or supplies Supervision of field operations The City's Minority and Women Business Enterprise Office will review your joint venture submission and will have final approval of the MBE percentage applied toward the goal for the project listed on this form. NOTE: From and after the date of project award, if any of the participants, the individually defined scopes of work or the dollar amounts/percentages change from the originally approved information, then the participants must inform the City's MIWBE Office immediately for approval. Any unjustified change or deletion shall be a material breach of contract and may result in debarment in accord with the procedures outlined in the City's BDE Ordinance. Rev.5/30/12 Joint Venture Page 3 of 3 AFFIDAVIT The undersigned affirms that the foregoing statements are true and correct and include all material information necessary to identify and explain the terms and operation of the joint venture. Furthermore,the undersigned shall agree to provide to the joint venture the stated scope of work, decision-making responsibilities and payments herein. The City also reserves the right to request any additional information deemed necessary to determine if the joint venture is eligible. Failure to cooperate and/or provide requested information within the time specified is grounds for termination of the eligibility process. The undersigned agree to permit audits, interviews with owners and examination of the books,records and files of the joint venture by any authorized representatives of the City of Fort Worth. Failure to comply with this provision shall result in the termination of any contract, which may be awarded under the provisions of this joint venture's eligibility and may initiate action under Federal, State and/or Local laws/ordinances concerning false statements or willful misrepresentation of facts. Name of MBE firm Name of non-MBE firm Printed Name of Owner Printed Name of Owner Signature of Owner Signature of Owner Printed Name of Owner Printed Name of Owner Signature of Owner Signature of Owner Title Title Date Date Notarization State of County of On this day of ,20 ,before me appeared and to me personally known and who,being duly sworn,did execute the foregoing affidavit and did state that they were properly authorized to execute this affidavit and did so as their free act and deed. Notary Public Print Name Notary Public Signature Commission Expires (sear) Rev.5130/12 GC-6.47 Wage Rates THIS PAGE LEFT INTENTIONALLY BLANK CITY OF FORT WORTH Mary's Creek Recycling Center Tree Planting STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No.01239 Revised July 1,2011 2013 PREVAILING WAGE RATES (Heavy and Highway Construction Projects) CLASSIFICATION DESCRIPTION Wage Rate Asphalt Distributor Operator $ 15.32 Asphalt Paving Machine Operator $ 13.99 Asphalt Raker $ 12.69 Broom or Sweeper Operator $ 11.74 Concrete Finisher,Paving and Structures $ 14.12 Concrete Pavement Finishing Machine Operator $ 16.05 Concrete Saw Operator $ 14.48 Crane Operator,Hydraulic 80 tons or less $ 18.12 Crane Operator,Lattice Boom 80 Tons or Less $ 17.27 Crane Operator,Lattice Boom Over 80 Tons $ 20.52 Crawler Tractor Operator $ 14.07 Electrician $ 19.80 Excavator Operator,50,000 pounds or less $ 17.19 Excavator Operator,Over 50,000 pounds $ 16.99 Flagger $ 10.06 Form Builder/Setter,Structures $ 13.84 Form Setter,Paving&Curb $ 13.16 Foundation Drill Operator,Crawler Mounted $ 17.99 Foundation Drill Operator,Truck Mounted $ 21.07 Front End Loader Operator,3 CY or Less $ 13.69 Front End Loader Operator,Over 3 CY $ 14.72 Laborer,Common $ 10.72 Laborer, Utility $ 12.32 Loader/Backhoe Operator $ 15.18 Mechanic $ 17.68 Milling Machine Operator $ 14.32 Motor Grader Operator,Fine Grade $ 17.19 Motor Grader Operator,Rough $ 16.02 Off Road Hauler $ 12.25 Pavement Marking Machine Operator $ 13.63 Pipelayer $ 13.24 Reclaimer/Pulverizer Operator $ 11.01 Reinforcing Steel Worker $ 16.18 Roller Operator,Asphalt $ 13.08 Roller Operator,Other $ 11.51 Scraper Operator $ 12.96 Servicer $ 14.58 Small Slipform Machine Operator $ 15.96 Spreader Box Operator $ 14.73 Truck Driver Lowboy-Float $ 16.24 Truck Driver Transit-Mix $ 14.14 Truck Driver,Single Axle $ 12.31 Truck Driver,Single or Tandem Axle Dump Truck $ 12.62 Truck Driver,Tandem Axle Tractor with Semi Trailer $ 12.86 Welder $ 14.84 Work Zone Barricade Servicer $ 11.68 The Davis-Bacon Act prevailing wage rates shown for Heavy and Highway construction projects were determined by the United States Department of Labor and current as of September 2013. The titles and descriptions for the classifications listed are detailed in the AGC of Texas'Standard Job Classifications and Descriptions for Highway, Heavy,Utilities,and Industrial Construction in Texas. Page 1 of 1 2013 PREVAILING WAGE RATES (Commercial Construction Projects) CLASSIFICATION DESCRIPTION Wage Rate AC Mechanic $ 25.24 AC Mechanic Helper $ 13.67 Acoustical Ceiling Installer $ 16.83 Acoustical Ceiling Installer Helper $ 12.70 Bricklayer/Stone Mason $ 19.45 Bricklayer/Stone Mason Trainee $ 13.31 Bricklayer/Stone Mason Helper $ 10.91 Carpenter $ 17.75 Carpenter Helper $ 14.32 Concrete Cutter/Sawer $ 17.00 Concrete Cutter/Sawer Helper $ 11.00 Concrete Finisher $ 15.77 Concrete Finisher Helper $ 11.00 Concrete Form Builder $ 15.27 Concrete Form Builder Helper $ 11.00 Drywall Mechanic $ 15.36 Drywall Helper $ 12.54 Drywall Taper $ 15.00 Drywall Taper Helper $ 11.50 Electrician(Journeyman) $ 19.63 Electrician Apprentice(Helper) $ 15.64 Electronic Technician $ 20.00 Floor Layer $ 18.00 Floor Layer Helper $ 10.00 Glazier $ 21.03 Glazier Helper $ 12.81 Insulator $ 16.59 Insulator Helper $ 11.21 Laborer Common $ 10.89 Laborer Skilled $ 14.15 Lather $ 12.99 Metal Building Assembler $ 16.00 Metal Building Assembler Helper $ 12.00 Metal installer(Miscellaneous) $ 13.00 Metal Installer Helper(Miscellaneous) $ 11.00 Metal Stud Framer $ 16.12 Metal Stud Framer Helper $ 12.54 Painter $ 16.44 Painter Helper $ 9.98 Pipehtter $ 21.22 Pipefitter Helper $ 15.39 Plasterer $ 16.17 Plasterer Helper $ 12.85 Plumber $ 21.98 Plumber Helper $ 15.85 Reinforcing Steel Setter $ 12.87 Page 1 of 2 Reinforcing Steel Setter Helper $ 11.08 Roofer $ 16.90 Roofer Helper $ 11.15 Sheet Metal Worker $ 16.35 Sheet Metal Worker Helper $ 13.11 Sprinkler System Installer $ 19.17 Sprinkler System Installer Helper $ 14.15 Steel Worker Structural $ 17.00 Steel Worker Structural Helper $ 13.74 Waterproofer $ 15.00 Equipment Operators Concrete Pump $ 18.50 Crane,Clamsheel, Backhoe,Derrick, D'Line Shovel $ 19.31 Forklift $ 16.45 Foundation Drill Operator $ 22.50 Front End Loader $ 16.97 Truck Driver $ 16.77 Welder $ 19.96 Welder Helper $ 13.00 The prevailing wage rates shown for Commercial construction projects were based on a salary survey conducted and published by the North Texas Construction Industry(Fall 2012)Independently compiled by the Lane Gorman Trubitt,PLLC Construction Group. The descriptions for the classifications listed are provided on the TEXO's(The Construction Association)website. www.texoassociation.org/Chapter/wagerates.asp Page 2 of 2