HomeMy WebLinkAboutContract 54212-AR2 CSC No. 54212-AR2
FORT 'WO RT H City of Fort Worth
Construction Allowance Request
Project Name 2018 CIP Year 2,Contract 17 City Sec No. 154212
Project No.(s) 56002-0600430-0700430&34018-0200431 M&C: 20-0457 City Pro.No. 101477-1
Project Combined Water,Sanitary Sewer and Paving Improvements for 2018 CIP Year 2, Contract 17
Description
Contractorl Stabile&Winn, Inc. Allowance No. Date: 5/26/2022
City Project Mgr.I Dena Johnson City Inspector Aaron Ybarra
Phone Number: 817-392-7866 Phone Number: 817-392-8306
Dept. UNIT 1:Water UNIT 2:Sewer UNIT 3:Paving UNIT 4:Drainage Totals
Original Contract Amount $1,675,777.50 $653,464.50 $4,217,834.30 $224,475.00 $6,771,551.30
Previous Allowances Allocated $3,232.50 $0.00 $0.00 $0.00 $0.00
Amount of Proposed Allocation $3,510.00 $0.00 $0.00 $0.00 $3,510.00
Original Allowance Available for Allocation $60,000.00 $40,000.00 $100,000.00 1 $30,000.001 $230,000.00
Remaining Funds Available for this Allocation $56,767.50 $40,000.00 $100,000.00 1 $30,000.001 $230,000.00
JUSTIFICATION (REASONS)FOR ALLOWANCE
Allowance No. 2 will provide for remobilization to the job site to allow the contractor's subcontractor to relocate
10 existing water services and meter boxes that are currently located within the driveways on a project street.
The water main on the street is in good condition and does not need to be replaced.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name Contr:.j,;tor Signature Date
Stabile&Winn,Inc. Jerry Henderson — 6/1/2022
Inspector Project Manager Date
5-31-2022 DQ �' 6/1/22
Director(Water Dept) Constructio Supervisor(TPW Dept) Date
h✓istophoroa✓dor Jun2,2022 Donald Watson 221
Assistant City Attorney Assistant City Manager Date
Jun 9,2022 8 3:55 CDT, Jun 9,2022
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name 2018 CIP Year 2,Contract 17 City Sec No. 54212
Project No.(s) 56002-0600430-0700430&34018-0200431 DOE No.O City Pro. No. 101477 1
Project Combined Water,Sanitary Sewer and Paving Improvements for 2018 CIP Year 2,Contract 17
Description
Contractor Stabile&Winn,Inc. Allowance No# =2 Date: 5/26/2022
City Project Mgr. Dena Johnson City Inspector F Aaron Ybarra
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
44 Remobilization UNIT 1:Water 1.00 LS $3,510.00 $3,510.00
UNIT 1:Water $3,510.00
UNIT 2:Sewer
UNIT 3:Paving
UNIT 4:Drainage
Additions Sub Total $3,510.00
Page 1 of 1
FORT WORTH City of Fort Worth
}— Change Order Deletions
Project Name 2018 CIP Year 2,Contract 17 City Sec No. 54212
Project No.(s) 56002-0600430-0700430&34018-0200431 DOE No. [� City Pro. No. 1 101477 1
Project Description Combined Water,Sanitary Sewer and Paving Improvements for 2018 CIP Year 2,Contract 17
Contractor Stabile&Winn, Inc. Allowance No#0 Date 5/26/2022
City Project Mgr. Dena Johnson City Inspector Aaron Ybarra
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
UNIT 1:Water
UNIT 2:Sewer
UNIT 3:Paving
UNIT 4:Drainage
Deletions Sub Total
Page 1 of 1
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
De4a�70hilSoll
Signature
Dena Johnson
Name of Employee
Project Manager
Title
ATTEST:
a� OR
G °0000
9arcr�atta s. ��v7aCG Q o°° 'o�
Jannette S.Goodall(Jun 10,2o22 o531 HST) ��y AlO° OO���
FF L 0 O
O °
Jannette Goodall Vo 00.
o °
o °
City Secretary �� 0 00 iC 1:
° 00 Y
0
°°00000 a
�t1 SEX Asap
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
6/2/2022
CPN 1.01477-1
2018 CIP Year 2, Contract 17
Allowance Request 2 Notes
Staff has reviewed the proposed unit price on the allowance and considers it to be fair
and reasonable when compared to the typical price of$5,000 to $7,000 for remobilization.