HomeMy WebLinkAboutContract 56582-CO2 CSC No. 56582-CO2
FORT WORTH City of Fort Worth
' r— Change Order Request
Project Name: Water and Sanitary Sewer replacement Contract 2011 WSM-D Part 2 City Sec No.: 56582
Project No.(s):1 1929-2 DOE No. � City Proj.No.: 1929
Project Description: Replacing water line,Sanitary Sewer lines on various streets.
Contractor: Woody Contractors Change Order# Date: F 6/2/2022
City Project Mgr.1 Suby Varughese City Inspector: I Tamara Vaughn
Phone Number:1 (817)392-7803 Phone Number: 682 225 9106
Dept. Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $2,031,329.25 $914,697.25 $2,946.026.50 365
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $2,031,329.25 $914,697.25 $0.00 $2,946,026.50 365
Amount of Proposed Change Order $0.00 $0.00 $0.00 $0.00 0
Revised Contract Amount $2,031,329.25 $914,697.25 $0.00 $2,946,026.50 365
Original Funds Available for Change Orders $101,566.75 $45,733.75 $0.00 $147,300.50
Remaining Funds Available for this CO $101,566.75 $45,733.75 $0.00 $147,300.50
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+2551o) $3,682,533.13
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Change order No.2 provide for a water PVC pipe DR-18 for replacing existing 6" Cl pipe on Roosevelt ave.This is
one-time waiver request for Roosevelt Street—in an effort to allow the work to be performed during the
summer.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name Corftractor Signature Date
Woody Contractors Troy Woody
Inspector Date Project Manager Date
Tamara Vaughn 6/15/22 Sub Varu hese
L
Director Water Dept Date Construction Supervisor(T Date
r I H"y
,.,h.r H.rd.r(o 16,2D2216:D2 CDT a, Jun 16,2022 6/16/22
Assistant City Attorney Date Assistant City Manager Date
.tun 17,2022 Jun 17,2022
�,-„,zo
Council Action If Re aired
M&C Date OFFICIAL RECORD
M&C Number NIA Approved
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Water and Sanitary Sewer replacement Contract 2011 WSM-D Part 2 City Sec No.: 56582
Project No.(s): 1929-2 DOE No. N/A City Proj.No.: 1929
Project Description Replacing water line,Sanitary Sewer lines on various streets.
Contractor Woody Contractors Change Order:= Date: 61212022
City Project Mgr. Suby Varughese City Inspector Tamara Vaughn
ADDITIONS
ITEM DESCRIPTIUN DEPT Qty Unit Unit Cost Total
58 8"PVC water pipe DR-18 Water 1940.00 LF $82.00 $159,080.00
Water $159,080.00
Sewer
Page 1 0i 1 Additions Sub Total
F[>RT' Woo wrm City of Fort Worth
Change Order Deletions
Project Name J Water and Sanitary Sewer replacement Contract 2011 WSM-D Part 2 City Sec No.: 1 56582
Project No.(s): 1929-2 DOE No. N/A City Proj.No.: 1929
Project Description Replacing water line,Sanitary Sewer lines on various streets.
Contractor Woody Contractors Change Order: F2 ] Date 6/2/2022
City Project Mgr. Suby Varughese City Inspector: Tamara Vaughn
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
3 8"Water PVC pipe Water 1,940.00 LF $82.00 $159,080.00
Water $159,080.00
Sewer
Page 1 of 1 Deletions Sub Total 1$159,080.00
MIWBE Breakdown for this Change Order
is _s.._:.
v:L p(:3:,0 :ip`.':i. �4".i }:i: .�r � :,�'.✓:J.. 1: :{J:�-�.A.,�i�'::,:t .S<:_ ___ .e:of,SerZ;ice.,.tr._ r' Amauntrfor;:tfiis.. .0,>:s
Total
Previous Change Orders
F �., :' �""'' .-� a#e,�.�. � ..jt-. ;:�si'i•,s ;�, � a:a�:. �'e,` f�1 "i' +� `?•rf�,9
Totals AT r ' itkp
Page 1 of 1
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
Signature
Suby Varughese
Name of Employee
Professional Engineer
Title
ATTEST: axz>; FORT��12
��0000000000����
�i�, rette s ��rrs7�GG °0'�
Jan nette S.Good a[[(Jun 21,202211:22 CDT) r O
_ O
O O
Jannette Goodall �� *o o 4 gd
°0 0° �
City Secretary � 0000000o a
tl SEX Asap
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH, TX
CPN-1929-2 Change order-2 notes
The City staff requested for the lowest price quotes,but the contractor provided the current
market price for the DR-18 pipes. The proposal covers the additional cost associated with the
fittings, equipment, fuel, and labor costs.
No additional time needed for the work.
WOODY
CONTRACTORS
WOODY CONTRACTORS INC.- _T
660 TOWER RD
KENNEDALE,TX 76060
PHONE-817-483-4787
FAX 817-483-2048
Job; WATER & S.S. CONTRACT 2011 WSM-D PART 2
Date May 12, 2022
GRANGE ORDER 6
Item Description Quantity Unit Price Total Price
3 8" PVC WATER DR 14 -1,940 LF $ 82.00 $ (159,080.00)
1 8"PVC WATER DR 18 1,940 LF $ 82.00 $ 159,080.00
Total for Sheet $ -
Total For.lob $ -
Signature:
Email: tressa.williams@fortworthtexas.gov