HomeMy WebLinkAboutOrdinance 25540-06-2022 ORDINANCE NO.25540-06-2022
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF$744,549.00, TRANSFERRED FROM AVAILABLE FUNDS
WITHIN THE WATER AND SEWER FUND, FOR THE PURPOSE OF FUNDING
THE WATER AND SANITARY SEWER CONTRACT, 2021 WSM-D PROJECT
(CITY PROJECT NO. 103619); PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;AND PROVIDING
AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2021-2022 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of$744,549.00, transferred from available funds within the
Water and Sewer Fund, for the purpose of funding the Water and Sanitary Sewer Contract, 2021 WSM-D,
project(City Project No. 103619).
SECTION 2.
That should any portion,section or part of a section of this ordinance be declared invalid,inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 25073-09-2021 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
,,?1711/1 tom" Gc��a�G
Mack(Jun 22,202211:58 CDT) Jannette S.Goodall(Jun 22,2022 14:10 CDT)
Douglas W.Black Jannette S.Goodall
Assistant City Attorney City Secretary
ADOPTED AND EFFECTIVE:June 14,2022
CAS
MAYOR AND COUNCIL COMMUNICATION MAP
60WSSC21 WSMD-DALTECH
,H?O
Lu
t t4 t
rWOOTENRECTOR VE r
*- WOSL'EYlDR'
r i i
F. WHARTON DR , a... �� a /= x�4`,� '4 t
f
Y, i• y D
' D
' REN AV f ' REN AV
m; riF'a
WALTON AVE
WALTON`AVE {f ;.WALTON AVE-
Am 61 LLJ
Lu w
CO
WAY LAND
— �• ril �. 1.. � —
. . Y
rMINOTAVE•
ull
Lu
FORT WORTH
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 06/14/22 M&C FILE NUMBER: M&C 22-0406
LOG NAME: 60WSSC21 WSMD-DALTECH
SUBJECT
(CD 6)Authorize Execution of an Engineering Agreement with Dal-Tech Engineering Inc.in the Amount of$569,240.00 for the Water and Sanitary
Sewer Contract,2021 WSM-D Project and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to Fiscal Years 2022-2026
Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of an engineering agreement with Dal-Tech Engineering Inc,in the amount of$569,240.00,for Water and Sanitary
Sewer Contract,2021 WSM-D project;and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of$744,549.00 transferred from available funds within the Water and Sewer fund,for the Water and Sanitary Sewer Contract,
2021 WSM-D(City Project No. 103619)to effect a portion of Water's contribution to Fiscal Years 2022-2026 Capital Improvement Program.
DISCUSSION:
This Mayor and Council Communication(M&C)is to authorize the preparation of plans and specifications for sanitary sewer and water main
replacements on the following streets,and easements:
Street From To Scope of
Work
Wharton Drive Vega Drive Colusa Drive Water/Sewer
Wren Avenue Vega Drive Westcreek Water/Sewer
it Drive
Wilkie Way JRega Drive Wayland Drive Water/Sewer
Easement between 392 feet west of Colusa 725 feet east o
Wharton Drive and Wren Drive Colusa Drive :Sewer
Avenue
Easement between 170 feet south of Morley
Morley Avenue and Avenue and Wharton Drive 415 feet south Sewer
Colusa Drive intersection
Wayland Drive Vega Drive Colusa Drive Water/Sewer
Colusa Drive Walton Avenue IlWayand Drive Water/Sewer
Morley Avenue 1 Wren Avenue —�150 feet south IlSewer
Easement between Wren 295 feet west of Colusa Morley Avenue Sewer
Drive and Walton Avenue Drive
Denbury Drive Colusa Drive WestcreekWater/Sewer
Drive
Easement between 215 feet south
Odessa Avenue and Walton Avenue of Wosley Sewer
Westcreek Drive Drive
Vega Drive Wharton Drive Wilkie Way Water/Sewer
Easement between 180 feet east o
Southgate Drive and Westcreek Drive Westcreek Sewer
Walton Avenue Drive
In addition to the contract amount,$175,309.00(Water:$113,465.00;Sewer: $61,844.00)is required for project management,utility coordination,
and material testing.This project will have no impact on the Water Department's operating budget when completed.The sewer component of the
project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.
It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year,instead of within the annual budget ordinance,as
projects commence,additional funding needs are identified,and to comply with bond covenants.The actions in the M&C will appropriate funds in
support of the Water's portion of the City of Fort Worth's Fiscal Years 2022-2026 Capital Improvement Program,as follows:
60WSSC21 WSMD-DALTECH
Capital Revised
Project FY2022 CIP Budget
Fund Authority FY2022
Name Name Appropriations Change(Increase/Decrease) 9
Bud et
W&S 103619
Capital W&SS
Projects Repl. $0.00 This M&C $744,549.00$744,549.00
-Fund Contract
56002 2021
WSM-D
Funding is budgeted in the Transfer to Water/Sewer account of the Water and Sewer operating budget for the purpose of funding the W&SS REPL
Contract 2021 WSM-D within the Water&Sewer Capital Projects Fund.
Appropriations for Water and Sanitary Sewer Replacement,Contract 2021 WSM-D,are as depicted below:
Fund Existing Additional Project
Appropriations Appropriations I Total*
W&S Capital
Projects-Fund $0.00 $744,549.00$744,549.00
56002
Project Total $0.00 $744,549.00 $744,549.00
`Numbers rounded for presentation purposes.
BUSINESS EQUITY OFFICE: Dal-Tech Engineering Inc.is in compliance with the City's Business Equity Ordinance by committing to 100 percent
Business Equity participation on this project.The City's Business Equity goal on this project is 13 percent. Dal-Tech Engineering Inc. is WBE
certified.
The project is located in COUNCIL DISTRICT 6.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Water&Sewer Fund,and upon approval of the above recommendations
and adoption of the attached appropriation ordinance,funds will be available in the W&S Capital Projects Fund for the W&SS REPL Contract,
2021 WSM-D project to support the approval of the above recommendations and execution of the engineering agreement.Prior to any
expenditure being incurred,the Water Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: Brenda Oropeza 8271