Loading...
HomeMy WebLinkAboutContract 57479-CO1 CSC No.57479-001 FORT WORTH. City of Fort Worth Change Order Request Project Name 2022 HMAC Surface Overlay Contract City Sec# 57479 Client Project#(s) 103455 Project Description Street rehabilitation of concrete curb and gutter,driveways,sidewalks,and asphalt pavement Contracto Advanced Paving Acquisition Change Order# 1 Date 6/28/2022 City Project Mgr. Iretomiwa Otuyelu City Inspector Curtis Hollingsworth Contract Time Dept. TPW Totals (CD) Original Contract Amount $1,027,828.84 $1,027,828.84 180 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1,027,828.84 $1,027,828.84 180 Go to ADD&DEL Tabs to Enter CO Backup $0.00 Revised Contract Amount $1,027,828.84 $1,027,828.84 180 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST,25%) $1,284,786.05 JUSTIFICATION(REASONS)FOR CHANGE ORDER This Change Order is to change one of the Project street limits for Contract#57479. Due to another city construction project ongoing at Virgina Ln,We propose to change the street limits from Virginia Ln(Oakland Blvd-Dead End)to S Virgina Ave(E Annie St-E Leuda St). It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. Contractor's Company Name Contractor(Name) Contract Signature Date Advanced Paving Acquisition Sam Garrett o,z ,,o« Jun 30,2022 Inspector/Inspection Super v Date Project and Contract Compliance Manager Date Ad-- Jun 29,2022 ,-w Jun 29,2022 Program Manager Date Senior Capital Project Officer Date Jul 1,2022 �gegJul 1,2022 �e1 asp, Assistant Director(Dept) Date Director,Contracting Department(Dept) Date p Jul 5, 2022 `„ ion Jul 5,2022 Assistant City Attorney Date Assistant City Manager Date e� Jul 5,2022 Jul 5,2 222 „k,Js=z2sIIIon 1��=. —sin Council Action(if required) �o4v�nn xc N11mber 22-0448 M&C Date Approved 6/14/2022 ATTEST: Aa FORr 114 Tannette 5.Gaa�lgll p 0 Q00000 Jannette S.C..&I[(Ju16,202213:12 CDT) 00 00 Od� Jannette Goodall,City Secretary p�0 a�� OFFICIAL RECORD �v° 01 $ o° CITY SECRETARY � d o0 0 000000000 p/-/ FT.WORTH,TX 4� l XASo.o, �>]dd�'d4 FORTWORTH City of Fort Worth 1y*`-- Change Order Additions Project Name 2022 HMAC Surface Overlay Contract City Sec# 57479 Cl ient Project# 103455 Contractor Advanced Paving Acquisition PM Irelomiwa Otuyelu Inspector Curtis Hollingsworth Change Order Submittal# O1 Date 6/28/2022 ADDITIONS ty Unit Unit Cost Total TPW $0.00 Sub Total Additions Change Order Additions Page 2 of 5 Foa_ T�H City of Fort Worth Change Order Deletions Project Name 2022 HMAC Surface Overlay Contract City Sec# 57479 Client Project# 103455 Contractor Advanced Paving Acquisition PM Iretomiwa Otuyelu Inspector Curtis Hollingsworth Change Order Submittal# O1 Date 6/28/2022 DELL I IONS ty Unit Unit Uost I ota TPW S0.00 �iub I otal Deletions Change Order Deletions Page 3 of 5 M/SBE for this Change Order M/SBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders co# DATE AMOUNT Total $0.00 City of Fort Worth, Texas Mayor and Council Communication DATE: 06/14/22 M&C FILE NUMBER: M&C 22-0448 LOG NAME: 202022 HMAC SURFACE OVERLAY CONTRACT CHANGE ORDER 1 SUBJECT (CD 8)Authorize Change Order No. 1 to 2022 Hot Mix Asphaltic Concrete Surface Overlay Contract Project with Advanced Paving Acquisition, Ltd.,to Replace a Street Segment with No Increase to the Contract Amount RECOMMENDATION: It is recommended that the City Council authorize the execution of Change Order No. 1 to City Secretary Contract No. 57479 with Advanced Paving Aquisition, Ltd.,for the 2022 Hot Mix Asphaltic Concrete Surface Overlay Contract project to replace a street segment in the scope of work at no increase to the contract amount(City Project No. 103455). DISCUSSION: On February 22, 2022, by Mayor and Council Communication (M&C)22-0117,the City Council authorized execution of contract 57479 with Advanced Paving Acquisition LTD., in the amount of$1,027,828.84 for 2022 Hot Mix Asphaltic Concrete Street Rehabilitation Contract project for the rehabiliation of approximately two lane miles of street segments on Mount View Avenue and Virginia Lane as part of the 2022 Hot Mix Asphaltic Concrete(HMAC)Surface Overlay Contract project(City Project No. 103455). Change Order No 1 is to replace a street segment from the original scope of work in the 2022 HMAC Surface Overlay Contract project(City Project No. 103455). Due to conflict with another city project ongoing at Virginia Lane,staff is removing this street segment and replacing it with S.Virginia Avenue.This change order will change the scope to provide street rehabilitation for approximately two lane miles of street sections as listed below.The value of the contract and the quantity of work anticipated to be performed is approximately the same as originally contemplated. No additional funding is required for this change order. St F From To CD Mount View Imeadowbrock Dr 71Panola Ave —87 S Virginia Avenue E Annie Street E Leuda Street Upon completion of the project,there will be no impact on the General Fund Operating budget. This project is located in COUNCIL DISTRICT 8. A Form 1295 is not required because:This contract legally does not require City Council approval. FISCAL INFORMATION/CERTIFICATION: The Director of Finance certifies that approval of this recommendation will have no material effect on City funds. Submitted for City Manager's Office by. Dana Burghdoff 8018 Originating Business Unit Head: William Johnson 7801 Additional Information Contact: Monty Hall 8662