City of Fort Worth
Change Order Request
Project Name' HMAC Surface Overlay (2012-3) At Various Locations 50/50
Client Project #(s)I City Project No.: 01865
Project Description) HMAC Surface Overlay - 50/50 Street Maintenance
CITY SECRETARY
CONTRACT NO.
DOE: 6813
City Sec # I 43305
Contractor' Advanced Paving Acquistion, LTD I Change Order # I 2 Date 2/28/2013
City Project Mgr.I Kristian Sugrim (817) 392-8902 I City Inspector I Ali Motamed (817) 944-1174
Dept. TPW Water Sewer Totals Contract Time
(CD)
Original Contract Amount $398,786.23 $266,443.34 $177,628.88 $842,858.45 90
Extras to Date $0.00 $0.00 $0.00 $0.00 5
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $398,786.23 $266,443.34 $177,628.88 $842,858.45 95
Amount of Proposed Change Order $11,550.12 $0.00 $0.00 $11,550.12 8
Revised Contract Amount $410,336.35 $266,443.34 $177,628.88 $854,408.57 103
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO
Additional Funding (if necessary)
$0.00 $0.00 $0.00
$11,550.12
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
$11,550.12
1.37%
$1,053,573.06
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This change order is necessary for the creation a new pay item, (Retaining Wall) on Columbus Ave (S. Dead End - Angle Ave.). Request that 8
Calendar Days (CD) be added to compensate for the completion of the additional added work .
'4
G
f 'Q0oo0000'404,
0plc 0.�6
o0
0 ' 0
00000- .a
h XA►S.o�a
OFFICIAL RECORD
CITY SECRETARY
FT WORTH TX
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and/atisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
Advanced Paving Acquistion, LTD
Insp ctor/Inspectigin .�1 per is
I >O /
Assista
it y' torney
Contractor (Name)I //A.00,„Ire / I ate,
A5 -4. 6/4-rxr n // C3//i !3
c
Date Project Ma ger/Program Mane) Date
3,%/ 201 3 14' //V" A:pia., `3h t s
,bate tor, Contra ting De artment (Dept) Date,
3.s/-3 � c 2 lin /3
Date t City Manager Date
-.1 -13 u .__Z ,L— 3/i9/i3
Council Action (if required)
M&C Number Ai/L
RECEIVED MAR 19 2013
M&C Date Approved
T" �r
FORT WORTH.
City of Fort Worth
Change Order Request
Project Name' HMAC Surface Overlay (2012-3) At Various Locations 50/50
Client Project#(s)I City Project No.: 01865
Project Description) HMAC Surface Overlay - 50/50 Street Maintenance
Contractor' Advanced Paving Acquistion, LTD
City Project Mgr.
Kristian Sugrim
(817) 392-8902
Dept. TPW
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
!Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
$398,786.23
$0.00
Water
DOE: 6813
Change Order #
City Inspector
C Sewer
City Sec # I 43305
2
Ali Motamed
$266,443.34 • K $177,628.88
$0.00 —' $0.00
$398,786.23 $266,443.34 $177,628.88
$11,550.12 $0.00 $0.00
$410,336.35 $266,443.34 $177,628.88
$0.00 $0.00 $0.00
$11,550.12
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This change order is necessary for the creation a new pay item, (Retaining Wall) on Columbus Ave (S. Dead End - Angle Ave.). Request that 8
Calendar Days (CD) be added to compensate for the completion of the additional added work .
I")
Date
Totals
$842,858.45
$0.00
$842,858.45
$11,550.12
$854,408.57
$0.00
$11,550.12
2/28/2013
(817) 944-1174
Contract Time
(CD)
90
5
95
8
103
1.37%
$1,053,573.06
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord andAatisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. ,�`
i
Contractor's Company Name
Advanced Paving Acquistion, LTD
Inspector/Inspecti n,gyper isgr
Me na 2 / 4Eti
Assistant Direct& (Dept)
gstistrf City -Attorney
Contractor (Name)
.'vv`, 6 A I _(=
Date
i20/ 3
Date
Date _
-lq.(3
I !lin�'n
Director, Contracting Department (Dept)
Assistant City Manager
..w__ L
Council Action (if required)
tra�1:��0 ture � pate,
Gam- 3iz(1:,�
Prolgct Manager/Program %anageeffi�
// V "(7 / N"'lk�
Date
Date
3/0//3
M&C Number I I; j/`( ..
M&C Date Approved
FORT WORTH City of Fort Worth
Change Order Request
Project Name' HMAC Surface Overlay (2012-3) At Various Locations 50/50
Client Project #(s)I City Project No.: 01865
Project Description
HMAC Surface Overlay - 50/50 Street Maintenance
Contractor) Advanced Paving Acquistion, LTD
City Project Mgr.' Kristian Sugrim
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
!Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
(817) 392-8902
I City Sec # I 43305
DOE: 6813
Change Order #
2
City Inspector I Ali Motamed
Date I2/28/2013
(817) 944-1174
TPW Water Sewer Totals
$398,786.23 $266,443.34 $177,628.88 $842,858.45
$0.00 $0.00 $0.00 $0.00
$398,786.23 $266,443.34 $177,628.88 $842,858.45
$11,550.12 $0.00 $0.00 $11,550.12
$410,336.35 $266,443.34 $177,628.88 $854,408.57
$0.00
$0.00 $0.00 $0.00
$11,550.12 $11,550.12
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This change order is necessary for the creation a new pay item, (Retaining Wall) on Columbus Ave (S. Dead End - Angle Ave.). Request that 8
Calendar Days (CD) be added to compensate for the completion of the additional added work .
Contract Time
(CD)
90
5
95
8
103
1.37%
$1,053,573.06
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
Advanced Paving Acquistion, LTD
Inspector/Inspection Supervisor
/; CA 1 / ik • / r (K_.
Assistant Director (Dept)
Assistant City Attorney
Contractor (Name)
Date
Date
Contract Signature
Project Manager/Program Manager
Director, Contracting Department (Dept)
Date Assistant City Manager
Council Action (if required)
Date
Date
Date
Date
M&C Number I )ii
I
M&C Date Approved
FORT WORTH
City of Fort Worth
Change Order Additions
Project Name HMAC Surface Overlay (2012-3) At Various Locations 50/50
Client Project # J City Project No.: 01865
Project Description
Contractor
City Project Mgr.
HMAC Surface Overlay - 50/50 Street Maintenance
Advanced Paving Acquistion, LTD
Kristian Sugrim (817) 392-8902
I 1 EM UESCR11' I IUN
31 (New) Retaining VVall (Columbus Ave.)
DOE: 6813
I Change Order #
2
City Inspector I Ali Motamed
ADDITIONS
DEFT
I I -NV
Uty
29.UU
Unit
C;Y
I City Sec # I 43305
Date I 2/28/2013
(817) 944-1174
Unit Cost I otal
$398.26 $11,bbU.12
Change Order Additions Page 1 of 2
TPW $11,550.12
Water $0.00
Sewer $0.00
Sub Total Additions $11,550.12
Change Order Additions Page 2 of 2
FORT WORTH
City of Fort Worth
Change Order Deletions
Project Name J HMAC Surface Overlay (2012-3) At Various Locations 50/50
Client Project # City Project No.: 01865
Project Description
HMAC Surface Overlay - 50/50 Street Maintenance
DOE: 6813
Contractor Advanced Paving Acquistion, LTD I Change Order #
City Project Mgr. Kristian Sugrim (817) 392-8902
2
City Inspector I Ali Motamed
I City Sec # I 43305
Date I 2/28/2013
(817) 944-1174 I
DELETIONS
1 I EIVI UESC:NIP I ION UEI- I Uty Unit Unit t;ost I otal
Change Order Deletions Page 1 of 2
TFVV $0.00
Water $0.00
Sewer $0.00
Sub Total Deletions
Change Order Deletions Page 2 of 2
MWBE Sub
MWWBE Breakdown for this Change Order
Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co # DATE AMOUNT
Total $0.00
PROJECT SUMMARY SHEET
(Change Order Attachment)
PROJECT NAME: HMAC SURFACE OVERLAY (2012-03)
PROJECT LIMITS: AT VARIOUS LOCATIONS 50/50
BuySpeed No (T/PW): PO-12-00072287
BuySpeed No (Water): PENDING
City Project No: 01865 Original M 8 C approved 05-15-12 C25613
Contract No: CS43305
D.O.E. No: 6813
Attachment to Change Order No: 2
Today's Date: 3/8/13
TOTAL T/PW Water Sewer
Original Contract Amount: $ 842,858.45 $ 398,786.23 $ 266,443.34 $ 177,628.88
Extras to Date: $ $ - $ - $ -
Credits to Date: $ $ - $ - $
Contract Amount to Date: $ 842,858.45 $ 398,786.23 $ 266,443.34 $ 177,628.88
Amount of Proposed Change Order: $ 11,550.12 $ 11,550.12 $ - $
Revised Contract Amount: $ 854,408.57 $ 410,336.35 $ 266,443.34 $ 177,628.88
Contingency Funds Avail. for Admin. Change Orders:
Remaining Funds Available for Change Orders: $ - $ - $
Additional Funding (if necessary): $ 11,550.12 $ 115,520.12 $
Prepared By: Etta Bacy T/PW Construction Services
$