HomeMy WebLinkAboutContract 44705 (2)COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS §
COUNTY OF TARRANT §
City Secretary
Contract No. L)L+-S
WHEREAS, the undersigned Developer ("Developer") desires to make certain
improvements ("Improvements") related to a project as described below ("Project") within the City
of Fort Worth, Texas ("City"); and
WHEREAS, the Developer and the City desire to enter into this Community Facilities
Agreement ("CFA" or "Agreement") in connection with the Improvements.
Developer and Project Information:
Developer Company Name: Hahei, Ltd.
Address, State, Zip Code: 365 Miron Dr., Suite A I Southlake, TX 76092
Phone, E-Mail: (817) 416-3981 I jancaster@offrceeyuitysolutions.com
Authorized Signatory/Title: James Lancaster, Director
Project Name and Brief Description: Water & Sewer Improvements to serve Heritage Trace Center Ph.
V, Lot 4
Project Location:SW Corner of Heritage Trace Pkwy. & N. Beach St.
Plat Case No.: FS-013-054 Plat Name: Heritage Addition
Council District: 2 City Project No: 02124 ICFA: 2013-043
To be completed by staff.
` 1
Received by: � V\ k��
RECEIVED AUG 13 2013
1
DOE: 7067
Date: i 1 3 i I 13
OFFICIAL RECORD
CITY SECRETARY
Ft WORTH, TX
NOW, THEREFORE, For and in consideration of the covenants and
conditions contained herein, the City and the Developer do hereby agree as follows:
General Requirements
A. The Policy for the Installation of Community Facilities ("Policy") dated March 2001,
approved by the City Council of the City of Fort Worth, as amended, is hereby
incorporated into this Agreement as if copied herein verbatim. Developer agrees to
comply with all provisions of said Policy in the performance of its duties and
obligations hereunder and to cause all contractors hired by Developer to comply with
the Policy in connection with the work performed by said contractors.
B. Developer shall provide financial security in conformance with paragraph 6, Section
II, of the Policy and recognizes that there shall be no reduction in the collateral until
the Project has been completed and the City has officially accepted the
Improvements. Developer further acknowledges that said process requires the
contractor to submit an Affidavit of Bills paid signed by its contractor and Consent
of Surety signed by its surety to ensure the contractor has paid the sub -contractor
and suppliers in full. Additionally, the contractor will provide in writing that the
contractor has been paid in full for all the services provided under this contract.
C. Developer agrees to cause the construction of the Improvements contemplated by
this Agreement and that said construction shall be completed in a good and
workmanlike manner and in accordance with all City standards and the City -
approved construction plans, specifications and cost estimates provided for the
Project and the exhibits attached hereto.
D. ;The following checked exhibits are made a part hereof: Water (A) X, Sewer (A-1)
__X, Paving (B) Storm Drain (B-1) , Street Lights & Signs (C)_
E. The Developer shall award all contracts for the construction of the Improvements in
accordance with Section II, paragraph 7 of the Policy and the contracts shall be
administered in conformance with paragraph 8, Section II, of the Policy.
F. For all Improvements included in this Agreement for which the Developer awards
construction contract(s), Developer agrees to the following:
i. To employ a construction contractor who is approved by the director of the
department having jurisdiction over the infrastructure to be constructed, said
contractor to meet City's requirements for being insured, licensed and bonded to do
work in public streets and/or prequalified to perform water/waste water
construction as the case may be.
ii. To require its contractor to furnish to the City a payment and performance bond in
2
the names of the City and the Developer for one hundred percent (100%) of the
contract price of the Improvements, and a maintenance bond in the name of the
City for one hundred percent (100%) of the contract price of the Improvements for
a period of two (2) years insuring the maintenance and repair of the constructed
infrastructure during the term of the maintenance bond. All bonds to be furnished
before work is commenced and to meet the requirements of Chapter 2253, Texas
Government Code.
iii. To require the contractor(s) it hires to perform the construction work contemplated
herein to provide insurance equal to or in excess of the amounts required by the
City's standard specifications and contract documents for developer -awarded
infrastructure construction contracts. The City shall be named as additional
insured on all insurance required by said documents and same will be evidenced on
the ACORD Certificate of Insurance supplied by the contractor's insurance
provider and bound in the construction contract book.
iv. To require its contractor to give 48 hours notice to the City's Construction Services
Division of intent to commence construction so that City inspection personnel will
be available; and to require the contractor to allow the construction to be subject to
inspection at any and all times by City inspection forces, and not to install or
relocate any sanitary sewer, storm drain, or water pipe unless a responsible City
inspector is present and gives his consent to proceed, and to make such laboratory
tests of materials being used as may be required by the City.
v. To require its contractor to have fully executed contract documents submitted to
the City to schedule a Pre -Construction Meeting. The submittal should occur no
less than 10 working days prior to the desired date of the meeting. No construction
will commence without a City -issued Notice to Proceed to the Developer's
contractor.
vi. To delay connections of buildings to service lines of sewer and water mains
constructed under this Agreement until said sewer and water mains and service
lines have been completed to the satisfaction of the Water Department.
G. Developer agrees to provide, at its expense, all engineering drawings and documents
necessary to construct the improvements required by this Agreement.
H. Developer shall cause the installation or adjustment of the required utilities to serve the
development or to construct the Improvements required herein.
I. City shall not be responsible for any costs that may be incurred by Developer in the
relocation of any utilities that are or may be in conflict with any of the community
facilities to be installed hereunder.
J. Developer hereby releases and agrees to indemnify, defend and hold the City
harmless for any inadequacies in the preliminary plans, specifications and cost
estimates supplied by the Developer for this Agreement.
K. Developer agrees to provide, at its expense, all necessary rights of way and easements
across property owned by Developer and required for the construction of the current
and future improvements provided for by this Agreement.
L. The Developer further covenants and agrees to, and by these presents does
hereby, fully indemnify, hold harmless and defend the City, its officers, agents
and employees from all suits, actions or claims of any character, whether real or
asserted, brought for or on account of any injuries or damages sustained by any
persons (including death) or to any property, resulting from or in connection
with the construction, design, performance or completion of any work to be
performed by said Developer, his contractors, subcontractors, officers, agents or
employees, or in consequence of any failure to properly safeguard the work, or
on account of any act, intentional or otherwise, neglect or misconduct of said
DEVELOPER, his contractors, sub -contractors, officers, agents or employees,
whether or not such injuries. death or damages are caused. in whole or in
part. by the alleged negligence of the City of Fort Worth. its officers. servants.
or enwlovees.
M. Developer will further require its contractors to indemnify, defend and hold
harmless the City, its officers, agents and employees from and against any and all
claims, suits or causes of action of any nature whatsoever, whether real or
asserted, brought for or on account of any injuries or damages to persons or
property, including death, resulting from, or in any way connected with, the
construction of the infrastructure contemplated herein, whether or not such
injuries. death or damages are caused. in whole or in part, by the alleged
negligence of the City of Fort Worth. its officers. servants. or employees. Further,
Developer will require its contractors to indemnify, and hold harmless the City for
any losses, damages, costs or expenses suffered by the City or caused as a result of
said contractor's failure to complete the work and construct the improvements in
a good and workmanlike manner, free from defects, in conformance with the
Policy, and in accordance with all plans and specifications.
N. Upon completion of all work associated with the construction of the infrastructure and
Improvements, Developer will assign to the City a non-exclusive right to enforce the
contracts entered into by the Developer with its contractor along with an assignment of
all warranties given by the contractor, whether express or implied. Further, Developer
agrees that all contracts with any contractor shall include provisions granting to the
City the right to enforce such contracts as an express intended third party beneficiary
of such contracts.
O. Inspection and material testing fees are required as follows:
i. Developer shall pay in cash water and wastewater inspection fees and material
testing fees equal to two percent (2%) for a total of 4% of the developer's share of the
total construction cost as stated in the construction contract.
ii. Developer shall pay in cash paving and storm drain inspection fees equal to four
percent (4%) and material testing fees equal to two percent (2%) for a total of 6% of
the developer's share of the total construction cost as stated in the construction
contract.
iii. Developer shall pay in cash the total cost of streetlights or if the city is not
installing the streetlights, inspection fees equal to four percent (4%) of the
developer's share of the streetlight construction cost as stated in the construction
contract.
iv. Developer shall pay in cash the total cost of street signs.
P. COMPLETION WITHIN 2 YEARS
i. If applicable, the City's obligation to participate (exclusive of front foot charges) in
the cost of the Improvements shall terminate if the Improvements are not
completed within two (2) years; provided, however, if construction of the
Improvements has started within the two year period, the developer may request
that the CFA be extended for one year. If the Improvements are not completed
within such extension period, there will be no further obligation of the City to
participate. City participation in a CFA shall be subject to the availability of City
funds and approval by the Fort Worth City Council.
ii. Nothing contained herein is intended to limit the Developer's obligations
under the Policy, this Agreement, its financial guarantee, its agreement with
its contractor or other related agreements.
iii. The City may utilize the Developer's financial guarantee submitted for this
Agreement to cause the completion of the construction of the Improvements if at
the end of two (2) years from the date of this Agreement the Improvements have
not been completed and accepted.
iv. The City may utilize the Developer's financial guarantee to cause the completion of
the construction of the Improvements or to cause the payment of costs for
construction of same before the expiration of two (2) years if the Developer
breaches this Agreement, becomes insolvent or fails to pay costs of construction
and the financial guarantee is not a Completion Agreement. If the financial
guarantee is a Completion Agreement and the Developer's contractors and/or
suppliers are not paid for the costs of supplies and/or construction, the contractors
and/or suppliers may put a lien upon the property which is the subject of the
Completion Agreement.
(REMAINDER OF PAGE INTENTIONALLY LEFT BLANK)
Cost Summary Sheet
Project Name: Heritage Trace Center Ph. V, Lot 4
CFA No.: 2013-043 DOE No.: 7067;
Items Developer's Cost
A. Water and Sewer Construction
1. Water Construction $ 51,153.00
2. Sewer Construction $ 38,979.00
Water and Sewer Construction Total $ 90,132.00
B. TPW Construction
1. Street $
2. Storm Drain $
3. Street Lights Installed by Developer $
TPW Construction Cost Total $
Total Construction Cost (excluding the fees): $ 90,132.00
Construction Fees:
C. Water/Sewer Inspection Fee (2%) $ 1,802.64
D. Water/Sewer Material Testing Fee (2%) $ 1,802.64
Sub -Total for Water Construction Fees $ 3,605.28
E. TPW Inspection Fee (4%) $
F. TPW Material Testing (2%) $
G. Street Light lnspsection Cost $
H. Street Signs Installation Cost $
Sub -Total for TPW Construction Fees $
Total Construction Fees: $ 3,605.28
Choice
Financial Guarantee Options, choose one Amount (ck one)
'Bond = 100% $ 90,132.00
'Completion Agreement = 100% / Holds Plat $ 90,132.00
'Cash Escrow Water/Sanitary Sewer= 125% $ 112,665.00
'Cash Escrow Paving/Storm Drain = 125% $ -
'Letter of Credit = 125% w/2yr expiration period $ 112,665.00 V
7
IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be executed
in quadruplicate in its name and on its behalf by its Assistant City Manager, attested by its City
Secretary, with the corporate seal of the City affixed, and said eloper has execute this
instrument in quadruplicate, at Fort Worth, Texas this day of
.20>�.
CITY OF FORT WORTH - Recommended by:
Water Department
(.6411,1
Wendy Chit Babulal, EMBA, P.E.
Development Engineering Manager
Approved as to Form & Legality:
Douglas W. Black
Assistant City Attorney
M&C No. /.-
Date:
ATTEST:
Mary J. a
City Secre
Transportation & Public Works Department
"V
Dougla. Wiersig, P.E.
Director
Approved by City Manager's Office
"7/4414.40‘
Fernando Costa
Assistant City Manager
ATTEST: Hahei, Ltd.
g0..kra\ t-1on *art L 1, W'\L. By: Hahei Management Corp.
its General Partner
l(A q/umut\
Signature
(Print) Name: Y_IrrAto-eAtl
8
Print Nal
Title:
ignature
iCUM1LS Lan CaS-t�'
OFFICIAL RECORD.
CITY SECRETARY
FT. WORTH, TX
Check items associated with the project being undertaken; checked items must be included as
Attachments to this Agreement
Included Attachment
►1 Location Map
® Exhibit A: Water Improvements
® Water Estimate
® Exhibit A-1: Sewer Improvements
® Sewer Estimate
❑ Exhibit B: Paving Improvements
111 Paving Estimate
❑ Exhibit B-1: Storm Drain Improvements
❑ Storm Drain Estimate
❑ Exhibit C: Street Lights and Signs Improvements
❑ Street Lights and Signs Estimate
(Remainder of Page Intentionally Left Blank)
9
DOE No: 7067
City Project No: 02124
OLD DENTON ROAD
OFFICE EQUITY SOLUTIONS
I I 365 Miron, Suite A
�R ISouthloke, TX 76092
r r
Tel. (817)416-3981 Fox: (817)416-8372
o Baird, Hampton & Brown, Inc.
4� c Engineering & Surveying
4550 SH 360 Ste. 180, 0(66.60o, TX 76051 Te16817)251-8550 To)(817)251-8810 woo 8H831Ccom
THE FRV 144
r
GLEN DR
SILVERWOOD TRAIL
VICINITY MAP
N
ALTA VISTA
N BEACH STREET
SHIVER
0 1,000' 2,000'
HERITAGE TRACE CENTER PHASE v
HERITAGE ADDITION LOT 4, BLOCK 162
FORT WORTH, TX
07
co
Ed
0
DATE: JULY 2013
SCALE 1"=1,000'
THIS DOCUMENT IS RELEASED FOR THE
PURPOSE OF INTERIM REVIEW UNDER
THE AUTHORITY OF KONSTANTINE
BAKINTAS, P.E. Tx No. 67022 IT IS NOT
INTENDED FOR CONSTRUCTION, BIDDING
OR PERMIT PURPOSES.
BHB PROJECT NO:
2013.700.000
DRAWING FILE: E:\2013.000.000\2013 700 000\dwg\CFA\CFA dwg I Vicinity lop
DOE No: 7067
City Project No: 02124
CONNECT TO EX. In Heritage Addtion
10" WATER LINE (Variable WidthRighlol-Wa)
PROPOSED 10"
svD H WATER LINE
oI
z
DOME TI
IRRIGATIOI+1'
IA IE i METER
III
9,824 SF
BUILDING
Document Ito D203220170, P.R T.0 T
16ti
W>>0i �PRIVATE SANITARY
SEWER SERVICE
v e Paaxo �.
v �et�V9 Jn�e L' C.
02 p5$bZ,Q
LEGEND
EXISTING PROPOSED
PROPERTY LINE
BUILDING FOOTPRINT
CURB & GUTTER
WATER LINE
WATER VALVE
FIRE HYDRANT
METER BOX
SANITARY SEWER
0 SEWER MANHOLE
Fer
Ie
0
PROPOSED
SSMH
OFFICE EQUITY SOLUTIONS
365 Miron, Suite A
Southlake, TX 76092
Tel: (817)416-3981 Fox; (817)416-8372
re=, o Baird, Hampton & Brown, Inc.
e� 0 Engineering ,Sc Surveying
4550 5 H. 360 Ste, 180, Crope/ne. TX 76051 TH(817)251-8650 Fo6(817)251-8810 ""w.BHB;;C torn
18PE FIR4 j44
DRAWING FILE; E:\2013.000.000\2013.700.00D\dog\CFA\CFA dwg I Woter
1
4
Si
•
Heritage Trace Parkway
GAS
PROPOSED
FIRE HYDRANT
VARIABLE WIDTH
WATER EASEMENT
(DEDICATED BY
SEPARATE INSTRUMENT)
N
\
TEMPORARY
CONSTRUCTION
EASEMENT
r--
Ji° 1 L-
°N.;
\ \\
I i
CONNECT TO ISTING _X
12" WATER
Remainder of ELECTRIC
Hillwoodi2500, LTD EASEMENT
Volume 9409, Page 1403,
D.R.T.C.T.
PPF:POSED 8"
SAN''TARY SEWER
15" SANITARY
(DE I
SEVER EASEMENT
CATED BY
SEPARATE INSTRUMENT)
t
TEMPORARY
CONSTRUCTION
EASEME
N 45°00'00" W 14.26'
—EX_8 _WATER
Document No. D212057882, P.j1.7.T. ��
��SEw C / �Pa/
(Vay)
Bewley Drive/
nieble WIdt -W
EXHIBIT "A"
10" WATER LINE
0 60'
/ SCALE 1"=60'
HERITAGE TRACE CENTER PHASE v
HERITAGE ADDITION LOT 4, BLOCK 162
FORT WORTH, TX
co
0
co
0
DATE: JULY 2013
x
w
120'
THIS DOCUMENT IS RELEASED FOR THE
PURPOSE OF INTERIM REVIEW UNDER
THE AUTHORITY OF KONSTANTINE
BAKINTAS, P.E. Tx No. 67022 IT IS NOT
INTENDED FOR CONSTRUCTION, BIDDING
OR PERMIT PURPOSES.
BHB PROJECT NO:
2013.700.000
Page 1 of 1
Engineer's Preliminary Opinion of
PROBABLE CONSTRUCTION COST
for
WATER IMROVEMENTS
to Serve Heritage Trace Center Phase V-Lot 4
Item BID LIST DESCRIPTION
ITEM No.
1 3305.0103 Exploratory Excavation of Existing Utilities
3
7
11
12
13
14
15
16
17
18
19
3305.0109 Trench Safe
3311.0361 10" PVC Water Pipe
3311.0001 Ductile Iron
3312.0001 Fire Hydrant
3311.0161 6" PVC Water Pipe
3312.2103 1 1/2" Water Service
3312.3002 6" Gate Valve w/ Box &.laid
3312.3004 10" Gate Valve w/ Box & Lid
3441.1301 Saw Cut (Driveway}
0241.0401 Remove Concrete Drive
3213.0401 6" Concrete Driveway.
0241.0300 Remove ADA Ramp
3213.0501 Barrier Free Ramp, Type
3312.4108 12" x 10" Tapping Sleeve & Valve
i1'S1
3471.0001 Traffic Control
3291.0100 Topsoi
3292.0100 Block Sod Replacement
ings
QTY UNIT PRICE AMOUNT
2 EA
471 LF
452
0.75
1
LF
EA
2 EA
$600.00 $1,200.00
$2.00 $942 00
$40.00 $18,080.00
0
$2,500.00
$2,500.00
$600.00 $1,200.00
1 EA $1,500.00 $1,500.00
620 SF
$3.00 $1,860.00
$200.00
1 EA $3,500.00 $3,500.00
LS $3,500.00 $3,500.00
518 SY $5.00 $2,590.00
Total for Water Improvements $51,153.00
CITY OF FORT WORTH
Water & Sewer Improvements
to Serve Heritage Trace Center Phase V-Lot 4
C.P. 02124
DOE No: 7067
City Project No: 02124
- sv0
,;
EXISTING
Heritage Trace Parkway
PROPOSED 10"
WATER LINE
DOMESTIC
IRRIGATIOtV
WATER METER
1 !II;
i
PRIVATE DOMES'pk
WATER SERV
9,824 SF
BUILDING
PRIVATE SANITARY
SEWER SERVICE
LEGEND
PROPERTY LINE
BUILDING FOOTPRINT
CURB & GUTTER
WATER LINE
WATER VALVE
FIRE HYDRANT
METER BOX
SANITARY SEWER
SEWER MANHOLE
in Heritage Addtion
(Venable WMth Rightol-Way)
Document Ho D203220170, P R T C T.
nns
PROPOSED
rn
PROPOSED
SSMH
Z
4
OFFICE EQUITY SOLUTIONS
365 Miron, Suite A
Southlake, TX 76092
Tel: (617)416-3981 Fox: (817)416-8372
Baird, Hampton & Brown, Inc.
L'— 0 e Engineering 8c Surveying
4550 SR 360 Ste. 100, Cropegne, 1X 76051 10.(817)251-8550 Fo, (817)251-8810 ....BHBliC cnm
1BPE MU 144
DRAWING FILE: E:\2013.000.000\2013700000\dog\CFA\CFA dog 1 Sewer
cis GAS
VARIABLE WIDTH
WATER EASEMENT
(DEDICATED BY
SEPARATE INSTRUMENT)
TEMPORARY
CONSTRUCTION
EASEMENT
Remainder of
Hillwood/2500, LTD
Volume 9409, Page 1403,
D.R.T.C.T.
PROPOSED
SSMH
PR POSED 8"
SAN TARY SEWER
15" SANITARY
(DE I
SEER EASEMENT
CATED BY
SEPARATE INSTRUMENT)
L
� L-
ELECTRIC
EASEMENT
TEMPORARY
CONSTRUCTION
EASEME
Bewley Drive/ \ti
VMt (Variable h Right -of -Way)
Document No. D212057082, P.R.TC
E 50 R cP
/ o
• —
8 11
EXHIBIT "A-1"
SANITARY SEWER LINE
HERITAGE TRACE CENTER PHASE v
HERITAGE ADDITION LOT 4, BLOCK 162
FORT WORTH, TX
R
Li
N
11
lk�
NII
X
W
et-
M11O D
1 NIL
CONNECT T EX
12" SANITAR SEWEF
60'
120'
aa
0
0 0
DATE: JULY 2013
SCALE 1"=60'
THIS DOCUMENT IS RELEASED FOR THE
PURPOSE OF INTERIM REVIEW UNDER
THE AUTHORITY OF KONSTANTINE
BAKINTAS, P.E. Tx No. 67022 IT IS NOT
INTENDED FOR CONSTRUCTION, BIDDING
OR PERMIT PURPOSES.
BHB PROJECT NO:
2013.700.000
Page 1 of 1
Engineer's Preliminary Opinion of
PROBABLE CONSTRUCTION COST
for
SANITARY SEWER IMPROVEMENTS
to Serve Heritage Trace Center Phase V-Lot 4
Item BID LIST DESCRIPTION
ITEM No.
1 3305.0103 Exploratory Excavation of Existing Utilities
2 3305.0109 Trench Safety
3 3331.4115 8" PVC Sewer Pipe
3301.0002 Post -CCTV Inspection_
3331.3101 4" Sewer Service
3339.1001 4' Manhole
7 9999.0002 Normal Drop at Ex. Manhole
9
11
3301.0101 Manhole Vacuum Testing
3305.0112 Concrete Collar
3339.0001 Corrosion Protection for Existing'IitlanHole
3339.1003 4' Extra Depth Manhole
12� 3291.0100 Topsoil,
13 3292.01001Block Sod Replacement
QTY UNIT PRICE AMOUNT
1 EA $1,250.00 $1,250.00
282 IF $3.00 $84+6.00
282 LF $36.00 $10,152.00
282 LF
1 EA
1 EA
4 EA
4 EA
16 VF
2 VF
56 CY
487 SY
3.00 $846.00
$550.00 $550.00
$3,500.00 $14,000 00
$2,000.00 $2,000.00
$200.00 - $000 00
$300.00 $1,200.00
$175.00 $2,800.00
$350.00 $700.00
$25.00 $1,400 00
$5.00 $2,435.00
Total Bid for Sanitary Sewer Improvements $38,979.00
CITY OF FORT WORTH
Water & Sewer Improvements
to Serve Heritage Trace Center Phase V-Lot 4
C.P. 02124
1 of 1
ITEM
NO.
1
2
CFA QUANTITY MATRIX FOR IMPROVEMENTS
TO SERVE
HERITAGE TRACE CENTER PHASE V-LOT 6
BID ITEM
Exploratory Excavation of Existing Utilities
Trench Safety
3 10" PVC Water Pipe
4 Ductile Iron Water Fittings
5 Fire Hydrant
6 6" PVC Water Pipe
7 1 1/2" Water Service
8 6" Gate Valve w/ Box & Lid
9 10" Gate Valve w/ Box & Lid
10 Saw Cut (Driveway)
11 Remove Concrete Drive
12 6" Concrete Driveway
13 Remove ADA Ramp
14
15
16
17
18
19
Barrier Free Ramp, Type R-1
12" x 10" Tapping Sleeve & Valve
SW3P
Traffic Control
Topsoil
Block Sod Replacement
17 Exploratory Excavation of Existing Utilities
is Trench Safety
19 8" PVC Sewer Pipe
20 Post -CCTV Inspection
21 4" Sewer Service
22 4' Manhole
23 Normal Drop at Ex. Manhole
24 Manhole Vacuum Testing
25 Concrete Collar
26 Corrosion Protection for Existing ManHole
27 4' Extra Depth Manhole
28 Topsoil
29 Block Sod Replacement
UNIT
EA
LF
LF
TON
EA
LF
EA
EA
EA
LF
SF
SF
EA
EA
EA
LS
LS
CY
SY
EA
LF
LF
LF
EA
EA
EA
EA
EA
VF
VF
CY
SY
SHEET NO.
3 4
2
471
452
0.75
1
19
2
1
1
170
620
620
2
2
1
1
56
518
ITEM TOTAL
UNIT PRICE COST
$600.00
$2.00
$40.00
$3,500.00
$2,500.00
$34.00
$600.00
$800.00
$1,500.00
$3.00
$3.00
$5.00
$100.00
$250.00
$3,500.00
$4,500.00
$3,500.00
$25.00
$5.00
WATER IMDROVEWATS TOTAL
ITEM
TOTAL
2
471
452
0.75
1
19
2
1
1
170
620
620
2
2
1
1
1
56
518
1 1 $1,250.00
282 282 $3.00
282 282 $36.00
282 282 $3.00
1 1 $550.00
4 4 $3,500.00
1 1 $2,000.00
4 4 $200.00
4 4 $300.00
16 16 $175.00
2 2 $350.00
56 56 $25.00
487 487 $5.00
SEWER IlVf2ROVEMNTS TOTAL
PROJECT TOTAL
$1,200.00
$942.00
$18,080.00
$2,625.00
$2,500.00
$646.00
$1,200.00
$800.00
$1,500.00
$510.00
$1,860.00
$3,100.00
$200.00
$500.00
$3,500.00
$4,500.00
$3,500.00
$1,400.00
$2,590.00
$51,153.00
$1,250.00
$846.00
$10,152.00
$846.00
$550.00
$14,000.00
$2,000.00
$800.00
$1,200.00
$2,800.00
$700.00
$1,400.00
$2,435.00
$38,979.00
$90,132.0T
CITY OF FORT WORTH
Water & Sewer Improvements
to Serve Heritage Trace Center Phase V-Lot 4
C.P. 02124