Project Name' 2008 CIP Contract 9A
Client Project #(s)' #01237 / DOE 6145
City of Fort Worth
Change Order Request
.;;)'11; k'rECRETAIIV
CONTRACT Mao 1 J 3I L / - (t' Li
Change Order Submittal # I 4
City Sec # I 43149
Date I 10/1/2013 I
Dept. TPW Water Sewer Contract Time
Totals (CD)
Original Contract Amount $631,268.50 $255,401.75 $0.00 $886,670.25 250
Extras to Date $18,452.50 $36,056.25 $54,508.75 32
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $649,721.00 $291,458.00 $0.00 $941,179.00 282
!Amount of Proposed Change Order $94,748.00 $0.00 $0.00 $94,748.00 65
Revised Contract Amount $744,469.00 $291,458.00 $0.00 $1,035,927.00 347
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00 $0.00 $0.00
Additional Funding (if necessary) $94,748.00 $94,748.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
16.83%
$1,108,337.81
I
The estimated quantity for the unclassified street excavation exceeded the original quantity. The actual quantity was confirmed from the
project cross -sections by both the contractor and the design engineer. The exisitng storm drain system on Beddell was found to not be working
properly and the storm drain department chose to replace the existing system under a seperate contract. The contractor chosen by the storm
drain department installed the curb inlet bottoms only in accordance with the revised city standard inlet details. The revised inlet details require
a larger inlet than the old standards, which was originally used for this project. Due to the configuration of the proposed inlet tops and the
adjacent drive approaches it has been determined to add the inlet tops to this contract to prevent any installation conflicts betweent the two
contracts and/or contractors.
JAN 0 3 2014
OFFICIAL RECORD
CITY SECRETARY
�T1 WORTH, TX
FORT WORTH® City of Fort Worth
Change Order Request
Foe r WORTH
City of Fort Worth
Change Order Additions
Project Name ( 2008 CIP Contract 9A
Client Project # I #01237 / DOE 6145
Change Order Submittal #
4
I City Sec # I 43149
Date I 10/1/2013
AUDI I IONS
I I tM UtSGKIN I IUN I UEP 1 Uty unit unit Cost I otai
I'AVINti SEC I IUN $0.UU $0.00
13 - INCH 3123.0101 Unclassitled Excavation by Han TPW 5,096.00 CY $18.00 591,/Z6.UU
38 - NEW 3305.0105 Inlet Adjustment- 10' Inlet lop Only TPW 2.00 EA 52,8/5.00 55,r5u.uu
39 - NEW 3471.0001 Traffic Control ITPW 2.0U MO $2,100.00 54,20U0U
I
TPW
Water
Sewer
Sub Total Additions
5101,678.00
$0.00
$0.001
5101,678.001
Change Order Additions Page 1 of 1
CFW Change Order Approval St-COApp02 Page 1 of 5
Routing
Assigned To:
Assigned By:
Due Date:
Due Time:
Links (11
fortworthaov/Infrastructure Proiects/01237 - 5th Ave 6th Ave Beddell St W 2008 CIP 9A/Contractor/Chance Orders/Chanae Order #4 Breakdown.xis
Attachments (01
No Attachments have been added to this form.
hops://projectpoint.buzzsaw.com/ bzweb/Forms/FormPrint.aspx?SiteId=51500&ProcessId... 1/3/2014
CFW Change Order Approval St-COApp02 Page 2 of 5
FORT WORTH® City of Fort Worth
Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.:
Change Order No.:
City Sec. No.:
Project Name:
Project Numbers:
Project
Description:
Project Manager:
Contractor:
St-COApp02
43149
4
Date Started:
Date Due:
2013-10-28
2013-12-17
5th Ave 6th Ave Beddell St W 2008 CIP 9A
01237 DOE Numbers:
DOE 6145
2008 CIP: Pavement Reconstruction and Water Mian Replacement
on Portions of Fifth Avenue, Sixth Avenue and Bedell Street
Gopal Sahu
City Inspector:
Kim Brenz
Stabile & Winn, Inc.
COUNCIL ACTION (If Required):
M&C Log Name:
M&C Number:
202008 CIP
C-25533
COST AND DAYS SUMMARY:
M&C Date:
2012-03-27
Requested
Department: Cost($) Fund Account Center: Days:
T/PW
Approval Status:
$ 94,748.00
C204 541200 209400123783
Total Cost: $ 94,748.00 Total Requested Days:
65
65
https://projectpoint.buzzsaw.com/ bzweb/Forms/FormPrint.aspx?SiteId=51500&ProcessId... 1/3/2014
CFW Change Order Approval St-COApp02 Page 3 of 5
https://projectpoint.buzzsaw.com/ bzweb/Forms/FormPrint.aspx?SiteId=51500&ProcessId... 1/3/2014
CFW Change Order Approval St-COApp02 Page 4 of 5
Approved: Yes
Comments:
User: Tara Fishback
Date: 2013-10-28 11:11 AM
Approved: Yes
Comments:
User: Jerry Henderson
Date: 2013-10-28 12:14 PM
Approved: Yes
Comments:
User: Gopal Sahu
Date: 2013-10-28 6:35 PM
Approved: Yes.
Comments:
User: Tara Fishback
Date: 2013-10-28 2:52 PM
Approved: Yes
Comments:
User: Jerry Henderson
Date: 2013-10-28 2:59 PM
Approved: Yes
Comments:
User: Gopal Sahu
Date: 2013-10-28 8:07 PM
Approved: Yes
Comments:
User: Najib Fares
Date: 2013-10-28 3:11 PM
Approved: Yes
Comments:
User: Andy Anderson
Date: 2013-10-29 8:42 AM
Approved: Yes
Comments:
User: Doug Wiersig
Date: 2013-11-18 3:33 PM
Approved: Yes
Comments:
https://projectpoint.buzzsaw.com/ bzweb/Forms/FormPrint.aspx?Siteld=51500&Processld... 1/3/2014
CFW Change Order Approval St-COApp02 Page 5 of 5
User: Doug Wiersig
Date: 2013-11-20 3:45 PM
Approved: Yes
Comments:
User: Fernando Costa
Date: 2013-11-20 9:54 PM
Action Required: No approval required by Water Departmrnt