Change Order Request CONTRACT NO. L , C
2008 Capital Improvement Program Artirial Street Project Ray White Road I City Sec # I 43167
C204-531200-202230129430 DOE#6226
Paving, Retaining Wall, Street Lights and Drainage Improvements for Ray White Road from North Tarrant Parkway to
Shiver Road.
McClendon Construction I Change Order # I 1
Wilma Smith City Inspector I Thomas Miller
Dept. TPW Water Sewer
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
$1,428,769.70
$0.00
$0.00
$0.00
$1,428,769.70
$4,045.00 $0.00
$1,432,814.70
$197,835.00
$197,835.00
$0.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
The 1" water service and the irrigation system re -location were city owned systems to provide irrigation for the landscaping around the entrance
to the neighbourhood at Senator Dr. These systems were in the way of the storm drain and roadway. The sanitary sewer item is to reimberse
the contractor for performing the work called for on plan sheet 38 at station 4+17.
Date I 9/25/2012
Totals
$1,428,769.70
$1,428,769.70
$4,045.00
$1,432,814.70
$197,835.00
$197,835.00
0.28%
$1,785,962.13
Contract Time
(CD)
424
424
3
427
as aV oanA ak
0.
o0d
oxA
rd
Kayser, City S iar'Y �� °°a000a�
cr
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
1 Contractor's Company Name
McClendon Construction
Apsi�ly'Rttorney
M&C Number I AthA.
Date
Date
11 iL.•(�
Pro'eci� M,tager/PrograriMana
Date
. 1/-5- l
tor,,Contractin Department (Dept) { 1 , Date
/i/J2-1/2
Manager r Date
64,/ ///3/z
Council Action (if required)
M&C Date Approved
Project Description
JRT WORTH,,
City of Fort Worth
Change Order Request
(0/2v / 0/ 2
L131-(0)
Project Name' 2008 Capital Improvement Program Artirial Street Project Ray White Road I City Sec # I 43167
Client Project #(s)I C204-531200-202230129430 DOE#6226
Paving, Retaining Wall, Street Lights and Drainage Improvements for Ray White Road from North Tarrant Parkway to
Shiver Road.
Contractor' McClendon Construction I Change Order # I 1 Date I 9/25/2012
City Project Mgr.' Wilma Smith
Dept. TPW
Original Contract Amount $1,428,769.70
Extras to Date $0.00
Credits to Date $0.00
Pending Change Orders (in M&C Process) $0.00
Contract Cost to Date $1,428,769.70
!Amount of Proposed Change Order $k()45.
Revised Contract Amount $f,432,814.76
Original Funds Available for Change Orders $i17,$35.66
Remaining Funds Available for this CO $19/,83b.00
City Inspector I Thomas Miller
Water Sewer
Contract Time
Totals (CD)
$1,428,769.70 424
$1,428,769.70 424
dU.JJ $4,045.00 3
$1,432,814.70 427
$197,835.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
$197,835.00
U.28%
$1M,§6.1 1
JUSTIFICATION (REASONS) FOR CHANGE ORDER
The 1" water service and the irrigation system re -location were city owned systems to provide irrigation for the landscaping around the entrance
to the neighbourhood at Senator Dr. These systems were in the way of the storm drain and roadway. The sanitary sewer item is to reimberse
the contractor for performing the work called for on plan sheet 38 at station 4+17.
,141.1 /.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
McClendon Construction
ContractAr,(Name)
•
Ne
Contract Signature ,
f .
D/pte
7,
Inspector/Igspectiory Supewisor Date Project Manager/Program Mane tr (�
� o o to
.- .: k;�% /. / , ; '' '' . ;I, 'i.t / , r /'-
1/- - �.
_
Assistant Directorj(Dept): "' Date D'reb or, Contracting Department (Dept) 1
, Date
-/2 ,� :,.ice.. 6J. 6. )L-
ll/g42
Assisj:an _ - ity Attorn Date .AssiSat,Cilw Manager
Date
r
J' 6,00,P
///3 a
Council Action (if required)
M&C Number I Ay(.. I M&C Date Approved I I
FORT WORTH;:, City of Fort Worth
Project Name'
Client Project #(s)I
Project Description)
Contractor'
City Project Mgr.'
Change Order Request
2008 Capital Improvement Program Artirial Street Project Ray White Road I City Sec # I 43167
C204-531200-202230129430 DOE#6226
Paving, Retaining Wall, Street Lights and Drainage Improvements for Ray White Road from North Tarrant Parkway to
Shiver Road.
McClendon Construction I Change Order # I 1
Wilma Smith
City Inspector I Thomas Miller
Dept. TPW Water Sewer
Original Contract Amount $1,428,769.70
Extras to Date $0.00
Credits to Date $0.00
Pending Change Orders (in M&C Process) $0.00
Contract Cost to Date $1,428,769.70
pAmount of Proposed Change Order $4,045.00 $0.00
Revised Contract Amount $1,432,814.70
Original Funds Available for Change Orders $197,835.00
Remaining Funds Available for this CO $197,835.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
Date I 9/25/2012
Totals
$1,428,769.70
$1,428,769.70
$0.00 $4,045.00
$1,432,814.70
$197,835.00
$197,835.00
0.28%
$1,785,962.13
Contract Time
(CD)
424
424
3
427
JUSTIFICATION (REASONS) FOR CHANGE ORDER
The 1" water service and the irrigation system re -location were city owned systems to provide irrigation for the landscaping around the entrance
to the neighbourhood at Senator Dr. These systems were in the way of the storm drain and roadway. The sanitary sewer item is to reimberse
the contractor for performing the work called for on plan sheet 38 at station 4+17.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
McClendon Construction
Inspector/Inspection. Supervisor
Assistant Director (Dept)
Assistant City Attorney
M&C Number I
Contractor (Name) (, Contract, Signature ,
I>'-1112.'A /
Date Project,Manager/Program Managgr I. ti(
Date Director, Contracting Department (Dept)
•
Date ,45 istabLCit Manager
/l . /t • % Lc► -,�-
Council Action (if required)
M&C Date Approved
Date
4d iDate
/1
Date
Date
FORT WORTH;; City of Fort Worth
Change Order Request
Project Name' 2008 Capital Improvement Program Artirial Street Project Ray White Road I City Sec # I 43167
Client Project #(s)I C204-531200-202230129430 DOE#6226
Project Description
Paving, Retaining Wall, Street Lights and Drainage Improvements for Ray White Road from North Tarrant Parkway to
Shiver Road.
Contractor' McClendon Construction I Change Order # I 1 I Date I 9/25/2012
City Project Mgr.' Wilma Smith I City Inspector I Thomas Miller
Dept. TPW Water Sewer Contract Time
Totals (CD)
Original Contract Amount $1,428,769.70 $1,428,769.70 424
Extras to Date $0.00
Credits to Date $0.00
Pending Change Orders (in M&C Process) $0.00
Contract Cost to Date $1,428,769.70 $1,428,769.70 424
!Amount of Proposed Change Order $4,045.00 $0.00 $0.00 $4,045.00 3
ltevised Contract Amount $1,432,814.70 $1,432,814.70 427
Original Funds Available for Change Orders $197,835.00 $197,835.00
Remaining Funds Available for this CO $197,835.00 $197,835.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT I 0.28%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) !j $1,785,962.13
JUSTIFICATION (REASONS) FOR CHANGE ORDER
The 1" water service and the irrigation system re -location were city owned systems to provide irrigation for the landscaping around the entrance
to the neighbourhood at Senator Dr. These systems were in the way of the storm drain and roadway. The sanitary sewer item is to reimberse
the contractor for performing the work called for on plan sheet 38 at station 4+17.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
McClendon Construction
Inspector/Inspection Supervisor
Assistant Director (Dept)
Assistant City Attorney
Contractor (Name) I Contract Signature I Date
Date Project Manager/Program Manager Date
Date Director, Contracting Department (Dept) Date
Date Assistant City Manager Date
Council Action (if required)
M&C Number
M&C Date Approved
FORTWORTH
City of Fort Worth
Change Order Additions
Project Name 2008 Capital Improvement Program Artirial Street Project Ray White Road
Client Project # 1 C204-531200-202230129430 DOE#6226
Project Description
I City Sec # I 43167
Paving, Retaining Wall, Street Lights and Drainage Improvements for Ray White Road from North Tarrant Parkway to Shiver Road.
Contractor J McClendon Construction
City Project Mgr. 1 Wilma Smith
Change Order #
City Inspector
1
Thomas Miller
Date
9/25/2012
ADDITIONS
I I tM UESURIF I ION ULN I city unit Unit Uost I otal
/9 1" Water Service 1 NVV 1.UU to $1,2bU.UU $1,2bU.UU
80 Re -locate, Re -plumb Irrigation System TPW 1.00 LS $935.00 $93b.UU
81 Replace 10" Sanitary Sewer with DIP TPW 20.00 LF $93.00 $1,t3bU.UU
Change Order Additions Page 1 of 2
TPW $4,045.00
Water $0.00
Sewer $0.00
Sub Total Additions $4,045.00
Change Order Additions Page 2 of 2
FORT WORTH
City of Fort Worth
Change Order Deletions
Project Name 2008 Capital Improvement Program Artirial Street Project Ray White Road I City Sec # I 43167
Client Project # C204-531200-202230129430 DOE#6226
Project Description
I I EM
Paving, Retaining Wall, Street Lights and Drainage Improvements for Ray White Road from North Tarrant Parkway to Shiver Road.
Contractor McClendon Construction
City Project Mgr. Wilma Smith
Change Order #
1
City Inspector I Thomas Miller
Date I 9/25/2012
DELETIONS
UESCKIN I IUN Uhl 1 Lity Unit I Unit Uost I otal
Change Order Deletions Page 1 of 2
TFVN $0.00
Water $0.00
Sewer $0.00
Sub Total Deletions
Change Order Deletions Page 2 of 2
MWBE Sub
MIWBE Breakdown for this Change Order
Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total
$o.00
PROJECT SUMMARY SHEET
(Change Order Attachment)
PROJECT NAME: RAY WHITE RD NORTH TARRANT PKWY TO SHIVER RD
BuySpeed No (T/PW): PO-12-0072407
BuySpeed No (Water): NIA
City Project No: 1294
Contract No: CS43167
D.O.E. No: 6226
Attachment to Change Order No: 1
Today`s Date: 10/24/12
Original Contract Amount:
Extras to Date:
Credits to Date:
TOTAL T/PW (C223) Water Sewer
$ 1,428,769.70
$
Contract Amount to Date: $ 1,428,769.70 $ - $ - $
Amount of Proposed Change Order: $ 4,045.00 $ - $
Revised Contract Amount: $ 1,432,814.70 $ - $ - $
Contingency Funds Avail. for Admin. Change Orders: $ 197,835.00
Remaining Funds Available for Change Orders: $ 197,835.00 $ $
Additional Funding (if necessary): $ $ $
Original Contract Time: 424
Additional Days requested on CO#1 3
Total Contract Days: 427