HomeMy WebLinkAboutContract 44190-CO1 (2)DISTRIQUTION:
\VHITE - FILE
CANARY - CONS7'RUC'fION FILE
PINK - PRO)ECT MANAGER
r.ni nFNann _ rnN��u n�Tnu
CITY OF FORT WORTH CITY SECR���� �
CHANGE ORDER REQUEST �������' ��� � ' ('�(' m
CHANGE ORDER NO. ONE I DATE: July 2, 2013 D.O.E. NO. (N/A) I PROJECT NO. 01952
PROJECT DESCRIPTION: WESTLAND GROUND STORAGE TANK REHABILITATION PROJECT
ORIGINAL CONTRACT AMOUNT ....................................................... $ 705300.00
EXTRAS TO DATE ........................................................ $ 0.00
CREDITS TO DATE ....................................................... $ 0.00
APPROVED CONTRACT TIME ADDITIONAL TIME FOR THIS CHANGE
TO DATE ORDER
180 Calendar Da s N/A
CONTRACTCOST TO DATE ........................................................................................................................................................................................$ 705.300.00
AMOUNTOF PROPOSED CHANGE ORDER ..............................................................................................................................................................$-11.000.00 •
REVISEDCONTRACT AMOUNT .................................................................................................................................................................................$ 694 300 00
ORIGINAL FUNDS AVAILABLE FOR CHANGE ORDERS ........................................................................................................................................$ 0.00
ADDITIONAL FUNDING (IF NECESSARY) ................................................................................................................................................................$ 0.00
REMAINING FUNDS AVAILABLE FOR CHANGE ORDER ......................................................................................................................................$ 0.00
[N ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL: modify/change the contract as shown below to provide a complete, functional, and
operationai ground storage tank meeting current regulatory requirements. The Contractar has completed the field work for the Westland Ground Storage Tank Rehabilitation
Project. T�vo contingency items, corrosion pit repair by patch plate welding and miscellaneous welding, used to compensate the Contractor for unforeseen structural repair
�vork, were not utilized during the course of this contract, and are therefore deleted by this change order.
Bid Item #20, Delete 20 corrosion pit repairs by patch plate welding at $50.00 per repair (CREDIT) ............................................................................-$1,000.00
Bid [tem A-1, Engineer directed miscellaneous �velding, $10,000 lump sum (CREDIT) ................................................................................................-$10,000.00
TOTALCRGDIT — Change Order #1 ..........................................................................................................................................................................-$I1,000.00
Staff has reviewed this change order and is in agreement with the reduction in contingency bid items and the associated credits.
It is understood and agreed that the acceptance of this Change Order by the Contractor constitutes an accord and satisfaction and represents payment in full
(both in time and money) for all costs arising out of, or incidental to, tlie Change Order.
ORIGINAL CONTRACT TIME I ADDITIONAL APPROVED TIME TO DATE
180 Calendar
CONTRACTOR � -
��
MANAGER/CONST. SER.
�I
,
CITY MANAGER
C,.''r�,t�� (..d��,�_�
� �� l
�
r�f..� �,/' `l1-�
ld P. Gonzal�i E
None
�
�
OFFICIAL RECORD
Cli'lf SECRET6l181(
�i'. lNORTfHg ��t
C.�
�EC�IV�d .IU�. 2 5 1�i��
DATE PROJECT MANAGER DATE
� 3�/3 �� � z
DATE DIRECTOR/MANAGING DEPT. DATE
DAT
�L L Y�
CITY SECRETARY CONTRACT NO.
44190
DATE
� �'z3-13
,
DATE COUNCIL ACTION (IF REQUIRED): �� /� DATE
� /`k'
'��%� j,� ❑ APPROVED ❑ DISAPPROVED ❑ OTHER
/✓