HomeMy WebLinkAboutContract 45415-CO1 (2)City of Fort Worth
Construction Change Order
Change Order No. Date Prepared Awarding M&C.
1 (ONE) 10/19/2015 C-26661
Project Description
NEW EVANS-ROSEDALE COMMUNITY FACILITY
CITY SECRETARY
CONTRACT NO.-S�i-�S -
Funding
R106-541200
020206006800
City Secretary Contract No.
CS-45415
ORIGINAL CONTRACT AMOUNT $ 3,252,777.00
EXTRAS TO DATE $ 0
CREDITS TO DATE
$ 0
CONTRACT COST TO DATE $ 3,252,777.00
AMOUNT OF PROPOSED CHANGE ORDER $ ( 7,938.35)
REVISED CONTRACT AMOUNT $ 3,244,838.65
ORIGINAL FUNDS AVAILABLE FOR CHANGE ORDERS $ 0
REMAINING FUNDS AVAILABLE FOR CHANGE ORDERS $ 0
ADDITIONAL FUNDING (IF NECESSARY) . $ 0
IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL:
JCC will credit the amount of the labor •,'.stall and material for the cover board for a roofing credit.
A d
7
g/ser, City Secre
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time
and money) for all costs arising out of, or incidental to, the above Change Order
Contractor's Name
J. C. Commercial Inc.
Original Contract Time
cd
Additional Approved Time To Date
cd
Contractor- J. C. Commercial Inc.
Assistant„City Attorne
PROPERTY MANAGEMENT
CHANGE ORDER FORM
May 28, 2015
Approved Contract Time To Date
cd
%cvtt .30ectcty,
Additional Time For This Change Order
cd
Date Pro'e Manager
/944—
Date
• .2v•j�
Date
(of zq��c��
Date
SCANNED
Department
Assistant City Manager
Council A re ,:,,,._Ikiur,;NNiiuubl
O M&C >tL IUIRE;O--
N-
trr-rICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Date
/�eb4- -
Efate'
/v/e/6-66-1
date
Date
.6111111111
COMMsp ERCIAL
.7
CHANGE ORDER REQUEST # 001-R
Date: October 7, 2015
PROJECT: Evans Rosedale Community Center
961 Evans Ave.
Fort Worth, Texas
TO: City of Ft.Worth
401 W. 13th Street
Fort Worth, Texas 76102
817-392-8072
ATTENTION: Jack Durham
FROM: Jason Gonzales
Re: Roofing Credit (Cover Board)
CREDIT: This is a credit to The City of Ft. Worth for the Cover Board
Material $4,315.35
Labor $2,773.00
OHP $ 850.00
Total $7.938.35 CREDIT
Contractor
J.C. Commercial, Inc.
1865 McGee Ln Suite 0
Lewisville, Texas 75077
Date 10-07-2015
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
1865 McGee Lane, Suite 0 Lewisville, Texas 75077
Larry R Wagnor, President (972) 436-4622 phone
(972) 436-4822 facsimile
Mit II/I;1
SPAP.E11;c11-"17
C O R P O
Reference Securock Website: httn://securockroofboardsbloe.use.com/ for the following:
Finally, using the very common FM 1-90 rating with a typical assembly (TPO adhered to a cover board that is mechanically fastened
onto a metal deck), it is easy to see how costs can add up depending on the roof board that you select. Below is a table of different
roof boards for this assembly. We assumed $.20 / fastener (screw and plate), average roof was 100' x 200' 025 4'x8'^roof boards),
and it took an average of 2 minutes to screw in a fastener with a labor rate of $20/hour.
Nurnb,, 01 Tutal
ruteners/ number of raoerers& Labor Tool Di!r_ntnco V. SECU90CK
Dyad laslenurs Kates Cost Cost Cost-Cyasmr.-Mer
SECU5CCKGypfur,tFiber 9 5000 51,020 $3,333 54,333
Gl:xs•itatGyOsoni 10 6250 51,250 54,166 55,416
F6 t0 Demity Polylsti 15 9375 51675 $6,250 59,125
Wood fiberboard 15 10000 52,010 $6,567 59,E57
51,093
53,792
54,333
As you can see, using Securock Gypsum -Fiber on a 20,000 square foot job can save you as much as $4,333 just in fasteners and
Tabor. So, not only will you get a great product that will be easier to install, enhance the safety of your client's building, and is made
from 950/0 recycled material, you will also save money on installation.
This clipping from the manufacturer's website shows that the specified cover board can be installed for a
typical 20,000 SF roof for a price of $4,333, which covers fasteners, plates, and labor.