CITY OF FORT WORTH, TEXAS
STANDARD AGREEMENT FOR ENGINEERING RELATED DESIGN SERVICES
This AGREEMENT is between the City of Fort Worth, a Texas home -rule
municipality (the "CITY"), and Kimley-Horn and Associates, Inc., authorized to do business
in Texas, (the "ENGINEER"), for a PROJECT generally described as: Caylor 5.0 Million
Gallon Ground Storage Tank and Associated Site Piping.
Article I
Scope of Services
A. The Scope of Services is set forth in Attachment A.
Article II
Compensation
A. The ENGINEER's compensation shall be in the amount of $422,850 as
set forth in Attachment B.
Article III
Terms of Payment
Payments to the ENGINEER will be made as follows:
A. Invoice and Payment
(1) The Engineer shall provide the City sufficient documentation, including but
not limited to meeting the requirements set forth in Attachment D to this
AGREEMENT, to reasonably substantiate the invoices.
(2) The ENGINEER will issue monthly invoices for all work performed under this
AGREEMENT. Invoices are due and payable within 30 days of receipt.
(3) Upon completion of services enumerated in Article I, the final payment of
any balance will be due within 30 days of receipt of the final invoice.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 1 of 16
to.crtivEni /thG, - 2O1
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
(4) In the event of a disputed or contested billing, only that portion so contested
will be withheld from payment, and the undisputed portion will be paid. The
CITY will exercise reasonableness in contesting any bill or portion thereof.
No interest will accrue on any contested portion of the billing until mutually
resolved.
(5)
If the CITY fails to make payment in full to ENGINEER for billings contested
in good faith within 60 days of the amount due, the ENGINEER may, after
giving 7 days' written notice to CITY, suspend services under this
AGREEMENT until paid in full. In the event of suspension of services, the
ENGINEER shall have no liability to CITY for delays or damages caused the
CITY because of such suspension of services.
Article IV
Obligations of the Engineer
Amendments to Article IV, if any, are included in Attachment C.
A. General
The ENGINEER will serve as the CITY's professional engineering
representative under this Agreement, providing professional engineering
consultation and advice and furnishing customary services incidental
thereto.
B. Standard of Care
The standard of care applicable to the ENGINEER's services will be the
degree of skill and diligence normally employed in the State of Texas by
professional engineers or consultants performing the same or similar
services at the time such services are performed.
C. Subsurface Investigations
(1) The ENGINEER shall advise the CITY with regard to the necessity for
subcontract work such as special surveys, tests, test borings, or other
subsurface investigations in connection with design and engineering
work to be performed hereunder. The ENGINEER shall also advise
the CITY concerning the results of same. Such surveys, tests, and
investigations shall be furnished by the CITY, unless otherwise
specified in Attachment A.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 2 of 16
(2) In soils, foundation, groundwater, and other subsurface investigations,
the actual characteristics may vary significantly between successive
test points and sample intervals and at locations other than where
observations, exploration, and investigations have been made.
Because of the inherent uncertainties in subsurface evaluations,
changed or unanticipated underground conditions may occur that
could affect the total PROJECT cost and/or execution. These
conditions and cost/execution effects are not the responsibility of the
ENGINEER.
D. Preparation of Engineering Drawings
The ENGINEER will provide to the CITY the original drawings of all plans in
ink on reproducible mylar sheets and electronic files in .pdf format, or as
otherwise approved by CITY, which shall become the property of the CITY.
CITY may use such drawings in any manner it desires; provided, however,
that the ENGINEER shall not be liable for the use of such drawings for any
project other than the PROJECT described herein.
E. Engineer's Personnel at Construction Site
(1) The presence or duties of the ENGINEER's personnel at a construction site,
whether as on -site representatives or otherwise, do not make the
ENGINEER or its personnel in any way responsible for those duties that
belong to the CITY and/or the CITY's construction contractors or other
entities, and do not relieve the construction contractors or any other entity of
their obligations, duties, and responsibilities, including, but not limited to, all
construction methods, means, techniques, sequences, and procedures
necessary for coordinating and completing all portions of the construction
work in accordance with the Contract Documents and any health or safety
precautions required by such construction work. The ENGINEER and its
personnel have no authority to exercise any control over any construction
contractor or other entity or their employees in connection with their work or
any health or safety precautions.
(2) Except to the extent of specific site visits expressly detailed and set forth in
Attachment A, the ENGINEER or its personnel shall have no obligation or
responsibility to visit the construction site to become familiar with the
progress or quality of the completed work on the PROJECT or to determine,
in general, if the work on the PROJECT is being performed in a manner
indicating that the PROJECT, when completed, will be in accordance with
the Contract Documents, nor shall anything in the Contract Documents or
the agreement between CITY and ENGINEER be construed as requiring
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 3 of 16
(3)
ENGINEER to make exhaustive or continuous on -site inspections to
discover latent defects in the work or otherwise check the quality or quantity
of the work on the PROJECT. If the ENGINEER makes on -site
observation(s) of a deviation from the Contract Documents, the ENGINEER
shall inform the CITY.
When professional certification of performance or characteristics of
materials, systems or equipment is reasonably required to perform the
services set forth in the Scope of Services, the ENGINEER shall be entitled
to rely upon such certification to establish materials, systems or equipment
and performance criteria to be required in the Contract Documents.
F. Opinions of Probable Cost, Financial Considerations, and Schedules
(1) The ENGINEER shall provide opinions of probable costs based on the
current available information at the time of preparation, in accordance
with Attachment A.
(2) In providing opinions of cost, financial analyses, economic feasibility
projections, and schedules for the PROJECT, the ENGINEER has no
control over cost or price of labor and materials; unknown or latent
conditions of existing equipment or structures that may affect operation
or maintenance costs; competitive bidding procedures and market
conditions; time or quality of performance by third parties; quality, type,
management, or direction of operating personnel; and other economic
and operational factors that may materially affect the ultimate
PROJECT cost or schedule. Therefore, the ENGINEER makes no
warranty that the CITY's actual PROJECT costs, financial aspects,
economic feasibility, or schedules will not vary from the ENGINEER's
opinions, analyses, projections, or estimates.
G. Construction Progress Payments
Recommendations by the ENGINEER to the CITY for periodic construction
progress payments to the construction contractor will be based on the
ENGINEER's knowledge, information, and belief from selective sampling
and observation that the work has progressed to the point indicated. Such
recommendations do not represent that continuous or detailed examinations
have been made by the ENGINEER to ascertain that the construction
contractor has completed the work in exact accordance with the Contract
Documents; that the final work will be acceptable in all respects; that the
ENGINEER has made an examination to ascertain how or for what purpose
the construction contractor has used the moneys paid; that title to any of the
work, materials, or equipment has passed to the CITY free and clear of liens,
claims, security interests, or encumbrances; or that there are not other
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 4 of 16
matters at issue between the CITY and the construction contractor that
affect the amount that should be paid.
H. Record Drawings
Record drawings, if required, will be prepared, in part, on the basis of
information compiled and furnished by others, and may not always represent
the exact location, type of various components, or exact manner in which the
PROJECT was finally constructed. The ENGINEER is not responsible for
any errors or omissions in the information from others that is incorporated
into the record drawings.
I. Minority Business and Small Business Enterprise (MBE)(SBE)
Participation
In accord with the City of Fort Worth Business Diversity Ordinance No.
20020-12-2011, as amended, the City has goals for the participation of
minority business enterprises and/or small business enterprises in City
contracts. Engineer acknowledges the MBE and SBE goals established for
this contract and its accepted written commitment to MBE and SBE
participation. Any misrepresentation of facts (other than a negligent
misrepresentation) and/or the commission of fraud by the Engineer may
result in the termination of this Agreement and debarment from participating
in City contracts for a period of time of not less than three (3) years.
J. Right to Audit
(1) ENGINEER agrees that the CITY shall, until the expiration of five (5) years
after final payment under this contract, have access to and the right to
examine and photocopy any directly pertinent books, documents, papers
and records of the ENGINEER involving transactions relating to this
contract. ENGINEER agrees that the CITY shall have access during normal
working hours to all necessary ENGINEER facilities and shall be provided
adequate and appropriate work space in order to conduct audits in
compliance with the provisions of this section. The CITY shall give
ENGINEER reasonable advance notice of intended audits.
(2) ENGINEER further agrees to include in all its subconsultant agreements
hereunder a provision to the effect that the subconsultant agrees that the
CITY shall, until the expiration of five (5) years after final payment under the
subcontract, have access to and the right to examine and photocopy any
directly pertinent books, documents, papers and records of such
subconsultant, involving transactions to the subcontract, and further, that the
CITY shall have access during normal working hours to all subconsultant
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/26/2013
Page 5 of 16
(3)
facilities, and shall be provided adequate and appropriate work space, in
order to conduct audits in compliance with the provisions of this article
together with subsection (3) hereof. CITY shall give subconsultant
reasonable advance notice of intended audits.
ENGINEER and subconsultant agree to photocopy such documents as may
be requested by the CITY. The CITY agrees to reimburse ENGINEER for
the cost of copies at the rate published in the Texas Administrative Code in
effect as of the time copying is performed.
K. INSURANCE
(1) ENGINEER'S INSURANCE
a. Commercial General Liability — the ENGINEER shall maintain
commercial general liability (CGL) and, if necessary, commercial
umbrella insurance with a limit of not less than $1,000,000.00 per each
occurrence with a $2,000,000.00 aggregate. If such Commercial General
Liability insurance contains a general aggregate limit, it shall apply
separately to this PROJECT or location.
i. The CITY shall be included as an insured under the CGL, using
ISO additional insured endorsement or a substitute providing
equivalent coverage, and under the commercial umbrella, if any.
This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the
CITY. The Commercial General Liability insurance policy shall
have no exclusions by endorsements that would alter or nullify:
premises/operations, products/completed operations, contractual,
personal injury, or advertizing injury, which are normally contained
within the policy, unless the CITY approves such exclusions in
writing.
ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the commercial general
liability or commercial umbrella liability insurance maintained in
accordance with this agreement.
b. Business Auto — the ENGINEER shall maintain business auto liability
and, if necessary, commercial umbrella liability insurance with a limit of
not less than $1,000,000 each accident. Such insurance shall cover
liability arising out of "any auto", including owned, hired, and non -owned
autos, when said vehicle is used in the course of the PROJECT. If the
engineer owns no vehicles, coverage for hired or non -owned is
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 6 of 16
acceptable.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the business auto liability or
commercial umbrella liability insurance obtained by ENGINEER
pursuant to this agreement or under any applicable auto physical
damage coverage.
c. Workers' Compensation —ENGINEER shall maintain workers
compensation and employers liability insurance and, if necessary,
commercial umbrella liability insurance with a limit of not less than
$100,000.00 each accident for bodily injury by accident or $100,000.00
each employee for bodily injury by disease, with $500,000.00 policy limit.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by workers compensation and
employer's liability or commercial umbrella insurance obtained by
ENGINEER pursuant to this agreement.
d. Professional Liability — the ENGINEER shall maintain professional
liability, a claims -made policy, with a minimum of $1,000,000.00 per
claim and aggregate. The policy shall contain a retroactive date prior to
the date of the contract or the first date of services to be performed,
whichever is earlier. Coverage shall be maintained for a period of 5 years
following the completion of the contract. An annual certificate of
insurance specifically referencing this project shall be submitted to the
CITY for each year following completion of the contract.
(2) GENERAL INSURANCE REQUIREMENTS
a. Certificates of insurance evidencing that the ENGINEER has obtained all
required insurance shall be delivered to the CITY prior to ENGINEER
proceeding with the PROJECT.
b. Applicable policies shall be endorsed to name the CITY an Additional
Insured thereon, as its interests may appear. The term CITY shall
include its employees, officers, officials, agents, and volunteers as
respects the contracted services.
c. Certificate(s) of insurance shall document that insurance coverage
specified in this agreement are provided under applicable policies
documented thereon.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 7 of 16
d. Any failure on part of the CITY to request required insurance
documentation shall not constitute a waiver of the insurance
requirements.
e. A minimum of thirty (30) days notice of cancellation or material change in
coverage shall be provided to the CITY. A ten (10) days notice shall be
acceptable in the event of non-payment of premium. Notice shall be sent
to the respective Department Director (by name), City of Fort Worth,
1000 Throckmorton, Fort Worth, Texas 76102.
f. Insurers for all policies must be authorized to do business in the State of
Texas and have a minimum rating of A:V or greater, in the current A.M.
Best Key Rating Guide or have reasonably equivalent financial strength
and solvency to the satisfaction of Risk Management.
g.
Any deductible or self insured retention in excess of $25,000.00 that
would change or alter the requirements herein is subject to approval by
the CITY in writing, if coverage is not provided on a first -dollar basis. The
CITY, at it sole discretion, may consent to alternative coverage
maintained through insurance pools or risk retention groups. Dedicated
financial resources or letters of credit may also be acceptable to the
CITY.
h. Applicable policies shall each be endorsed with a waiver of subrogation
in favor of the CITY as respects the PROJECT.
i. The CITY shall be entitled, upon its request and without incurring
expense, to review the ENGINEER's insurance policies including
endorsements thereto and, at the CITY's discretion; the ENGINEER may
be required to provide proof of insurance premium payments.
Lines of coverage, other than Professional Liability, underwritten on a
claims -made basis, shall contain a retroactive date coincident with or
prior to the date of the contractual agreement. The certificate of
insurance shall state both the retroactive date and that the coverage is
claims -made.
k. Coverages, whether written on an occurrence or claims -made basis,
shall be maintained without interruption nor restrictive modification or
changes from date of commencement of the PROJECT until final
payment and termination of any coverage required to be maintained after
final payments.
I. The CITY shall not be responsible for the direct payment of any
insurance premiums required by this agreement.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 8 of 16
m. Sub consultants and subcontractors to/of the ENGINEER shall be
required by the ENGINEER to maintain the same or reasonably
equivalent insurance coverage as required for the ENGINEER. When
sub consultants/subcontractors maintain insurance coverage,
ENGINEER shall provide CITY with documentation thereof on a
certificate of insurance.
L. Independent Consultant
The ENGINEER agrees to perform all services as an independent
consultant and not as a subcontractor, agent, or employee of the CITY.
M. Disclosure
The ENGINEER acknowledges to the CITY that it has made full disclosure
in writing of any existing conflicts of interest or potential conflicts of interest,
including personal financial interest, direct or indirect, in property abutting the
proposed PROJECT and business relationships with abutting property cities.
The ENGINEER further acknowledges that it will make disclosure in writing
of any conflicts of interest that develop subsequent to the signing of this
contract and prior to final payment under the contract.
N. Asbestos or Hazardous Substances
(1) If asbestos or hazardous substances in any form are encountered or
suspected, the ENGINEER will stop its own work in the affected portions
of the PROJECT to permit testing and evaluation.
(2) If asbestos or other hazardous substances are suspected, the CITY may
request the ENGINEER to assist in obtaining the services of a qualified
subcontractor to manage the remediation activities of the PROJECT.
O. Permitting Authorities - Design Changes
If permitting authorities require design changes so as to comply with
published design criteria and/or current engineering practice standards
which the ENGINEER should have been aware of at the time this
Agreement was executed, the ENGINEER shall revise plans and
specifications, as required, at its own cost and expense. However, if design
changes are required due to the changes in the permitting authorities'
published design criteria and/or practice standards criteria which are
published after the date of this Agreement which the ENGINEER could not
have been reasonably aware of, the ENGINEER shall notify the CITY of
such changes and an adjustment in compensation will be made through an
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 9 of 16
amendment to this AGREEMENT.
P. Schedule
ENGINEER shall manage the PROJECT in accordance with the schedule
developed per Attachment D to this AGREEMENT.
Article V
Obligations of the City
Amendments to Article V, if any, are included in Attachment C.
A. City -Furnished Data
ENGINEER may rely upon the accuracy, timeliness, and completeness of
the information provided by the CITY.
B. Access to Facilities and Property
The CITY will make its facilities accessible to the ENGINEER as required for
the ENGINEER's performance of its services. The CITY will perform, at no
cost to the ENGINEER, such tests of equipment, machinery, pipelines, and
other components of the CITY's facilities as may be required in connection
with the ENGINEER's services. The CITY will be responsible for all acts of
the CITY's personnel.
C. Advertisements, Permits, and Access
Unless otherwise agreed to in the Scope of Services, the CITY will obtain,
arrange, and pay for all advertisements for bids; permits and licenses
required by local, state, or federal authorities; and land, easements, rights -
of -way, and access necessary for the ENGINEER's services or PROJECT
construction.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 10 of 16
D. Timely Review
The CITY will examine the ENGINEER's studies, reports, sketches,
drawings, specifications, proposals, and other documents; obtain advice of
an attorney, insurance counselor, accountant, auditor, bond and financial
advisors, and other consultants as the CITY deems appropriate; and render
in writing decisions required by the CITY in a timely manner in accordance
with the project schedule prepared in accordance with Attachment D.
E. Prompt Notice
The CITY will give prompt written notice to the ENGINEER whenever CITY
observes or becomes aware of any development that affects the scope or
timing of the ENGINEER's services or of any defect in the work of the
ENGINEER or construction contractors.
F. Asbestos or Hazardous Substances Release.
(1) CITY acknowledges ENGINEER will perform part of the work at CITY's
facilities that may contain hazardous materials, including asbestos
containing materials, or conditions, and that ENGINEER had no prior
role in the generation, treatment, storage, or disposition of such
materials. In consideration of the associated risks that may give rise to
claims by third parties or employees of City, City hereby releases
ENGINEER from any damage or liability related to the presence of
such materials.
(2) The release required above shall not apply in the event the discharge,
release or escape of hazardous substances, contaminants, or asbestos
is a result of ENGINEER's negligence or if ENGINEER brings such
hazardous substance, contaminant or asbestos onto the project.
G. Contractor Indemnification and Claims
The CITY agrees to include in all construction contracts the provisions of
Article IV.E. regarding the ENGINEER's Personnel at Construction Site, and
provisions providing contractor indemnification of the CITY and the
ENGINEER for contractor's negligence.
H. Contractor Claims and Third -Party Beneficiaries
(1) The CITY agrees to include the following clause in all contracts with
construction contractors and equipment or materials suppliers:
"Contractors, subcontractors and equipment and materials
suppliers on the PROJECT, or their sureties, shall maintain
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 11 of 16
no direct action against the ENGINEER, its officers,
employees, and subcontractors, for any claim arising out of,
in connection with, or resulting from the engineering
services performed. Only the CITY will be the beneficiary
of any undertaking by the ENGINEER."
(2) This AGREEMENT gives no rights or benefits to anyone other than the CITY
and the ENGINEER and there are no third -party beneficiaries.
(3)
The CITY will include in each agreement it enters into with any other entity
or person regarding the PROJECT a provision that such entity or person
shall have no third -party beneficiary rights under this Agreement.
(4) Nothing contained in this section V.H. shall be construed as a waiver of any
right the CITY has to bring a claim against ENGINEER.
CITY's Insurance
(1) The CITY may maintain property insurance on certain pre-existing structures
associated with the PROJECT.
(2) The CITY will ensure that Builders Risk/Installation insurance is maintained
at the replacement cost value of the PROJECT. The CITY may provide
ENGINEER a copy of the policy or documentation of such on a certificate of
insurance.
(3)
The CITY will specify that the Builders Risk/Installation insurance shall be
comprehensive in coverage appropriate to the PROJECT risks.
J. Litigation Assistance
The Scope of Services does not include costs of the ENGINEER for required
or requested assistance to support, prepare, document, bring, defend, or
assist in litigation undertaken or defended by the CITY. In the event CITY
requests such services of the ENGINEER, this AGREEMENT shall be
amended or a separate agreement will be negotiated between the parties.
K. Changes
The CITY may make or approve changes within the general Scope of
Services in this AGREEMENT. If such changes affect the ENGINEER's cost
of or time required for performance of the services, an equitable adjustment
will be made through an amendment to this AGREEMENT with appropriate
CITY approval.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 12 of 16
Article VI
General Legal Provisions
Amendments to Article VI, if any, are included in Attachment C.
A. Authorization to Proceed
ENGINEER shall be authorized to proceed with this AGREEMENT upon
receipt of a written Notice to Proceed from the CITY.
B. Reuse of Project Documents
All designs, drawings, specifications, documents, and other work products of
the ENGINEER, whether in hard copy or in electronic form, are instruments
of service for this PROJECT, whether the PROJECT is completed or not.
Reuse, change, or alteration by the CITY or by others acting through or on
behalf of the CITY of any such instruments of service without the written
permission of the ENGINEER will be at the CITY's sole risk. The CITY shall
own the final designs, drawings, specifications and documents.
C. Force Majeure
The ENGINEER is not responsible for damages or delay in performance
caused by acts of God, strikes, lockouts, accidents, or other events beyond
the control of the ENGINEER that prevent ENGINEER's performance of its
obligations hereunder.
D. Termination
(1) This AGREEMENT may be terminated only by the City for convenience on
30 days' written notice. This AGREEMENT may be terminated by either the
CITY or the ENGINEER for cause if either party fails substantially to perform
through no fault of the other and does not commence correction of such
nonperformance with in 5 days of written notice and diligently complete the
correction thereafter.
(2) If this AGREEMENT is terminated for the convenience of the City, the
ENGINEER will be paid for termination expenses as follows:
a.) Cost of reproduction of partial or complete studies, plans,
specifications or other forms of ENGINEER'S work product;
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 13 of 16
b.) Out-of-pocket expenses for purchasing electronic data files and other
data storage supplies or services;
c.) The time requirements for the ENGINEER'S personnel to document
the work underway at the time of the CITY'S termination for
convenience so that the work effort is suitable for long time storage.
(3) Prior to proceeding with termination services, the ENGINEER will
submit to the CITY an itemized statement of all termination expenses. The
CITY'S approval will be obtained in writing prior to proceeding with
termination services.
E. Suspension, Delay, or Interruption to Work
The CITY may suspend, delay, or interrupt the services of the ENGINEER
for the convenience of the CITY. In the event of such suspension, delay, or
interruption, an equitable adjustment in the PROJECT's schedule,
commitment and cost of the ENGINEER's personnel and subcontractors,
and ENGINEER's compensation will be made.
F. Indemnification
In accordance with Texas Local Government Code Section 271.904, the
ENGINEER shall indemnify, hold harmless, and defend the CITY
against liability for any damage caused by or resulting from an act of
negligence, intentional tort, intellectual property infringement, or
failure to pay a subcontractor or supplier committed by the ENGINEER
or ENGINEER's agent, consultant under contract, or another entity
over which the ENGINEER exercises control.
G. Assignment
Neither party shall assign all or any part of this AGREEMENT without the
prior written consent of the other party.
H. Interpretation
Limitations on liability and indemnities in this AGREEMENT are business
understandings between the parties and shall apply to all the different
theories of recovery, including breach of contract or warranty, tort including
negligence, strict or statutory liability, or any other cause of action, except for
willful misconduct or gross negligence for limitations of liability and sole
negligence for indemnification. Parties mean the CITY and the ENGINEER,
and their officers, employees, agents, and subcontractors.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 14 of 16
I. Jurisdiction
The law of the State of Texas shall govern the validity of this AGREEMENT,
its interpretation and performance, and any other claims related to it. The
venue for any litigation related to this AGREEMENT shall be Tarrant County,
Texas.
J. Severability and Survival
If any of the provisions contained in this AGREEMENT are held for any
reason to be invalid, illegal, or unenforceable in any respect, such invalidity,
illegality, or unenforceability will not affect any other provision, and this
AGREEMENT shall be construed as if such invalid, illegal, or unenforceable
provision had never been contained herein. Articles V.F., VI.B., VI.D., VI.F.,
VI.H., and VI.I. shall survive termination of this AGREEMENT for any cause.
K. Observe and Comply
ENGINEER shall at all times observe and comply with all federal and State
laws and regulations and with all City ordinances and regulations which in
any way affect this AGREEMENT and the work hereunder, and shall
observe and comply with all orders, laws ordinances and regulations which
may exist or may be enacted later by governing bodies having jurisdiction or
authority for such enactment. No plea of misunderstanding or ignorance
thereof shall be considered. ENGINEER agrees to defend, indemnify and
hold harmless CITY and all of its officers, agents and employees from and
against all claims or liability arising out of the violation of any such order, law,
ordinance, or regulation, whether it be by itself or its employees.
Article VII
Attachments, Schedules, and Signatures
This AGREEMENT, including its attachments and schedules, constitutes the entire
AGREEMENT, supersedes all prior written or oral understandings, and may only be
changed by a written amendment executed by both parties. The following attachments
and schedules are hereby made a part of this AGREEMENT:
Attachment A - Scope of Services
Attachment B — Compensation
Attachment C - Amendments to Standard Agreement for Engineering Services
Attachment D - Project Schedule
Attachment E - Location Map
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 15 of 16
Executed and effective this the
BY:
CITY OF FORT WORTH
2-?vi-Aqtg-ne
Fernando Costa
Assistant City Manager
Date: 7/3 //3
APPROVAL. RECOMMEND
cm/iv
By:
S. Frank Crumb, P.E.
Director, Water Department
dfiir
day of trot) , 20))
BY:
ENGINEER
Kimley-Horn and Associate, Inc.
Glenn A. Gary, P.E.
Senior Vice President
Date: %-
APPROVED AS TO FORM AND M&C No.: C-26358
LEGALITY
By: /t 1 / ,tL'. r]vi 1,' vw
--Dauglas_W. Black , c h e / (e ,-- .
Assistant City Attorney.izp
4'�'�14
414.
O r 4(
ATTEST: �� «°°°o°°oop �Q%%0,
°0g 'vow 8.4
M&C
Date: 7/23/2013
�,,�<prig
Mar`yJ. Kayser (J P�oq° °o�.��
City Secretary �g °0000a°° ,a
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 16 of 16
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
ATTACHMENT A
Scope for Engineering Design Related Services for Water Improvements
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
WORK TO BE PERFORMED
Phase 1. Design Services
Task 1. Design Management
Task 2. Conceptual Design
Task 3. Preliminary Design
Task 4. Final Design
Phase 2 Bidding Services
Task 5. Bid Phase Services
Phase 3 Construction Services
Task 6. Construction Phase Services
Phase 4. Division 01 Specifications
Task 7 Division 01 Specifications
PHASE 1 DESIGN
TASK 1. DESIGN MANAGEMENT.
ENGINEER shall ensure efficient and effective use of ENGINEER's and CITY's time and
resources.
ENGINEER shall manage change,
• communicate effectively,
• coordinate internally and externally as needed, and
• proactively address issues with the CITY's Project Manager and others as
necessary to make progress on the work.
1.1. Managing the Team
• Lead, manage and direct design team activities
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 1 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
• Ensure quality control is practiced in performance of the work
• Communicate internally among team members
• Task and allocate team resources
1.2. Communications and Reporting
• Attend a pre -design project kickoff/chartering meeting with CITY staff to confirm and
clarify scope, understand CITY objectives, and ensure economical and functional
designs that meet CITY requirements
• Conduct review meetings with the CITY at the end of each design phase
• Prepare invoices and submit monthly in the format requested by the CITY.
• Prepare and submit monthly progress reports in the format provided by the Water
Department.
• Prepare and submit baseline Project Schedule initially, and Project Schedule updates
with a schedule narrative monthly, as required in Attachment D to this Standard
Agreement and according to the City of Fort Worth's Schedule Guidance Document.
• Complete Monthly M/WBE Report Form and Final Summary Payment Report Form at
the end of the project
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare the
design: Church of Christ, City of Southlake, Subdivision HOA.
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements are
appropriately reflected in the designs. ENGINEER shall work with regulatory
authorities to obtain approval of the designs, and make changes necessary to meet
their requirements, as part of the design scope.
• Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub -consultants shall carry readily visible
information identifying the name of the company and the company representative.
ASSUMPTIONS
• 20 MWBE reports will be prepared
• 9 meetings with city staff
• 8 monthly water department progress reports will be prepared
• 8 monthly project schedule updates will be prepared
DELIVERABLES
A. Meeting summaries with action items
B. Monthly invoices
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 2 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
C. Monthly progress reports
D. Baseline design schedule
E. Monthly schedule updates with schedule narrative describing any current or
anticipated schedule changes
F. Monthly M/WBE Report Form and Final Summary Payment Report Form
TASK 2. CONCEPTUAL DESIGN (30 PERCENT).
The Conceptual Design shall be submitted to CITY per the approved Project Schedule.
The purpose of the conceptual design is for the ENGINEER to
• Study the project,
• Identify and develop alternatives that enhance the system,
• Present (through the defined deliverables) these alternatives to the CITY
• Recommend the alternatives that successfully addresses the design problem, and
• Obtain the CITY's endorsement of this concept.
ENGINEER will develop the conceptual design of the infrastructure as follows.
2.1. Data Collection
• In addition to data obtained from the CITY, ENGINEER will research proposed
improvements in conjunction with any other planned future improvements that
may influence the project.
• The ENGINEER will also identify and seek to obtain data for existing conditions
that may impact the project including but not limited to; utilities, agencies (TxDOT
and railroads), City Master Plans, and property ownership as available from the
Tax Assessor's office.
• The data collection efforts will also include conducting special coordination
meetings with affected property owners and businesses as necessary to develop
sewer re-routing plans.
• The ENGINEER shall visit the project site and obtain the meter numbers and sizes
on all existing meters to be replaced on the project and shall identify existing
sample stations and fire line locations.
2.2. Geotechnical Investigations
• ENGINEER's subconsultant will perform up to two (2) preliminary soil borings at
a depth of 60' to determine preliminary site soil conditions and how they will
affect the tank design. A preliminary letter report will be provided summarizing
the findings.
2.3. The Conceptual Design Package shall include the following:
• Cover Sheet
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 3 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
• Graphic exhibits and written summary of alternative design concepts considered,
strengths and weaknesses of each, and the rationale for selecting the
recommended design concept.
• Summary of Site Alternatives to include:
• Evaluation of Existing Site access, constructability, grading requirements,
foundation requirements, and necessary easements
• Alternative Site Evaluation including: access, property acquisition impacts,
grading, foundation requirements, required easements, platting impacts, and
scheduling concerns.
• An Opinion of Probable Construction Cost will be prepared for each
alternative.
• Tank Material Evaluation
• Contact two (2) steel tank manufacturers and two (2) prestressed concrete
tank manufacturers to obtain current tank costs.
• Evaluate results and summarize findings in a letter submitted to the City.
• Documentation of key design decisions related to:
• Hydraulics, Electrical improvements, SCADA improvements, Tank
requirements and appurtenances, and Site Improvements
• Estimates of probable construction cost.
ASSUMPTIONS
• 2 Geotechnical borings are expected for this project.
• 5 copies of the conceptual design package (30% design) will be delivered.. Letter
Report shall be letter sized and comb- bound with a clear plastic cover.
Drawings will be _11x17 size fold outs bound in the report
• ENGINEER shall prepare the meeting notes of the Concept Review meeting and
revise the report, if needed.
• ENGINEER shall not proceed with Preliminary Design activities without obtaining
written approval by the CITY of the Conceptual Design Package.
DELIVERABLES
A. Conceptual Design Package
TASK 3. PRELIMINARY DESIGN (60 PERCENT).
Preliminary plans and specifications shall be submitted to CITY per the approved Project
Schedule.
ENGINEER will develop the preliminary design of the infrastructure as follows.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 4 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
3.1. Development of Preliminary Design Drawings and Specifications shall include the
following:
• Cover Sheet
• A Proiect Control Sheet, showing all Control Points, used or set while gathering
data. Generally on a scale of not less than 1:400. The following information shall
be indicated for each Control Point: Identified (existing City Monument #8901, PK
Nail, 5/8" Iron Rod); X, Y and Z Coordinates, in an identified coordinate system,
and a referred bearing base. Z coordinate on City Datum only; descriptive location
(i.e. set in the centerline of the inlet in the South curb line of North Side Drive at the
East end of radius at the Southeast corner of North Side Drive and North Main
Street).
• Overall proiect easement layout sheet(s) with property owner information.
• Overall proiect water and/or sanitary sewer layout sheets. The water layout sheet
shall identify the proposed water main improvement/ existing water mains in the
vicinity and all water appurtenances along with pressure plane boundaries, water
tanks, pump stations, valves, and fire hydrants. The sewer layout sheet shall
identify the proposed sewer main improvement/existing sewer mains and all
sewer appurtenances in the vicinity.
• Overall water and/or sanitary sewer abandonment sheet.
• Coordinates on all P.C.'s, P.T.'s, P.I.'s, manholes, valves, mainline fittings, etc.,
in the same coordinate system as the Control Points.
• Bench marks per 1,000 ft of plan/profile sheet — two or more.
• Bearings given on all proposed centerlines, or baselines.
• Station equations relating utilities to paving, when appropriate.
• Plan and profile sheets which show the following: proposed water and/or sanitary
sewer plan/profile and recommended pipe size, fire hydrants, water service lines
and meter boxes, gate valves, isolation valves, manholes, existing meter
numbers and sizes that are to be replaced, existing sample locations, existing fire
line locations, existing utilities and utility easements, and all pertinent information
needed to construct the project. Legal description (Lot Nos., Block Nos., and
Addition Names) along with property ownership shall be provided on the plan
view.
• Plan Sheets will consist of approximately 13 Sheets including: Site Plan,
Paving Plan, Grading Plan, Drainage Plan, Yard Piping Plan, Piping Profiles,
Tank Plan View(Two Tank Materials), Tank Elevation View(Two Tank
Materials), Tank Details, Control Valve Vault and Details, Erosion Control
Plan.
• The ENGINEER will prepare standard and special detail sheets for water line
installation and sewer rehabilitation or replacement that are not already included in
the D-section of the CITY's specifications. These may include connection details
between various parts of the project, tunneling details, boring and jacking details,
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 5 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
waterline relocations, details unique to the construction of the project, trenchless
details, and special service lateral reconnections.
3.2. Geotechnical Investigation
• Soil investigations, including field and laboratory tests, borings, related
engineering analysis and recommendations for determining soil conditions will be
made. Four (4) soil borings will be performed within the tank footprint at depths
of 60 feet. A Geotechnical Report will be prepared summarizing the insitu
material characteristics and recommendations for construction of the ground
storage tank.
3.3. Constructability Review
• Prior to the 60 percent review meeting with the CITY, the ENGINEER shall
schedule and attend a project site visit with the CITY Project Manager and
Construction personnel to walk the project. The ENGINEER shall summarize the
CITY's comments from the field visit and submit this information to the CITY in
writing.
3.4. Utility Clearance
• The ENGINEER will consult with the CITY's Transportation and Public Works
Department, Water Department, and other CITY departments, public utilities,
private utilities, private utilities and government agencies to determine the
approximate location of above and underground utilities, and other facilities
(current and future) that have an impact or influence on the project. ENGINEER
will design CITY facilities to avoid or minimize conflicts with existing utilities, and
where known and possible consider potential future utilities in designs.
• The ENGINEER shall upload individual DWF files for each plan sheet of the
approved preliminary plan set to the designated project folder in Buzzsaw for
forwarding to all utility companies which have facilities within the limits of the
project. The DWF files should be created directly from the CAD files as opposed
to PDF files.
3.5. Traffic Control Plan
• Traffic Control Plans will not be prepared for this project.
ASSUMPTIONS
• 1 public meeting(s) will be conducted or attended during the preliminary design
phase.
• 4 borings at an average bore depth of 60 feet each will be provided.
• 5 sets of 11x17 size plans will be delivered for the Preliminary Design (60%
design).
• 2 sets of specifications will be delivered for the Preliminary Design (60% design).
• The CITY's front end and technical specifications will be used. The ENGINEER
shall supplement the technical specifications if needed.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 6 of 18
ATTACHMENT
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
• 1 sets of DWF drawings will be delivered on BuzzSaw for Utility Clearance.
• ENGINEER shall not proceed with Final Design activities without written approval
by the CITY of the Preliminary Design plans.
DELIVERABLES
A. Preliminary Design drawings and specifications
B. Utility Clearance drawings
C. Estimates of probable construction cost
D. Data Base listing names and addresses of residents and businesses affected by
the project.
TASK 4. FINAL DESIGN (90 PERCENT) AND FINAL CONSTRUCTION DOCUMENTS
(100 PERCENT).
Upon approval of the Preliminary plans, ENGINEER will prepare construction plans as
follows:
• For projects that disturb an area greater than one (1) acre, the Contractor will be
responsible for preparing and submitting the Storm Water Pollution Prevention Plan
(SWPPP) with appropriate regulatory agencies. The Engineer will prepare the iSWM
Construction Plan according to the current CITY iSWM Criteria Manual for Site
Development and Construction which will be incorporated into the SWPPP by the
contractor.
• For projects that disturb an area greater than one-half (1/2) acre, the Engineer will
prepare the application for the Grading Permit to include a Stormwater Management
Plan; iSWM plan submital; and an Urban Forestry Permit.
• The Stormwater Management Plan, iSWM plan, and Grading Permit services will
consist of a downstream assessment to determine the capacity of the receiving
system, calculations to determine the on -site existing and proposed flows, and
coordination with T/PW staff for a streamlined approval of the inter -department
agreement.
• Preparations for documents or design plans required for the execution of a Storm
Water Facilities Maintenance Agreement for on -site or off -site improvements will be
considered additional services.
• Draft Final plans (90%) and specifications shall be submitted to CITY per the approved
Project Schedule.
• Following a 90% construction plan review meeting with the CITY, the ENGINEER shall
submit Construction Documents (100%) to the CITY per the approved Project Schedule.
Each plan sheet shall be stamped, dated, and signed by the ENGINEER registered in
State of Texas.
• The ENGINEER shall submit a final design estimate of probable construction cost with
both the 90% and 100% design packages. This estimate shall use ONLY standard CITY
bid items.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 7 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
ASSUMPTIONS
• Bid Proposal Form will be prepared for Lump Sum type bidding
• 5 sets of 11x17 size drawings and 2 sets of specifications will be delivered for the 90%
Design package.
• A DWF file for the 90% Design will be created from design CAD drawings and will be
uploaded to the project folder in Buzzsaw.
• 5 sets of 11x17 size drawings and 5 specifications will be delivered for the 100% Design
package.
• A DWF file for the 100% Design will be created from design CAD drawings and will be
uploaded to the project folder in Buzzsaw.
• Estimated Plan Sheets:
• Cover Sheet
• Control Sheet
• Easement Layout Sheet
• Water Layout Sheet
• Water Abandonment Sheet
• Plan Sheets
Site Plan
• Paving Plan
• Grading and Drainage Plan
• Yard Piping Plan
• Piping Profiles
• Tank Plan View (Steel and Concrete-2 Sheets)
• Tank Elevation View (Steel and Concrete-2 Sheets)
• Tank Details (Steel and Concrete-2 Sheets)
• Control Valve Vault, Structural & Details
• Details 1
• Details 2
• Details 3
• Details 4 - Connections
• Erosion Control Plan
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 8 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
• Electrical Sheets (7)
DELIVERABLES
A. 90% construction plans and specifications.
B. 100% construction plans and specifications.
C. Detailed estimates of probable construction costs including summaries of bid items and
quantities using the CITY's standard bid items and format.
D. Original cover mylar for the signatures of authorized CITY officials.
ROW/EASEMENT SERVICES.
ENGINEER will support and perform activities related to ROW and land as outlined below,
per scoping direction and guidance from the CITY's Project Manager.
Right -of -Way Research
• The ENGINEER shall determine rights -of -way, easements needs for construction of the
project. Required temporary and permanent easements will be identified based on available
information and recommendations will be made for approval by the CITY.
Right-of-Way/Easement Preparation and Submittal.
• The ENGINEER shall prepare documents to be used to obtain right-of-way and
permanent and/or temporary easements required to construct the improvements.
• The ENGINEER shall submit the right-of-way and/or easement documents to CITY PM
for real property acquisition
• The documentation shall be provided in conformance with the checklists and templates
available on the CITY's Buzzsaw site.
Temporary Right of Entry Preparation and Submittal
• Prior to construction, the ENGINEER shall prepare and submit Temporary Right of Entry
documents for landowners to CITY PM for real property acquisition. It is assumed that letters
will only be required for land owners adjacent to temporary construction easements or who
are directly affected by the project and no easement is required to enter their property.
• The documentation shall be provided in conformance with the checklists and templates
available on the CITY's Buzzsaw site.
ASSUMPTIONS
• 2 Easements or right-of-way documents will be necessary.
• 2 Temporary right -of -entry documents will be necessary.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 9 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
• Right -of -Way research and mapping includes review of property/right-of-way records
based on current internet based Tarrant Appraisal District (TAD) information available at the
start of the project and available on -ground property information (i.e. iron rods, fences,
stakes, etc.). It does not include effort for chain of title research, parent track research,
additional research for easements not included in the TAD, right-of-way takings, easement
vacations and abandonments, right-of-way vacations, and street closures.
DELIVERABLES
A. Easement exhibits and meets and bounds provided on CITY forms.
B. Temporary Right of Entry Letters
SURVEY AND SUBSURFACE UTILITY ENGINEERING SERVICES.
ENGINEER will provide survey support as follows.
Design Survey
• ENGINEER will perform field surveys to collect horizontal and vertical elevations and
other information needed by ENGINEER in design and preparation of plans for the project.
Information gathered during the survey shall include topographic data, elevations of all
sanitary and adjacent storm sewers, rim/invert elevations, location of buried utilities,
structures, trees (measure caliper, identify overall canopy, and have qualified arborist
identify species of trees), and other features relevant to the final plan sheets. Existing
drainage at intersections will be verified by field surveys. Spot elevations will be shown on
intersection layouts with cross slope to fit intersecting grade lines.
• The minimum survey information to be provided on the plans shall include the following:
— A Project Control Sheet, showing ALL Control Points, used or set while gathering data.
Generally on a scale of not less than 1:400:
— The following information about each Control Point;
a. Identified (Existing. CITY Monument#8901, PK Nail, 5/8" Iron Rod)
b. X, Y and Z Coordinates, in an identified coordinate system, and a referred bearing
base. Z coordinate on CITY Datum only.
c. Descriptive Location (Ex. Set in the centerline of the inlet in the South curb line of
North Side Drive at the East end of radius at the Southeast corner of North Side Drive and
North Main Street).
— Coordinates on all P.C.'s, P.T.'s, P.I.'s, Manholes, Valves, etc., in the same coordinate
system, as the Control.
— No less than two horizontal bench marks, per line or location.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 10 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
— Bearings given on all proposed centerlines, or baselines.
— Station equations relating utilities to paving, when appropriate.
Temporary Right of Entry Preparation and Submittal
• Prior to entering property, the ENGINEER shall prepare and submit Temporary Right of
Entry for landowners to CITY PM.
• The documentation shall be provided in conformance with the checklists and templates
available on the CITY's Buzzsaw site.
Subsurface Utility Engineering
A. The SUE shall be performed in accordance with Cl/ASCE 38-02.
B. Level A
1. Location (Test Hole) Services: Locating the horizontal and vertical position
of the utility by excavating a test hole using vacuum excavation
techniques and equipment. In performing locating (test hole) services
ENGINEER will:
a.) Excavate Three (3) test holes to expose the utility to be measured in
such a manner that insures the safety of the excavation and the
integrity of the utility to be measured. Excavations will be performed
using specially developed vacuum excavation equipment that is non-
destructive to existing facilities. If contaminated soils are discovered
during the excavation process, the ENGINEER will notify the
CITY.Obtain x,y and Z information at each test hole.
C. Level B
1. Location of underground utilities by obtaining two-dimensional (x,y)
information obtained through the application and interpretation of non-
destructive surface geophysical methods will be performed for the 2-acre
site.
ASSUMPTIONS
• Topographic survey at intersection will include no more than 100 ft. in each direction.
• 3 Level A SUE locations
• 1 Level B SUE for 2-acre site
DELIVERABLES
A.
B.
C.
Copies of field survey data and notes signed and sealed by a licensed surveyor.
Drawing of the project layout with dimensions and coordinate list.
Level A and B SUE documentation
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 11 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
PHASE 2 BIDDING SERVICES
TASK 5. BID PHASE SERVICES.
ENGINEER will support the bid phase of the project as follows.
5.1. Bid Support
• The ENGINEER shall sell contract documents (11x17 and 22x34 plans) and
maintain a plan holders list on Buzzsaw from documents sold and from
Contractor's uploaded Plan Holder Registrations in Buzzsaw.
• The ENGINEER will develop and implement procedures for receiving and
answering bidders' questions and requests for additional information. The
procedures shall include a log of all significant bidders questions and requests
and the response thereto. The log shall be housed and maintained in the
project's Buzzsaw folder titled Request for Information. The ENGINEER will
provide technical interpretation of the contract bid documents and will prepare
proposed responses to all bidders questions and requests, in the form of
addenda. The ENGINEER shall upload all approved addenda onto Buzzsaw and
mail addenda to all plan holders.
• Attend the prebid conference in support of the CITY.
• Assist the CITY in determining the qualifications and acceptability of prospective
contractors, subcontractors, and suppliers.
• When substitution prior to award of contracts is allowed in the contract
documents, the ENGINEER will advise the CITY as to the acceptability of
alternate materials and equipment proposed by bidders.
• Attend the bid opening in support of the CITY.
• Tabulate and review all bids received for the construction project, assist the CITY
in evaluating bids, and recommend award of the contract. A copy of the Bid
Tabulation and the CFW Data Spreadsheet created utilizing CFW Bidtools only
are to be uploaded into the project's Bid Results folder on Buzzsaw.
5.2
• Incorporate all addenda into the contract documents and issue conformed sets.
ASSUMPTIONS
• The project will be bid only once and awarded to one contractor.
• _5 sets of construction documents will be sold to and made available on
Buzzsaw for plan holders and/or given to plan viewing rooms.
• _10_ sets of _11 x17 size and 5 sets of _22x34 size
drawings plans and 10_ specifications will be held at Engineer's office for
selling to bidders.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 12 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
• 5 sets of 11 x17 size and 5 sets of _22x34 size
drawings plans and 5_ specifications (conformed, if applicable) will be
delivered to the CITY.
• PDF files will be uploaded to Buzzsaw.
DELIVERABLES
A. Addenda
B. Bid tabulations
C. Recommendation of award
D. Construction documents (conformed, if applicable)
PHASE 3 CONSTRUCTION SERVICES
TASK 6. CONSTRUCTION PHASE SERVICES.
ENGINEER will support the construction phase of the project as follows.
6.1 Construction Support
• The ENGINEER shall attend the preconstruction conference.
• After the pre -construction conference, the ENGINEER shall provide project
exhibits and attend public meeting to help explain the proposed project to
residents. The CITY shall select a suitable location and mail the invitation letters
to the affected customers.
• Visits to Site and Observation of Construction. ENGINEER will provide on -site
construction observation services during the construction phase. ENGINEER will
make visits at intervals as directed by Client in order to observe the progress of
the Work, up to sixteen (16). Such visits and observations by Consultant are not
intended to be exhaustive or to extend to every aspect of Contractor's work in
progress. Observations are to be limited to spot checking, selective
measurement, and similar methods of general observation of the Work based on
ENGINEER's exercise of professional judgment. Based on information obtained
during such visits and such observations, Consultant will evaluate whether
Contractor's work is generally proceeding in accordance with the Contract
Documents, and ENGINEER will keep Client informed of the general progress of
the Work. The purpose of ENGINEER's site visits will be to enable ENGINEER to
better carry out the duties and responsibilities specifically assigned in this
Agreement to ENGINEER, and to provide Client a greater degree of confidence
that the completed Work will conform in general to the Contract Documents.
ENGINEER shall not, during such visits or as a result of such observations of
Contractor's work in progress, supervise, direct, or have control over Contractor's
work, nor shall ENGINEER have authority over or responsibility for the means,
methods, techniques, equipment choice and usage, sequences, schedules, or
procedures of construction selected by Contractor, for safety precautions and
programs incident to Contractor's work, nor for any failure of Contractor to comply
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 13 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
with laws and regulations applicable to Contractor's furnishing and performing the
Work. Accordingly, ENGINEER neither guarantees the performance of any
Contractor nor assumes responsibility for any Contractor's failure to furnish and
perform its work in accordance with the Contract Documents.
• Clarifications and Interpretations. ENGINEER will respond to reasonable and
appropriate Contractor requests for information and issue necessary clarifications
and interpretations of the Contract Documents to Client as appropriate to the
orderly completion of Contractor's work. Any orders authorizing variations from
the Contract Documents will be made by Client.
• Change Orders. ENGINEER may recommend Change Orders to Client, and will
review and make recommendations related to Change Orders submitted or
proposed by the Contractor.
• Shop Drawings and Samples. ENGINEER will review and approve or take other
appropriate action in respect to Shop Drawings and Samples and other data
which Contractor is required to submit, but only for conformance with the
information given in the Contract Documents. Such review and approvals or other
action will not extend to means, methods, techniques, equipment choice and
usage, sequences, schedules, or procedures of construction or to related safety
precautions and programs.
• Substitutes and "or -equal." Evaluate and determine the acceptability of substitute
or "or -equal" materials and equipment proposed by Contractor in accordance with
the Contract Documents, but subject to the provisions of applicable standards of
state or local government entities.
• Inspections and Tests. ENGINEER may require special inspections or tests of
Contractor's work as ENGINEER deems appropriate, and may receive and review
certificates of inspections within ENGINEER's area of responsibility or of tests and
approvals required by laws and regulations or the Contract Documents.
ENGINEER's review of such certificates will be for the purpose of determining that
the results certified indicate compliance with the Contract Documents and will not
constitute an independent evaluation that the content or procedures of such
inspections, tests, or approvals comply with the requirements of the Contract
Documents. ENGINEER shall be entitled to rely on the results of such tests and
the facts being certified.
• Disagreements between Client and Contractor. ENGINEER will, if requested by
Client, render written decision on all claims of Client and Contractor relating to the
acceptability of Contractor's work or the interpretation of the requirements of the
Contract Documents pertaining to the progress of Contractor's work. In rendering
such decisions, ENGINEER shall be fair and not show partiality to Client or
Contractor and shall not be liable in connection with any decision rendered in
good faith in such capacity.
• Applications for Payment. Based on its observations and on review of
applications for payment and accompanying supporting documentation,
ENGINEER will determine the amounts that ENGINEER recommends Contractor
be paid. Such recommendations of payment will be in writing and will constitute
ENGINEER's representation to Client, based on such observations and review,
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 14 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
that, to the best of ENGINEER's knowledge, information and belief, Contractor's
work has progressed to the point indicated and that such work -in -progress is
generally in accordance with the Contract Documents subject to any qualifications
stated in the recommendation. In the case of unit price work, ENGINEER's
recommendations of payment will include determinations of quantities and
classifications of Contractor's work, based on observations and measurements of
quantities provided with pay requests. By recommending any payment,
ENGINEER shall not thereby be deemed to have represented that its
observations to check Contractor's work have been exhaustive, extended to every
aspect of Contractor's work in progress, or involved detailed inspections of the
Work beyond the responsibilities specifically assigned to ENGINEER in this
Agreement. It will also not impose responsibility on ENGINEER to make any
examination to ascertain how or for what purposes Contractor has used the
moneys paid on account of the Contract Price, nor to determine that title to any
portion of the work in progress, materials, or equipment has passed to Client free
and clear of any liens, claims, security interests, or encumbrances, nor that there
may not be other matters at issue between Client and Contractor that might affect
the amount that should be paid.
• Substantial Completion. ENGINEER will, promptly after notice from Contractor
that it considers the entire Work ready for its intended use, in company with Client
and Contractor, conduct a site visit to determine if the Work is substantially
complete. Work will be considered substantially complete following satisfactory
completion of all items with the exception of those identified on a final punch list.
If after considering any objections of Client, ENGINEER considers the Work
substantially complete, ENGINEER will notify Client and Contractor.
• Final Notice of Acceptability of the Work. ENGINEER will conduct a final site visit
to determine if the completed Work of Contractor is generally in accordance with
the Contract Documents and the final punch list so that ENGINEER may
recommend, in writing, final payment to Contractor. Accompanying the
recommendation for final payment, ENGINEER shall also provide a notice that the
Work is generally in accordance with the Contract Documents to the best of
ENGINEER's knowledge, information, and belief based on the extent of its
services and based upon information provided to ENGINEER upon which it is
entitled to rely.
• Limitation of Responsibilities. ENGINEER shall not be responsible for the acts or
omissions of any Contractor, or of any of their subcontractors, suppliers, or of any
other individual or entity performing or furnishing the Work. ENGINEER shall not
have the authority or responsibility to stop the work of any Contractor.
The ENGINEER shall attend the "Final" project walk through and assist with preparation of
final punch list
6.2 Record Drawings
• The ENGINEER shall prepare Record Drawings from information provided by
the CITY depicting any changes made to the Final Drawings during construction.
• The ENGINEER shall modify the Final Drawings electronically and shall place a
stamp on the plans indicating that they represent Record Drawings of the project
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 15 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
as constructed. The stamp shall be signed and dated by the ENGINEER and
shall be placed on each plan sheet, whether there are any revisions on the sheet
or not. Each sheet shall clearly indicate all changes which apply to that sheet by
clouding and numbering, or other suitable means.
• The following disclaimer shall be included with the Record Drawing stamp:
o These Record Drawings were prepared using information provided by
others and represent the as constructed conditions to the extent that
documented changes were provided for recording. The ENGINEER
assumes no liability for undocumented changes and certifies only that the
documented changes are accurately depicted on these drawings.
• The ENGINEER shall submit a set of sealed Final Drawings, modified and
stamped as Record Drawings, on mylarfor record storage. The ENGINEER may
keep copies of the information provided by the CITY for their files, but all original
red -lined drawings shall be returned to the CITY with the mylars.
PDF files shall be uploaded to the project's Record Drawings folder in Buzzsaw.
ASSUMPTIONS
• 5 RFI's are assumed.
• 2 Change Orders are assumed
• 75 Shop Drawings reviews are assumed
• 16 Site Observation Visits are assumed.
• 12 Application for Payment Requests are assumed.
• One PDF copy of full size (11"x17") plans will be delivered to the CITY.
DELIVERABLES
A. Public meeting exhibits
B. Response to Contractor's Request for Information
C. Review of Change Orders
D. Review of shop drawings
E. Final Punch List items
F. Record Drawings on PDF
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 16 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
PHASE 4
TASK 7 DIVISION 01 SPECIFICATIONS
A draft of Division 01 — General Requirement specifications in CSI MF04 format will be
developed for consideration by the CITY. The proposed list of specifications will be
presented at a kickoff meeting with CITY department staff to solicit feedback and finalize the
specifications. Initial, 2nd and Final Draft versions of the documents will be prepared and
submitted for review by staff. Workshops will be conducted with CITY staff during various
stages of completion of the documents to solicit feedback and comments. Outside
consultants that are familiar with the City's facility -type project will also be provided draft
documents for review and comment.
ASSUMPTIONS
• 10 Specifications will be developed.
DELIVERABLES
A. Division 01 Specifications uploaded to Buzzsaw
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services described in
the tasks above. However, ENGINEER can provide these services, if needed, upon the
CITY's written request. Any additional amounts paid to the ENGINEER as a result of any
material change to the Scope of the Project shall be agreed upon in writing by both parties
before the services are performed. These additional services include the following:
• Negotiation of easements or property acquisition including temporary right -of -
entries.
• Document preparation related to property acquisition.
• Platting and development services related to property acquisition.
• Services related to acquiring a building permit for construction.
• Design services related to off -site drainage improvements.
• Services related to preparation and execution of Stormwater Facility Maintenance
Agreement.
• Services related to development of the CITY's project financing and/or budget.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 17 of 18
ATTACHMENT A
DESIGN SERVICES FOR
CAYLOR 5MG GROUND STORAGE TANK
CITY PROJECT NO.: 02111
Services related to disputes over pre -qualification, bid protests, bid rejection and
re -bidding of the contract for construction.
• Construction Phase Services associated with Weld Testing.
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of
God.
• Services related to warranty claims, enforcement and inspection after final
completion.
•
•
•
Services related to submitting for permits (ie.TxDOT, railroad, etc...)
Services related to Survey Construction Staking
Services related to acquiring real property including but not limited to easements,
right-of-way, and/or temporary right -of -entries.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Performance of miscellaneous and supplemental services related to the project as
requested by the CITY.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07.23.2012
Page 18 of 18
Design Services for
Caylor 5MG Ground Storage Tank
City Project No. 02111
Time and Materials with Multiplier Project
I. Compensation
A. The ENGINEER shall be compensated for personnel time, non -labor expenses,
and subcontract expenses in performing services enumerated in Attachment A
as follows:
i. Personnel Time. Personnel time shall be compensated based upon hours
worked directly in performing the PROJECT multiplied by Direct Salaries
multiplied by a factor of 3.35.
Direct Salaries are the amount of wages or salaries paid ENGINEER's
employees for work directly performed on the PROJECT, exclusive of all payroll -
related taxes, payments, premiums, and benefits.
ii. Non -Labor Expenses. Non -labor expenses shall be reimbursed as Direct
Expenses at invoice or internal office cost.
Direct Expenses (non -labor) include, but are not limited to, mileage, travel and
lodging expenses, mail, supplies, printing and reproduction services, other direct
expenses associated with delivery of the work; plus applicable sales, use, value
added, business transfer, gross receipts, or other similar taxes.
iii. Subcontract Expenses. Subcontract expenses and outside services shall
be reimbursed at cost to ENGINEER plus a markup of ten percent (10%).
iv. Budgets. ENGINEER will make reasonable efforts to complete the work
within the budget and will keep the City informed of progress toward that end so
that the budget or work effort can be adjusted if found necessary.
ENGINEER is not obligated to incur costs beyond the indicated budgets, as may
be adjusted, nor is the City obligated to pay ENGINEER beyond these limits.
If ENGINEER projects, in the course of providing the necessary services, that the
PROJECT cost presented in Article 2 of this Agreement will be exceeded, whether
by change in scope of the project, increased costs or other conditions, the
ENGINEER shall immediately report such fact to the City and, if so instructed by
the City, shall suspend all work hereunder.
When any budget has been increased, ENGINEER's excess costs expended prior
to such increase will be allowable to the same extent as if such costs had been
incurred after the approved increase.
B. The ENGINEER shall be paid monthly payments as described in Section II -
Method of Payment.
II. Method of Payment
A. The ENGINEER shall be paid by the City based upon an invoice created on the
basis of statements prepared from the books and records of account of the
ENGINEER, based on the actual hours and costs expended by the ENGINEER
in performing the work.
B. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
C. ENGINEER shall prepare and submit invoices in the format and including content
as presented in Exhibit B-1.
D. Payment of invoices will be subject to certification by the City that such work has
been performed.
III. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Water Department monthly progress reports and schedules in the format
required by the City.
IV. Summary of Total Project Fees
Firm
Prime Consultant
Kimley-Horn
Primary Responsibility
Fee Amount
Design, Bidding, and $316,900
Construction Phase Services
Proposed MBE/SBE Sub -Consultants
JQ, Inc. Structural Design $13,000
CMJ, Inc. Geotechnical Services $17,000
Gojer-McCreary Electrical Design $30,500
The Rios Group SUE $9,500
Gorrondona and Survey $10,500
Associates
V&A Engineering Cathodic Protection $8,200
PIC Reproduction $1,750
Blackstone Engineering Conceptual Design and Review $15,500
Non-MBE/SBE Consultants
None $0
Project Number & Name
TOTAL
Total Fee
$422.850
$ 422,850
MBE/SBE Fee
$ 105,950
74.9
100%
MBE/SBE
%
25.06 % 1
City MBE/SBE Goal = 25% Consultant Committed Goal = 25.06 %
City of Fort Worth
Caylor 5 MG Ground Storage Tank
Gty No. 02111
Exhibit a-1
Summary of Fees
Kimley-Horn Subconsultants*
Gojer- Blackstone Subconsultant
Task Labor Expenses JQ CMJ McCreary Gorondonna Rios V&A PIC Engineering TOTAL Total
Design Services $161,100 $14,500 $9,700 $15,800 $24,000 $10,500 $9,500 $8,200 $1,750 $15,500 $94,950 $270,550
Bidding Phase Services $19,900 $875 $750 $750 $21,525
Construction Phase Services $97,900 $3,625 $2,550 $1,200 $6,500 $10,250 $111,775
Division 01 Specification Implementation $18,600 $400 $19,000
Total $297,500 $19,400 $13,000 $17,000 $30,500 $10,500 $9,500 $8,200 $1,750 $15,500 I $105,950 $422,850
*M/SBE % 25.06%
Kimley-Horn
and Associates, Inc.
Project Workplan Budget
General Project Information
Client:
Project:
KHA No.
PM:
City of Fort Worth Water Dpt
Caylor 5MG GST
Jeni Tatum
Budget Summary
Date: Jun 3, 2013
Fee Information
Fee Type:
Expense Mult:
Computer Mult:
Allocation:
CP
1.10
0.00
0.0%
C7' Fix. Mult.
('' Schedule:
Task Budget Summary
Task 700
Task 888
No. Task Name
1 Design
2 Bid Phase Services
3 Construction Phase Svcs
4 Division 01 Specs
777 Contingency
Hours Labor Expense
1,425 $
187 $
923 $
145 $
161,100 $
19,900 $
97,900 $
18,600 $
TOTALS:I 2,6801 $ 297,500 I $
5,000
800
2,600
400
8,800 I $
Allocation
Subtotal
$ 166,100
$ 20,700
$ 100,500
$ 19,000
- I $ 306,300
Subconsultant Summary
Task No.
701
702
703
704
705
706
707
708
Task Name
JQ-Foundation Consulting/Structural Design
CMJ - Geotech
McCreary - Electrical and SCADA
Gorrondona - Survey and Easements
Rios - SUE
V&A - Cathodic Protection
PIC - Reproduction
Blackstone Engineering
rojec = u • ge ummary
Effort Totals:
Labor: $
Expense: $
TOTAL: $
297,500
125,345
422,845
Cost Multiplier Subtotal
$ 13,000 1.10 $ 14,300
$ 17,000 1.10 $ 18,700
$ 30,500 1.10 $ 33,550
$ 10,500 1.10 $ 11,550
$ 9,500 1.10 $ 10,450
$ 8,200 1.10 $ 9,020
$ 1,750 1.10 $ 1,925
$ 15,500 1.10 $ 17,050
TOTALS:I $ 105,950 I I $ 116,545
K:\FTW_Marketing\Fort_Worth\2013-A-FW W D-RFP\Caylor-GST\PPP\Caylor GST WorkPlanBudgetV5_.xds
Page 1 of 11
Printed: 6/3/2013, 12:07 PM
ATTACHMENT "C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
Caylor 5MG Ground Storage Tank
City Project No. 02111
No changes to the Standard Agreement.
City of Fort Worth, Texas
Attachment C
MO Release Date: 05.19.2010
Page 1 of 1
FORT WORTH
WATER
COPYRIGHT 2011 CITY OF FORT WORTH
UNAUTHORIZED REPRODUCTION IS A VIOLATION OF APPLICABLE LAY,
Caylor Ground Storage TankTHClICiYIS NOT TO BETAA
KERNA
FUSED AS DATA PRODUCED F1V
ENGINEERING PURPOSES OR BY A REGISTERED PROFESSIONAL LAT D
SURVEYOR. THE CITY OF FORT WORTH ASSUMES NO RESPONSIBILITY
FOR THE ACCURACY OF SAID DATA.
U
o.
8"
P.V.C.
42" C none
81" PIV.C,I_ Iv' ,
ro
U
a.
P.V.C.
tJ
co
re
0
V
O.
U
d
co
0
Q
12 " P.V.C.
30 " Ce.,erete
42" Concrete
A" PV�
TIMBERLAND
U
d
U
a
o
6" P.V.C.
Caylor Site
U
Legend
All Water Lines
♦ Fire Hydrant
Tank Site
CFW Caylor GST\Caylor GST Site surroundings.mxd (Fgoderya) 06/03/2013
0 100 200
Feet
NAD 1983 StatePlane Texas North Central FIPS 4202 Feet
ID Task Name
1
2
Contract Execution
Notice to Proceed
Site Assessment and
Conceptual Design
4 Data Collection
5 Preliminary Geotechnical
Analysis
6 Topographic Survey
7 Tank Material Evaluation
8 Site Evaluation
9 Hydraulic Analysis
10 Conceptual Design (30%)
11 Letter Summary Report
12 City Review (30%)
13 Preliminary Design
14 Final Geotechnical Analysis
15 Design Plans and
Specifications
16 City Review (60%)
17 Stakeholder Meetings
18 Final Design
19 Easement Documents
20 Easement Acquisition
21 Final Plans and
Specifications
22 Grading Permit/iSWM
23 Urban Forestry Permit
24 City Final Plan Review (90%)
25 Bid Documents
26 Bidding and Award
27 Advertisement 1
28 Advertisement 2
29 Pre Bid Meeting
30 Bid Opening
31 M/DBE Approval
32 M&C Circulation
33 M&CAward
34 Pre -Construction Meeting
35 Public Meeting
36 Construction
37 Notice to Proceed
38 Substantial Completion
39 Final Completion
Project: Caylor_
Date: Wed 7/24
Task
Split
Milestone
Thu 1/30/14
Thu 2/6/14
Thu 2/13/14
Thu 2/20/14
Fri 2/21/14
Fri 3/7/14
Fri 3/28/14
Start
Finish
Predeci
Mon 7/29/1'c Mon 7/29/13
Mon 7/29/13Mon 7/29/13
Mon Fri 10/25/13 2
7/15/13
Tue 7/30/13 Mon 8/12/13 2
Tue 7/30/13 Mon 8/26/13 2
Tue 7/30/13 Mon 8/26/13 2
Tue 8/13/13 Mon 8/26/13 4
Tue 8/27/13 Mon 9/9/13 5,6
Tue 8/13/13 Mon 8/26/13 4
Tue 8/27/13 Mon 9/23/13 9
Tue 9/10/13 Mon 9/16/13 8
Tue 9/17/13 Mon 9/23/13 11
Tue 9/24/13 Mon 11/18/1E12
Tue 9/24/13 Mon 12
10/21/13
Tue 9/24/13 Mon 11/4/13 12
Tue 11/5/13 Mon 11/11/1215
Tue 11/5/13 Mon 11/18/1215
Tue 11/12/1; Wed 1/29/14 16
Tue 11/12/12Mon 12/2/13 16
Tue 12/3/13 Mon 1/27/14 19
Tue Mon 1/6/14 16
11/12/13
Tue 11/12/12 Mon 12/2/13 15
Tue 11/12/1E Mon 11/25/1215
Mon 1/20/14 21
Tue 1/7/14
Tue 1/21/14 Wed 1/29/14 24
Thu 1/30/14 Tue 4/29/14 20,25
Thu 1/30/14
Thu 2/6/14
Thu 2/13/14
Thu 2/20/14
Thu 3/6/14 30
Thu 3/27/14 31
Tue 4/15/14 32
Wed 4/16/14Tue 4/22/14 33
Wed 4/23/14Tue 4/29/14 34
Wed 4/16/14Tue 4/28/15
Wed 4/16/14Tue 4/29/14 33
Wed 4/30/14Tue 3/3/15 37
Wed 3/4/15 Tue 4/28/15 38
imminimil Summary
Project Summary
♦ External Tasks
Jun
2013
Jul 1 Aug
Sep Oct Nov Dec
External Milestone P
4 Inactive Task
Inactive Milestone
Caylor SMG Ground Storage Tank
City Project No. 02111
Attachment D- Schedule
2014
Jan 1 Feb 1 Mar 1 Apr 1 May 1 Jun 1 Jul 1 Aug 1 Sep 1 Oct I Nov 1 Dec
rmi;r:
Inactive Summary
Manual Task
Duration -only
r
J Manual Summary Rollup
Manual Summary
Start -only
Finish -only
Deadline
Progress
♦
Jan Feb 1 Mar 1 Apr May 11
iiil --- -
Page 1
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 7/23/2013
DATE: Tuesday, July 23, 2013 REFERENCE NO.: **C-26358
LOG NAME: 60CAYLOR GST, DESIGN OF SECOND TANK
SUBJECT:
Authorize Execution of an Engineering Agreement in the Amount of $422,850.00 with Kimley—Horn and
Associates, Inc., for Design and Engineering Services During Construction of the Caylor 5.0 Million Gallon
Ground Storage Tank and Associated Site Piping (COUNCIL DISTRICT 7)
RECOMMENDATION:
It is recommended that the City Council authorize the execution of an Engineering Agreement with
Kimley—Horn and Associates, Inc., in the amount of $422,850.00 for design and engineering services during
construction of the Caylor 5.0 million gallon ground storage tank and associated site piping.
DISCUSSION:
On March 19, 2002, (M&C C-19013) the City Council authorized the Water System Master Plan. The
Master Plan provides the schedules for major water capital improvement projects through the year 2025. The
proposed second Caylor Ground Storage Tank (GST) was identified in the Master Plan and will serve the
Northside II pressure plane. This is a major water supply source for three large wholesale customers, the
cities of Southlake and Keller and the (future) City of Westlake. This proposed second tank will be located
next to the existing Caylor GST, at 1300 Caylor Street North.
As part of the scope of work within this Agreement, the Engineer will perform all engineering and design
functions necessary for the preparation of construction plans and specifications for this new second Caylor
GST. The engineer will also prepare construction estimates, provide bidding services and shop drawing
review, and provide engineering services during the construction of this GST.
Staff has reviewed the scope and fee, and recommends awarding the contract. In addition to the engineering
contract cost of $422,850.00, an additional amount of $50,000.00 is provided for Staff support and time.
M/WBE Office — Kimley—Horn and Associates, Inc., is in compliance with the City's BDE ordinance by
committing to 25 percent SBE participation. The City's SBE goal on this project is 25 percent.
This project is located in COUNCIL DISTRICT 7, Mapsco 8Y.
FISCAL INFORMATION:
The Financial Management Services Director certifies that funds are available in the current capital budget,
as appropriated, of the Water Capital Projects Fund.
FUND CENTERS:
TO Fund/Account/Centers FROM Fund/Account/Centers
P265 531200 607180211130 $422.850.00
CERTIFICATIONS:
Submitted for City Manager's Office bv:
Originating Denartment Head:
Additional Information Contact:
ATTACHMENTS
Fernando Costa (6122)
S. Frank Crumb (8207)
Farida Goderya (8214)
1. 152. 60 CAYLOR GST — Design of Second Tank(FAR funds verification)(JCT 6-27-2013).docx
2. 60CAYLOR GST. DESIGN OF SECOND TANK FAR.n df
3. Cavlor GST Site surroundings.ndf
4. SBE Compliance for Design Contract KHI.ndf