HomeMy WebLinkAboutContract 44733-CO1 (2)CITY SECRETARY FORT WORTH. City of Fort Worth CO CT( m®o, Lf Change Order Request Breakdown Project Name' Concrete Restoration (2013-11) At Various Locations Client Project #(s)I City Project No.: 0001-537110-0202002 Dept. T/PW Original Contract Amount $539,640.00 Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date Amount of Proposed Change Order Revised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) Change Order Submittal # I 1 $539,640.00 $6,098.50 $545,738,50 $0.00 $6,098,50 CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) JUSTIFICATION (REASONS) FOR CHANGE ORDER City Sec # I 44733 Date I 5/2/2014 I Contract Time Totals (CD) $539,640.00 160 $539,640.00 160 $6,098.50 34 $545,738.50 194 $0.00 $6,098.50 1.13% $674,550.00 This change order is to add (7) days to the contract for time and cost of filling the voids on Frye Road and (7) calendar days to cover the repair cost of 2 signal light loops on Sycamore School Road. Also add 15 days to the contract for time lost due to unusually cold weather and 5 days for the time that work was suspended at the City's request during the Christmas Holidays. OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX FORT WORTH City of Fort Worth Change Order Additions Project Name ( Concrete Restoration (2013-11) At Various Locations Client Project # j City Project No.: GG01-537110-0202002 Change Order Submittal # 1 City Sec # j 44733 Date j 5/2/2014 1 ADDITIONS I I tM ULSUKIN I IUN ULF' I Uty Unit Unit Cost I otal 1I Fm in Void Un Frye Road (lime, tguipment & Matenal) I INW 1.00 LS $1,236.50 $1,236.50 18 Repair 2 Signal Light Loops On Sycamore School Road T/PW 1.00 LS $4,862.00 $4,8bL.UU TIPW Sub Total Additions $6,098.50 $6,098.50 Change Order Additions Page 1 of 1 FORT WORTH City of Fort Worth Change Order Deletions I I EM Project Name 1 Concrete Restoration (2013-11) At Various Locations Client Project # 1 City Project No.: GG01-537110-0202002 Change Order Submittal # 1 City Sec # 1 44733 Date 1 5/2/2014 1 DELETIONS UESCKIP I IUN UEP I City Unit Unit Cost I otal T/PW Sub Total Deletions Change Order Deletions Page 1 of 1 M/SBE Breakdown for this Change Order M/SBE Sub.,091iinIFiTY00::.OL.S004001111.giliittiERINOEAmount for this CO Total Previous Change Orders Co # DATE AMOUNT Total $0.00 CFW Change Order Approval St-COApp01 Page 1 of 3 Routing Assigned To: Due Date: Assigned By: Due Time: Links (1) fortworthaov/Infrastructure Proiects/Concrete Restoration (2013-111/Contractor/Chance Orders/Bradlev Douglas Chance Order Breakdown #1 7132 Revised.xls Attachments (01 No Attachments have been added to this form. https://projectpoint.buzzsaw.com/ bzweb/Forms/FormPrint.aspx?SiteId=51500&Processl... 5/29/2014 CFW Change Order Approval St-COApp01 Page 2 of 3 FORT WORTH® city of Fort Worth Change Order Request Approval (Change Order Breakdown Available in Links) For Change Order Submittal No.: COSub01 Change Order No.: St-COApp01 Date Started: 2014-05-22 City Sec. No.: 44733 Date Due: 2014-06-13 Project Name: Concrete Restoration (2013-11) GG01-537110-0202002 DOE Numbers: Project Numbers: DOE No. 7132 ProjectConcrete restoration at various locations Description: Project Manager: Tariqul Islam City Inspector: Gary Deyon Contractor: Bradley Douglas Construction Services, LLC. COUNCIL ACTION (If Required): M&C Log Name: M&C Number: COST AND DAYS SUMMARY: M&C Date: Requested Department: Cost($) Fund Account Center: Days: TPW $ 6,098.50 GG01-537110-0202006 34 Total Cost: $ 6,098.50 Approval Status: Total Requested Days: 34 https://projectpoint.buzzsaw.com/ bzweb/Forms/FormPrint.aspx?SiteId=51500&Processl... 5/29/2014 CFW Change Order Approval St-COApp01 Page 3 of 3 Approved: Yes Comments: User: Cheryl McKnight Date: 2014-05-22 11:25 AM Approved: Yes Comments: No M&C required User: Tariqul Islam Date: 2014-05-22 11:26 AM Approved: Yes Comments: User: Najib Fares Date: 2014-05-22 1:17 PM Approved: Yes Comments: User: Andy Anderson Date: 2014-05-22 1:21 PM Approved: Yes Comments: User: Doug Wiersig Date: 2014-05-22 5:53 PM Approved: Yes Comments: User: Grant Jordan Date: 2014-05-29 11:26 AM Approved: Yes Comments: User: Fernando Costa Date: 2014-05-29 4:29 PM Action Required: https://projectpoint.buzzsaw.com/ bz web/Forms/ForiiiPrint.aspx?Siteld=51500&Processl... 5/29/2014