Contract 44208-CO1 (2)
City of Fort Worth Change Order Request CITY SECRETARY, rn CONTRACT NO. ,.- Change Order No. Date TPW Project No. 1 (one) 4/15/13 Facility and Project Description WRMC Richardson Bass Exhibit Area Renovation Funding (FAC) C291 541200 247060207880 City Secretary Contract No. 44208 ORIGINAL CONTRACT AMOUNT $1,571,000 $ 0 $ 0 EXTRAS TO DATE CREDITS TO DATE CONTRACT COST TO DATE AMOUNT OF PROPOSED CHANGE ORDER REVISED CONTRACT AMOUNT ORIGINAL FUNDS AVAILABLE FOR CHANGE ORDERS REMAINING FUNDS AVAILABLE FOR CHANGE ORDERS ADDITIONAL FUNDING (IF NECESSARY) IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL: Provide all labor and materials as per attached PCR's: 1, 2, 3, 4, 5, 6, and 7. Summary attached. ADD $ 1,571,000 $ 31,810 $ 1,602,810 $ 249,000 $ 217,190 0 $31,810 TOTAL ADD PCR 1 Rejected $ 31,810 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order Contractor's Name Modern Contractors, Inc. Original Contract Time Additional Approved Time To Date 115cd 0 cd Contractor- Modern Contractors, Inc NIL Architectural Services Manager P1 TRW Project Architect /HahnHoffer Stanford Distribution: File Construction Manager Project Manager Contractor RECEIVED APR Approved Contract Time To Date 115 cd OFFICIAL 12E©01 CITY SECRETARY FT, ®V r 9 `jj'„'WFacilities Management Division, C ange Order Form (3/20/12) Mary Date y .5i/3 Date 4/2042vv. batd 44/r3 Date 41013 Additional Time For This Change Order cd C. ructiop M ger 3 nsportation and Public works v•6....., Assistar}t ¢ity Manager Council Action (If Required) ❑ Approved ❑ Disapproved ❑ Other Date Li/z2.j0 Date Date ti#AS Change Order 1 WRMC Richardson Bass Exhibit Area PCR 1- Modification to Folding Partition REJECTED PCR 2 — ADD telecom Room and minor revisions as per ASI 1 ADD $ 19,211 PCR 3- Add additional water valves at concession area ADD $ 1,609 PCR 4- Install main cut off valves and bypass valves for stalls ADD $ 1,625 PCR 5- Revise electrical as per ASI 2 ADD $ 5,178 PCR 6- Revise light fixtures per RFI 2 ADD $ 1,241 PCR 7- Change overhead door finish to bronze with bronze glass ADD $ 2,946 Total This Change ADD $ 31,810 PROPOSAL To: Hahnfeld Hoffer Stanford 200 Bailey Ave, Suite 200 Fort Worth, TX 76107 via email DATE: 3/7/2013 RE: Richardson Bass Exhibit Area Renovations - WiIl Rogers Memorial Center Modern Proposed Change Order (PCO) # 2, HHS ASI # 1 We hereby propose to supply all supervision, labor, materials, and equipment necessary to complete the following described work. All work will be performed in a professional manner with quality craftsmanship Scone Of Work Provide changes per ASI 1 See attached $16,956.00 Sub Total Markup - 10% Sub Total Bonds and Insurances $16,956.00 $1,695.60 $18,651.60 $559.55 Net Change This Proposal ADD 19,211.15 Net Change in Days This Proposal Acceptance This proposal is accepted and agreed to this date as indicated by the signatures below: For the Owner Date For the Architect 2 G. For Modern ontriactors Date L'2. ? Date PROPOSAL ESTIMATE Item # Description QTY UP Lsum Total Remarks Changes per ASI 1 12" thickened slab for new room Masonry for new room (see attached from Pryor &Pryor Masonry) New door, frame and hardware for new room (see attached from Woodard) Install new door, frame and hardware 80 sft $7 $560 $8,370 $1,550 $350 Painting of new room (see attached from Posadas) $606 Add sprinkler head to this room (see attached from EFS) $200 Electrical changes for ASI 1 (see attached from Stufflebeam Electric) $5,320 AV changes and correct model for AN floor boxes (see attached from Able Communications) void TOTAL COST $16,956 PRYOR & PR.YOR. MASONRY, INC. 4732 Meadowview Dr., Mesquite, Texas 75150 Office: (972) 613-2036 Fax: (972) 613-2556 CELL 214-577-2952 ATTN: AJ Date 3-29-2013 Fax: Pages (1) RE: Will Rogers ASI #1 Pricing REVISED Material Reg. CMU Score $ 600.00 Glazed CMU $ 350.00 Mortar $ 110.00 Grout $ 285.00 Wire $ 90.00 Equipment $ 500.00 Rebar $ 300.00 Cleaning $ 150.00 Misc. $ 500.00 Total $ 2,885.00 $ 2,885.00 4,725.00 $ 7,610.00 $ 760.00(O&H 10%1 $ 8,370.00 Labor $ 1,500.00 $ 300.00 $ 70.00 $ 450.00 $ 40.00 $ 500.00 $ 120.00 $ 300.00 $ 500.00. $ 3,780.00 $ 945.00 (Labor Burden 25%) $ 4,725.00 EIGHT THOUSAND SIX HUNDRED THIRTY-SEVEN DOLLARS Thanks e Pryor Phone: 817/831-6423 Fax: 817/831-6547 Woodard Builders Supply Builders Hardware P.O. Box 161849 6405 Airport Freeway Fort Worth, Texas 76161-1849 Fort Worth, Texas 76117 • Quote • Date: February 28, 2013 To: Modern Contractors Attn: Anil Jacob Phone: (817) 571-2320 From: Shelby Boren Re: Will Rogers Renovation - ASI No. 01 We wish to quote you the following prices to furnish material listed below as an extra to the contract. Finish Hardware: $770.00 3 Each Hinges BB1191 4.5 x 4.5 NRP 10B 1 Each Lockset ML2057 NSA M17 CT6 626 1 Each Closer CLP7500 SNB 690 1 Each Door Sweep 750S-N 36" DBA 1 Each Threshold 413S 36" DBA Hollow Metal: $780.00 1 Each 3'0"x 7'0"x 5-7/8"Hollow Metal Frame, 3-Sided, A60, Prepped, for Hinges & Strike, Non -Rated, LHR 1 Each 3'0"x 7'0"x 1-3/4" Hollow Metal Door, Flush, A60, Prepped for Hinges & Mortise Lockset, Non -Rated, LHR Tax: $0.00 This price is net FOB the jobsite for material only and does not include sales tax or installation. * If we are to proceed as outlined above, we must have a signed purchase/ change order agreement prior to ordering and/or fabricating any material Should you require additional information, please let us know. 1 V4i' P 9027 Quinn St. Dallas, Texas 75217 Phone 21'4-391-7179 Fax 214-391,7109 OMERsave Modern Contractors AAORESS ExisnNa coivYRAOrNo. OC TMOT DAT YOU ARE HEREBY AUTRORIZED TO (PERFORM TUFF )LL. Change Orders#01 AL WORK IZATION J°8N4'5 Will Rogers Renovation ASH JO!'i I.abAfQN • SPECIFICALLY;IJESGR?BED ADDITIONAL WORK Block Filler and paint CMU walls, 1 additional door; and frarme add $606.00 Materials $122.00 Labor $484.00 i4 bit id AAYMENrYI 6 MAD ASFOlp s • jObEpf/t)aMEa"UNO�R1lfESd,NFCi�NQ1'JIDNSASSPEGIACII oRlpINAL,0101fA.DTWig SOT WAWISEST1PVtATEL OWNER SIGNATURE NDTE:TNISHEVISIONaaoMES`twIroPANDINAGGARAANG$.i0THk; $Ti WENFA 93AQA To'FURNlSNWiORANDMA7Et?IAIS<GOMPIETEINAGCQgDgNGE mat THE AO* SPgCIFidAT10NSATABOVESTATEOPPi E Feniqiilo rata 03.04.2013 C°NMACTORS(GNAT J 1E• oRlG1NAL ANIL JACOB From: Michael W. Beckman, P.E. <efs.tx©sbcglobal.net> Sent: Wednesday, February 27, 2013 11:28 PM To: 'ANIL JACOB' Subject: RE: Will Rogers Renovation - ASI 1 AJ, EFS's cost to add one head and make revisions to its design is $200. mb From: ANIL JACOB [mallto:aiacob@modernctrs.coml Sent: Wednesday, February 27, 2013 3:43 PM To: Joe Pryor, Jr.; Jeremy; susanlarrvmilierroofina.com; Justin Roberts; Steve Frank; sboren@woodardbldrs.com; artexoverheaddoor@msn.com; daravaarlandam.com; marvmoore@alliedinteriors.com; bill.aroce@ronparco.com; posadaspaintinainc(avahoo.com; Blake Walker; Sarah Kiley; Craig Cowsert; rkossmanCa�txrr.com; DipeconnectionDlumbina@amail.com; billvls@oremierservicestx.com; 'Michael W. Beckman, P.E.'; Stufflebeam, Eddie; James Wicker; mikeOcnfiresystems.com Cc: 'Keith Farmer'; ihamiltonmodernctrs.com Subject: Will Rogers Renovation - ASI 1 See attached ASI 1. If there are any costs, please submit by 3/4/2013. Anil Jacob "AJ" President OD RN 2008 Plaza Drive Bedford, Texas 76021 www.modernctrs.com Office 817.571.2320 Fax 817.571.5805 Cell 214.883.2626 aiacob@modernctrs.com No virus found in this message. Checked by AVG - www.ava.com Version: 2012.0.2238 / Virus Database: 2641/5636 - Release Date: 02/27/13 i STUFFLEBEAM ELECTRIC Change Order #1 Date: March 5, 2013 PROJECT: Will Rogers Memorial Center Richardson -Bass Exhibits Area 1591 Rip Johnson Fort Worth, Texas Changes and additions for ASI#1 include: 1. New RB4 panel and 100 amp feeder. 2. New light fixture type C1 and wall switch. 3. Three new 120 volt 20 amp circuits from panel RB4 to the AV Rack in room #116 and ground buss with #3/0 ground conductor to the main ground connection at panel DPHRB. 4. Six new 120 volt 20 amp circuits from panel RB4 to the electric floor boxes. Material Labor: Total Item #1 $978.00 $689.00 $1,667.00 Item #2 $203.00 $180.00 $ 383.00 Item #3 $725.00 $763.00 $1,488.00 Item #4 $368.00 $700,00 $1,068.00 Total: $4,606.00 Overhead 10% $ 460.60 $5,066.60 Profit 5% $ 253.33 Total this Change order: $5,319.93 E. STUFFLEBEAM STUFFLEBEAM ELECTRIC (817)284-7405 License Stufflebeam Electric 132 Arbol Court Ft Worth, TX 76108 817-284-7405 License # 22110 Regulated by the Texas Department of Licensing Regulation Po Box 12157 Austin, TX 78711 1-800-803-9202 1-512-463-6599 www.license.state.tx.us/complaints ANIL JACOB From: Mason Brooks <MBrooks@ablecomm.net> Sent: Wednesday, March 06, 2013 2:10 PM To: 'Anil Jacob' Cc: James Wicker; Scott Brooks Subject: RE: Will Rogers Renovation - ASI # 1 - 3rd Request Anil, Thank you for your quick response. Please let me know if you need any further details. City of Ft Worth Richardson Bass ASI #1 = $ 0.00 Total of six (6) FPI Back Boxes (FSR # FLH2O-0-B) for Richardson Bass = $ 2,688,30 Mason Brooks, CTS Project Manager -. Phone 972.660.2253 Fax 972.660.2254 Toil Free 800.717.7411 Cell: 469.544.7795 mbrooksC8�a blecomm.net 11c+Qii1 •`svigda pjalui'toaitiera;ii QvrrFeed prolc►a:'otiiiiacf Think Green) Before printing this email, think if it is really necessary. From: Anil Jacob rmailto:alacob(Omodernctrs.comj Sent: Wednesday, March 06, 2013 1:15 PM To: Mason Brooks Cc: James Wicker; Scott Brooks Subject: Re: Will Rogers Renovation - ASI # 1 - 3rd Request Please include it but break all items down. Sent from my iPhone On Mar 6, 2013, at 11:16 AM, Mason Brooks <MB, ooks@ablecomm.net> wrote: I Anil, ng ourour submittal process is been found that the floor box part number, FSR FLH2O-OS-C, within the Audio Visual Lege on AVO-0 is for the lid only. Addendum Specification 11770"Sound reinforcement Systems" do s not specify or reference a part number for the floor boxes. Our proposal includes the specified par number shown on AVO-0. Would you like me to include the cost for the back boxes within this ASI or submit as a change order? / L .S'PE w=1#1) UV V DThiti,`I,v i4.;; 77.11.6 prat Co tzace"7 F1 it, . 0-6- 8 Mason Brooks, CTS Project Manager Phone 972.660.2253 <image001.gifs Hahnfeid Hoffer Stanford :otEk/Iu1nQr /j1thiribrA ARCHITECT'S SUPPLEMENTAL INSTRUCTIONS i7c$,L ..• Prol!ct game: .A§1.146..: 01 ownpro,..14 Will Rogers:Mernorial.Oenter Arolibot:l j rifoli4rcleoti 13Ei86' Eidilbits.S pads It:+f)ti'6. Date' 2/19/1a Cori:puitoot;-:f?cl . . 'ConteablOry 1)j Otitift04 'Proleof i‘fa.... ikiokbo, - - Field (x) City -Of PortWOrih. c.).fl-iof ] TIPW..':,F4011it10$.'Mjiiit GtooPlArOhltOOtt01 .,Seit'9104. • Coniraetor: Modern 00Att.00tOrsi g0bB Plkag.Pfly.e: tledfordirD(761 ontraofPor General ConstrucOn F.110 Exl 'COnttitiottE9te: 2/0.5/:13 Submit an :Itemized propp.a1 for .chanes In 1h0 COtift6Ot SO.rti Andialr : COlitriaOt Tirrio fr ft,:i0—prOO.O4gt SCWOOritarliigr(40,031- i_'40r.c.11f1.0flpii,(6yfolhti:OOntr.401.0e4n16.0-.16(i.000112,04.h:f#01,r.b.W11.01.r)•fc.i.4119.•00 (1A'YE10, Oik Opptrckr)r-oNtl :isOrtitt tho.•ri:top,900 HOfp!..-$14nfbrci.,, in Arlrifing,: of the,tiale.,whlotilhb PrOPOsOf.M111 ha'.avbriliftercf,,*.ie WorK;;Oen 6pp,iroVed;thOff be...btirridef ou In adoOrtlahOe.,v41111.;tlie. 4166'3111j-6d 8upplorteildlinstriaoflonkand.in ildOokftiribtVtfijIhiiOtintrAdO0Otirtiiirifp, „ •••—•• . •.- •••. • • ••• • • .• . • . . ...•••••• • . 71.1;11S. IS NPT,ACI:.14NP_E':Qt1PISIT A 0.9.0gT.IIPPTIQN OR6NOE pIgge-ME,,OF.1 41)113aarltmi T9 PROCEED. WITH. THE -WORK bESORitiED.;IN.THE PROPOSED. MoDIFICATION(Sy., . . PcliOriPtIotil;• .A00.0:00_41"4te_AN Ati4bhrfierifs.: • ,p; Ay2,0; AV3 0, And Oataiipc1 vy.tillan: .0e0.-ottption:qcf•oralcin.s.; . • Issie4tMinai4 "tor Stqnfor moot) Tpitlf97.,yfin!gtiygo) Haiti 1-10-17 . Stanford tron6,11./. FOruAry. 18, 2o1-8' EbIfs Space Will-R6gor6 MEirridtiol Contoi. Fort ASI NO..1! ThO 001V00005 advised of the followN; ARCH11701393)kL, fi.ROJECT MANUAL. SpOdifidatitili SOOori .08710 PIN(SH HARDWARE., PargrophA:41,1 Sdhedulbi .HEADING 5, gdd ORAWINa$, 1, ShootAl a.Add. now room -AN ' 11 Os 0.4:stiqw.n. b.y13,4v.jPI9P, .#4 on ri6ddjull4z6Olgubd drqwjrig.5.1:ipo:t, .00hed h.ereto AII A/V tcluIP'OebtAd:.bsEildp.atecl to .1)1,10-.r4P111.- 2. ..5h*A7-1.: a. Add. riow room ii. .as shown. by '13.eyi0prt:#4..on foVibbd full-Olzo_toisauOid OraY.+4.110:0.1.0:0t., attached STRUCTURAL pRAWINOP ',Roy:log $.fiept-a.,41) po'r'flp\i0-On?sm,. on full size ciraWitig.ohoOt., a0-61-1.ed hereto, MEtHANiCAL.J. ELECTRICAL tptu MBi N6 • ORAWi006.. :RovlogoVlootEll perBov.Ision #4 90:4t1).:04od.Wh1thO-eit :6ttAbhOcihO.t0to: .2: .86mItha:$.1-.rpOt E2 1, per Revision #4 pn„..fol!-Oizb drawing het, attached iiereta, 3• Revise'Sheet E41, per Reviion #4 on fult slze drawing allot,i4goohorojp.:. ..„.- • P000 1 11042.-qp ASI NO 1 . . „ AUDIO/VISUAL DRAWINGS 1. Revise. Sheet AVO.O, per Revision #4 on lull size drawing sheet, attached hereto. 2. Revise Sheet AV1.0, per Revision #4 on full size drawing sheet, attached hereto, 3. Revise Sheet AV2,0, per Revision #4 on full size drawing sheet, attached hereto. 4. Revise Sheet AV3,0, per Revision #4 an full size drawing sheet, attached hereto.. ATTACHMENTS: NUMBER OF PAGES/SHEETS Architectural Rai Sle Drawings 2 Structural Full Size Drawings 1 Electrical Full Size Drawings 3 Audio/Visual Full Size Drawings 4 11042.00 END OF ASI NO. 1 EXCEPT ATTACHMENTS ASI NO. 1 Page 2 of 12 �. t- PROPOSAL To: Hahnfeld Hoffer Stanford 200 Bailey Ave, Suite 200 Fort Worth, TX 76107 DATE: 3/28/2013 via email RE: Richardson Bass Exhibit Area Renovations - Will Rogers Memorial Center Modern Proposed Change Order (PCO) # 3, HITS # We hereby propose to supply all supervision, labor, materials, and equipment necessary to complete the following described work. All work will be performed in a professional manner with quality craftsmanship Scone Of Work As per City request to provide cutoff valve and acess panel to provide shutdown for concession stand. The original was continuous line with no cutoff valves to shutdown concessions separately See attached Sub Total Markup - 10% Sub Total Bonds and Insurances $1,420.00 $1,420.00 $142.00 $1,562.00 $46.86 Net Change This Proposal ADD 1,608.86 Net Change in Days This Proposal Acceptance This proposal is accepted and agreed to this date as indicated by the signatures below: For the Owner For�i@,�},rchitect/ For Mo ern Contractors Date Date Date J'4Sr�/3 PIPE CONNECTION PLUMBING CO., INC. Change Order TO: Modern Contractors 2008 Plaza Drive Bedford, Texas-76021 PROJECT: Will Rodgers DATE 2/28/2013 DESCRIPTION OF CHANGE Seperating water line from RR to concession stand. We will install a 1 1/2" water line with cut off valve from existing 2" water line. Then, connect to existing 3/4" water line from underground, going to conce;S/Dd stand with cut off valve and stainless steel access door. Materials pipe, fittings, insulation. $700.00 Rental Labor $448.00 Labor Burden $143.00 Subtotal $1,291.00 OH&P 10% $129.00 Total change -order $1,420,00 Respectfuly-Andrew Rodriguez 4811 MOTLEY DRIVE MESQUITE TX 75150 PH 972/279/2709 FAX 972-686-7195 „ k C)14%4 C rf r 1 i t 's PROPOSAL To: Hahnfeld Hoffer Stanford 200 Bailey Ave, Suite 200 Fort Worth, TX 76107 via email DATE: 3/28/2013 RE: Richardson Bass Exhibit Area Renovations - Will Rogers Memorial Center Modern Proposed Change Order (PCO) # 4, HHS # We hereby propose to supply all supervision, labor, materials, and equipment necessary to complete the following described work. All work will be performed in a professional manner with quality craftsmanship Scone Of Work As per Will Rogers Maintenance request to provide main cutoff valve and bypass valves for water lines to other side of our project area for maintenance. See attached Sub Total Markup - 10% Sub Total Bonds and Insurances $1,434.40 $1,434.40 $143.44 $1,577.84 $47.34 Net Change This Proposal ADD 1,625.18 Net Change in Days This Proposal - Acceptance This proposal is accepted and agreed to this date as indicated by the signatures below: For the Owner Date For the Arr hitect % Date For Modern Contractors Date PIPE CONNECTION PLUMBING CO., INC. Change Order TO: Modern Contractors 2008 Plaza Drive Bedford, Texas-76021 PROJECT: Will Rodgers DESCRIPTION OF CHANGE Install main cut off valves and bypass valves. Materials DATE 3/27/2013 Copper pipe, valves and fittings. $520.00 Labor $594.00 Labor Burden $190.00 Subtotal $1.304,00 OH&P 10% $130.40 Total change -order $1,434.40 Respectfuly-Andrew Rodriguez 4811 MOTLEY DRIVE MESQUITE TX 75150 PH 972/279/2709 FAX 972-686-7195 PROPOSAL To: Hahnfeld Hoffer Stanford 200 Bailey Ave, Suite 200 Fort Worth, TX 76107 via email DATE: 3/28/2013 RE: Richardson Bass Exhibit Area Renovations - Will Rogers Memorial Center Modern Proposed Change Order (PCO) # 5, HIS ASI #2 We hereby propose to supply all supervision, labor, materials, and equipment necessary to complete the following described work. All work will be performed in a professional manner with quality craftsmanship Scone Of Work ASI # 2 - Note 10 indicates to add 120volt circuits to seven doors. Please note that the allowance for security hardware did not specify any electrical work. The hardware schedule indicated the hardware changes for aalowance but electrical drawings or specs did not include and related work for this allowance. See attached $4,570.00 Sub Total Markup - 10% Sub Total Bonds and Insurances $4,570.00 $457.00 $5,027.00 $150.81 Net Change This Proposal ADD 5,177.81 Net Change in Days This Proposal - Acceptance This proposal is accepted and agreed to this date as indicated by the signatures below: For the Owner For the Architfect % For odern Contractors AA/i r o'ircaogt, Date Date 312 <1IA Date STUFFLEBEAM ELECTRIC Change Order #3 Date: March 25, 2013 PROJECT: Will Rogers Memorial Center Richardson -Bass Exhibits Area 1591 Rip Johnson Fort Worth, Texas Changes and additions for ASI#2 include: Furnish one 20 amp 120 volt circuit at seven doors for the access controls. Provide wall conduit and boxes for the card reader and door hardware. Controls and control wiring are not included. Material: $1,135.00 Labor: $2,822.00 Total: $3, 957.00 Overhead 10%: Profit 5%: Total this C.O.: E. STUFFLEBEAM $ 395.70 $ 217.64 $4,570.34 STUFFLEBEAM ELECTRIC (817)284-7405 License Stufflebeam Electric 132 Arbol Court Ft Worth, TX 76108 817-284-7405 License # 22110 Regulated by the Texas Department of Licensing Regulation Po Box 12157 Austin, TX 78711 1-800-803-9202 1-512-463-6599 www.license.state.tx.us/complaints Hahnfeld Hoffer Stanford nrcAlitpc:(4 phinnom / bilevioNs ARCHITECT'S SUPPLEMENTAL INSTRUCTIONS Proleat Namet Wilt Rogers Memorial Center Richardson Baas Exhibits Specie ASI No,: 02 Owner: [x] Architect: t ] Issue Date; 0/08/13 Consultant: tX] Contreetor; [x] Owner: Pro 12042-00 Field: (4 City of Fort Worth Other: [ ] TPW - Facilities Mgmt Group/Architectural &ark/ices Conlractort Modern Contractors, !no:, 2008Flaza Drive Dedford.-TX 70021 Contrast For: General Conetruotion Elle: [x] Contract Datet,2/05/13 Submit an Iterrilzed proposal for changeIn the. Contract Sum and/or Contract Time for the proposed Supplernental InStructIonhodificatIon(s) to the-oontraaclocuments:descrIbed hmin. Within fourteen (14) days, the Contractor .shall submit the '01.0001 or notify Hahnfeld Hoffer Stanford, in WrItIng, of the date Which, the proposal will be .submitted. The Work, when abproved, shal(lcie carried out hi accordance with -the described Supplemental InstruotIons and In accordance with the Contract Documents, THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE, OR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED IN THE PROPOSED MODIFICATIONS), DesCrIptIon: Power and .dlagrarne for.pocepted. Alternate #01 -Aopess control hardWare In ileu of Standard hardware, Attaehments; Revised drawing.sheets E2-1 and E4-1 , Supplemental sheets AS12-1 and ASI2-2. Issqed 1 h fold. Net Stanford: (Sign ITo Le8, A " 14(1.1 ga ,Tr (Mr I air Naine I hilo) A Mar 05, 2013 - 08:53:33 Filename. S:\2011\11042-00 -,NRMC Rich -Boss Mod -\Coast Admin\ASI\ASI#02\Door Access Cantro:s.dwg Updated By. lee Copyright © 2013 Hahnfeld Hoffer Stanford 00-dt'O1.L :ON HOC LOW VOLTAGE ) COMMUNICA11ONS CABLE BY OTHERS 110V POWER IN J—BOX MOUNTED ADJACENT TO POWER SUPPLY POWER SUPPLY AND ACCESS CONTROLLER MOUNTED ABOVE DOOR IN NEW ROOM L 000RS 106.1, 105.1, 101.4, 104.1, 103.1, 101.3 NOTE: ALL WIRING BETWEEN POWER SUPPLY/CONTROLLER AND EACH DEVICE SHALL BE 18 GAUGE/6 CONDUCTOR WIRE 1/2' CONDUIT (TYPICAL) JUNCTION BOX LOCATED WITHIN DOOR FRAME (POWER TRANSFER) (TYP_ OF 2) (1) GANG J—BOX INSTALLED FLUSH IN WALL MOUNIEU HORIZONTAL (CARD READER) ELECTRIC EXIT DEVICE (TYP. OF 2) ELEVATION TWIN LEAF ACCESS CONTROLLED DOOR NOT TO SCALE RICHARDSON - BASS EXHIBITS AREA WILL ROGERS MEMORIAL CENTER FORT WORTH, TEXAS FINISH FLOOR Hahnfeld architects 1425 8th Avenue Hoffer planners Fort Worth, Texas 76104 81fax 817..59 28 Stanford interiors flax 7.429.9336 Mar 14, 2011 - 09:40:12 Filename: S:\2007\07068-03 -Ali Church 13-?t2 Redraw-\Bidding\0wgs\Allchurch-Suposhect.dvrg Updated Br lee Copyright © 2013 Hahnfeld Hoffer Stanford cn n m m 8 0o Z4ot l 'ON 9or POWER SUPPLY AND ACCESS CONTROLLER MOUNTED ABOVE DOOR IN NEW ROOM (1) GANG J—BOX INSTALLED FLUSH IN WALL MOUNTED HORIZONTAL (CARD READER) L • DOOR 101.2 CAT 5 CABLE NO CONDUIT 110V POWER IN J—BOX MOUNTED ADJACENT TO POWER SUPPLY NOTE: ALL WIRING BETWEEN POWER SUPPLY/CONTROLLER AND EACH DEVICE SHALL BE 18 GAUGE/6 CONDUCTOR WIRE 1/2" CONDUIT (TYPICAL) JUNCTION BOX LOCATED WITHIN DOOR FRAME (POWER TRANSFER) ELECTRIC EXIT DEVICE ELEVATION SINGLE LEAF ACCESS CONTROLLED DOOR NOT TO SCALE RICHARDSON - BASS EXHIBITS AREA WILL ROGERS MEMORIAL CENTER FORT WORTH, TEXAS Hahnfeld architects 1425 8th Avenue Hoffer planners Fort Worth, Texas 76104 87 7.921.5928 Stanford interiors fax 81 7.429.9336 A NED 0 FLOOR PLAN - AREA ELECTRICALL,OWER 107#".75 Hahnfeld Hoffer Stanford FLP?* Fcat vIc.rth. 70..4 70107 a:Tglgt ° GENERAL trOTES zutt- RICHARDSON - BASS EXHIBITS AREA • k WILL ROGERS MEMORIAL CENTER FORT WORTH, TEXAS PARTIAL ROO,. E.ECMCAL P..32 Gi E 2 - 1 03 144a Maillkt 131 :24TItti 4-141 t ;02 2 .14 .n.JM r2511g si4 .m4VF, 4 q-- rt:14i 2,k4,42A V.,71 4.46N 2.tii __Ig! Ct tg 2`N Hat j- 2, iJ44Mit tit 1 0, A:23d kittliAUJ.42, ii$45,251; gt 4I '; 4" 3, 41.1414141-141424i4H+1+1 e, HP,An g 11.424n1 44 4 , qi ;iq 31.24.4E/g !!! 44 4: 4444,241 .1 -t „44,- 44 „M y yyvvmS' my vm Yn wY rn yyt, 222' 2 2 2 2 2 gi".21 111 2:2 a ,c7 77 7 7, c77 2- 30 __ "MIrM ti 7, 4102 4-kti ii 2 J F 22, -Jit tt 1M1 .228! 33 dk:R! ! r31 23:6 ;1 RICHARDSON - BASS EXHIBITS AREA 42 4 WILL ROGERS MEMORIAL CENTER FORT WORTH, TEXAS d 23; d ',.,:2 ',2•IVA'i 4 ill:RL Zt ij,43;-4,4], 0,4 1 trT, P; 1 1 Ili PROPOSAL To: Hahnfeld Hoffer Stanford 200 Bailey Ave, Suite 200 Fort Worth, TX 76107 via email DATE: 3/28/2013 RE: Richardson Bass Exhibit Area Renovations - Will Rogers Memorial Center Modern Proposed Change Order (PCO) # 6, HHS RFI #2 We hereby propose to supply all supervision, labor, materials, and equipment necessary to complete the following described work. All work will be performed in a professional manner with quality craftsmanship Scone Of Work Added light fixtures per RFT 2 See attached Sub Total Markup - 10% Sub Total Bonds and Insurances Net Change This Proposal Net Change in Days This Proposal $1,094.94 $1,094.94 $109.49 $1,204.43 $36.13 ADD 1,240.57 Acceptance This proposal is accepted and agreed to this date as indicated by the signatures below: For the Owner Date For the A hitec , For Modem„ Contractors Date Date STUFFLEBEAM ELECTRIC Change Order #2 Date: March 22, 2013 PROJECT: Will Rogers Memorial Center Richardson -Bass Exhibits Area 1591 Rip Johnson Fort Worth, Texas Changes and additions for RFI#2 include: Replace the fluorescent cove Tight fixture in the existing restrooms. Material: $528.00 Labor: $420.00 Total: $948.00 Overhead 10%: $94.80 Profit 5%: $52.14 Total this C.O.: $1094.94 E. STUFFLEBEAM STUFFLEBEAM ELECTRIC (817)284-7405 License Stufflebeam Electric 132 Arbol Court Ft Worth, TX 76108 817-284-7405 License # 22110 Regulated by the Texas Department of Licensing Regulation Po Box 12157 Austin, TX 78711 1-800-803-9202 1-512-463-6599 www.license.state.tx.us/complaints ID" I—:1&Nr PROPOSAL To: Hahnfeld Hoffer Stanford 200 Bailey Ave, Suite 200 Fort Worth, TX 76107 DATE: 3/29/2013 via email RE: Richardson Bass Exhibit Area Renovations - Will Rogers Memorial Center Modern Proposed Change Order (PCO) # 7, HHS # We hereby propose to supply all supervision, labor, materials, and equipment necessary to complete the following described work. All work will be performed in a professional manner with quality craftsmanship Scone Of Work Provide bronze aluminum finish for overhead doors and bronze tinted glass in lieu of standard finishes specified See attached Sub Total Markup - 10% Sub Total Bonds and Insurances Net Change This Proposal Net Change in Days This Proposal $2,600.00 $2,600.00 $260.00 $2,860.00 $85.80 ADD 2,945.80 Acceptance This proposal is accepted and agreed to this date as indicated by the signatures below: For the Owner Date For th,44t.Achitect� Date ` For I?Iodeen Contractors Date / rit OVERHEAD DOOR COMPANY TO: MODERN CONTRACTORS LEONARD VITEK/AJ 817-571-2320/F:817-571-5805 Ivttekmoderncontractors. com RE: WILL ROGERS MEM, CTR. FTW, TEXAS QUANTITY POST OFFICE BOX 182783 ARLINGTON, TEXAS 76096 817-467-4550 METRO 972-641-3080 FAX DESCRIPTION QUOTATION DATE 3.28.13 QUOTE NUMBER DELIVERY 3WKS/ ARO TERMS 30 DAYS 1 EA, 11'10"W X 10'9"H C.H.I. MODEL 902 BRONZE ANODIZED ALUMINUM SECTIONAL DOOR, ALL SECTIONS GLAZED WITH 1/2" INSULATED BRONZE TINTED GLASS, INSIDE SLIDE LOCK, 3" TRACK WITH STANDARD LIFT, FULL WEATHER SEAL, 50,000 CYCLE SPRINGS, MANUAL OPERATION. 1 EA. 1 EA. 1 EA. 11'8"W X 10'9"H SAME 12'8"W X 10'9"H SAME 12'2"W X 11'9"H SAME, EXCEPT LOW HEADROOM TRACK -INSTALLATION INCLUDED, NO TAX APPLIED. "SAFETY TRAINING EXCLUDED* *QUOTE GOOD FOR 90 DAYS* IF ACCEPTABLE PLEASE SIGN AND RETURN BY FAX OR EMAIL ACCEPTED: SIGNED: original bid change Doug Short AMOUNT $13,600,00 $11,000.00 $2,600.00