City of Fort Worth
Change Order Request
CITY SECRETARY ) jiCONTRACT NO.. ('/ zI --/. 0
Project Name' East Rosedale - US287 to Miller Ave. I City Sec # I 44218
Client Project #(s)I C116-541200-02116021222,C200-541200-205230014283,P253-541200-605170014283,P258-541200-705170014283,P221
Project Description
Water- Sewer- Storm Drain- Paving- Street Light- Signal Light -Fiber- Bridge Improvements
Contractor Jackson Construction
City Project Mgr.J Dena Johnson
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
Change Order # I 2 I Date
City Inspector I Mike Myers
TPW Water
$12,135,268.40 $2,344,405.00
$13,987.27 $7,965.53
$12,149,255.67 $2,352,370.53
$ 0,4o6.82 $ll.00
$12, 79,662.40 $2,352,370.0
$497,674.01 $65,000.50
$483,686.74 $57,034.97
Sewer
$621,215.00
$621,215,00
$0.00
01,215.00
$17,500.00
$17,500.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
Totals
$15,100,888.40
$21,952.80
$15,122,841.20
30,406.82
$15,153,248.02
$580,174.51
$558,221.71
0.35%
$18,876,110.t0
9/10/2013
Select Day Typel
600
10
610
90
700
RD
During construction, it was determined that a gas pipeline owned by Texas Midstream-SENE1A RY
Services, LLC,(TMGS) is in conflict with the pier structure at the bridge approach being FT WORTH,1'X
reconstructed in conjunction with the ongoing East Rosedale project.
TMGS is required by its easement Agreement with the City to relocate the gas pipeline at its
expense to accommodate the bridge construction. TMGS has requested that it be allowed to
leave the gas pipeline in its current location in exchange for paying for all additional costs
associated with the redesign and construction of the proposed bridge approach. Staff reviewed
and accepted the request.
This change order will provide additional pay item quantities for the relocation of the proposed
bridge
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Oyddr. /
ji
Jackson Construction
A
/ �' if dci '1-1,
Irispe for/Inspection,S,upetvisor,
Pirector
Assistan
ECEI\f ED SEP 27 '1013
`J j lral? ul_ii1 1< ;-41Ar
rI lli- ;i�� entmGtl i� i ri 1 ;:l. i ,r O.',
MC Number I G -t i loot*
%7
'y J. K
s/ , City
cretaxy
Apex o
\JoOo,/o��ooc�rco .rA
a
Date:Sit
ZG /3
FORT WORTH
City of Fort Worth
Change Order Additions
Project Name I East Rosedale - US287 to Miller Ave. I City Sec # I 44218
Client Project # I C116-541200-02116021222,C200-541200-205230014283,P253-541200-605170014283,P258-541200-705170014283,P227-
Project Description
Water- Sewer- Storm Drain- Paving- Street Light- Signal Light -Fiber- Bridge Improvements
Contractor Jackson Construction Change Order #
City Project Mgr. Dena Johnson
ADDITIONS
II EN UtSUh II- I IUN
V-1 / UL U Uoncrete (Abut) I PVV
V-18 CL S Concrete (Appr Slab) TPW
V-19 Rail (TY C411) TPW
V-20 Cement Stabalized Backfill @ Abutment TPW
V-21 Removal- Approach Slab TPW
V-22 Embankment/ Acceptable Backfill for Abutments TPW
V-23 Armor Joint TPW
411033'1 Mr10�dd
City Inspector
DEl-' I
2
Mike Myers
Date I 9/10/2013
(Ay Unit Unit lost I otal
86.1U UY $1,495.UU 8128,/19.bU
179.30 CY $667.00 $119,693.1U
208.00 LF $237.00 $49,296.UU
40.00 CY $225.00 $9,000.UU
185.00 SY $21.00 $3,885.UU
120.00 CY $15.00 $1,8UU.UU
49.60 LF $110.00 $b,4bb.UU
Change Order Additions Page 3 of 7
TPW $317,749.60
Water $0.00
Sewer $0.00
Sub Total Additions $317,749.60
Change Order Additions Page 4 of 7
FORT WORTH
City of Fort Worth
Change Order Deletions
Project Name East Rosedale - US287 to Miller Ave. I City Sec # J 44218
Client Project # 1 C116-541200-02116021222,C200-541200-205230014283,P253-541200-605170014283,P258-541200-705170014283,P227-
Project Description Water- Sewer- Storm Drain- Paving- Street Light- Signal Light -Fiber- Bridge Improvements
Contractor Jackson Construction I Change Order # Date I 9/10/2013
City Project Mgr. 1 Dena Johnson
I I EIVI UESUNII- I IUN
V-b Unll Shaft (3b")
V-9 Reinforced Concrete Slab
V-10 Prestressed Concrete Girder (TX40)
V-11 Concrete Surface Treatment (Class 1)
V-5 Drill Shaft (18")
V-7 CL C Concrete (Abutment)
V-8 CL S Concrete (Approach Slab)
V-14 Rail (TYT411)
adO31ti '19I
City Inspector
DELETIONS
2
Mike Myers
UEI-) I Uty Unit Unit cost I otal
I I-'VV 33.UU LI- $1 /B.UU $5,8/4.UU
TPW 680.00 SF $29.50 $20,060.00
TPW 99.98 LF $186.00 $18,59b.26
TPW 85.00 SY $2.50 $212.50
TPW 80.00 LF $45.00 $3,bUU.UU
TPW 90.00 CY $1,400.00 $12b,000.UU
TPW 110.00 CY $630.00 $b9,3UU.UU
TPW 230.00 LF $190.00 $43,/UU.UU
Change Order Deletions Page 5 of 7
TFW $287,342.78
Water $0.00
Sewer $0.00
Sub Total Deletions $287,342.78
Change Order Deletions Page 6 of 7
MWWBE Breakdown for this Change Order
MWBE Sub
1
Type of Service I Amount for this CO I
Total
Previous Change Orders
CO #
DATE
1
AMOUNT
1
Total
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
PROJECT SUMMARY SHEET
(Change Order Attachment)
PROJECT NAME: East Rosedale - US287 to Miller Ave
PROJECT LIMITS: US287 to Miller Ave
CS. No.: CS44218
D.O.E. No.:
Attachment to Change C 2
Today's Date: 9/18/2013
Contract Time
TOTAL TPW Water Sewer (Days)
Original Contract Amount: $ 15,100,888.40 $ 12,135,268.40 2,344,405.00 621,215.00 600
Extras to Date: $ 21,952.80 $ 13,987.27 $ 7,965.53 10
Credits to Date: $ i`•
Contract Amount to Date: $ 15,122,841.20 $ 12,149,255.67 2,352,370.53 621,215.00 610
Amount of Proposed Change Order: $ 30,406.82 $ 30,406.82 90
Revised Contract Amount: $ 15,153,248.02 $ 12,179,662.49 2,352,370.53 621,215.00 700
Contingency Funds Avail. for Admin. 1 $ 497,674.01 $ 497,674.01 65,000.50 17,500.00
Remaining Funds Available for Chanc $ 558,221.71 $ 483,686.74 57,034.97 17,500.00
Additional Funding (if necessary): $ - $
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
M&C Review
Page 1 of 2
Official site of the City of Fort Worth, Texas
FORT WORT I l
COUNCIL ACTION: Approved on 9/10/2013 - Ordinance No. 20893-09-2013
DATE: 9/10/2013 REFERENCE NO.: **C-26419 LOG NAME:
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of an Agreement with Texas Midstream Gas Services, LLC, in the
Amount of $74,606.82 for Recovery of the City's Design and Construction Costs Resulting
from a Gas Pipeline Conflict with the Sycamore Park Bridge on East Rosedale Street and
Adopt Appropriation Ordinance (COUNCIL DISTRICT 8)
20E ROSEDALE -
MIDSTREAM
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the execution of an Agreement with Texas Midstream Gas Services, LLC, in the amount
of
$74,606.82 for recovery of the City's design and construction costs resulting from a gas pipeline
conflict
with the Sycamore Park Bridge on East Rosedale Street;
2. Authorize the acceptance of payment in the amount of $74,606.82 for the additional costs
associated
with the redesign and construction to remediate the gas pipeline conflict; and
3. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in
the
Street Improvements Fund in the amount of $74,606.82.
DISCUSSION:
On February 12, 2013, (M&C C-26098) the City Council authorized execution of a contract with
Jackson Construction, Ltd, in the amount of $16,589,133.65 for the construction of East Rosedale
Street from Miller to U.S. Highway 287. The project includes the reconstruction of the east approach
of the Sycamore Park Bridge at the western limits of the project.
During construction, it was determined that a gas pipeline owned by Texas Midstream Gas Services,
LLC, is in conflict with the pier structure at the bridge approach being reconstructed in conjunction
with the ongoing East Rosedale project.
Texas Midstream Gas Services is required by its easement Agreement with the City to relocate the
gas pipeline at its expense to accommodate the bridge construction. TMGS has requested that it be
allowed to leave the gas pipeline in its current location in exchange for paying for all additional costs
associated with the redesign and construction of the proposed bridge approach. Staff and its design
consultant, Freese and Nichols, have reviewed TMGS's request and find it acceptable.
The anticipated construction changes will be accomplished through a construction change order with
Jackson Construction, Ltd.
FISCAL INFORMATION/CERTIFICATION:
The Financial Services Director certifies that upon approval of the recommendations and adoption of
the attached appropriation ordinance, funds will be available in the current capital budget, as
appropriated, of the Street Improvements Fund. Transportation and Public Works is responsible for
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=1 8 8 91 &councildate=9/1 0/20 13 9/24/2013
M&C Review Page 2 of 2
collection of these funds.
TO Fund/Account/Centers
3) C200 531200 205230014230 $44.200.00
3) C200 541200 205230014230 $30,406.82
2&3) C200 488100 $44,200.00
205230014230
2&3) C200 488100 $30.406.82
205230014230
FROM Fund/Account/Centers
Submitted for City Manaaer's Office bv: Fernando Costa (6122)
Oriainatina Department Head: Douglas W. Wiersig (7801)
Additional Information Contact: Dena Johnson (7866)