Loading...
HomeMy WebLinkAboutContract 44218-CO3 (2)FORT WORTH.. City of Fort Worth Change Order Request Project Name' East Rosedale - US287 to Miller Ave. Client Project#(s)I C116-541200-02116021222,C200-541200-205230014283,P253-541200-605170014283,P258-541200-705170014283,P227! Project Description' Water- Sewer- Storm Drain- Paving- Street Light- Signal Light -Fiber- Bridge Improvements Contractor) Jackson Construction City Project Mgr.j Dena Johnson Dept. Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date (Amount of Proposed Change Order evised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) TPW $12,135,268.40 $44,394.09 $12,179,662.49 $0.00 $12,179,662.49 $497,674.01 $453,279.92 Change Order# City Inspector Water $2,344,405.00 $7,965.53 $2,352,370.53 $0.00 $2,352,370.53 $65,000.50 $57,034.97 CITY SECRETARY CONTRACT NO 0 City Sec # I 44218 13 I I Mike Myers Sewer $621,215.00 $621,215.00 $49,870.00 $671,085,00 $17,500.00 $17,500.00 $32,370.00 CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) JUSTIFICATION (REASONS) FOR CHANGE ORDER During construction of the 8-inch sewer main Line-D , the contractor encountered a conflict with multiple duct ban belong to AT&T. In order to clear the conflict , it was necessary to redesign the segment of the line and to install an additional depth of 8.5 foot . Date Totals $15,100,888.40 $52,359.62 1/7/2014 Select Day Type 600 100 $15,153,248.02 700 $49,870.00 $15,203,118.02 $580,174.51 $527,814.89 $32,370.00 0.68% $18,876,1 This change order will compensate the contractor the following pay items for installing the sewer main at the addition -Exploritory excavation of existing utilities in relation to the extra depth of line "D" A -Connection to existing manhole -Diggi through 8,5-feet _of solid=rec Staff I11i8tfto ri v� f tl gut the d CITY SECRETARY FT. !NORTH, TX for backfill`r'�/ west for the additional calendar days on the project foY the.a 71/7 naew8rk. City Secretary 10 710 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company Name Jackson Construction Inspector/,Inspection Supervisor Assistant Assi M&C Number I �� Cort*ritor(Name)/ / `:/ 2,!/fi' Date Proj 0/// /•r oily SA.. ru 14 rir Ani,., 4.'Atc4 / O 'Fr N Jl� I /� Date Assist nt City Managr , he t•t5•LY Council Action (if required) M&C Date Approved csen)Aitin 44 /%/ Manager/Program Manager Date Dicttr, Contracting Department (Dept) ? /A I Date Date /J////y Date 3//4 RECEIVED JAN 14 2014 FORT WORTH Project Name Client Project # Project Description City of Fort Worth Change Order Additions East Rosedale - US287 to Miller Ave. I City Sec # I 44218 C116-541200-02116021222,C200-541200-205230014283,P253-541200-605170014283,P258-541200-705170014283,P227- I Water- Sewer- Storm Drain- Paving- Street Light- Signal Light -Fiber- Bridge Improvements Contractor Jackson Construction City Project Mgr. I Dena Johnson Change Order # 3 City Inspector I Mike Myers Date I 1/7/2014 ADDITIONS l 1 EIA UESCINII- I IUN UEN 1 Ulty Una Unit host I otal 34 Sanitary Sewer- Kb' Extra uepth by Upen eut Sewer 1.UU LS $49,8/U.UU $49,8/U.UU Change Order Ac-ditions Page 3 of 7 TPW Water Sewer Sub Total Additions $0.00 $0,00 $49,870.00 $49,870.001 Change Order Additions Page 4 of 7 FORT WORTH City of Fort Worth Change Order Deletions Project Name East Rosedale - US287 to Miller Ave. I City Sec # ! 44218 Client Project # 1 C116-541200-02116021222,C200-541200-205230014283,P253-541200-605170014283,P258-541200-705170014283,P227- I Project Description Water- Sewer- Storm Drain- Paving- Street Light- Signal Light -Fiber- Bridge Improvements Contractor Jackson Construction City Project Mgr. Dena Johnson I Change Order # 3 City Inspector I Mike Myers Date I 1/7/2014 DELETIONS Ul=SI:kIN I IUIV UEN I ... 11tV . Unit • . Unit Lost 'I otal Change Order Deletions Page 5 of 7 TPW Water LSewer Sub Total Deletions $0.00 $0.00 $0.00 Change Order Deletions Page 6 of 7 MWWBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total Previous Change Orders $0.00 co# DATE AMOUNT