Change Order Request
Project Name' Avondale -Haslet Road - East From Water Tank Site to Willow Creek Drive
Client Project #(s)I 01414
Project Description
Paving, drainage and street light improvements
Contractorl Conatser
City Project Mgr.l Leon Wilson
CITY =MAW
commamoor_11
City Sec # I 44102
Change Order# I 1 I Date I 1/16/2014
City Inspector I Tom Miller
Contract Time
Dept. TPW Water Sewer Totals (CD)
Original Contract Amount $1,988,779.45 $0.00 $0.00 $1,988,779.45 270
Extras to Date $0.00
Credits to Date $0.00
Pending Change Orders (in M&C Process) $0.00
Contract Cost to Date $1,988,779.45 $0.00 $0.00 $1,988,779.45 270
Amount of Proposed Change Order $220,674.05 $0.00 $0.00 $220,674.05 231
Revised Contract Amount $2,209,453.50 $0.00 $0.00 $2,209,453.50 501
Original Funds Available for Change Orders $59,660.00 $59,660.00
Remaining Funds Available for this CO $59,660.00 $0.00 $0.00 $59,660.00
Additional Funding (if necessary) $161,014.05 $161,014.05
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
The original contract provided for an asphalt transition at Willow Creek Drive, but after the project began it was determined that it would be
better to extend the transition beyond Willow Creek Drive. The additional days are needed due to the additional bid items and delays as a
result of franchise utility relocations and additional railroad coordination. Also, this project began concurrently with the Wal-Mart portion of
Avondale -Haslet Rd. After construction began the primary focus wa ; . • • in completing the portion of Avondale -Haslet included in the
4.
Wal-Mart CFA, so that the opening of the store would not be t i "• •};, paving � have the same avin contractor. The revised
completion date with the added days is June 27, 2014. 41,
• £t
11.10%
$2,485,974.31
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TY
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
Conatser
Assistant Direct
Assistan
M&C Number I C-26587
LIZ
Contractor (Name) Contract Signajure
--,/-- G,__.
Date,/ rpPArojec}IrflManager/Program Manager
` \-JJ1 .'/7`-( /, rJ
Date Dir c Co tractmg Department (Dept)
3-3 -14 V (.--J , 0
Date Assistant ,ity Manager
-11-1 if
Council Action (if required)
M&C Date Approved I 12/10/2013
Date
2 - 24. -2ot`f
Date
Z- 27-14-
Date
314/f4
Date
3/4/4
RECEIVED MAR 0 6 2014
FORT WORTH
City of Fort Worth
Change Order Additions
Project Name Avondale -Haslet Road - East From Water Tank Site to Willow Creek Drive
Client Project # 01414
Project Description
Paving, drainage and street light improvements
Contractor 1 Conatser
City Project Mgr. 1 Leon Wilson
ADDITIONS
I 1 EM UESU IP I ION
Paving 10 3" Asphalt Pvmt I ype U
Paving 11 6" Flex Base, Type D, GR-1
Paving 16 8" Lime Treatment (42lb/sy)
Paving 17 Lime
Paving 2 10" Conc Pvmt (3600 psi)
Paving 18 4" Conc Sidewalk
Paving 14 Unclassified Excavation
Paving 15 Fill
Paving 22 TxDOT Pedestrian Rail
Paving 23 Manhole Adjustment, Minor
Paving 4 6" Gravel Driveway
Paving 44 Relocate mailbox (CO#1)
Demo 5 6"-12" Tree Removal
Paving 45 Relocate monument sign (CO#1)
Change Order# 1
City Inspector I Tom Miller
City Sec # ! 44102
Date I 1/16/2014
DEP I Uty Unit Unit Cost I otal
I PVV bbb.U0 SY $ 18.00 $11,1 /0.U0
TPW 565.00 SY $ 6.75 $3,813./b
TPW 3,530.00 SY $ 3.00 $1(.1,b90.UU
TPW 74.13 TN $ 160.00 $11,661).8U
TPW 2,790.00 SY $ 45.00 $'L25 550.00
TPW 1,730.00 SF $ 3.00 $5,190.00
TPW 1,180.00 CY $ 9.00 $10,620.00
TPW 704.00 CY $ 4.00 $2,816.00
TPW 23.00 LF $ 75.00 $1,/2b.U1)
TPW 2.00 EA $ 300.00 $600.00
TPW 600.00 SF $ 3.00 $1,800.00
TPW 1.00 EA $ 500.00 $500.00
TPW 9.00 EA $ 300.00 $2,700.00
TPW 1.00 EA $ 5,500.00 $b,bkU.UU
Drainage 19 15" RCP, Class III TPW 130.00 LF $ 50.00 $l ,bU0.00
Drainage 2 21" RCP, Class III TPW 110.00 LF $ 60.00 $6,600.00
Drainage 20 21" Slotted Drain TPW 40.00 LF $ 90.00 $3,6UU.00
Drainage 17 Medium Stone Riprap, dry TPW 41.00 SY $ 75.00 $3,0/b.UU
Drainage 21 PSET SP TXDOT TPW 1.00 EA $ 2,000.00 $2,000.00
Drainage 22 Topsoil & Sod TPW 60.00 SY $ 5.00 $3UU.UU
Drainage 23 Remove Ex 30" RCP TPW 50.00 LF $ 20.00 $1,0U0.UU
Drainage 24 21" CMP TPW 40.00 LF $ 55.00 $2,2U0.00
S&PM 4 4" SLD Pvmt Marking Paint (Y) TPW 924.00 LF $ 0.50 $462.00
S&PM 11 REFL Raised Marker TY II -A -A TPW 12.00 EA $ 4.25 $b1.00
S&PM 2 8" SLD Pvmt Marking Paint (W) TPW 492.00 LF $ 1.00 $492.01)
S&PM 9 REFL Raised Marker TY I-C TPW 13.00 EA $ 4.50 $b8.b0
Change Order Additions Page 1 of 2
S&PM 6 Lane Legend Arrow
S&PM 7 Lane Legend Only
S&PM 14 4" SLD Pvmt Marking Paint (W)
TPW
TPW
TPW
2.00 EA $ 100.00 $200.00
2.00 EA $ 110.00 $220.00
960.00 LF $ 0.50 $480.00
TPW $220,674.05
Water $0.00
Sewer $0.00
Sub Total Additions $220,674.05
Change Order Additions Page 2 of 2
FORT WORTH
City of Fort Worth
Change Order Deletions
Project Name I Avondale -Haslet Road — East From Water Tank Site to Willow Creek Drive
Client Project # I 01414
Project Description Paving, drainage and street light improvements
Contractor Conatser
City Project Mgr. I Leon Wilson
I I EIVI
Change Order #
1
City Inspector I Tom Miller
City Sec # I 44102
Date I 1/16/2014 I
DELETIONS
DESCKIP I ION DEP I city Unit Unit Cost 1 otal
Change Order Deletions Page 1 of 2
TFW $0.00
Water $0.00
Sewer $0.00
Sub Total Deletions
Change Order Deletions Page 2 of 2
MWBE Sub
Robert Granados Trucking
CO #
MIWBE Breakdown for this Change Order
Type of Service Amount for this CO
Haul Off -Trucking $15,000.00
Previous Change Orders
DATE
Total $15,000.00
AMOUNT
Total $0.00
M&C Review Page 1 of 2
Official site of the City of Fort Worth, Texas
CITY COUNCIL AGENDA FORTH
COUNCIL ACTION: Approved on 12/10/2013
REFERENCE 20AVONDALE HASLET
**
DATE: 12/10/2013 NO.: C-26587 LOG NAME: EAST CO 1
PUBLIC
CODE: C TYPE: CONSENT HEARING: NO
SUBJECT: Authorize Execution of Change Order No. 1 to City Secretary Contract No. 44102 with
Conatser Construction TX, LP, in the Amount of $220,674.05 for the Construction of
Avondale -Haslet Road from the Water Tank Site to Willow Creek Drive, Thereby Increasing
the Total Contract Amount to $2,209,453.50 (COUNCIL DISTRICT 7)
RECOMMENDATION:
It is recommended that the City Council authorize the execution of Change Order No. 1 to City
Secretary Contract No. 44102 with Conatser Construction TX, LP, in the amount of $220,674.05 for
the construction of Avondale -Haslet Road from the Water Tank Site to Willow Creek Drive, thereby
increasing the total contract amount to $2,209,453.50.
DISCUSSION:
This City Project No. 01414 provides for the construction of Avondale -Haslet Road from 700 feet east
of Haslet Court (Water Department Tank Site) to Willow Creek Drive as a four -lane undivided
roadway. Construction is funded from the Street Improvements 2008 Fund.
This change order is needed for additional concrete pavement and storm drainage in Willow Creek
Drive. The original contract provided for an asphalt transition at Willow Creek Drive, but after the
project began it was determined that it would be better to construct the transition of concrete.
The net effect of proposed Change Order No. 1 is as follows:
Original Contract
Proposed Change Order No. 1
Revised Contract Amount
TPW AMOUNT
$ 1,988,779.45
$ 220,674.05
$ 2,209,453.50
M&C NUMBER
C-26062
N/A
APPROVED M&C
01/15/2013
Pending
M/WBE Office - Conatser Construction TX, LP, is in compliance with the City's Business Diversity
Ordinance by committing to an additional seven percent MBE participation on this change order No. 1.
The City's MBE goal on this change order is five percent.
Staff has reviewed this change order and considers it to be fair and reasonable.
This project is located in COUNCIL DISTRICT 7, Mapsco 4V and 5S.
http://apps.cfwnet.org/council_packet/mc review.asp?ID= 1 91 6 1 &councildate=1 2/1 0/20 13 2/27/2014
M&C Review Page 2 of 2
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies funds are available in the current capital
budget, as appropriated, of the Street Improvements 2008 Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
C204 541200 207230141483 $220,674.05
Submitted for Citv Manaaer's Office bv: Fernando Costa (6122)
Oriainatina Department Head: Douglas W. Wiersig (7801)
Additional Information Contact: Leon Wilson (8883)
ATTACHMENTS
Location Mao 1.odf
http://apps.cfwnet.org/council_packet/me review.asp?ID=1 9161 &councildate=12/10/2013 2/27/2014
FORT WORTH,, City of Fort Worth
Change Order Request
Project Name' Avondale -Haslet Road - East From Water Tank Site to Willow Creek Drive
Client Project #(s)I 01414
Project Description) Paving, drainage and street light improvements
Contractor Conatser
City Project Mgr.I Leon Wilson
City Sec # I 44102
Change Order# I 1 I Date I 1/16/2014
City Inspector I Tom Miller
Dept. TPW Water Sewer Contract Time
Totals (CD)
Original Contract Amount $1,988,779.45 $0.00 $0.00 $1,988,779.45 270
Extras to Date $0.00
Credits to Date $0.00
Pending Change Orders (in M&C Process) $0.00
Contract Cost to Date $1,988,779.45 $0.00 $0.00 $1,988,779.45 270
!Amount of Proposed Change Order $220,674.05 $0.00 $0.00 $220,674.05 231
Revised Contract Amount $2,209,453.50 $0.00 $0.00 $2,209,453.50 501
Original Funds Available for Change Orders $59,660.00 $59,660.00
Remaining Funds Available for this CO $59,660.00 $0.00 $0.00 $59,660.00
Additional Funding (if necessary) $161,014.05 $161,014.05
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT I 11.10%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) 11 $2,485,974.31
JUSTIFICATION (REASONS) FOR CHANGE ORDER
The original contract provided for an asphalt transition at Willow Creek Drive, but after the project began it was determined that it would be
better to extend the transition beyond Willow Creek Drive. The additional days are needed due to the additional bid items and delays as a
result of franchise utility relocations and additional railroad coordination. Also, this project began concurrently with the Wal-Mart portion of
Avondale -Haslet Rd. After construction began the primary focus was placed on completing the portion of Avondale -Haslet included in the
Wal-Mart CFA, so that the opening of the store would not be delayed. Both projects have the same paving contractor. The revised
completion date with the added days is June 27, 2014.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
Conatser
/
I Iryector/,Ig/speG i� �Sup�fvisor
r Assistant Director (Dept)
Assistarlt-9ty•At@y
M&C Number I C-26587 I
Contractor (Name)
Contract Signature
Date
Projec) Manager/Program )tanager Date
tib ! 17- 1 4'77 i //i / �• i i a7 — t,(
Date DirQctdr Contracting Department (Dept) Date
). i _ 1'
Date Assistant ttity Manager
Date
Council Action (if required)
M&C Date Approved I 12/10/2013
FORT WORTH, : City of Fort Worth
Change Order Request
Project Name' Avondale -Haslet Road — East From Water Tank Site to Willow Creek Drive
Client Project #(s)I 01414
Project Description
Paving, drainage and street light improvements
Contractor) Conatser
City Project Mgr.I Leon Wilson
City Sec # I 44102
Change Order# I 1 I Date I 1/16/2014
City Inspector I Tom Miller
Dept. TPW Water Sewer
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
Totals
$1,988,779.45 $0.00 $0.00 $1,988,779.45
$0.00
$0.00
$0.00
$1,988,779.45 $0.00
$220,674.05 $0.00
$2,209,453.50 $0.00
$59,660.00
$59,660.00 $0.00
$161,014.05
$0.00 $1,988,779.45
$0.00 $220,674.05
$0.00 $2,209,453.50
$59,660.00
$0.00 $59,660.00
$161,014.05
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
11.10%
$2,485,974.31
Contract Time
(CD)
270
270
231
501
JUSTIFICATION (REASONS) FOR CHANGE ORDER
The original contract provided for an asphalt transition at Willow Creek Drive, but after the project began it was determined that it would be
better to extend the transition beyond Willow Creek Drive. The additional days are needed due to the additional bid items and delays as a
result of franchise utility relocations and additional railroad coordination. Also, this project began concurrently with the Wal-Mart portion of
Avondale -Haslet Rd. After construction began the primary focus was placed on completing the portion of Avondale -Haslet included in the
Wal-Mart CFA, so that the opening of the store would not be delayed. Both projects have the same paving contractor. The revised
completion date with the added days is June 27, 2014.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
Conatser
Inspector/Inspectign Supervisor
Assistant DireOtoi (Dept)
Contractor (Name)
D te.
Date
Date
Assi tapt.gity,AtyQmey
M&C Number I C-26587 I
Contract Signature 1 Date
Project Manager/Program Manager
Director, Contracting Department (Dept)
Assistant City Manager
Council Action if required)
M&C Date Approved I 12/10/2013 I
Date
Date
Date
3/.p/i*
FORT WORTH: City of Fort Worth
Change Order Request
Project Name' Avondale -Haslet Road — East From Water Tank Site to Willow Creek Drive
Client Project #(s)I 01414
Project Description
Paving, drainage and street light improvements
Contractor) Conatser
City Project Mgr. 1 Leon Wilson
City Sec # l 44102
Change Order # l 1 I Date l 1/16/2014
City Inspector l Tom Miller
Contract Time
Dept. TPW Water Sewer Totals (CD)
Original Contract Amount $1,988,779.45 $0.00 $0.00 $1,988,779.45 270
Extras to Date $0.00
Credits to Date $0.00
Pending Change Orders (in M&C Process) $0.00
Contract Cost to Date $1,988,779.45 $0.00 $0.00 $1,988,779.45 270
!Amount of Proposed Change Order $220,674.05 $0.00 $0.00 $220,674.05 231
Revised Contract Amount $2,209,453.50 $0.00 $0.00 $2,209,453.50 501
Original Funds Available for Change Orders $59,660.00 $59,660.00
Remaining Funds Available for this CO $59,660.00 $0.00 $0.00 $59,660.00
Additional Funding (if necessary) $161,014.05 $161,014.05
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 11.10% I
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%) $2,485,974.31 Ij
JUSTIFICATION (REASONS) FOR CHANGE ORDER
The original contract provided for an asphalt transition at Willow Creek Drive, but after the project began it was determined that it would be
better to extend the transition beyond Willow Creek Drive. The additional days are needed due to the additional bid items and delays as a
result of franchise utility relocations and additional railroad coordination. Also, this project began concurrently with the Wal-Mart portion of
Avondale -Haslet Rd. After construction began the primary focus was placed on completing the portion of Avondale -Haslet included in the
Wal-Mart CFA, so that the opening of the store would not be delayed. Both projects have the same paving contractor. The revised
completion date with the added days is June 27, 2014.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name I Contractor (Name) I Contract Signature
Conatser
Inspector/Inspection Supervisor Date Project Manager/Program Manager
Assistant Director (Dept) Date Director, Contracting Department (Dept)
Assistant City Attorney Date Assistant City Manager
Council Action (if required)
M&C Number I C-26587 l M&C Date Approved I 12/10/2013