HomeMy WebLinkAboutContract 55162-CO2 CSC No. 55162-CO2
FORT WORTH. City of Fort Worth
Change Order Request
Project Name 2021 Resurfacing Project City Sec# 55162
Client Project#(s) 102864
Project Description Pulverization of existing street and 3 inch asphalt overlay at various locations
Contracto Peachtree Construction Ltd Change Order# 2 Date 7/5/2022
City Project Mgr. Tariqul Islam City Inspector Robert Riley
Contract Time
Dept. TPW Totals (CD)
Original Contract Amount $1,563,752.00 $1,563,752.00 230
Extras to Date $54,481.20 $54,481.20 30
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,618,233.20 $1,618,233.20 260
Amount of Proposed Change Order $44,428.25 $44,428.25 80
Revised Contract Amount $1,662,661.45 $1,662,661.45 340
Original Funds Available for Change Orders $100,000.00 $100,000.00
Remaining Funds Available for this CO $45,518.80 $45,518.80
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 6.33%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,954,690.00
JUSTIFICATION(REASONS)FOR CHANGE ORDER
This change order is to add$44,428.25 and 80 calendar days to contract#55162 with a revised contract amount of$1,662,661.45. During
construction it was identified that Slate St and Redbud Ln need additional curb&gutter than estimated quantities to address drainage issue.Clayton Rd was identified a major
drainage issue at intersection of Woodstock Rd.As a result additional valley gutters are required to install at this location.The contract is also required to add sidewalk and ramps
more than the estimated quantities at various locations.The major items included in this change order are:1200 LF curb and gutter,900 SF sidewalk,165 SF valley gutter,472
SF curb ramps and 230 CY unclassified excavation.This change order also delete following major items:1500 SY 3 inch paving,4 tree removal and 1200 SY sodding work as
these are not needed to complete the contract.
This change order is proposed to add 80 calendar days to the contract.Below is a breakdown of the delays:
1.Scope increase(50 days):To install additional curb and gutter,valley gutter,sidewalks and curb ramps in several locations.2.Delay in cement availability(15 days):cement
supplier had delay in supplying cement for pavement stabilization at Rockwood Park Dr,and 3.Crew engaged in emergency work(15 days):Contractor's crew were engaged to
address emergency pavement repair work caused by water main break during winter frost in February 2022 per request of water department.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements.
Contractor's Company Name Contractor(Name) Contract Signature Date
Peachtree Construciton Ltd. Brendan Taylor 8°a"dan Taylor Jul 13,2022
Inspector/Inspection Supervisor Project and Contract Compliance Manager
t,e Jul 14,2022 7Date
Program Manager Date Senior Capital Project Officer
P6 Jul 14,2022 L3.
Assistant Director(Dept) Date Director,Contracting Department(Dept)
llywe Jul 15,2022 Jul 15,2022
Date JAssistant City Manager Date
og Jul 19,2022 �e o' 111
Jul 19,2022
Council Action(if required)
M&C Number M&C Date Approved
ATTEST:
� eta t aaala/L �,p"d IF OR?.
o,aaa.w coP A7 0000000
0
6iOFFICIAL RECORD
�d�lannette Goodall,City Secretary PA o° o.p
0
o d
�vo o=A CITY SECRETARY
% �o 000000000
a FT. WORTH, TX
�a4Exps�aa
FORTWORTH City of Fort Worth
v---- Change Order Additions
Project Name 2021 Resurfacing Project City Sec# 55162 ###
ClientProject# 102864
Contractor Pulverization and asphalt overlay at various locations PM Tariqul Islam InspectorF Robert Riley
Peachtree Construction Ltd O2 Date 7/5/2022 4/1/2022
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
"GONG CURB AND GUTTER TPW 1,200.00000000 LF $37.00
TPW 21b.UUUUUUUU SF
7 3213.0301 4"CONC SIDEWALK TPW 900.00000000 SF $6.30
REMOVE CONC VALLEY GUTTER TPW 140.00000000 SF
10 3216.0301 7"CONC VALLEY GUTTER TPW 165.00000000 SF $113.50
BARRIER FREE RAMP,TYPE M- TPW 237.00000000 SF
15 3213.0506 BARRIER FREE RAMP,TYPE P-1 TPW 235.00000000 SF $30.50
UNCLASSIFIED EXCAVATION TPW 230.00000000 CY
38 3305.0112 MANHOLE ADJUSTMENT(WITH CONCRETE COLLAR) TPW 8.00000000 EA $900.00
TPW $103,848.25
Sub Total Additions
Change Order Additions Page 2 of4
FORH City of Fort Worth
Change Order Deletions
Project Name 2021 Resurfacing Project City Sec# 55162 ###
Client Project# 102864
Contractor PM Tanclul Islam Inspectof Robert Riley
Peachtree Construction Ltd O2 Date 7/5/2022 4/1/2022
DELETIONS
ITEM DESCRIPTION DEPT y Unt nd ost ota
"ASPHALT PAVEMENT,TYPE D TPW SY
INCH AND LARGER,TREE REMOVALI TPW 4.00000000 EA
BLOCKSOD REPLACEMENT TPW SY
TPW 1 $59,420.00
Sub Total Deletions
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
2021 Resurfacing Project
102864
Pulverization and asphalt overlay at various loca
Total $0.00
Peachtree Construction Ltd
Previous Change Orders
Co# DATE AMOUNT
Total 1 $0.00