HomeMy WebLinkAboutContract 57279-CO1 CSC No. 57279-COl
FOR`Y' 'WORTH City of Fort Worth
Change Order Request
Project Name;1 Water Sanitary Sewer Replacement on Horne Street City Sec No,. 1 57279
Project No,(s):l 103123 —7:1DOE No. N/A CityProj.No.:1 103123
Project Description; Replacing water line,Sanitary Sewer lines on Horne St.,Carver Dr.,Diaz Ave,and alleyways.
Contractor; William J.Schultz,Inc.dba Circle C Construction,Co. Change Order fI 0 Dale: 7/8/2022
City Project Mgr.1 Suby Varughese City Inspector: I Cody Horton
Phone Number: 817-392-7803 I Phone Number: 817-475.6903
Dept, Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $2,905,104.25 $1,519,011.95 $4,424,116.20 550
Extras to Dale
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $2,905,104.26 $1,519,011.95 $4,424,116.20 550
Amount of Proposed Change Order $0.00 $0.00 $0.00 025
Revised Contract Amount $2,905,104.25 $1,519,011.95 $4,424,116.20 575
Original Funds Available for Change Orders $145,255.00 $75,951.00 $221,206.00
Remaining Funds Available for this CO $145,255.00 $76,951.00 1 221,206.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 1 0.00%
MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $5,530,145.25
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Change Order No, 1 will provide compensation for the installation of standard 4ft diameter concrete manholes
that were inadvertantly installed by contractor in lieu of polymer concrete manholes.The change order will also
provide for the installation of temporary asphalt paving on Carver Drive that is required due to the delay of TPW
contractor to conduct asphalt paving improvements on the street.Staff recommends the addition of 25 calendar
days to the project for the change order.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
In full(both time and money)for all costs arising out of,or incidental to,the above Change Order,
Contractor's Company Name Contractor Name tractor signature Dale
wolam J.Schultz,Inc,dba clrclo c constmclbn,co. Teri S.Skelly
Inspector Q Dale Project Manager 10, Dale
7/15/2022 5u ll 7/20/2022
Director Water Dept Date Con Iru on Su ervisor TPW Dale
`j. Jul 20,2022
Assistant City Attorney Date Assistant'City" ana er Dale
WWI Jul 21, 2022 Dana eTndoffu a�o7 Ju121,2022
Council Action If Required)
M&C Number NIA M&C Date Approved OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Fc-)r.-r Vrc)Y-r m City of Fort Worth
"''-- Change Order Additions
Project Name Water Sanitary Sewer Replacement on Horne Street City Sec No.: 57279
Project No.(s): 103123 DOE No. R= City Proj,No.: 103123
Project Replacing water line,Sanitary Sewer lines on Horne St.,Carver Dr.,Diaz Ave.and alleyways.
Description
Contractor William J.Schultz,Inc,dba Circle C Construction,Co. Change Order:0 Dale;1 71812022
City Project Mgr, Suby Varughese City Inspector Cody Horton
ADDITIONS
DEPT G1ty Unit Unit Cost Total
45 4'STD Concrete MH Sewer 3.00 EA $6,500.00 $19,500.00
46 4'STD Drop MH Sewer 2.00 EA $7,500.00 $15,000.00
47 4'STD Concrete Extra Depth MH Sewer 15.73 VF $200.00 $3,146.00
46 Epoxy MH Liner Sewer 31.70 VF $325.00 $10,302.50
49 Temporary Asphalt Paving(2"HMAC on 6"Flex Base) Sewer 700,00 LF $25.00 $17,500.00
-- Water
Sewer $65,448.50
Page 2 of 4 Additions Sub Total $65,448.50
it
L'�o P,-r WC)P"r City of Fort Worth
Change Order Deletions
Project Name l Water Sanitary Sewer Replacement on Horne Street Cily Sec No.: 1 57279
Project No,(s): 103123 DOE No. N/A City Proj.No.: 103123
Project Description Replacing wafer line,Sanitary Sewer lines on Horne St.,Carver Dr.,Diaz Ave.and alleyways.
Contractor William J.Schultz,Inc.dba Circle C Construction,Co. Change Order: I '] Dale 7/a12022
City Project Mgr. Suby Varughese City Inspector: FCody Horton
DELETIONS
ITEM DESCRIPTION DEPT 01ty Unit (Unit Cost Total
45A Pre Cast Polymer MH Sewer 3.00 EA $10,500.00 $31,500.00
46A Pre Cast Polymer Drop MH Sewer 2.00 EA $12,500.00 $25,000.00
47A Pre Cast Polymer Extra Deplh MH Sewer 15.73 VF $350.00 $5,505.50
44 Sanitary Sewer Construction Allowance iSewer 0.03443 LS $100,000.00 $3,443.00
Water
Sewer $65,448.50
Deletions Sub Total $65,448.50
Page 3 of 4
MIWBE breakdown for this Change Order
MWBE Sub Type of Service I Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
Page 4 of 4
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration ofthis contract, including
ensuring all performance and reporting requirements,
Signature
Suby Varughese
Name of Employee
Professional Engineer
Title
ATTEST;
Tannf7 -0 S. Goodall a�FFO000 RT
Jannette S.Goodall(Ju 02213:51 CDT)
��A-j4.1
�o °Jannette S. Goodall O0VoodCity Secretary � o �d
° °o ICY
0
°000000 a
��SEX Asap
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
CPN-103123 Change order-1 notes
The Contractor provided a price proposal for the 4' concrete manhole, 4' drop
manhole, and epoxy manhole liner exchange with polymer manhole. The
Contractor also provides the price proposal for the temporary asphalt paving,
which is required on Carver drive due to the delay of the TPW paving crew. The
project manager negotiated the temporary asphalt-paving price ($28/lf to $25/1f).
The proposal covers the additional cost associated with the fittings, equipment,
fuel, and labor costs. This proposed price is fair and reasonable compared to other
projects and bid values.
The Contractor requested additional 25 days for the additional work.