Project Name: Lake Arlington Lift Station I City Sec No.: r 54223
Project No.(s): 56019/07004301001480 NTP N/A CityProj.No,:l 100995
Project Description: Construction of a new Sanitary Sewer Lift Station for the Lake Arlington Force Main Project
Contractor: Bar Constructors Inc. Change Order# 0 Date: 7/13/2022
City Project Mgr.1 Pratima Poudyal City Inspector: I Nathan Gray
Phone Number: 817-392-6149 Phone Number: 817-392-4961
Dept. Unit I Lift Station Unit II Water Alternate A-2 Totals Contract Time
(Calender days)
Original Contract Amount $9,422,126.00 $72,565.00 $583,002,00 $10,077,693.00 487
Extras to Date •$31,809.91 $0.00 $0.00 -$31,809.91 92
Credits to Date
Pending Change Orders(in M&C Process) _
Contract Cost to Date $9,390,316.09 $72,565.00 $583,002.00 $10,045,883.09 579
Amount of Proposed Change Order $34,736.54 $0.00 $0.00 $34,736.54 140
Revised Contract Amount $9,425,052.63 $72,565.00 $583,002.00 $10,080,619.63 719
Original Funds Available for Change Orders $201,554.00 $0.00 $0.00 $201,554.00
Remaining Funds Available for this GO $233,363.91 $0.00 $0.00 $233,363.91
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.03%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST¢25%) $12,597,116.25
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Change Order No.3 provides compensation for temporary power suppy that was necessary for 6 months until the building permit necessary
for connecting to Oncor lines was approved.This change order also provides for three 24 feet wide swing gates on the north and east sides
of the lift station site to access the 24"and the 78"sewer lines and also to Site Barricades property per the easement negotiation.Staff
recommends the approval of an additional 140 days on the project for the delay due to deliver of Variable Frequency Drives(VFDs)and a
Switchboard component.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name Contractor.Si n ture Dale
Bar Constructors Inc. Mike Aye s
Inspector Date P t Damm
7/21/202 2_S Zo 2-
Director Water apt) 17 Date GGtru4o S � r DepQ Date
CN�v 0' S. Jul 25, 2022
1o,)
Attorney Date Dab
Jul 28, 2022 on Jul 31 2022
Council Action If Required) OFFICIAL RECORD
M&C Number (—NIA M&C Date Approved CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Lake Arlington Lift Station City Sec No.: 54223
Project No.(s): 56019/0700430/001480 DOE No. N/A City Proj.No.: 100995
Project Construction of a new Sanitary Sewer Lift Station for the Lake Arlington Force Main Project
Description
Contractor Bar Constructors Inc. Change Order: Date: 7113/2022
City Project Mgr. Pratima Poudyal City Inspector Nathan Gray
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
44 Temporary Power Supply Unit I Lift Station 1.00 LS $21,866.54 $21,866.54
45 24'Swing Gate Unit I Lift Station 3.00 LS $4,290.00 $12,870.00
Unit I Lift Station $34,736.54
Unit II Water
Alternate A-2
Page 1 of 3 Additions Sub Total $34,736.54
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Lake Arlington Lift Station City Sec No.: 54223
Project No.(s): 56019/0700430/001480 DOE No. N/A City Proj.No.: 100995
Project Description Construction of a new Sanitary Sewer Lift Station for the Lake Arlington Force Main Project
Contractor Bar Constructors Inc. Change Order: F3 ] Date 7/13/2022
City Project Mgr. Pratima Poudyal City Inspector: FNWhFGray
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
Unit I Lift Station
Unit 11 Water
Alternate A-2
Deletions Sub Total
Page 2 of 3
MWWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
Page 3 of 3
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Pratima Poudyal, P.E.
Name of Employee
Project Manager
Title
ATTEST: a F OR
000OOO4 �oTO�.yaO 0k�12
o0
0
JannetteS.Good aII(Aug1,202208:34CDT) ��o o0"
Jannette Goodall *% Ij
o o
o oo° �
0
j, 0000000 /,/
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
7/13/2022
CPN 100995
Lake Arlington Lift Station
Change Request 3 Notes
Staff has reviewed the change order price and considers it to be fair and reasonable.