HomeMy WebLinkAboutResolution 5597-08-2022 A Resolution
NO. 5597-08-2022
STATEMENT EXPRESSING
OFFICIAL INTENT TO REIMBURSE
EXPENDITURES WITH PROCEEDS OF FUTURE DEBT FOR THE M-210
MOCKINGBIRD COLONIAL COUNTRY CLUB
WHEREAS, the City of Fort Worth, Texas (the "City") is a home-rule
municipality and political subdivision of the State of Texas; and
WHEREAS, the City expects to pay expenditures in connection with the design,
planning, acquisition and construction for the M-210 Mockingbird Colonial Country
Club Project (the "Project") prior to the issuance of obligations by the City in
connection with the financing of the Project from available funds; and
WHEREAS, the City finds, considers, and declares that the
reimbursement of the City for the payment of such expenditures will be
appropriate and consistent with the lawful objectives of the City and, as such,
chooses to declare its intention, in accordance with the provisions of Section
1 .150-2 of the Treasury Regulations, to reimburse itself for such payments at
such time as it issues obligations to finance the Project;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FORT WORTH, TEXAS, THAT:
Section 1. The City reasonably expects debt, as one or more series of
obligations, may be issued or incurred by the City with an aggregate maximum
principal amount not to exceed $7,200,000.00 for the purpose of paying the
aggregate costs of the Project.
Section 2. All costs to be reimbursed pursuant hereto will be capital
expenditures. No obligations will be issued by the City in furtherance of this
Statement after a date which is later than 18 months after the later of (1) the date
the expenditures are paid or (2) the date on which the property, with respect to
which such expenditures were made, is placed in service.
Section 3. The foregoing notwithstanding, no obligation will be issued
pursuant to this Statement more than three years after the date any expenditure
which is to be reimbursed is paid.
Adopted this 23`d day of August2022. FORT
ATTEST: �' ��
By; -Jan nette S,Goodall(Aug 24,2022 16:30 CDT) !
Jannette S. Goodall, City Secretary
�XAs
MAYOR AND COUNCIL COMMUNICATION MAP
60M210P5-CIRCLEC
r #�
Vol
,COLONIAL'
COUNTRY " r
CLULu
B r
PAF?F{ WILL UFt• � y
' $ •" � +- 0
y L[I J
.- M7. ri �• ..
, 41
.311 � ,f
N [, JJAOCKINGSIRCcl
ANN'ARBOR CT `r rt Lu
ci
UJ
F � - ry
4
.' # � �.
. { l r! r06
� •r4 �•r J �i �, a �� 1 ! F
FORT NORTH ;* . ,. - 3 . `
T � f
O i
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 08/23/22 M&C FILE NUMBER: M&C 22-0650
LOG NAME: 60M21OP5-CIRCLEC
SUBJECT
(CD 3)Authorize Execution of a Contract with William J Schultz,Inc.dba Circle C Construction Company, in the Amount of$5,462,235.00 for the
M-210 Mockingbird Colonial Country Club Project,Adopt Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds of Future
Debt,and Adopt Appropriation Ordinances to Effect a Portion of Water's Contribution to the Fiscal Years 2022-2026 Capital Improvement
Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a contract with William J Schultz, Inc.dba Circle C Construction Company, in the amount of$5,462,235.00 for the M-
210 Mockingbird Colonial Country Club project;
2. Adopt the attached resolution expressing official intent to reimburse expenditures with proceeds from future debt for M-210 Mockingbird
Colonial Country Club project;
3. Adopt the attached appropriation ordinance adjusting appropriations in the Water&Sewer Commercial Paper Fund by increasing
appropriations in the M-210 Mockingbird Colonial Country Club project(City Project No.103389)in the amount of$5,553,322.00 and
decreasing appropriations in the W&S Commercial Paper project(City Project No. UCMLPR)by the same amount to Effect a Portion of
Water's Contribution to the Fiscal Years 2022-2026 Capital Improvement Program;
4. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the General Capital Projects Fund,by
increasing estimated receipts and appropriations in the M-210 Mockingbird Colonial Country Club project(City Project No. 103389)in the
amount of$539,672.00,and decreasing estimated receipts and appropriations in the Contract Street Maintenance programmable project
(City Project No. P00020)by the same amount;and
5. Amend TPWs Contribution to the Fiscal Years 2022-2026 Capital Improvement Program.
DISCUSSION:
This Mayor and Council Communication(M&C)is to authorize a contract for the replacement of deteriorated water and/or sanitary sewer mains for
M-210 Mockingbird Colonial Country Club(Clear Fork Drainage Basin M-210 Sanitary Sewer Improvements,Part 5)in the vicinity of Colonial
Country Club as indicated on the following streets:
Street From To Scope of
Work
Mockingbird Simondale Drive/Mockingbird Westerly Water/Sewer
Lane Lane intersection II 1,650 feet
Mockingbird Mockingbird Lane Cul-de-Sac Water/Sewer
Court
Hartwood Mockingbird Lane Southerly Water
Drive 160 feet
Additionally,asphalt pavement rehabilitation will be conducted on streets subsequent to the water and sanitary sewer main replacement.The
Transportation&Public Works Department's share of this contract is$452,175.00 and the Water Department's share of the contract is
$5,010,060.00.
The project was advertised for bids on March 17,2022,and March 24,2022,in the Fort Worth Star-Telegram.On May 5,2022,the following bids
were received:
Bidder Amount Time of
Completion
William J Schultz,Inc.dba Circle C Construction $5,462,235.00 380 Calendar
Company Days
S.J.Louis Construction of Texas, LTD $7,902,615.17
In addition to the contract amount,$335,038.00(Water:$102,578.00;Sewer:$190,181.00; Paving:$42,279.00)is required for project
management,material testing and inspection,and$295,721.00(Water:$75,731.00;Sewer:$174,772.00; Paving:$45,218.00)is provided for
project contingencies.The sanitary sewer component of this project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.
Additionally, approximately 2,017 linear feet of cast iron water pipe will be removed and replaced as part of this project. Construction is
anticipated to begin in October 2022 and be completed by November 2023.
This project will have no impact on the Transportation&Public Works'or the Water Department's operating budgets when completed.
The action in this M&C will amend TPWs contribution to the Fiscal Years 2022-2026 Capital Improvement Program as approved in connection
with Ordinance 25073-09-2021,Section 6.Capital Improvements,page 23,as follows:
Capital Revised
Project FY2022 CIP FY2022 CIP
Fund Authority FY2022
Name Name Appropriations Appropriations 9
Bud et
P00020
30100- Contract $20,441,000.00 M&C 21- $(1,056,034.00) $19,390,966.00
General Street 0827
Maintenance
22- $(311,148.00) $19,079,818.00
003
0036
M&C 22- $(603,254.00) $18,476,564.00
�101 27
This M&C $(539,672.00) $17,936,892.00
It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year,instead of within the annual budget ordinance,as
projects commence,additional funding needs are identified,and to comply with bond covenants.The actions in the M&C will appropriate funds in
support of the Water's portion of the City of Fort Worth's Fiscal Years 2022-2026 Capital Improvement Program,as follows:
Capital BudgetRevised
Project FY2022 CIP Change
Fund Authority FY2022
Name Name Appropriations (Increase/ Budget
Decrease) g
56021 — 103389—
W&S M-210 $0.00 This M&C $5,553,322.00$5,553,322.00
Commercial Mockingbird
Paper Fund Colonial CC
Funding is budgeted in the UCMLPR project within the W&S Commercial Paper Fund and the General Capital Projects Fund for the purpose of
funding the M-210 Mockingbird Colonial Country Club project.
Appropriations for the M-210, Part 5 Sanitary Sewer Improvements project are as depicted below:
Existing Additional
Fund Appropriations Appropriations Project Total*
W&S
Commercial $0.00 $5,553,322.00 $5,553,322.00
Paper Fund-
56021
General
Capital $0.00 $539,672.00 $539,672.00
Projects Fund
30100
Project Total $0.00 $6,092,994.00 $6,092,994.00
*Numbers rounded for presentation purposes.
This project is anticipated to be included in a future revenue bond issue for the Water&Sewer Fund.Available cash within the Water and Sewer
portfolio and the City's portfolio along with the appropriation authority authorized under the callable Commercial Paper Program(CP)will be used
to provide interim financing for this project until debt is issued.Once debt associated with this project is sold,bond proceeds will be used to
reimburse the Water and Sewer portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution. Under federal law,
debt must be issued within approximately three years in order for these expenses to be reimbursable.Adoption of the attached resolution does not
obligate the City to sell bonds,but preserves the ability to reimburse itself from tax-exempt bond proceeds.
Business Equity: William J.Schultz,Inc.dba Circle C Construction Company,its in compliance with the City's Business Equity Ordinance by
committing to eight percent Business Equity participation and documenting good faith effort.William J.Schultz, Inc.dba Circle C Construction
Company, Inc.identified several subcontracting and supplier opportunities.However,the firms contacted in the areas identified did not respond or
did not submit the lowest bids.The City's Business Equity goal for this project is 17 percent.
The project is located in COUNCIL DISTRICT 3.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the UCMLPR project within the W&S Commercial Paper Fund and the General Capital
Projects Fund,and upon approval of the above recommendations and adoption of the attached appropriation ordinances,funds will be available in
the W&S Commercial Paper Fund and the General Capital Projects Fund for the M-210 Mockingbird Colonial CC project to support the approval
of the above recommendations and execution of the contract.Prior to any expenditure being incurred,the Water and Transportation&Public
Works Departments have the responsibility of verifying the availability of funds.
Submitted for City Manager's Office b�L. Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: Liam Conlon 6824