HomeMy WebLinkAboutContract 56985-CO1 CSC No. 56985-COI
FOR_ _T WORTH,., City of Fort Worth
Change Order Request
Project Name Athletic Field Lighting at 101961,101962 City Sec# 56985
Client Project#(s) 101961,101962
Project
Description Athletic Field Lighting
Contractor Groves Electrical Service,Inc. Change Order# 1 Date 8/3/2022
City Project Mgr. Helen Florez City Inspector Tolliver Lipka/Ron Cordova
Contract Time
Dept. PARD Totals (CD)
Original Contract Amount $1,832,140.00 $1,832,140.00 200
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,832,140.00 $1,832,140.00 200
Amount of Proposed Change Order $368,000.00 $368,000.00 60
Revised Contract Amount $2,200,140.00 $2,200,140.00 260
Original Funds Available for Change Orders $368,000.00 $368,00.00
Remaining Funds Available for this CO $368,000.00 $368,000.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 20.09%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,290,175.001
JUSTIFICATION(REASONS)FOR CHANGE ORDER
On November 30,2021,City Council authorized the execution of a construction contract with Groves Electrical Service,Inc.,in the amount of$1,832,140.00 for the
installation of atheltic field lighting at Harmon Field and Rolling Hills Park(MC-21-0926).After the award of the contract it was determined there were still funds available for
additional lighting at Rolling Hills Park.The additional scope of work will increase the contract time from 200 calendar days to 260 calendar days.The Change Order was
authorized by M&C 22-0474.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges
that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting
requirements.
OFContractor's Company Nam-A ontractor(Name) Contract Signature
Groves Electrical Service,Inc. William H.Groves 8/4/2022
Inspector/Inspection Supervisor ate Project and Contract Compliance Manager
� J����°iA�a��� Aug a,2o2z �(�� �( 8/3/22
Program Manager Date Senior Capital Project 0 icer Date
Aug 11,2022
Assistant Director(Dept) Date Director,Contracting Department(Dept) Date
Aug 15,2022 dwAug 15,2022
Assistant City Attorney Date Assistant City Manager Date
wl� Aug 24,2022 Aug 25,2022
ae
Council Action(if required)
M&C Number 22-0474 M&C Date Approved 6/28/2022
ATTEST: g44nnU1�
J�hhort�,rrada/L
0 000000% a
Jannette Goodall,City Secretary ,�0 0O dd OFFICIAL RECORD
o�d
jJ,0 OX CITY SECRETARY
P� 000 *11 FT.WORTH, TX
000pp000
��nEXP`-�0o4p
FORT NORTH City of Fort Worth
�T--- Change Order Additions
Project Name Athletic Field Lighting at 101961,101962 City Sec# 56985
Client Project# 101961,101962
Contractor Groves Electrical Service,Inc. PM Helen Florez Inspector®
Change Order Submittal# F-7 Date 7/19/2022
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
017123 Construction Staking
3_02 26 05 00 Excavation,trenching,and backfll PARD 1.00000000 LS $20,263.00
Conductors PARD 1.00000000 LS
3_04 26 05 33 Conduit and boxes PARD 1.00000000 LS $30,247.00
Wire devices PARD Toom000 LS
3_05 26 56 68 Light fixtures,poles,and controls PARD 1.00000000 LS $241,218.00
"Concrete Pad 'x' PARD 1.00000000 LS
3_07 Switchgear incluing panels,enclosures,etc. PARD 1.00000000 LS
PARD $368,000.00
Sub Total Additions $368,000.00
Change Order Additions Page 3 of 4
FORTWORTH City of Fort Worth
Change Order Deletions
Project Name I Ath let ic F ie Id Li g hti ng at101961,101962 City Sec# 56985
Client Project# 1 101961,101962
Contractor Groves Electrical Service,Inc. PM Helen Florez Inspector®
Change Order Submittal# O1 Date 7/19/2022
UtLL I IONS
nit ni os I o a
PARAD
Sub TotalDeletions
Change Order Deletions Page 1 of 4
MISBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
maintaining commitment on origninal agreement of 13%
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total 1 $0.00
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 06/28/22 M&C FILE NUMBER: M&C 22-0474
LOG NAME: 80ATHLETIC FIELD LIGHTING HARMON FIELD AND ROLLING HILLS PARK*
SUBJECT
(CD 8)Authorize Change Order No. 1 to a Construction Contract with Groves Electrical Service, Inc.,to the Athletic Field Lighting for Harmon Field
and Rolling Hills Park Project in the Amount of$368,000.00 for a Total Contract Value of$2,200,140.00(2018 Bond Program)
RECOMMENDATION:
It is recommended that the City Council authorize Change Order No. 1 to the construction contract with Groves Electrical Service, Inc., (City
Secretary No. 56985)to the Athletic Field Lighting for Harmon Field and Rolling Hills Park Project(City Project No. 102962) in the Amount of
$368,000.00 for a Total Contract Value of$2,200,140.00(2018 Bond Program)
DISCUSSION:
The purpose of this Mayor and Council Communication (M&C)is to authorize Change Order No. 1 to the construction contract with Groves
Electrical Service, Inc., (City Secretary No. 56985) to the Athletic Field Lighting for Harmon Field and Rolling Hills Park Project in the amount of
$368,000.00 for a total contract value of$2,200,140.00.
On November 30, 2021 the City Council authorized execution of a construction contract(M&C 21-0926, City Secretary Contract No. 56985)with
Groves Electrical Service, Inc., in the amount of$1,832,140.00 for the installation of athletic field lighting at Harmon Field and Rolling Hills Park. Of
this award amount$1,301,310.00 was allocated for lighting at Rolling Hills Park.
On September 23, 2021 bids were received for the installation of athletic field lighting, including 6 ball fields at Rolling Hills Park.Groves Electrical
Services, Inc., accepted bid was$498,690.00 below budget for improvements.Change Order No. 1 in the amount of$368,000.00 will fund the
lighting of an additional ball field at Rolling Hills Park.
This project is included in the 2018 Bond Program.Available resources within the general fund will be used to provide interim financing until debt is
issued.Once debt associated with the project is sold, bond proceeds will reimburse the general fund in accordance with the statement expressing
official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election (Ordinance No.23209-05-2018)and
subsequent actions taken by the Mayor and Council.
Construction of this project began in April 2022 and completion is projected to be in August 2022.
The impact of the additional project scope on the Park&Recreation Department's annual operating budget when the project is completed will be
$5,000.00.As of April 30, 2022,the cumulative total of all previously approved M&C's increased the department's estimated annual maintenance
by$418,331.00 beginning in FY2023.
Compliance with the City's Business Equity Ordinace has been achieved by the following method: Groves Electrical Service, Inc., is in compliance
with the City's Business Equity Ordinance by committing to 13% participation on this project's base bid.The City's Business Equity goal for this
project is 11%.
Rolling Hills Park is located in COUNCIL DISTRICT 8.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the 2018 Bond Program Fund for the Rolling Hills Athletic Field Lighting project to
support the approval of the above recommendations and execution of the amendment. Prior to an expenditure being incurred,the Park&
Recreation Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by: Valerie Washington 6192
Originating Business Unit Head: Richard Zavala 5704
Additional Information Contact: David Creek 5704
FOR TWOR"I(H City of Fort worth
ACCEPTANCE OF PREVIOUS M/WBE COMMITMENT FORM
(for use with CHANGE ORDERS or AMENDMENTS greater than $100,000)
To be Completed by City Project Manager
Amendment(for Contractual Services Agreement)
Project Name: City Project Number
ATHLETIC FIELD LIGHTING HARMON FIELD AND 102962
ROLLING HILLS PARK City Project Manager
Contractor: Helen Florez
Groves Electrical Service, Inc. City's M/WBE Project Goal: 11 %
Original Amount of Agreement: $1,759,850.00 Accepted M/WBE Commitment: 13 %
Total of Previous Amendments: Date of Last M/WBE Report:
Amount for this Amendment: $400,000.00 Amendment#: 1
Revised Amount of Agreement: $2,159,850.00 Date: 4/27/2022
Language to be inserted in the M&C for this Agreement
Groves Electrical Service, Inc. agrees to maintain its initial M/WBE commitment of 13% that it
made on the original agreement and extend and maintain that same M/WBE commitment of 13%
to this first amendment. Therefore Groves Electrical Service, Inc. remains in compliance with the
City's M/WBE Ordinance and attests to its commitment by its signature on the Acceptance of
Previous M/WBE Commitment form executed by an authorized representative of its company.
To be Completed by the Representative of the Change Order(for Construction Contract)
William H. Groves President a / --
Printed Name Title A thorized Signature/Date
Groves Electrical Service, Inc. Billy Brown
Company Name Contact Name (if different)
2410 Squire Place billv(@Rroveselectric.com
Address E-mail address
Farmers Branch, Texas 75234 972-484-2717 972-484-2263
City/State/Zip Phone number Fax Number
0% as of 4/29/2022
M/WBE % Paid to Date Date
City Project Manager has reviewed the work associated with this Amendment,
considers it the same or similar to work in the original Agreement, and recommends that the
Change Order (for Construction Contract) have the option to retain and confirm its existing M/WBE
commitmeL .�tDAt�,
Helen Florez � 5/2/22
City Project Manager City Project Manager tignature Date
tit
To be Completed by the MIWBE Compliance Staff
Walter K. Newman 0
M/WBE Compliance Staff ID# M/WBE Current% Level via Last Report Rec'd
05/11/2022
M/WBE Signature Date