HomeMy WebLinkAboutContract 55324-AR2 CSC No. 55324-AR2
FORS[' WORTH City of Fort Worth
Construction Allowance Request
Project Name[ Water and Sanitary Sewer Rehabilitation,Contract 101 City Sec No. r 55324
Project No.(s)l 56002-0700430-CO2722-CO1780 M&C: 21-0056 City Proj,No, 27 22
Project Description: Water,Sanitary Sewer and Paving improvements on Winton Terrace East and Winton Terrace West
Conlraclod Wiliam J.Schultz,Inc.dba Circle C Const. Allowance No: Date: 812412022
City Project Mgr.l J.Chris Underwood City Inspector: I Stephen Martinez
Phone Number:[ 817-392-2629 Phone Number: 682-432-5485
Dept. Water Sewer Paving Totals
Original Contract Amount $1,333,263.00 $1,345,890.00 $336,025.00 $3,015,178.00
Previous Allowances Allocated $10,000.00 $20,000.00 $0.00 $30,000.00
Amount of Proposed Allocation $38,200.00 $47,600.00 $10,000.00 $95,800.00
Original Allowance Available for Allocation $60,000.00 $90,000.00 $20,000.00 $170,000.00
Remaining Funds Available for this Allocation $50,000.00 $70,000.00 $20,000.00 $140,000.00
JUSTIFICATION (REASONS) FOR ALLOWANCE
Allowance No. 2 provides for the following:
• Hand Excavation around large trees in the parkway to protect the roots and life of the trees during the
installation of new water and sewer services.
• Irrigation Repairs required in the parkway during the installation of new water services,new sewer services
and curb and gutter replacement.
• Retaining walls built around two manholes that are located in the parkway on a sloped surface.
• Removal of trees that cannot be protected during sewer installation.
• Extensive cleaning than typically necessary for a sewer pipe segment proposed to be rehabilitated via cured-
in-place pipe method.
It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and satisfaction and
represents payment in full for all costs arising out of,or incidental to,the above Construction Allowance Request,
Contractor's Company Name Contractor Name C mctor Signature Date
Wiliam J.Schultz,Inc,dba Circle C Const. Teri Skelly 2 Z
Inspector Date Pro eaj;Manager Date
D_irecfor Water Dept Date 4on7tructian Supervisor WaterMe t Date
hristopher Hard (Aug 31,202215:58 CDT) Aug31,2022
Assistant City,Attorney Date Assistant C1 _Mana er Date
lack772202u CCori Sep 2, 2022 ym3,,dh__:r; .A,iCL,�3�o-; Sep 4,2022
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT W"RTH City of Fort Worth
Construction Allowance Request
Project Name Water and Sanitary Sewer Rehabilitation, Contract 101 City Sec No. 55324
Project No.(s) 56002-0700430-0O2722-001780 M&C: 21 0056 City Proj. No. 2722
Project Water, Sanitary Sewer and Paving Improvements on Winton Terrace East and Winton Terrace West
Description
Contractor Wiliam J. Schultz, Inc.dba Circle C Const. Allowance No: 0 Date: 8/24/2022
City Project Mgr. J. Chris Underwood City Inspector Stephen Martinez
UUN51 KUGT IUN ALLUWANGE ITEMS 1-0 6E ADDED
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
49 Hand Excavation to Protect Trees Water 4.00 EA $5,800.00 $23,200.00
50 Irrigation Repairs Water 3.00 EA $5,000.00 $15,000.00
55 Hand Excavation to Protect Trees Sewer 3.00 EA $5,800.00 $17,400.00
56 Irrigation Repairs Sewer 2.00 EA $5,000.00 $10,000.00
57 Retaining Wall Around Manhole Sewer 24.00 LF $175.00 $4,200.00
58 Tree Removal up to 24-inch Diameter Sewer 4.00 EA $2,000.00 $8,000.00
59 Heavy Cleaning for Cured In Place Pipe Rehabilitation Sewer 2.00 EA $4,000.00 $8,000.00
22 Irrigation Repairs Paving 2.00 EA $5,000.00 $10,000.00
Water $38,200.00
Sewer $47,600.00
Paving $10,000.00
Page 2 of 4 Additions Sub Total $95,800.00
FORT WORTH City of Fort Worth
Construction Allowance Request
Project Name F Water and Sanitary Sewer Rehabilitation, Contract 101 City Sec No. 55324
Project No.(s) 56002-0700430-CO2722-001780 M&C: 21 0056 City Proj. No. 2722
Project Description Water, Sanitary Sewer and Paving Improvements on Winton Terrace East and Winton Terrace West
Contractor Wiliam J. Schultz, Inc.dba Circle C Const. Allowance No: E Date 1 8/24/2022
City Project Mgr. J. Chris Underwood City Inspector Stephen Martinez
CONSTRUCTION ALLOWANCE ITEMS TO BE DELETED
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
Water
Sewer
Paving
Page 3 of 4 Deletions Sub Total
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
Page 4 of 4
8/29/2022
CPN 2722
Water Sanitary Sewer Rehabilitation, Contract 101
Allowance Request 2 Notes
Staff has reviewed the allowance request prices and considers them to be fair and
reasonable.
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Sr6nature
_ J��Pcs
Name of Employee
S12-
Title
ATTEST: pp��OR �
O OOO000000 0
0
ette 5.Goodall(SeD 6,2022 09: DT) 1! 0 00 O
P °
Jannette Goodall °00 0
° 0
°000000° /,
City Secretary 1 r*XAga�A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX