HomeMy WebLinkAboutContract 58074 DocuSign Envelope ID: B4B705E9-CDB9-4EB6-962C-8550D29806FF
CSC No. 58074
UPRR REMS
Project 771414
AUTHORIZATION FOR CROSSING IMPROVEMENTS
Effective Date: 9/6/2022
THIS AUTHORIZATION FOR CROSSING IMPROVEMENTS ("Agreement") is made and
entered into as of the Effective Date above, by and between UNION PACIFIC RAILROAD
COMPANY, a Delaware corporation ("Railroad"), and CITY OF FORT WORTH, TEXAS
("Agency").
RECITALS
In accordance with the terms and conditions of this Agreement, Agency and Railroad
desire to improve the existing crossing area ("Project") along, over and across Railroad's track
and right of way, as such crossing area is more particularly described on Exhibit A attached hereto
and made a part hereof("Crossing Area").
AGREEMENT
NOW THEREFORE, the parties hereto agree as follows:
1. Railroad agrees to perform the Project work described on Exhibit B attached
hereto the ("Railroad Work"). Railroad's estimated cost for the Railroad Work is included on
Exhibit C attached hereto ("Estimate") and may include without limitation costs of engineering
review, construction, inspection, flagging, procurement and delivery of materials, equipment
rental, manpower and all direct and indirect overhead labor/construction costs, including
Railroad's standard additive rates. Such standard additive rates may be subject to upward or
downward adjustment based on industry standards and practices, and the parties acknowledge
and agree that any such adjustment to standard additive rates may be made retroactively.
2. Agency has appropriated sufficient funds to complete the Project and shall
reimburse Railroad for costs incurred by Railroad in connection with the Railroad Work in
accordance with Exhibit D attached hereto.
3. If Agency will be performing any Project work, such work is described on Exhibit B
attached hereto ("Agency Work"). Agency shall perform the Agency Work, if any, at its sole cost,
and Railroad consents to Agency (or any contractor or other agent hired by Agency) performing
the Agency Work within the Crossing Area, subject to complying with the terms and conditions of
this Agreement. Railroad's consent shall not be deemed to grant Agency (or any contractor or
other agent hired by Agency) any property interest in the Crossing Area or other Railroad property.
4. If Agency hires a contractor or other agent to perform the Agency Work, Agency
shall require such contractor or agent to execute Railroad's then current form of Contractor's Right
of Entry Agreement and to comply with the requirements set forth therein.
5. No work of any kind shall be performed, and no person, equipment, machinery,
tools, materials, vehicles or other items shall be located, operated, placed or stored within twenty-
five (25) feet of any track at any time for any reason except as otherwise provided herein. Prior to
commencing the Agency Work, and if the performance of any Agency Work requires any person
OFFICIAL RECORD
CITY SECRETARY
1 FT. WORTH, TX
DocuSign Envelope ID:B4B705E9-CDB9-4EB6-962C-8550D29806FF
or equipment to be within twenty-five (25)feet of any track, Agency shall provide Railroad at least
thirty (30) working days advance notice of the performance of such proposed work, and upon
Railroad's receipt of such notice, Railroad will determine and inform Agency whether a flagman
need to be present or whether Agency needs to implement any special protective or safety
measures. Subject to Exhibit D, in the event that flagging or other special protection or safety
measures are required to be performed in connection with the Railroad Work specifically or the
Project generally, and regardless if the costs for such measures are included in the Estimate,
Agency shall be responsible for all such costs incurred in connection therewith.
6. Fiber optic cable systems may be buried on the Railroad's property. Protection of
the fiber optic cable systems is of extreme importance since any break could disrupt service to
users resulting in business interruption and loss of revenue and profits. Prior to commencing any
Agency Work, Agency shall visit up.com/CBUD to complete and submit the required form to
determine if fiber optic cable is buried anywhere on Railroad's property to be used in connection
with the Agency Work. If fiber optic cable is present, Agency will telephone (or will cause its
contractor or agent to coordinate) the telecommunications company(ies) involved, arrange for a
cable locator, and make arrangements for relocation or other protection of the fiber optic cable.
7. Agency, for itself and for its successors and assigns, hereby waives any right of
assessment against Railroad, as an adjacent property owner, for any and all improvements made
under this Agreement.
8. Neither party shall assign this Agreement without the prior written consent of the
other party, which consent shall not be unreasonably withheld, conditioned or delayed.
9. This Agreement sets forth the entire agreement between the parties regarding the
Project and the installation and maintenance of the Project improvements within the Crossing
Area. To the extent that any terms or provisions of this Agreement regarding the installation and
maintenance of such Project improvements are inconsistent with the terms or provisions set forth
in any existing agreement affecting the Crossing Area, such terms and provisions shall be
deemed superseded by this Agreement to the extent of such inconsistency.
IN WITNESS WHEREOF, the parties hereto have duly executed this Agreement as of the
Effective Date.
CITY OF FORT WORTH, TEXAS UNION PACIFIC RAILROAD COMPANY,
a Delaware Corporation
Fi
OCUSigned by:
ii�G�rtvid
William Johnson(A g30,202216:19 CDT)
Signature S igna ure
William M. Johnson Erik Lewis
Printed Name Printed Name
Assistant City Manager _Manager I, Engineering — Public Projects
Title Title
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
2
DocuSign Envelope ID:B4B705E9-CDB9-4EB6-962C-8550D29806FF
APPROVAL RECOMMENDED:
By: Z-Vi/,+i P11�
Lauren L Prieur, Interim Director
Transportation and Public Work
APPROVED AS TO FORM AND LEGALITY:
�l
By:
Douglas W. Black
Senior Assistant City Attorney
FORM 1295: N/A
CONTRACT AUTHORIZATION
M&C: N/A
Date Approved: N/A
ATTEST: 00���
B\ °i c r_ a u o c.n8 CDT) r ,
J 0 °°O4 'lam
Jannette Goodall �� °000Opp0000 d
d
City Secretary ��,�EXASa�p
CONTRACT COMPLIANCE MANAGER:
By signing, I acknowledge that I am the person responsible for the monitoring and
administration of this contract, including ensuring all performance and reporting
requirements.
By: Tariqul Islam(Aug 25,202213:51 CDT`
Tariqul Islam
Project Manager
3
DocuSign Envelope ID: B4B705E9-CDB9-4EB6-962C-8550D29806FF
EXHIBIT A
Description of Crossing Location
Street Long Avenue DOT# 275243M
Subdivision Choctaw Milepost 751.039
City Fort Worth State TX
County Tarrant
DocuSign Envelope ID: B4B705E9-CDB9-4EB6-962C-8550D29806FF
EXHIBIT B
Scope of Work
Railroad Work:
• Construction observations and inspections
Agency Work:
Replacement of existing bridge deck.
DocuSign Envelope ID: B4B705E9-CDB9-4EB6-962C-8550D29806FF
EXHIBIT C
Estimate Cover Page
(see attached)
DocuSign Envelope ID: B4B705E9-CDB9-4EB6-962C-8550D29806FF
ESTIMATE OF MATERIAL AND FORCE ACCOUNT WORK BY THE
UNION PACIFIC RAILROAD COMPANY
FOR FORT WORTH TX
DESCRIPTION OF WORK: Fort Worth, TX 275243M.Removal and replacement of bridge deck. Union Pacific Railroad to
provide plan review, construction management, coordination,and observation.Project location:
Fort Worth, TX,Long Avenue,MP 751.039 Choctaw Subdivision,DOT 275243M.
LOCATION: FORT WORTH STATE: TX DATE: 08/08/2022
DESCRIPTION LABOR DIRECT COSTS TOTAL
JOB 001 -ENGINEERING
Engineering Labor $2,500 $0 $2,500
Engineering Consultant $45,000 $2,500 $47,500
TOTAL PROJECT: $47,500 $2,500 $50,000
EXISTING REUSABLE MATERIAL:NONE
EXISTING NONREUSABLE MATERIAL:NONE
TOTAL ESTIMATED COST OF PROJECT LESS CREDITS: $50,000
THE ABOVE FIGURES ARE ESTIMATES ONLY AND SUBJECT TO FLUCTUATION.
IN THE EVENT OF AN INCREASE OR DECREASE IN THE COST OR QUANTITY OF
MATERIAL OR LABOR REQUIRED,THE RAILROAD WILL BILL FOR ACTUAL
CONSTRUCTION COSTS AT THE CURRENT EFFECTIVE RATE.
DocuSign Envelope ID: B4B705E9-CDB9-4EB6-962C-8550D29806FF
EXHIBIT D
Reimbursement Method
Agency agrees to reimburse Railroad for ONE HUNDRED PERCENT (100%) of actual costs
incurred by Railroad in connection with the Railroad Work. During the performance of the Railroad
Work, Railroad will provide progressive billing to Agency based on Railroad's actual costs. Within
one hundred twenty (120) days after completion of the Project, Railroad will submit a final billing
to Agency for any balance owed Railroad in connection with the Railroad Work. Agency shall pay
Railroad within thirty (30) days after Agency's receipt of any progressive and final bills submitted
by Railroad.