HomeMy WebLinkAboutResolution 5618-09-2022 A Resolution
NO. 5618-09-2022
AUTHORIZING AN ADVANCE FUNDING AGREEMENT WITH THE
TEXAS DEPARTMENT OF TRANSPORTATION IN THE AMOUNT OF
$726,279.00 WITH FEDERAL PARTICIPATION IN THE AMOUNT OF
$433,992.00, STATE PARTICIPATION IN THE AMOUNT OF $118,486.00
AND LOCAL PARTICIPATION IN THE AMOUNT OF $173,801.00 FOR
ENGINEERING, ENVIRONMENTAL SERVICES AND CONSTRUCTION
OF THE SH183 AT GREEN OAKS ROAD HIGHWAY SAFETY
IMPROVEMENT PROJECT
WHEREAS, federal law establishes federally funded programs for transportation improvements
to implement its public purposes, and
WHEREAS, the Texas Transportation Code, Section 201.103 establishes that the State shall
design, construct and operate a system of highways in cooperation with local governments, and Section
222.052 authorizes the Texas Transportation Commission to accept contributions from political
subdivisions for development and construction of public roads and the state highway system within the
political subdivision, and
WHEREAS, federal and state laws require local governments to meet certain contract standards
relating to the management and administration of State and federal funds, and
WHEREAS, the Texas Transportation Commission has codified 43 TAC, Rules 15.50-15.56
that describe federal, state, and local responsibilities for cost participation in highway improvement and
other transportation projects, and
WHEREAS, the Texas Transportation Commission passed Minute Order Number 115814
authorizing the State to undertake and complete a highway improvement or other transportation project
generally described as intersection improvements; and
WHEREAS, the City of Fort Worth identified the need for signal rebuild, American with
Disabilities Act (ADA) ramps, safety lighting, flashing yellow arrow for northbound and southbound
movements, new crosswalks and pavement markings, signal advance warning sign for westbound
approach and improve northbound/southbound left turn offset; and
WHEREAS, the City of Fort Worth and Texas Department of Transportation have
negotiated terms of an Advance Funding Agreement in the Amount of $726,279.00 with
Federal Participation in the Amount of $433,992.00, State Participation in the Amount of
$118,486.00 and Local Participation in the Amount of $173,801.00 for engineering,
environmental services and construction of the SH183 at Green Oaks Road Highway
Safety Improvement Project.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FORT WORTH, TEXAS, THAT:
The City Manager is hereby authorized to execute an Advance Funding Agreement
with the Texas Department of Transportation (CSJ: 0094-05-071) in the Amount of
$726,279.00 with Federal Participation in the Amount of $433,992.00, State Participation
in the Amount of $118,486.00 and Local Participation in the Amount of $173,801 .00, plus
cost overruns, for engineering, environmental services and construction of the SH183 at
Green Oaks Road Highway Safety Improvement Project.
Adopted this 271h day of September2022.
ATTEST:
;M 1
By: Jannette S.Goodall(Sep 30,202214:26 CDT) e-
t �it
i
Janette S. Goodall, City Secretary
MAYOR AND COUNCIL COMMUNICATION MAP
SH183 at GREEN OAKS HSIP PROJECT
� . N
X�t83' ,
J -
m
1fe4 LV 5�^
W
r
U Ridgmar Meadaw Roan Q
°rep HOaA P O
i F
q v
5 Rdgma �Gc
5`�,.
e�
Spur 341 -. + ,11 I' � �4 0°
o P xiagmor o
1 Mall I 1
ks
!
� b
c9
West ( i {data
i I i
� I
1- 30
CPN#103640
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 09/27/22 M&C FILE NUMBER: M&C 22-0765
LOG NAME: 2022 SH183 AT GREEN OAKS RD AFA
SUBJECT
(CD 3)Adopt Resolution Authorizing Execution of an Advance Funding Agreement with the Texas Department of Transportation in the Amount of
$726,279.00,of Which$173,801.00 is City Participation for the State Highway 183 at Green Oaks Road Highway Safety Improvement
Project(2018 Bond Program)
RECOMMENDATION:
It is recommended that the City Council adopt the attached resolution authorizing execution of an advance funding agreement(CSJ#0094-05-
071)with the Texas Department of Transportation in the amount of$726,279.00 of which$173,801.00 is City participation for the State Highway
183 at Green Oaks Road Highway Safety Improvement project(City Project No. 103640).
DISCUSSION:
The purpose of this Mayor and Council Communication(M&C)is to adopt a resolution authorizing execution of an Advance Funding Agreement
(AFA)with the Texas Department of Transportation(TXDOT)in the amount of$726,279.00 of which$173,801.00 is City participation for the State
Highway 183 at Green Oaks Road Highway Safety Improvement project(City Project No. 103640).
The scope of this project includes signal rebuild,American with Disabilities Act(ADA)ramps,safety lighting,flashing yellow arrow for northbound
and southbound movements, new crosswalks and pavement markings,signal advance warning sign for westbound approach and improve
northbound/southbound left turn offset.
This project will be let by TXDOT in June 2023.The State will be responsible for securing the federal and State share of the funding required for
the development and construction of the project. City funds have been appropriated to this project for design, right-of-way utilities and project
management purposes.The City bears the responsibility to pay for cost overruns.
The table below summarizes funding for the project:
Total Projects Costs for the SH183 at Green Oaks Road Highway Safety Improvement project(City Project No.
103640)
Fund Federal State Local Total
34014-2014 Bond $150,551.00 $150,551.00
Program Fund
34018-2018 Bond $23,250.00 $23,250.00
Program Fund
Unappropriated $433,992.00 $118,486.00 $552,478.00
Total $433,992.00 $118,486.00 $173,801.00 $726,279.00
This project is included in the 2018 Bond Program. Available resources within the General Fund will be used to provide interim financing until debt
is issued. Once debt associated with the project is sold, bond proceeds will reimburse the General Fund in accordance with the statement
expressing official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election(Ordinance No.23209-05-2018)
and subsequent actions taken by the Mayor and Council.
Funding for the required City participation would be from the 2014&2018 Bond Programs of which a portion of this funding was appropriated to
the project in a separate M&C.
This project is located in COUNCIL DISTRICT 3.
A Form 1295 is not required because:This contract will be with a governmental entity,state agency or public institution of higher education:
TXDOT&Federal
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current capital budget,as previously appropriated,in the 2014 Bond Program Fund
and the 2018 Bond Program Fund for the SH183 at Green Oaks Rd project to support the approval of the above recommendation and execution
of the advance funding agreement. Prior to any expenditure being incurred,the Transportation&Public Works Department has the responsibility
to validate the availability of funds.
Submitted for City Manager's Office W. William Johnson 5806
Originating Business Unit Head: Lauren L. Prieur 6035
Additional Information Contact: Monty Hall 8662
Expedited