HomeMy WebLinkAboutOrdinance 25746-09-2022 ORDINANCE NO.25746-09-2022
AN ORDINANCE ADJUSTING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE COMMUNITY FACILITIES AGREEEMENT
DEVELOPER FUND, BY INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE COMMUNITY FACILITIES AGREEMENT-OAK
GROVE ROAD NORTH OF JOEL EAST PROJECT (CITY PROJECT NO.
101902) IN THE AMOUNT OF $93,394.00 AND DECREASING ESTIMATED
RECEIPTS AND APPROPRIATIONS IN THE COMMUNITY FACILITIES
AGREEMENT BUCKET PROGRAMMABLE PROJECT (CITY PROJECT NO.
P00001) BY THE SAME AMOUNT; PROVIDING FOR A SEVERABILITY
CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;
AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2021-2022 in the
Budget of the City Manager, there shall also be adjusted estimated receipts and appropriations in the
Community Facilities Agreement Developer Fund,by increasing estimated receipts and appropriations in the
Community Facilities agreement- Oak Grove Road North of Joel East project(City Project No. 101902) in
the amount of $93,394.00 and decreasing estimated receipts and appropriations in the Community
Facilities Agreement Bucket programmable project(City Project No.P00001)by the same amount.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or
void for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way
impair the remaining portions, sections, or parts-of sections of this ordinance, which said remaining
provisions shall be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 25073-09-2021 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions
of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY F O& '
�/�
WWI Yann fe S.
D$lack(Oct 3,202213:07 CDT) Jannette S.Goodall(Oct 3, 1
Jannette S.Goodal
Assistant City Attorney City Secretary '
ADOPTED AND EFFECTIVE: September 27,2022
MAYOR AND COUNCIL COMMUNICATION MAP
062022 OAK GROVE ROAD APPROPRIATION
ALTAMESA BLVD, E - JOEL EAST RD
FORTWORTH .
ALTAMESA BLVD,�E, �-`A.LT,
pp e�r, �4� s •—_ 1 —
.
A
11. •*
t.1. i I,�
i - -
Fort Worth&Western Railroad
r
Q
low
�`" Yt
Il L k
•
rr.
JOEL EAST RD_jo bid=
21I N
--1°3
~\ /l ® 10 .SLY_ As-- E r��'«
121 IOr. t�..-.. Legend
' Oak Grove Rd
1. Ji-- � �, so I Y, fir y ♦ Z
\—m '°' r O (� City Streets '
i _ Railroads
i Project 0 0.0325 0.065 0.13 Fort Worth Cit Limit
Location . Miles Im r y
OneDnve-City of Fort Vlorfl1 0es;topU.52022 Cal,Greve Kh-d Jafar--`DE'022,OAK GFOVE RD 4PPRi�PRI..Jlof l.m<d
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 09/27/22 M&C FILE NUMBER: M&C 22-0732
LOG NAME: 062022 OAK GROVE RD APPROPRIATION
SUBJECT
(CD 8)Authorize Execution of a Roadway and Crossing Rehabilitation Agreement with the Fort Worth&Western Railroad in the Amount of
$313,598.90 for the Oak Grove Road North of Joel East Project,Amend the Fiscal Years 2022-2026 Capital Improvements Program,and Adopt
Appropriation Ordinances
RECOMMENDATION:
It is recommended that the City Council;
1. Authorize execution of a Roadway and Crossing Rehabilitation Agreement with the Fort Worth&Western Railroad in the estimated amount
of$313,598.90 for the Oak Grove Road North of Joel East project.(City Project No.101902);
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Developer Contribution Fund in the
amount of$257,882.00,from available funds,for the purpose of funding the Community Facilities Agreement-Oak Grove Road North of Joel
East project(City Project No.101902);
3. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the CFA Developer Fund in the amount of
$93,394.00,by increasing estimated receipts and appropriations in the Community Facilities Agreeement-Oak Grove Road North of Joel
East project(City Project No.101902),and decreasing estimated receipts and appropriations in the CFA Bucket programmable project(City
Project No. P00001)by the same amount;and
4. Amend the Fiscal Years 2022-2026 Capital Improvements Program.
DISCUSSION:
The purpose of this Mayor and Council Communication(M&C)is to authorize execution of a railroad crossing agreement and adopt the attached
appropriation ordinances to allocate funding to the Oak Grove Road from Altamesa Blvd to Joel East Road project(City Project No.101902).On
April 17,2018,by Mayor&Council Communication M&C C-28660,the City Council authorized execution of a Community Facilities Agreement
(CFA)with Rob Riner Companies GP, LLC, (Developer)in the amount of$2,487,274.00,which includes City participation in an amount not to
exceed$2,100,000.00 to construct Oak Grove Road from Alta Mesa Boulevard to Joel East Road,which includes adding lanes across existing
railroad right-of-way(City Project No.101902).
On July 21,2022,the City executed a Developer Funding Agreement for the Railroad Crossing at Oak Grove Road improvements
with the Developer in which the Developer contributed$257,881.90 toward the cost of the railroad crossing upgrades at the existing Union Pacific
Railroad(UPRR)tracks,which have been leased to the Fort Worth&Western Railroad(FWWR)for its use.This M&C authorizes execution of the
railroad crossing agreement with the FWWR,which has a controlling interest in the right-of-way.The balance, in the amount of$100,000.00,is
funded by the City.
Union Pacific Railroad (UPRR),has agreed to the improvements and the City has negotiated a license agreement in the amount of$44,283.00.
The City earmarked$100,000.00 as part of the$2,100,000.00 City participation to be applied towards the railroad crossing permit and
improvement work within railroad right of way,as reflected in CFA number 18-0187.
The table below summarizes the funding for the CFA-Oak Grove Rd N of Joel East project:
CFA-Oak Grove Rd N of Joel East(CPN 101902)
Fund Existing Budget Change Project
Funding (Increase/Decrease) Funding
Total
E
$0.00 $257,881.90 $257,881.90
operbution
30108 $2,100,000.00 $0.00 $2,100,000.00
Transportation
Impact Fee
Cap
30114 CFA 1 $93,394.001 $0.00 $93,394.00
Developer
Project Total $2,193,394.00 $257,881.90�$2,451,275.90
The action in this M&C will amend the Fiscal Year 2022 Adopted Budget as approved in connection with Ordinance 25073-09-2021, Section 6.
Capital Improvements as listed on page 23.
Capital Project FY2022 CIP Budget Revised
Fund Name Name Appropriations Authority Adjustment FY2022
Budget
30114-
Community P00001-
Facilities CFA $7,100,000.00 This M&C ($93,394.00) $7,006,606.00
Agreement Bucket
Fund
Funding is available in the Developer Contribution and Transportation Impact Fee Cap Funds for the CFA-Oak Grove Rd N of Joel East project.
Approval of Recommendation 3 will adjust appropriations between a programmable project and convert the CFA-Oak Grove Rd N of Joel East
project into a static capital project.This action is needed as future funding for this project is anticipated from other funding sources and the scope
of this project differs from that of the current programmable project.
This project is located in COUNCIL DISTRICT 8.
A Form 1295 is not required because:This M&C does not request approval of a contract with a business entity.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the CFA-Oak Grove Rd N of Joel Eas project within the Developer
Contribution Fund and in the Unspecified-All Funds project within the Transportation Impact Fee Cap Fund and upon approval of the above
recommendations and adoption of the attached appropriation ordinances,funds will be available in the Transportation Impact Fee Cap and
Developer Contribution Funds for the CFA-Oak Grove Rd N of Joel Eas project. Prior to an expenditure being incurred,the Transportation and
Public Works Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office b Dana Burghdoff 8018