HomeMy WebLinkAboutOrdinance 25747-09-2022 ORDINANCE NO. 25747-09-2022
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF $7,349,998.00, TRANSFERRED FROM AVAILABLE
FUNDS IN THE WATER AND SEWER FUND, FOR THE PURPOSE OF
FUNDING THE SANITARY SEWER REHABILITATION CONTRACT 99
PROJECT (CITY PROJECT NO. CO2720); PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2021-2022 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of$7,349,998.00, transferred from available funds in the
Water and Sewer Fund,for the purpose of funding the Sanitary Sewer Rehabilitation Contract 99 project(City
Project No. CO2720).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or
void for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way
impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining
provisions shall be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 25073-09-2021 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions
of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
D PR��I Yanno he,S. Goodall
D@lack(0ct 3,202213:07 CDT) Jannette S.Goodall(Oct 3,202213:09 CDT)
Douglas W.Black Jannette S.Goodall zt�
Senior Assistant City Attorney City Secretary ";.............
ADOPTED AND EFFECTIVE:September 27, 2022
"N...• 'fir`'
MAYOR AND COUNCIL COMMUNICATION
60SSRC99-CIRCLEC
SUNBURST DR
ONE
ati�
f. WtW I m r
Ir
ca
- O
t
.EVERMAN,PKWYL-L:' -
�s
.40
MgNpK
FF
n
ui
FORTWORTH N s
Ir
rq
�. . W- i
-
a», L ,-
� jam
C a�•- b �'�
TtIA
.� .♦. .�'$'te,�.' S n6'�3�� i i '�>� Rtid�''nL�g.�71 . �v,. .'-�..� 1':� �
per. , �;�.'V•+�� �� ,�,�"' ;�, *� - . �" � ��
Q3-• t ��t �' - t 9` `_ 7'] Pi�am' bppi� �l+ii
- �.+.f. ik � _ � ' `emu ��'�+""�'lid� tdsr-�st •��Y { ,rf�..
-
�'
rr�w[- _ �' .� '��J �. 1/�:s_ 131:�s•r � iZ- -.t � ��5
�u�l •�:. JK.; ''7.'Pw �f 1�,ei..a•. �M1.-3, �# «� N S F� "• ..,
RiAm
�bi�P`�a -,• _ 'ice��;f-�'� �i �, i
Al
illlMl
sm
WAM
.� ��'�p� ��'�� ..->{ � �:, •.�� O ����, +y' `ai' ''fit ,1� � `+ yam'
FORTWORTH.
Juml
` ('-"�17'r' ���� `-'�G. dw� !l. �1 O: J •'Ra-I 7'f. •I�DI �.� .3f 5}�
-
c
A
MAYOR AND COUNCIL COMMUNICATION
60SSRC99—CIRCLEC
I r
emOt
�+ , hI�ST.
1
# r
N- -oia,
\
115
_ �Ia NSA -
,�
_ ONG AUE�o > _ , -
r
s a Wlu
!' 9
Lu
t •1 ¢`'� rt # .{ 1 4 ;.Its \
-
1
N
FORT WORTH. s
31.STv STD . ,4
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 09/27/22 M&C FILE NUMBER: M&C 22-0734
LOG NAME: 60SSRC99-CIRCLEC
SUBJECT
(CD 2)Authorize Execution of a Contract with William J.Schultz, Inc.dba Circle C Construction Company, in the Amount of$6,457,527.00 for the
Sanitary Sewer Rehabilitation, Contract 99 Project and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal
Years 2022-2026 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a contract with William J. Schultz, Inc. dba Circle C Construction Company, in the amount of$6,457,527.00 for the
Sanitary Sewer Rehabilitation Contract 99 project;and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of$7,349,998.00,transferred from available funds within the Water and Sewer Fund,for the purpose of funding the Sanitary
Sewer Rehabilitation Contract 99 project(City Project No. CO2720)to effect a portion of Water's contribution to the Fiscal Years 2022-2026
Capital Improvement Program.
DISCUSSION:
This Mayor and Council Communication(M&C)is to authorize a construction contract with William J.Schultz, Inc.dba Circle C Construction
Company for the replacement of the deteriorated water and sanitary sewer mains located in the following streets,alleys,and easement:
LocationI From To Scope
Angle Avenue 152 ft.Southeast 30th Street Water/Sewer
�of Loraine Street
29th Str( JAngle Avenue ]Pearl Avenue Water/Sewer
Alley between Clinton
Avenue&Houston 30th Street 31 st Street Sewer
Street
Alley between Ross
Avenue&Clinton [29th Street 30th Street Sewer
Avenue
Prospect Avenue 585 feet south of 585 feet south Sewer/Point
31 st Street ��of 31 st Street Repair
157 feet West
Frank Felten Street Angle Avenue of Angle Sewer
Avenue
Alley between Clinton 250 feet North
Avenue&Ross Long Avenue of 34th Street Sewer
Avenue
Alley between Ellis 200 feet North
Avenue&Houston Long Avenue of 34th Street Sewer
Street
Alley between Ellis 130 feet North of 135 feet South Sewer
Avenue&Main Street 34th Street of 32nd Street
Alley between Main
Street&Commerce Long Avenue 34th Street Sewer
Street
Alley between Clinton 250 feet North
Avenue&Houston Long Avenue of 34th Street Sewer
Street
210 feet West
Loraine Street Angle Avenue of Loraine Sewer
Street
Gould Street 29th Street 320 feet South Sewer
_ � _ _ 11of 29th Street ]L---__
Alleyway between 29th Pearl Avenue Angle Avenue Sewer
Street&30th Street
100 feet North%15 feet North ��enue 29th Street f 29th Street Sewer
280 feet North
Market Avenue 29th Street of Market Sewer
_ Street _
Easement between 85 feet East of
Loraine Street&29th Angle Avenue Lincoln Avenue Sewer
Street
Oak Grove Road Everman Enon Road Sewer
Parkway
The project was advertised for bids on July 28,2022,and August 4,2022, in the Fort Worth Star-Telegram.On August 25,2022,the following bids
were received:
Bidder [_Amo�untFTime of
Completion
William J.Schultz, Inc.dba Circle C 540
Construction Company $6,457,527.00 Calendar
Days
In addition to the contract amount,$633,549.00(Water:$163,949.00;Sewer: $469,600.00)is necessary for project management,inspection and
material testing and$258,922.00(Water:$78,980.00;Sewer:$179,942,00)is provided for project contingencies.The sewer component of this
project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.Approximately 1,555 linear feet of cast iron pipe will be
replaced as part of this project.
This project will have no impact on the Water Department's operating budgets when completed.
It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year,instead of within the annual budget ordinance,as
projects commence,additional funding needs are identified,and to comply with bond covenants.The actions in the M&C will amend the City of
Fort Worth's Fiscal Year 2022-2026 Capital Improvement Program as follows:
60SSRC99-CIRCLEC
Budget Capital Revised
Project FY2022 CIP Change
Fund Authority FY2022
Name Name Appropriations (Increase/ Budget
Decrease) g
56002- CO2720—
W&S SaniSewer
Capital Rehab $0.00 This M&C $7,349,998.00 $7,349,998.00
Projects Contract
Fund 99
Funding is budgeted in the Transfer to Water/Sewer account of the Water and Sewer operating budget for the purpose of funding the SaniSewer
Rehab Contract 99 project within the Water&Sewer Capital Projects Fund.
Appropriations for the Sanitary Sewer Rehabilitation Contract 99 project are as depicted below:
Fund Existing rAr
ditional project Total*
Appropriations propriations
W&S Capital
Projects-Fund $569,200.00 $7,349,998.00$7,919,198.00
56002
Project Total 11 $569,200.00 $7,349,998. 00�$7,919,198.00
*Numbers rounded for presentation purposes.
Business Equity: William J.Schultz, Inc.dba Circle C Construction Company,is in compliance with the City's Business Equity Ordinance by
committing to 16 percent Business Equity participation on this project.The City's Business Equity goal on this project is 16 percent.
The project is located in COUNCIL DISTRICT 2.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the Water& Sewer Fund and upon approval of the above recommendations and
adoption of the attached appropriation ordinance, funds will be available in the W&S Capital Projects Fund for the SaniSewer Rehab Contract
99 project to support the approval of the above recommendations and execution of the contract. Prior to any expenditure being incurred,the Water
Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: Pratima Poudyal 6149