HomeMy WebLinkAboutOrdinance 25756-09-2022 ORDINANCE NO. 25756-09-2022
AN ORDINANCE ADJUSTING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE GENERAL CAPITAL PROJECTS FUND, BY
INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE LAKE
WORTH WATER LINE SANITARY SEWER IMPROVEMENTS PROJECT(CITY
PROJECT NO. 100962) IN THE AMOUNT OF $765,188.00 AND DECREASING
ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE CONTRACT STREET
MAINTENANCE PROGRAMMABLE PROJECT (CITY PROJECT NO. P00020)
BY THE SAME AMOUNT; PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;AND PROVIDING
AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2021-2022 in the
Budget of the City Manager,there shall also be adjusted estimated receipts and appropriations in the General
Capital Projects Fund, by increasing estimated receipts and appropriations in the Lake Worth Water Line
Sanitary Sewer Improvements project(City Project No. 100962)in the amount of$765,188.00 and decreasing
estimated receipts and appropriations in the Contract Street Maintenance Programmable Project(City Project
No.P00020)by the same amount.
SECTION 2.
That should any portion,section or part of a section of this ordinance be declared invalid,inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 25073-09-2021 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
BEV, Gl`legae S opd ZZ
D$lack(Oct 3,202214:24 CDT) Jannette S.Goodall(Oct 3,202214: OR T
Douglas W.Black Jannette S.Goodall Gji®
Senior Assistant City Attorney City Secretary Al;
'A
ADOPTED AND EFFECTIVE: September 27,2022
MAYOR AND COUNCIL COMMUNICATION MAP
60LWWSSP2-WOODY
r y.
Ile
04
Xx
\ ;, s 3i
Allo S�
Soo 41�' i
It
i �'�' ,?� �� ,fit, ,, � • �' � •tiR\\1�� ,A'/
\ ,`/ �, ���;,�" A�, \/ •✓�� ��`'• r
44
PIZ
, +.� ,��-�;`%� '_ ��`'i'.,�� � ',' � < f.` . .tlo�'�` ,�/��! ,•'`�'�
, .,
j
—AL ���fJfVVV
loo
ok
FART NORTH T.. �n �/ .�, `. ; N X .
r
MAYOR AND COUNCIL COMMUNICATION MAP
60LWWSSP2-WOODY
l¢ jTRF G
Li
Lu
Yr '
f
u o j
"- -iu CAR `r C�,Q,
ui
cof - i`. iQ� d rk.14m
j* O�, \ 4
- � =,�RD� • �, ,+ p Z. � ilk, rye
VA
BOICOURTST'
w
W �� �d y xN"
LL
O
LL
FOR
w U uj L$1D
Lu
LLI
m
Z
_SOUTHBROOKDR'\ ,L
t �
r —
FORT WORTH
Lu
; .;.
�..
MAYOR AND COUNCIL COMMUNICATION MAP
60 LWWSS P2-WOODY
ICI yy _ ELL
f
BASSWOODDR —
RHEA RIDGEDR__ m
DAXD
I]ROXANNEWAY V, p_; I. �'�
r
cod .`
h N WAY
,y E `
WOppCT ��
Cj
fi.
'- : =Ofi, .jV °Q�'� -
�(�� i j J�f 1 ��tv.,�t%,.\ ti JOOQCj. z }�
Oo .51
, , 1s Or�E_Cl�ip�
I
L�I r f
w' r ��,; - I.. JOHNS WAY , Jill
ff
v �� i i i KEYHOL'ECIRr
z Z
O
LAKESIDEDR!' �p
ui
Q CANYONTRL _ _ � - -
Ir ht
IJ
LONGHORNTRL '
(2' ;BIG'BENDTRL
FORT WART
' 1fi �iCIRCLETRL1:
f I , 1 �j, .... �. I.—, . 11, el
ti
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 09/27/22 M&C FILE NUMBER: M&C 22-0753
LOG NAME: 60LWWSSP2-WOODY
SUBJECT
(CD 2 and CD 7)Authorize Execution of a Contract with Woody Contractors, Inc.,in the Amount of$6,232,406.50,for the Lake Worth Water Line
Sanitary Sewer Improvements Project and Adopt Appropriation Ordinances to Effect a Portion of Water's Contribution to the Fiscal Years 2022-
2026 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a contract with Woody Contractors, Inc., in the amount of$6,232,406,50,for the Lake Worth Water Line Sanitary
Sewer Improvements project;
2. Adopt the attached appropriation ordinance increasing appropriations in the Water and Sewer Capital Projects Fund in the amount of
$6,346,752.00,transferred from available funds within the Water and Sewer Fund,for the purpose of funding the Lake Worth Water Line
Sanitary Sewer Improvements project(City Project No. 100962)to effect a portion of Water's contribution to the Fiscal Years 2022-2026
Capital Improvement Program;
3. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the General Capital Projects Fund by
increasing receipts and appropriations in the Lake Worth Water Line Sanitary Sewer Improvements project(City Project No. 100962)in the
amount of$765,188.00, and decreasing receipts and appropriations in the Contract Street Maintenance programmable project(City Project
No. P00020)by the same amount;and
4. Amend the Transportation and Public Works FY2022-2026 Capital Improvement Program.
DISCUSSION:
This Mayor and Council Communication(M&C)is to authorize a construction contract for the replacement of deteriorated water and sanitary sewer
mains on the following streets:
L_street From To Scope of
Work
Johns Way Norris Valley Drive Shadydell Drive Water/Sewer)
Huntdale Johns Way Cul-de-sac Water/Sewer
Court
Rushwood Johns Way Johns Way Water/Sewer
Court I----
Jolley Court Johns Way Johns Way Water/Sewer
Circle Ridge Skyline Drive Circle Ridge Drive Water/Sewer
Drive W
Crown Road JlSkyline Drive Cul-De-Sac Water/Sewer
Circle Ridge Circle Ridge Drive F
sboro Highway Water/Sewer
Drive W
Jacksboro Circle Ridge Drive Capri Drive Water
Highway
Easement 500 feet east of the
east of Circle Ridge/ Northeasterly 860 feet Sewer
Circle Ridge Hillside Drive
Drive Intersection
Easement
between 250 feet south of
Skyline Drive Montrose Drive/ Westerly 200 feet Sewer
/ Brookhollow Drive
Brookhollow Intersection
Drive
Easement
between 250 feet south of
Montrose the Montrose Drive Southerly 300 feet Sewer
Drive and /Skyline
Southbrook Intersection
Drive �I--------��---- --_�L__
Easement A point located 200 Southwesterly 800 feet,
between feet north and 450 westerly 200 feet,
Sherman feet east of the southwesterly 800 feet, Sewer
Avenue and Sherman Avenue/ then westerly 200 feet,
Titus Street 30th Street then southwesterly 800
intersection feet
Additionally,asphalt pavement rehabilitation will be conducted on all streets subsequent to the water and sanitary sewer main replacement.The
Water Department's share of this contract is$5,517,277.75 and the Transportation&Public Works Department's share of the contract is
$715,128.75.
The project was advertised for bids on July 21,2022,and July 28,2022,in the Fort Worth Star-Telegram.On August 18,2022,the following bids
were received:
Bidder i—t7l Time of Completion
Woody Contractors, Inc. $6,232,4 16.50 500 Calendar Days
In addition to the contract amount,$534,402.00(Water:$182,222.00; Sewer:$352,180.00)is required for project management,material testing
and inspection,and$345,131.50(Water: $115,245.50;Sewer:$179,826.75; Paving:$50,059.25)is provided for project contingencies.
The sanitary sewer component of this project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.Approximately 4,600
linear feet of cast iron pipe will be replaced as part of this project.
This project will have no impact on the Water or Transportation&Public Works Department's operating budget when completed.
The action in this M&C will amend TPW's contribution to the Fiscal Years 2022-2026 Capital Improvement Program as approved in connection
with Ordinance 25073-09-2021,Section 6.Capital Improvements, page 23,as follows:
Capital Revised
Fund Project FY2022 CIP Authority Budget FY2022
Name Name Appropriations Adjustment Budget
30100
- P00020-
General Contract $20,441,000.00 M&C 21- $(1 050,034.00) $19,390,966.00
Capital Street 0827
Projects Maintenance
Fund JI
MO 362 $(311,148.00) $19,079,818.00
EIE71 M01 22- $(603,254.00) $18,476,564.00
27
M&C 22- $(1,403,324.00) $17,073,240.00
0323
��� M&C 22- $(1,000,000.00) $16,073,240.00
0541
M06 22- $(200,000.00) $15,873,240.00
0630
M 06 22- $(539,672.00) $15,333,568.00
0650
=0 This M&C $(765,188.00) $14,568,380.00
It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year, instead of within the annual budget ordinance, as
projects commence,additional funding needs are identified,and to comply with bond covenants.The actions in the M&C will appropriate funds in
support of the Water's portion of the City of Fort Worth's Fiscal Years 2022-2026 Capital Improvement Program,as follows:
60LWWSSP2-WOODY
Capital Revised
Fund Project FY2022 CIP Authority (I Budget Change Decrease) FY2022
Name Name Appropriations g
Bud et
W&S 100962-
Capital Lake Worth
Projects WL SS $0.00 This M&C $6,346,752.00$6,346,752.00
—Fund Improvements
56002
General 100962-
Capital Lake Worth
Projects WL SS $0.00 This M&C $765,188.00 $765,188.00
—Fund Improvements
30100
Funding is budgeted in the Contract Street Maintenance Programmable project within the General Capital Projects Fund and in the Transfer to
Water/Sewer account of the Water and Sewer operating budget for the purpose of funding the Lake Worth Water Line Sanitary Sewer
Improvements project within the Water&Sewer Capital Projects Fund.
Appropriations for the Lake Worth Sanitary Sewer Improvements project are as depicted below:
Ex Additional
F— Fun�Appropriatistingions Appropriations Project Total*
Water&Sewer
Capital Projects $3,704,821.00 $6,346,752.00 $10,051,573.00
Fund 56002
General Capital
Projects Fund $0.00 $765,188.00 $765,188.00
30100
Project Total $3,704,821.00] $7,111,940.00 $10,816,761.00
*Numbers rounded for presentation purposes.
MM/BE OFFICE: Woody Contractors, Inc.,is in compliance with the City's Business Equity Ordinance by committing to 16 percent MWBE
participation on this project.The City's MWBE goal on this project is 17 percent,
The project is located in COUNCIL DISTRICTS 2 and 7.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current operating budget of the Water&Sewer Fund and the Contract Street
Maintenance programmable project within the General Capital Projects Fund,and upon approval of the above recommendations and adoption of
the attached appropriation ordinances,funds will be available in the W&S Capital Projects Fund and the General Capital Projects Fund for the
Lake Worth SS project to support the above recommendations and execution of the contract. Prior to any expenditure being incurred,the Water
and Transportation&Public Works Departments have the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by. Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: Walter Norwood 5026
Expedited