HomeMy WebLinkAboutContract 54223-CO4 CSC No. 54223-CO4
FORT WORTH City of Fort Worth
Change Order Request
Project Name: Lake Arlington Lift Station City Sec No.: 54223
Project No.(s): 56019107004301001480 NTP N/A City Proj.No.: 100995
Project Description: Construction of a new Sanitary Sewer Lift Station for the Lake Arlington Force Main Project
Contractor: Bar Constructors Inc. Change Order# ® Date: 9/26/2022
City Project Mgr,J Pratima Poudyal City Inspector: I Nathan Gray
Phone Number: 817-392-6149 � Phone Number: 817-392-4961
Dept. Unit I Ltft Station Unit II Water Alternate A•2 Totals Contract Time
Calendar days
Original Contract Amount $9,422,126.00 $72,565.00 $583,002.00 $10,077,693.00 487
Extras to Date $34 736,54 $0.00 $0.00 $34,736.54 232
Credits to Date $31,809.91 $0.00 $0.00 $31,809.91
Pending Change Orders(in M&C Process)
Contract Cost to Date $9,425,052.63 $72,565.00 $583,002.00 $10,080,619.63 719
Amount of Proposed Change Order •$3 724.15 $0.00 $0.00 •$3,724.15
Revised Contract Amount $9,421,328.48 $72,565.00 $583,002.00 $10,076,895,48 719
Original Funds Available for Change Orders $201,554.00 $0.00 $0.00 $201,554.00
Remaining Funds Available for this CO $198,627.37 $0.00 $0.00 $198,627.37
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT -0.01%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $12,597,116.25
JUSTIFICATION(REASONS)FOR-CHANGE ORDER
Change Order No.4 provides compensation for a sample precast building panel for the electrical building before a final selection was made.
The change order also provides credits for remaining work for the 24"sanitary sewer line tie-in which is being delayed until construction of
the force main.The credit includes installation of remaining pipe,by-pass pumping,core hole into existing manhole,manhole coating and
weir wall installation.Additional credit is also provided for remaining Commissioning Activities:pump performance testing,discharge
transmitter calibration,flow meter calibration,check valve adjustment,odor control testing,and level instrument calibration.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Chango Order.
(:Mtm*es Compaq Name comractor Noma cowa*rStrature Date
Bar Constructors Inc. IMarlene Arrambide 09/27/22
Ins or Date Pro1w Mweger Date
Zile-
9/27/2022 09/27/2022
Director Water e t Oats Co cifont r afar Dept) Date.
Sep 28,2022
A"istant City Attome Date I I Assistant City MaMer Date
Sep 29,2022 Dana au�n o Sep 29, 2022
Comell A t7h of So i*odl OFFICIAL RECORD
M&C Number NIA M&C Date Approved CITY SECRETARY
FT.WORTH,TX
FCi RT W"RT H City of Fort Worth
Change Order Additions
Project Name Lake Arlington Lift Station City Sec No.: 1 54223
Project No.(s): 56019/07004301001480 DOE No. N/A City Proj.No.: 100995
Project Construction of a new Sanitary Sewer Lift Station for the Lake Arlington Force Main Project
Description
Contractor Bar Constructors Inc. Change Order: ® Date: 9/26/2022
City Project Mgr. Pratima Poudyal City Inspector Nathan Gray
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
46 Electrical Building Pre-cast Panel Unit I Lift Station 1.00 LS $6,600.00 $6,600.00
Unit I Lift Station $6,600.00
Unit II Water
Alternate A-2
Page 1 of 3 Additions Sub Total 1$6,600.00
FCo RT WO RT H City of Fort Worth
Change Order Deletions
Project Name Lake Arlington Lift Station City Sec No.: 54223
Project No.(s): 56019/0700430/001480 DOE No. N/A City Proj. No.: 100995
Project Description Construction of a new Sanitary Sewer Lift Station for the Lake Arlington Force Main Project
Contractor Bar Constructors Inc. Change Order: F4 Date F 9/26/2022
City Project Mgr. Pratima Poudyal City Inspector: Nathan Gray
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
4 3331.4311 24"Fiberglass Sewer Pipe with Select Backfill Unit I Lift Station 9.11 LF $174.00 $1,585.14
10 3339.1101 5'Diameter Sewer Manhole Unit I Lift Station 0.12 EA $24,100.00 $2,988.40
38 Variable Frequency Drive(500hp VFDs) Unit I Lift Station 0.03113 EA $184,705.00 $5,750.61
Unit I Lift Station $10,324.15
Unit II Water
Alternate A-2
Deletions Sub Total 1$10,324.15
Page 2 of 3
IVIMBE Breakdown for this Change Order
MWBE iSub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
Page 3 of 3
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
v ''l
Signature
Pratima Poudyal,P.E.
Name of Employee
Project Manager
Title
,dpF,o 0000°Opo
ATTEST: ��a° °°�0���
0
�o .
7a11118tte c�GooclaCC V o °Z
Ja..em S.eooaan(SIP z9,mzueai CDT) 1 o
O° O Ty
° 00 /y
°OOOOo° b
Jannette Goodall rEXpSoaQ
City Secretary
i
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
i
09/26/2022
CPN 100995
Lake Arlington Lift Station
Change Request 4 Notes
Staff has reviewed the change order price and considers it to be fair and reasonable.