Change Order Request
O°0°000° !y
rEX p5oap Facility and
Project Existing Drop-Off Stations-Building Modifications&Site Modifications:Old City Sec No. 52793
t Hemphill Road
Description:
Funding(FID)54002-0239901-5740010-100192-000880-9999 City Proj.No. 100192
No.(s)
Contractor: Basecom,Inc. Change Order#F_ Date: 9I26I2022
City Project Mgr.Alfonso Meza City Inspector: I Don Isaacs
Phone Number:(817)392-8274 Phone Number: (817)392-8078
Contract Time
(CD)
Original Contract Amount $1,194,241.00 190
Extras to Date $0.00 0
Credits to Date $0.00 0
Pending Change Orders(in M&C Process) $0.00 0
Contract Cost to Date $1,194,241.00 0
Amount of Proposed Change Order $64,955.00 30
Revised Contract Amount $1,259,196.00 220
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00
Additional Funding(if necessary) $0.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 5.44 %
MAXALLOWABLECONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $1,492,801.25
JUSTIFICATION(REASONS)FOR CHANGE ORDER
The purpose of Change Order#1 is to install 6 light poles around the perimeter of the site.Change Order No.1 increases the original contract
($1,194241.00)by$64,955 for a revised contract amount of$1.259,196.00.A 5.44 percent increase to the original contract price.Additionally,
there are 30 days added to the contract for this work.
It is understood and agreed that the acceptance of this Change Order by the contractor consitutes an accord and satisfaction and represents
payment in full(both time and money)for all costs arising out of,or incindental to the above Change Order.
AkjBasecom,Inc. 0__(s,p27, 7:09CDT) Sep 27,2022
a�
Contractor's Company Name Contractor Name Contractor Signature Date
6/G Sep 27,2022 Oct 3,2022
on iaaa6(SIP 2 a0 CDT
PMD Inspector Date Architecural Services Manager Date
awe Sep 28,2022 Oct 3,2022
PMD Superintendent Date Director Property Management Department Date
Oct 3,2022 C�a s � Oct 4,2022
PMD Project Manager Date Assistant City Attorney Date
Oct 3,2022 75ar i &, a�da Oct 4,2022
Dana BurDana Dur h- 0:321 6 CDT
Project Architect Date Assistant City Manager Date OFFICIAL RECORD
M&C Number N/A M&C Date Approved N/A CITY SECRETARY
FT.WORTH, TX
Contrail Compliance Manager:
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including Brian R.Glass,AIA
ensuring all performance and reporting requirements. Architectural Services Manager
June 2018 Rev 1
' BASECOM
CONSTRUCTION SERO E
722 Missouri Ave., Fort Worth,Texas 76104
(817) 589-0050 Fax: (817)483-2609
January 21,2021
The City of Fort Worth
Attn: Scott Fisher
Re: City of Fort Worth—Old Hemphill Drop Off Station
Revision 1 Request for Change #8
Mr. Fisher,
Basecom, Inc. is pleased to submit Revision 1 for RFC 98 for the City of Fort Worth—
Drop Off Station—Old Hemphill project. This RFC reflects the changes issued in Revisions 10
& 11.
Please see below for pricing and breakout.
Item 2 -Additional Pole Lights (6)
- Basecom Electrical to Install 6—30' Poles & Lighting $ 38,548.00
- Convenience Outlets at Poles (2) $ 1,350.00
- BASECOM ADDITIONAL GENERAL CONDITIONS $ 15,172.00
OVERHEAD& FEE FOR BASECOM WORK (15%) $ 8,260.00
BONDS $ 1,625.00
TOTAL $64,955.00