HomeMy WebLinkAboutContract 54212-CO5 CSC No. 54212-CO5 FORT WORTH. City of Fort Worth Change Order Request Project Name 2018 CIP Year 2-Contract 17 City Sec# 54212 Client Project#(s) 101477-Year 2 Contract 17 Project This is a combined street paving improvements and water and sanitary sewer main replacements project Description Contractor Stabile and Winn,Inc. Change Order# 5 Date 9/23/2022 City Project Mgr. Jose A Orozco City Inspector Aaron Ybarra Dept. Unit 1:Water Unit 2:Sewer Unit 3:Paving Unit 4:Storm Contract Time Totals (CD) Original Contract Amount $1,675,777.50 $653,464.50 $4,217,834.30 $224,475.00 $6,771,551.30 450 Extras to Date $0.00 $109,950.00 $106,474.50 $212,689.00 $429,113.50 93 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1,675,777.50 $763,414.50 $4,324,308.80 $437,164.00 $7,200,664.80 543 Amount of Proposed Change Order $0.00 $0.00 $0.00 $0.00 84 Revised Contract Amount $1,675,777.50 $763,414.50 $4,324,308.80 $437,164.00 $7,200,664.80 627 Original Funds Available for Change Orders $83,789.00 $32,673.00 $210,892.00 $22,448.00 $349,802.00 Remaining Funds Available for this CO $83,789.00 $0.00 $104,417.50 $0.00 $188,206.50 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 6.34% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $8,464,439.13 JUSTIFICATION(REASONS)FOR CHANGE ORDER This change order adds additional time and scope to the project to cover delays caused by several factors. The total number of days requested by the contractor was negotiated and vetted by the project management team. Additional time approval was considered justified for the following factors: 1)12 days for Construction Allowance#2 forsub-contractorto remobilize&relocate 10 existing waterservices along Willing Ave-12/2/2021-12/13/2021 2)19 days for Extended cold/freezing weather days-(2021)2/11-2/19&(2022)1/20,2/3,2/4,2/23-2/25 3)11 days for additional sidewalk curb scope at 3012,3009,3008,3004,3001&2940 Willing-3/18/2022-3/28/2022 4)37 days for Concrete&material supplier issues limiting Concrete delivery,reduced from 200 CY/day to 50 CY/day,Beginning 8/2021&through project end. 5)5 days for AT&T delay to adjust manhole at Willing and Bowie-6/8/2022-6/15/2022 In total,84 Callendar Days(CD)were approved. This change order will also add new bid item for`Remove and rest forms"at 3109 Willing as a result of changing scope to install retaining wall after the contractor installed the forms per the original scope.It will also add a bid item to`install Railroad cross ties and Backfill°at 3121 Willing to install railroad ties per the property owner request to match before project condition.The change order will also add new bid item`FH Stem Extension;for adjusting the existing Fire Hydrant at NE comer of Willing&Berry on a segment of the water line that was not replaced as part of this project. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. Contractor's Company Name'l Contractor(Name Contract Signature Date STABILE&WINN INC Jerry Henderson — Sep 26,2022 Inspector/Inspection Supervisor Date Project and Contrac ompliance Manager Date _Aa.e Sep 27,2022 '-A 0— Sep 26,2022 Program Manager Date Senior Capital Project Officer Date rs,�.�.✓✓ Sep 27,2022 tom` Sep 29,2022 Assistant Director(Dept) Date Director,Contracting Department(Dept) &L Date Oct 1,2022 ,..,. /`1 Oct 3,2022 Assistant City Attorney ssistant City Manager Date fort worth Oct 3,2022 o Oct 4, 2022 ouncil Action(if required) M&C Number M&C Date Approved ATTEST: Ja-1ell?s good- FoRr��a Jannette Goodall,City Secretary d 0°°o°o°o°° � a a�° °°°0 OFFICIAL RECORD 0 °2d CITY SECRETARY Y °0. o d °°°°°°°°° o`y° FT.WORTH, TX � �EXASoAp FORTWORTH City of Fort Worth Ir- Change Order Additions Project Name 2018 CIP Year 2-Contract 17 City Sec# 54212 Client Project# 101477-Year 2 Contract 17 Contractor Stabile and Winn,Inc. PM Jose A Orozoo Inspecto Aaron Yba- Change Order Submittal# OS Date 9/23/2022 AUUI I IUN5 Unit Units o a 1-45 Fire Hydrant Stem Extension m a er Remove and rest torms m among Install i roa cross Ties and Backfillm among Unit 1:Water $900.00 Unit 2:Sewer $0.00 Unit 3:Paving $2,891.00 Unit 4:Storm $0.00 Sub Totalirons Change Order Additions Page 2 of4 FOx aH City of Fort Worth Change Order Deletions Project Name 2018 CIP Year 2-Contract 17 City Sec# Client Project# 101477-Year 2 Contract 17 Contraclo Stabile and Winn,Inc. PM Jose A Orozco InspectorF Aaron Ybarra Change Order Submittal# O5 Date 9/23/2022 DELL I IUNS y Unit UnitCost o a Construction Allowance 77 77ater 71-815 Construction Allowance m among Unit :Water Unit 2:Sewer S0.00 Unit 3:Paving S Unit4:8torm 50.00 Sub I otal Deletons Change Order Deletions Page 3 of 4 M/SBE for this Change Order M/SBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders co# DATE AMOUNT Total $0.00