HomeMy WebLinkAboutContract 57154-CO2 CSC No. 57154-CO2 FORT WORTH. City of Fort Worth Change Order Request Project Name Trail Gap Connections City Sec# 57154 Client Project#(s) 101632 Construction of accessible trails connecting to the existing trail system at two separate locations throughout the city:Arcadia Trail Park to Beach Street Project Description (48594899 Seneca Dr,Fort Worth,TX 76137)and Buck Sansom Park to HWY 820(3600 Sansom Park Dr,Fort Worth,TX 76106) Contractor 2L Construction,LLC Change Order# 2 Date 8/24/2022 City Project Mgr. Robert Kevin Rodriguez City Inspector Jason Bradley Dept. PARD Totals Contract TimeCD Original Contract Amount $1,386,580.00 $1,386,580.00 180 Extras to Date Credits to Date Pending Change Orders(in M&C Process) $17,660.00 $17,660.00 10 Contract Cost to Date $1,404,240.00 $1,404,240.00 190 Amount of Proposed Change Order $15,600.00 $15,600.00 10 Revised Contract Amount $1,419,840.00 $1,419,840.00 200 Original Funds Available for Change Orders $33,260.00 $33,260.00 Remaining Funds Available for this CO $15,600.00 $15,600.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 2.40% MAX ALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $1,733,225.00 JUSTIFICATION(REASONS)FOR CHANGE ORDER On December 14,2021,City Council authorized the execution of a construction contract with 2L Construction,LLC,in the amount of$1,386,580.00 for the Trail Gap Connections project(M&C 21-0998).Since the award of construction,regarding the trail portion from Arcadia Trail Park to Beach Street,additional trees(not shown or accounted for in the original plan set)have been required to be removed.The additional scope of work will increase the contract time from 190 calendar days to 200 calendar days. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. Contractor's Company Name NJJMG10r ame) rac r 2L Construction,LLC Chip Fisher Aug 29,2022 Inspector/Inspection Supervisor Date Pro ect and Contract Compliance Manager Date �aa Sep 6,2022 JteuiaJ Aug 24,2022 Program Manager Date Senior Capital Project Officer Date Sep 6,2022 Assistant Director(Dept) Date Director,Contracting Department(Dept) Date 1 ' Sep 23,2022 ,a.�9' Sep 29,2022 Assistant City Attorney Date lAssistant City Manager Date Oct 3,2022 'v' , j_ Oct l l,2022 Council Action if required) M&C Number M&C Date Approved ATTEST: Jannette Goodall,City Secretary p OL°o°000°°O��a� 0~0 0..4d OFFICIAL RECORD 0d0 o o��d CITY SECRETARY °°°°°°°°°°° a FT.WORTH, TX FORT WORTH City of Fort Worth - W--- Change Order Additions Project Name Trail Gap Connections City Sec# 57154 Client Project# 101632 Contractor 2L Construction,LLC PM Robert Kevin Rodriguez Inspector Jason Bradley Change Order Submittal# O2 Date 8/24/2022 AUUI I IONS y Unit UnitCost Total PARD $15,600.00 bub I otal Additions Change Order Additions Page 2 of 4 FORF W RrrH City of Fort Worth Change Order Deletions Project Name Trail Gap Connections City Sec# 57154 Client Project# 101632 Contractor 2L Construction..LLC PM Robert Kevin Rodriguez Inspector Jason Bradley Change Order Submittal# O2 Date 8/24/2022 DLLLIIUNJ City Unit ni os I ota PARD El u ota Deletions Change Order Deletions Page 3 of 4 M/SBE for this Change Order M/SBE Sub Type of Service Amount for this CO Maintaining commitment on original agreement of 17% Total $0.00 Previous Change Orders co# DATE AMOUNT 1 7/27/2022 $17,660.00 Total $17,660.00