HomeMy WebLinkAboutContract 54041-CO3 CSC No. 54041-CO3
FORT WORTH City of Fort Worth
Change Order Request
Project Name f Riverside Community Park Phase I Improvements Project City Sec# 1 54041
Client Project#(s) C01196
Project Description Riverside Community Park Phase I Improvements
Contractor Nodhstar,Construction LLC Change Order#I 3 Date 8/31/22
City Project Mgr. — Tonda Rice f City Inspector[ Ozzie Ouimelte
Dept. PARD 240 Calendar Days Contract Time
Totals (CD)
Original Contract Amount 180
Extras to Dale A $45,677.20 1 1 . 45,677.20 90
Credits to Dale $2,353.00 $2,353.00 -
Pending Change Orders(in MSC Process) I $0.00 I I I I I
Contract Cost to Dale $1,911,179.20 $1,911,179.20 270
Amount of Proposed ange Order .00 $0.00
ewsed onlracl Amount
Original Funds Available for Change Orders $0.00
Remaining Funds Available for[his CO $0.00 i I
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OFORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST♦25%) $2,334, TS
JUSTIFICATION(REASONS)FOR CHANGE ORDER
During construction it was determined that:
1. Due to water erosion and sandy sediment buildup under the asphalt surface of parking lot#1 and#2. The asphalt surface was not stable
enough to be resurfaced.Requiring both parking lots to be reinforced with 6"concrete.
2 .One additional bench was needed due to under run on plan count.
3.A height adjustment of a sanitary sewer manhole was required at the entry drive of parking lot#3.
4.Installation of 4 temporary battery control irrigation valves for Bio-swales were added to keep the Bio-swale plant materials alive.
5.Drainage swales were needed on south side of playground for water flow control.
6.Repair and straightening of 8"bollards around parking lot#2 were required due to degradation of the asphalt caused by the erosion and
sediment build up under the asphalt parking lot.
Additional 100 calendar days were added to the project for a total of 370 calendar day for the project.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract,Including ensuring all performance and reporting requirements.
Contractor's Company Name Contractor(Name) Contract Sionalure Date
Northslar Conslurclion,LLC Michael Heimlich '-
Ifowamn
ectorllnspection Supervisor a roject and Contract Compliance Manager Date
•�;,'r�%.L, •? ep 15,2022 •� Sep 15,2022
Manager Date enor Capital ProjectOfficer Date
Sep 22,2022
Nsislanl Director(Dept) Date-11 Acting Director,Contracting Department Date
Oct 5,2022 Oct 5,2022
ssislanlCityAllamev I Date lAssistantCiMManB ram;_" I_ Dale
Oct 5,2022 Oct 10,2022
Council Action if required)
M&C Number M&C Date Approved
AAFWo 5.Goodall
J tte S.G..&11(0112,202216s0 CDT)
a o F°Rr�aa
Jannette S. Goodall OF °°°°°°
a� d�
�o °o���
000° g=�
�A�'�°000000000,°° d OFFICIAL RECORD
a�n>1 AS�ao
CITY SECRETARY
FT.WORTH, TX
For, WokrH City of Fort Worth
v___ Change Order Additions
Project Name Riverside Community Park Phase I Improvements Project City Sec# 54041
Client Project# C01196
Conbaclor Northstar,Construction LLC PM Tonda Rice Inspeclofl Ozzie Ouimetle
Change Order Submittal# 0 Dale 4/21/2022
ADDITIONS
ITEM —DESCRIPTION DEPf ty Unit Unit Cost Total
3.4 Benches
3.1 Reconstruct North Parking Lot#1 with "reinforced concrete 1.00000000 LS 45,272.00
3.2 Reconstruct Playground Parking Lot#2 with 6'reinforced concrete 1.0000 000 L 42,642.00
3.3 Adjust sanitary sewer manhole in approach to Parking Lot#3 1.00000000 LS $ 65.00
3.4 Install 4 each temporary battery controlled Irrigation vales 1,00000000 LS $1.470.00
3.5 Install drainage Swale on south side of playground 1.0000000 LS 775.00
3.6 Repair/straighten 0"bollards around parking lots PARD 1.00000000 LS $1,545.00
PARD 594,069.00
240 Calendar Days $0.00
Sub TOIaI Additions S9 ,069.00
Change Order Additions Page 1 of 1
Four Won m City of Fort Worth
Change Order Deletions
Project Name I Riverside Community Park Phase I Improvements Project City Sec# 54041
Client Project 4 1 C01196
Contractor Northslar,Construction LLC I PM Tonda Rice Inspector Ouie Ouimelle
Change 0rderSubmitlal# 0 Date 412112022
DELETIONS
ITEM DESCRIPTION DEPT ly Unit Unitcostiota!
1.6 Construction AllowaRce PARD 0D L 50,00
ignagemowance PARD ---LT-- 5,
Asphalt Resu acing PARD 6,180.00000005
Pedestrian Paving 8 Sidewalks PARD 5,5. 0 F .0 ,b .
PARD 5115,806.00
240 Calendar Days $0.00
Sub Total Deletions 115,
Change Order Deletions Page 1 of 1
MISBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
Co# DATE AMOUNT
Total $0.00
NORTHSTAR
CONSTRUCTION,LLC
April 21, 2022
Change Order Proposal #: 03
Ms. Tonda Rice
City of Fort Worth
200 Texas Street
Fort Worth, Texas 76102
RE: City Project No: C01196
Riverside Community Park - Phase 1 Improvements
Dear Ms. Rice,
Northstar offers the following Change Order Cost Proposal for the site grading and concrete
adjustments on the above referenced project.
Seq# Description Quantity Units Unit Price Extended Price
Additions
3.4 Benches 1 EA $ 1,900.00 $ 1,900.00
Reconstruct North Parking Lot#1 With 6" Reinforced
3.1 Concrete 1 LS $ 45,272.00 $ 45,272.00
Reconstruct Playground Parking Lot#2 With 6"
3.2 Reinforced Concrete 1 LS $ 42,642.00 $ 42,642.00
Adjust Sanitary Sewer Manhole In Approach To Parking
3.3 Lot 3 1 LS $ 465.00 $ 465.00
Install 4 Each Temporary Battery Controlled Irrigation
3.4 Valves 1 LS $ 1,470.00 $ 1,470.00
3.5 Install Drainage Swale on South Side Of Playground 1 LS $ 775.00 $ 775.00
3.6 Repair/straighten 8" Bollards Around Parking Lots 1 LS $ 1,545.00 $ 1,545.00
Subtotal $ 94,069.00
Deletions
1.02 Asphalt Resurfacing 6180 SF $ 4.20 $ 25,956.00
1.06 Pedestrian Paving &Sidewalks 5250 SF $ 6.60 $ 34,650.00
1.18 Construction Allowance 1 LS $ 50,000.00 $ 50,000.00
1.19 Signage Allowance 1 LS $ 5,200.00 $ 5,200.00
Subtotal $ 115,806.00
TOTAL CHANGE ORDER REQUEST $ (21,737.00)
Please let me know if you have any questions or need additional information.
Sincerely,
NORlTHS/TARj)C�O�NSTRUCTIIO- N, LLC
Michael A. Heimlich
President
817-244-8885 Office 2112 Solona Street Fort Worth,Texas 76117