HomeMy WebLinkAboutOrdinance 25797-10-2022 ORDINANCE NO.25797-10-2022
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE 2007 CRITCAPPROJ-CO2013A FUND, IN THE
AMOUNT OF$800,000.00,FROM AVAILABLE FUNDS,FOR THE PURPOSE OF
FUNDING THE KELLER-HASLET ROAD EXTENSION PROJECT (CITY
PROJECT NO.104391);PROVIDING FOR A SEVERABILITY CLAUSE;MAKING
THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;REPEALING ALL
ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE
DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2022-2023 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the 2007
CritCapProj-0O2013A Fund in the amount of$800,000.00,from available funds,for the purpose of funding
the Keller-Haslet Road Extension project(City Project No. 104391).
SECTION 2.
That should any portion,section or part of a section of this ordinance be declared invalid,inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be incorporated into the ordinance effecting the budget of the municipal government
of the City of Fort Worth for the ensuing Fiscal Year beginning October 1,2022,and ending September 30,
2023, and all other ordinances and appropriations amending the same except in those instances where the
provisions of this ordinance are in direct conflict with such other ordinances and appropriations, in which
instance said conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
Dglack(0h 21,202210:47 CDT) ette 5.Goodall(Oct 21,2022 10) DT)
Jannette S.Goodall
Assistant City Attorney City Secretary
oF FORr���
X. N:53
ADOPTED AND EFFECTIVE:October 11,2022
�XAS.
ol
� 9S1 iY2
$x I 8
I
a � r
' 1 �
I I
I
r
r ry
� I I
1
a y,
I � W
r , Q
•, .wcw—� �
I�
r
r � 7
" I �
I '
City of Fort Worth,Texas
Mayor and Council Communication
DATE: 10/11/22 M&C FILE NUMBER: M&C 22-0841
LOG NAME: 20KELLER HASLET ROAD ILA
SUBJECT
(CD 7)Authorize Execution of an Interlocal Agreement with the City of Haslet for Construction of the Keller-Haslet Road Extension to Blue Mound
Road Project in an Amount Not to Exceed$800,000.00,Adopt Appropriation Ordinance and Amend the Fiscal Years 2023—2027 Capital
Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of an Interlocal Agreement with the City of Haslet for construction of the Keller-Haslet Road Extension to Blue Mound
Road project(City Project No. 104391),in an amount up to$800,000.00;
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the 2007 CritCapProj—CO2013A Fund in
the amount of$800,000.00 from available funds for the Keller-Haslet Road Extension project(City Project No. 104391);and
3. Amend the Fiscal Years 2023—2027 Capital Improvement Program.
DISCUSSION:
Keller-Haslet Road is listed in the City of Fort Worth Master Thoroughfare Plan(MTP)as a Neighborhood Connector and the MTP calls for the
extension of Keller Haslet road to connect to Blue Mound Road. Most of the proposed roadway is within the City of Fort Worth City Limits.
However,the proposed connection to Blue Mound Road(FM 156)is within the City of Haslet City Limits due to a proposed curve in the roadway to
provide better alignment of this intersection with existing development on the east side. This project benefits the City of Haslet by providing an
alternative route for traffic to avoid congestion in Old Town Haslet from North Fort Worth and the Burlington Northern Santa Fe(BNSF)facility to the
northwest. This project benefits the City of Fort Worth by providing a direct connection to Blue Mound Road(FM 156)to our citizens and business
developments on the north side. The City of Haslet submitted this project to Tarrant County for consideration in the Tarrant County 2021
Transportation Bond Program and the Tarrant County selected this project to receive funding.
The City of Haslet proposes to provide the design,including a signal warrant study at Blue Mound Road(FM156),and to provide all materials
necessary for this construction. Haslet is negotiating an agreement with Tarrant County to perform the construction of Keller-Haslet Road and a
southbound turn lane on Blue Mound Road(FM 156)as required by the Texas Department of Transportation(TxDOT). Haslet also has negotiated
an agreement with TxDOT to install traffic signals at the Keller-Haslet Road and Blue Mound Road(FM 156)intersection should they be
warranted. The City of Fort Worth contribution would be in the form of supportive funding to the City of Haslet. Once the project is completed,the
City of Haslet has agreed to perform a joint a boundary adjustment with the City of Fort Worth resulting in the entire roadway being within the City of
Fort Worth.
The breakdown of responsibilities associated with the proposed Interlocal Agreement are as follows:
Fort Worth shall be responsible for:
1. Contributing up to$800,000.00 to the City of Haslet upon execution of this proposed Interlocal Agreement(ILA)prior to construction,to be
used to support design and construction costs;
2. Consider a boundary adjustment with City of Haslet for the new Keller Haslet Road extension right-of-way after project completion.
Haslet shall be responsible for:
1. Serve as grantee and grant manager for Tarrant County transportation bond funds;
2. Advancing design and construction documents until project costs can be reimbursed by Tarrant County;
3. Design of the project;
4. Coordination with Tarrant County and TxDOT for construction of the project;
a. Preparation of project contract documents,
b. Inspection of project construction,
c. All cost overruns should they occur,
d. Providing monthly updates to City of Fort Worth on project status until completion,
e. Consider boundary adjustment with the City of Fort Worth for the new Keller Haslet Road extension right-of-way after project
completion,
f. Complete the project by June 30,2023.
The table below summarizes funding for this project:
Fund Existing Funding Additional Funding Project Total
34012-2007 CritCapProj-CO2013A $ - $800,000.00 $800,000.00
Project Total $ - $800,000.00 $800,000.00
Funding for this project was not included in the Fiscal Years 2023-2027 Capital Improvement Program(CIP)because negations on this ILA were
completed after the development of the CIP plan.
Funding is available for appropriation in the Unspecified-All Funds project for the purpose of funding the Keller Haslet Road Extension project..
This project is located in COUNCIL DISTRICT 7.
A Form 1295 is not required because:This contract will be with a governmental entity, state agency or public institution of higher education:City of
Haslet
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Unspecified-All Funds within the 2007 CritCapProj-CO2013A Fund and
upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds will be available in the 2007
CritCapProj-CO2013A Fund for the Keller Haslet Road Extension project. Prior to an expenditure being incurred,the Transportation&Public
Works Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by: William Johnson 7801
Originating Business Unit Head: Lauren Prieur 6035
Additional Information Contact: Monty Hall 8662