HomeMy WebLinkAboutContract 56457-PM1PROJECT MANUAL FOR THE CONSTRUCTION OF Lot 1, Block 1 Trinity Basin Preparatory Addition Trinity Basin Preparatory - Bolt IPRC Record No. IPRC 21-0100 City Project No. CPN 103537 FID No. 30114-0200431-103537-E07685 File No. K-2852 X File No. X-27041 Mattie Parker David Cooke Mayor City Manager Christopher P. Harder, P.E. Director, Water Department William Johnson Director, Transportation and Public Works Department Prepared for The City of Fort Worth 2021 Engineer: Hart Gaugler + Associates 12801 North Central Expressway, Suite 1400 Dallas, Texas 75243 Texas Registered Engineering Firm #F-5053 Contact: John D. Blacker, P.E. jblacker@hartgaugler.com CSC No. 56457-PM1 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 1 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 103537 Revised March 20, 2020 SECTION 00 00 10 TABLE OF CONTENTS DEVELOPER AWARDED PROJECTS Division 00 - General Conditions Last Revised 00 42 43 Proposal Form Unit Price 08/06/2021 00 45 12 Prequalification Statement 07/26/2021 00 45 26 Contractor Compliance with Workers' Compensation Law 10/20/2021 00 52 43 Agreement 10/20/2021 00 61 25 Certificate of Insurance 11/10/2021 Developers Bond 09/29/2021 00 62 13 Performance Bond 01/31/2012 00 62 14 Payment Bond 01/31/2012 00 62 19 Maintenance Bond 11/01/2021 00 73 10 Standard City Conditions of the Construction Contract for Developer Awarded Projects 01/10/2013 Division 01 - General Requirements Last Revised 01 11 00 Summary of Work 07/27/2021 01 25 00 Substitution Procedures 08/30/2013 01 31 19 Preconstruction Meeting 08/30/2013 01 31 20 Project Meetings 07/01/2011 04 32 16 Construction Progress Schedule 07/01/2011 01 32 33 Preconstruction Video 08/30/2013 01 33 00 Submittals 08/30/2013 01 35 13 Special Project Procedures 08/30/2013 01 45 23 Testing and Inspection Services 03/20/2020 01 50 00 Temporary Facilities and Controls 07/01/2011 01 55 26 Street Use Permit and Modifications to Traffic Control 07/01/2011 01 57 13 Storm Water Pollution Prevention Plan 07/01/2011 01 58 13 Temporary Project Signage 04/07/2014 01 60 00 Product Requirements 03/20/2020 01 66 00 Product Storage and Handling Requirements 04/07/2014 01 70 00 Mobilization and Remobilization 04/07/2014 01 71 23 Construction Staking and Survey 02/14/2018 01 74 23 Cleaning 04/07/2014 01 77 19 Closeout Requirements 04/07/2014 01 78 23 Operation and Maintenance Data 04/07/2014 01 78 39 Project Record Documents 04/07/2014 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 2 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 103537 Revised March 20, 2020 Technical Specifications which have been modified by the Engineer specifically for this Project; hard copies are included in the Project’s Contract Documents NONE – no technical specifications have been modified Division 02 - Existing Conditions Date Modified 02 41 13 Selective Site Demolition 02 41 14 Utility Removal/Abandonment 02 41 15 Paving Removal Division 03 - Concrete 03 30 00 Cast-In-Place Concrete 03 34 13 Controlled Low Strength Material (CLSM) 03 34 16 Concrete Base Material for Trench Repair 03 80 00 Modifications to Existing Concrete Structures Division 26 - Electrical 26 05 00 Common Work Results for Electrical 26 05 10 Demolition for Electrical Systems 26 05 33 Raceways and Boxes for Electrical Systems 26 05 43 Underground Ducts and Raceways for Electrical Systems Division 31 - Earthwork 31 10 00 Site Clearing 31 23 16 Unclassified Excavation 31 23 23 Borrow 31 24 00 Embankments 31 25 00 Erosion and Sediment Control 31 36 00 Gabions 31 37 00 Riprap Division 32 - Exterior Improvements 32 01 17 Permanent Asphalt Paving Repair 32 01 18 Temporary Asphalt Paving Repair 32 01 29 Concrete Paving Repair 32 11 23 Flexible Base Courses 32 11 29 Lime Treated Base Courses 32 11 33 Cement Treated Base Courses 32 11 37 Liquid Treated Soil Stabilizer 32 12 16 Asphalt Paving 32 12 73 Asphalt Paving Crack Sealants 32 13 13 Concrete Paving 32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 32 13 73 Concrete Paving Joint Sealants 32 14 16 Brick Unit Paving 32 16 13 Concrete Curb and Gutters and Valley Gutters 32 17 23 Pavement Markings 32 17 25 Curb Address Painting 32 31 13 Chain Fences and Gates 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 3 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 103537 Revised March 20, 2020 32 31 26 Wire Fences and Gates 32 31 29 Wood Fences and Gates 32 32 13 Cast-in-Place Concrete Retaining Walls 32 91 19 Topsoil Placement and Finishing of Parkways 32 92 13 Hydro-Mulching, Seeding, and Sodding 32 93 43 Trees and Shrubs Division 33 - Utilities 33 01 30 Sewer and Manhole Testing 33 01 31 Closed Circuit Television (CCTV) Inspection 33 03 10 Bypass Pumping of Existing Sewer Systems 33 04 10 Joint Bonding and Electrical Isolation 33 04 11 Corrosion Control Test Stations 33 04 12 Magnesium Anode Cathodic Protection System 33 04 30 Temporary Water Services 33 04 40 Cleaning and Acceptance Testing of Water Mains 33 04 50 Cleaning of Sewer Mains 33 05 10 Utility Trench Excavation, Embedment, and Backfill 33 05 12 Water Line Lowering 33 05 13 Frame, Cover and Grade Rings - Cast Iron 33 05 13.10 Frame, Cover and Grade Rings - Composite 33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 33 05 16 Concrete Water Vaults 33 05 17 Concrete Collars 33 05 20 Auger Boring 33 05 21 Tunnel Liner Plate 33 05 22 Steel Casing Pipe 33 05 23 Hand Tunneling 33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 33 05 26 Utility Markers/Locators 33 05 30 Location of Existing Utilities 33 11 05 Bolts, Nuts, and Gaskets 33 11 10 Ductile Iron Pipe 33 11 11 Ductile Iron Fittings 33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type 33 11 14 Buried Steel Pipe and Fittings 33 11 15 Pre-Stressed Concrete Cylinder Pipe 33 12 10 Water Services 1-inch to 2-inch 33 12 11 Large Water Meters 33 12 20 Resilient Seated Gate Valve 33 12 21 AWWA Rubber-Seated Butterfly Valves 33 12 25 Connection to Existing Water Mains 33 12 30 Combination Air Valve Assemblies for Potable Water Systems 33 12 40 Fire Hydrants 33 12 50 Water Sample Stations 33 12 60 Standard Blow-off Valve Assembly 33 31 12 Cured in Place Pipe (CIPP) 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 4 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 103537 Revised March 20, 2020 33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer 33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer Pipe 33 31 22 Sanitary Sewer Slip Lining 33 31 23 Sanitary Sewer Pipe Enlargement 33 31 50 Sanitary Sewer Service Connections and Service Line 33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 33 39 10 Cast-in-Place Concrete Manholes 33 39 20 Precast Concrete Manholes 33 39 30 Fiberglass Manholes 33 39 40 Wastewater Access Chamber (WAC) 33 39 60 Epoxy Liners for Sanitary Sewer Structures 33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain 33 41 12 Reinforced Polyethlene (SRPE) Pipe 33 46 00 Subdrainage 33 46 01 Slotted Storm Drains 33 46 02 Trench Drains 33 49 10 Cast-in-Place Manholes and Junction Boxes 33 49 20 Curb and Drop Inlets 33 49 40 Storm Drainage Headwalls and Wingwalls Division 34 - Transportation 34 41 10 Traffic Signals 34 41 10.01 Attachment A – Controller Cabinet 34 41 10.02 Attachment B – Controller Specification 34 41 10.03 Attachment C – Software Specification 34 41 11 Temporary Traffic Signals 34 41 13 Removing Traffic Signals 34 41 15 Rectangular Rapid Flashing Beacon 34 41 16 Pedestrian Hybrid Signal 34 41 20 Roadway Illumination Assemblies 34 41 20.01 Arterial LED Roadway Luminaires 34 41 20.02 Freeway LED Roadway Luminaires 34 41 20.03 Residential LED Roadway Luminaires 34 41 30 Aluminum Signs 34 71 13 Traffic Control 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 5 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 103537 Revised March 20, 2020 Technical Specifications listed below are included for this Project by reference and can be viewed/downloaded from the City’s website at: http://fortworthtexas.gov/tpw/contractors/ or https://apps.fortworthtexas.gov/ProjectResources/ Division 02 - Existing Conditions Last Revised 02 41 13 Selective Site Demolition 12/20/2012 02 41 14 Utility Removal/Abandonment 12/20/2012 02 41 15 Paving Removal 02/02/2016 Division 03 - Concrete 03 30 00 Cast-In-Place Concrete 12/20/2012 03 34 13 Controlled Low Strength Material (CLSM) 12/20/2012 03 34 16 Concrete Base Material for Trench Repair 12/20/2012 03 80 00 Modifications to Existing Concrete Structures 12/20/2012 Division 26 - Electrical 26 05 00 Common Work Results for Electrical 11/22/2013 26 05 10 Demolition for Electrical Systems 12/20/2012 26 05 33 Raceways and Boxes for Electrical Systems 12/20/2012 26 05 43 Underground Ducts and Raceways for Electrical Systems 07/01/2011 26 05 50 Communications Multi-Duct Conduit 02/26/2016 Division 31 - Earthwork 31 10 00 Site Clearing 12/20/2012 31 23 16 Unclassified Excavation 01/28/2013 31 23 23 Borrow 01/28/2013 31 24 00 Embankments 01/28/2013 31 25 00 Erosion and Sediment Control 12/20/2012 31 36 00 Gabions 12/20/2012 31 37 00 Riprap 12/20/2012 Division 32 - Exterior Improvements 32 01 17 Permanent Asphalt Paving Repair 12/20/2012 32 01 18 Temporary Asphalt Paving Repair 12/20/2012 32 01 29 Concrete Paving Repair 12/20/2012 32 11 23 Flexible Base Courses 12/20/2012 32 11 29 Lime Treated Base Courses 12/20/2012 32 11 33 Cement Treated Base Courses 12/20/2012 32 11 37 Liquid Treated Soil Stabilizer 08/21/2015 32 12 16 Asphalt Paving 12/20/2012 32 12 73 Asphalt Paving Crack Sealants 12/20/2012 32 13 13 Concrete Paving 12/20/2012 32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 06/05/2018 32 13 73 Concrete Paving Joint Sealants 12/20/2012 32 14 16 Brick Unit Paving 12/20/2012 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 6 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 103537 Revised March 20, 2020 32 16 13 Concrete Curb and Gutters and Valley Gutters 10/05/2016 32 17 23 Pavement Markings 11/22/2013 32 17 25 Curb Address Painting 11/04/2013 32 31 13 Chain Fences and Gates 12/20/2012 32 31 26 Wire Fences and Gates 12/20/2012 32 31 29 Wood Fences and Gates 12/20/2012 32 32 13 Cast-in-Place Concrete Retaining Walls 06/05/2018 32 91 19 Topsoil Placement and Finishing of Parkways 12/20/2012 32 92 13 Hydro-Mulching, Seeding, and Sodding 12/20/2012 32 93 43 Trees and Shrubs 12/20/2012 Division 33 - Utilities 33 01 30 Sewer and Manhole Testing 12/20/2012 33 01 31 Closed Circuit Television (CCTV) Inspection 03/03/2016 33 03 10 Bypass Pumping of Existing Sewer Systems 12/20/2012 33 04 10 Joint Bonding and Electrical Isolation 12/20/2012 33 04 11 Corrosion Control Test Stations 12/20/2012 33 04 12 Magnesium Anode Cathodic Protection System 12/20/2012 33 04 30 Temporary Water Services 07/01/2011 33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06/2013 33 04 50 Cleaning of Sewer Mains 12/20/2012 33 05 10 Utility Trench Excavation, Embedment, and Backfill 12/12/2016 33 05 12 Water Line Lowering 12/20/2012 33 05 13 Frame, Cover and Grade Rings – Cast Iron 01/22/2016 33 05 13.10 Frame, Cover and Grade Rings – Composite 01/22/2016 33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 12/20/2012 33 05 16 Concrete Water Vaults 12/20/2012 33 05 17 Concrete Collars 12/20/2012 33 05 20 Auger Boring 12/20/2012 33 05 21 Tunnel Liner Plate 12/20/2012 33 05 22 Steel Casing Pipe 12/20/2012 33 05 23 Hand Tunneling 12/20/2012 33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 06/19/2013 33 05 26 Utility Markers/Locators 12/20/2012 33 05 30 Location of Existing Utilities 12/20/2012 33 11 05 Bolts, Nuts, and Gaskets 12/20/2012 33 11 10 Ductile Iron Pipe 12/20/2012 33 11 11 Ductile Iron Fittings 12/20/2012 33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11/16/2018 33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type 12/20/2012 33 11 14 Buried Steel Pipe and Fittings 12/20/2012 33 12 10 Water Services 1-inch to 2-inch 02/14/2017 33 12 11 Large Water Meters 12/20/2012 33 12 20 Resilient Seated Gate Valve 12/20/2012 33 12 21 AWWA Rubber-Seated Butterfly Valves 12/20/2012 33 12 25 Connection to Existing Water Mains 02/06/2013 33 12 30 Combination Air Valve Assemblies for Potable Water Systems 12/20/2012 33 12 40 Fire Hydrants 01/03/2014 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 7 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 103537 Revised March 20, 2020 33 12 50 Water Sample Stations 12/20/2012 33 12 60 Standard Blow-off Valve Assembly 06/19/2013 33 31 12 Cured in Place Pipe (CIPP) 12/20/2012 33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 12/20/2012 33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer 12/20/2012 33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 06/19/2013 33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer Pipe 12/20/2012 33 31 22 Sanitary Sewer Slip Lining 12/20/2012 33 31 23 Sanitary Sewer Pipe Enlargement 12/20/2012 33 31 50 Sanitary Sewer Service Connections and Service Line 04/26/2013 33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 12/20/2012 33 39 10 Cast-in-Place Concrete Manholes 12/20/2012 33 39 20 Precast Concrete Manholes 12/20/2012 33 39 30 Fiberglass Manholes 12/20/2012 33 39 40 Wastewater Access Chamber (WAC) 12/20/2012 33 39 60 Epoxy Liners for Sanitary Sewer Structures 12/20/2012 33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 07/01/2011 33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain 12/20/2012 33 41 12 Reinforced Polyethlene (SRPE) Pipe 11/13/2015 33 46 00 Subdrainage 12/20/2012 33 46 01 Slotted Storm Drains 07/01/2011 33 46 02 Trench Drains 07/01/2011 33 49 10 Cast-in-Place Manholes and Junction Boxes 12/20/2012 33 49 20 Curb and Drop Inlets 12/20/2012 33 49 40 Storm Drainage Headwalls and Wingwalls 07/01/2011 Division 34 - Transportation 34 41 10 Traffic Signals 10/12/2015 34 41 10.01 Attachment A – Controller Cabinet 12/18/2015 34 41 10.02 Attachment B – Controller Specification 02/2012 34 41 10.03 Attachment C – Software Specification 01/2012 34 41 11 Temporary Traffic Signals 11/22/2013 34 41 13 Removing Traffic Signals 12/20/2012 34 41 15 Rectangular Rapid Flashing Beacon 11/22/2013 34 41 16 Pedestrian Hybrid Signal 11/22/2013 34 41 20 Roadway Illumination Assemblies 12/20/2012 34 41 20.01 Arterial LED Roadway Luminaires 06/15/2015 34 41 20.02 Freeway LED Roadway Luminaires 06/15/2015 34 41 20.03 Residential LED Roadway Luminaires 06/15/2015 34 41 30 Aluminum Signs 11/12/2013 34 41 50 Single-Mode Fiber Optic Cable 02/26/2016 34 71 13 Traffic Control 11/22/2013 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 8 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 103537 Revised March 20, 2020 Appendix GC-4.01 Availability of Lands GC-4.02 Subsurface and Physical Conditions GC-4.04 Underground Facilities GC-4.06 Hazardous Environmental Condition at Site GC-6.06.D Minority and Women Owned Business Enterprise Compliance GC-6.07 Wage Rates GC-6.09 Permits and Utilities GC-6.24 Nondiscrimination GR-01 60 00 Product Requirements END OF SECTION 00 42 43 DAP - BID PROPOSAL Page 1 of 5 1 3312.2103 1-1/2" water service 33 12 10 EA 2 $5,000.00 $10,000.00 2 3312.2203 2" water service 33 12 10 EA 1 $7,268.00 $7,268.00 3 3311.0142 6" water pipe, css backfill 33 11 10, 33 11 12 LF 52 $100.00 $5,200.00 4 3312.4106 12" x 6" Tapping sleeve and valve 33 12 25 EA 1 $15,000.00 $15,000.00 5 3312.4004 8" x 6" Tapping sleeve and valve 33 12 25 EA 1 $14,000.00 $14,000.00 6 3312.0117 Connection to Existing 4"-12" water main 33 12 25 EA 2 $10,000.00 $20,000.00 7 3305.0109 Trench Safety 33 05 10 LF 52 $10.00 $520.00 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 Bidder's Proposal Description TOTAL UNIT I: WATER IMPROVEMENTS Bidlist Item No. UNIT I: WATER IMPROVEMENTS SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID Bid Quantity Unit Price Bid Value Project Item Information Bidder's Application Specification Section No. Unit of Measure $71,988.00 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version May 22, 2019 CPN 103537 00 42 43_Bid Proposal_DAP 00 42 43 DAP - BID PROPOSAL Page 2 of 5 Bidder's Proposal DescriptionBidlist Item No. SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID Bid Quantity Unit Price Bid Value Project Item Information Bidder's Application Specification Section No. Unit of Measure 1 3331.3301 8" Sewer Service 33 31 50 EA 2 $1,415.00 $2,830.00 2 3331.5302 8" SEWER, css backfill 33 31 20 LF 6 $100.00 $600.00 3 3339.1001 4' DIA. MANHOLE 33 39 10, 33 39 20 EA 1 $8,000.00 $8,000.00 4 3305.0109 Trench Safety 33 05 10 LF 6 $20.00 $120.00 5 3301.0002 Post-CCTV Inspection 33 01 31 LF 6 $50.00 $300.00 6 3301.0101 Manhole Vacuum Testing 33 01 30 EA 1 $2,000.00 $2,000.00 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 UNIT II: SANITARY SEWER IMPROVEMENTS TOTAL UNIT II: SANITARY SEWER IMPROVEMENTS $13,850.00 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version May 22, 2019 CPN 103537 00 42 43_Bid Proposal_DAP 00 42 43 DAP - BID PROPOSAL Page 3 of 5 Bidder's Proposal DescriptionBidlist Item No. SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID Bid Quantity Unit Price Bid Value Project Item Information Bidder's Application Specification Section No. Unit of Measure 1 0241.0100 Remove Sidewalk 02 41 13 SF 1,670 $3.95 $6,596.50 2 0241.0300 Remove ADA Ramp (included in removal of sidewalk) 02 41 13 EA 1 .$0.00 .$0.00 3 0241.0401 Remove Concrete Drive 02 41 13 SF 1,725 $4.69 $8,090.25 4 0241.1300 Remove Conc. Curb&Gutter 02 41 13 LF 300 $21.98 $6,594.00 5 3213.0401 6" Concrete Driveway 32 13 20 SF 1,040 $14.84 $15,433.60 6 3213.0302 5" Concrete Sidewalk 32 13 20 SF 4,670 $7.91 $36,939.70 7 3116.0101 6" Conc Curb and Gutter 32 16 13 LF 440 $36.95 $16,258.00 8 3213.0506 Barrier Free Ramp, Type P-1 32 13 20 EA 3 $1,105.00 $3,315.00 9 3213.0507 Barrier Free Ramp, Type P-2 32 13 20 EA 1 $1,105.00 $1,105.00 10 3213.0501 Barrier Free Ramp, Type R-1 32 13 20 EA 1 $2,435.00 $2,435.00 11 3291.0100 Topsoil 32 91 19 CY 48 $52.08 $2,499.84 12 3292.0400 Seeding, Hydromulch 32 92 13 SY 480 $2.50 $1,200.00 13 0241.0402 Remove Asphalt 02 41 13 SF 1330 $2.16 $2,872.80 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 $103,339.69TOTAL UNIT IV: PAVING IMPROVEMENTS UNIT IV: PAVING IMPROVEMENTS CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version May 22, 2019 CPN 103537 00 42 43_Bid Proposal_DAP 00 42 43 DAP - BID PROPOSAL Page 4 of 5 Bidder's Proposal DescriptionBidlist Item No. SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID Bid Quantity Unit Price Bid Value Project Item Information Bidder's Application Specification Section No. Unit of Measure 1 3441.3352 Furnish/install rdwy illum ty 18 pole 34 41 20 EA 3 $2,838.30 $8,514.90 2 3441.3351 Furnish/install rdwy illum ty 11 pole 34 41 20 EA 4 $2,597.30 $10,389.20 3 3441.3037 Furnish/install 10' Washington w/ pole 34 41 20 EA 12 $3,666.20 $43,994.40 4 3441.1501 Ground box type B 34 41 10 EA 5 $1,000.00 $5,000.00 5 3441.1772 Furnish/install 240-480V metered ped 34 41 20 EA 1 $6,000.00 $6,000.00 6 2605.3011 2" conduit pvc sch 40 (t) 26 05 33 LF 990 $22.00 $21,780.00 7 3441.1408 #6 INSULATED GROUND 34 41 10 LF 990 $2.55 $2,524.50 8 3441.1408 #6 INSULATED ILLUM. 34 41 10 LF 1980 $2.55 $5,049.00 9 3441.3301 Rdwy illum Foundation Type 1 34 41 20 EA 4 $1,170.00 $4,680.00 10 3441.3302 Rdwy illum Foundation Type 3 34 41 20 EA 3 $1,450.00 $4,350.00 11 3441.3302 Rdwy illum Foundation Type 7 34 41 20 EA 12 $1,050.00 $12,600.00 12 3441.1645 Furnish/Install Type 33A Arm 34 41 20 EA 3 $448.00 $1,344.00 13 3441.1646 Furnish/Install Type 33B Arm 34 41 20 EA 4 $448.00 $1,792.00 14 3441.3050 F/I LED Lighting fixture (70 Watt ATBO) 34 41 20 EA 4 $650.00 $2,600.00 15 3441.3051 F/I LED Lighting fixture (137 Watt ATBO) 34 41 20 EA 3 $700.00 $2,100.00 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 $132,718.00TOTAL UNIT V: STREET LIGHTING IMPROVEMENTS UNIT V: STREET LIGHTING IMPROVEMENTS CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version May 22, 2019 CPN 103537 00 42 43_Bid Proposal_DAP 00 42 43 DAP - BID PROPOSAL Page 5 of 5 Bidder's Proposal DescriptionBidlist Item No. SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID Bid Quantity Unit Price Bid Value Project Item Information Bidder's Application Specification Section No. Unit of Measure This Bid is submitted by the entity named below: BIDDER:BY: Butler-Cohen 3200 Southwest Freeway Suite 1575 TITLE: Houston, Texas 77027 DATE: 50 END OF SECTION $321,895.69Total Construction Bid Bid Summary Vice President 8/6/2021 Sean Butler UNIT I: WATER IMPROVEMENTS Contractor agrees to complete WORK for FINAL ACCEPTANCE within working days after the date when the CONTRACT commences to run as provided in the General Conditions. $103,339.69 $132,718.00 $71,988.00 UNIT II: SANITARY SEWER IMPROVEMENTS UNIT IV: PAVING IMPROVEMENTS UNIT V: STREET LIGHTING IMPROVEMENTS $13,850.00 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version May 22, 2019 CPN 103537 00 42 43_Bid Proposal_DAP BY: TITLE: DATE: Vice President 8/6/2021 Sean ButlerBY: TITLE: DATE: Vice President 8/6/2021 Sean Butler 00 45 12 DAP PREQUALIFICATION STATEMENT Page 1 of 1 CITY OF FORT WORTH STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT – DEVELOPER AWARDED PROJECTS original.docx Form Version September 1, 2015 SECTION 00 45 12 DAP – PREQUALIFICATION STATEMENT Each Bidder is required to complete the information below by identifying the prequalified contractors and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the “Major Work Type” box provide the complete major work type and actual description as provided by the Water Department for water and sewer and TPW for paving. Butler-Cohen/ Subcontractor TBD Major Work Type Contractor/Subcontractor Company Name Prequalification Expiration Date Water Butler-Cohen/ Sanitary Sewer and Storm Butler-Cohen/ Street Lighting Butler-Cohen/ The undersigned hereby certifies that the contractors and/or subcontractors described in the table above are currently prequalified for the work types listed. BIDDER: Butler-Cohen, BY: Sean Butler 3200 Southwest Freeway, Suite 1575 Houston, Texas 77027 _________________________________________ (Signature) TITLE: Vice President DATE: 7/26/2021 END OF SECTION Doc ID: bb2a29b70a0c5b2d6882e39e64c2ba49b31dc345 Tridal Utilities Tridal Utilities Bean Electrical Water Distribution, Development, 12-inch diameter and smaller 4/30/2022 4/30/2022Sewer Collection System, Development, 8-inches and smaller 3/9/2023 00 45 26 - 1 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Page 1 of 1 CITY OF FORT WORTH Trinity Basin Bolt Campus STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CFA21-0126 Revised April 2, 2014 SECTION 00 45 26 1 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW 2 3 Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it 4 provides worker’s compensation insurance coverage for all of its employees employed on City 5 Project No. CPN103537. Contractor further certifies that, pursuant to Texas Labor Code, Section 6 406.096(b), as amended, it will provide to City its subcontractor’s certificates of compliance with 7 worker’s compensation coverage. 8 9 CONTRACTOR: 10 11 _Butler-Cohen, LLC______ By: ___Sean Butler_________________________ 12 Company (Please Print) 13 14 3200 Southwest FWY, Suite 1575 Signature: ______________________________ 15 Address 16 17 _Houston, TX 77027_ Title: _President_____________________________ 18 City/State/Zip (Please Print) 19 20 21 THE STATE OF TEXAS § 22 23 COUNTY OF TARRANT § 24 25 BEFORE ME, the undersigned authority, on this day personally appeared 26 ___________________________________, known to me to be the person whose name is 27 subscribed to the foregoing instrument, and acknowledged to me that he/she executed the same as 28 the act and deed of ____________________________________ for the purposes and 29 consideration therein expressed and in the capacity therein stated. 30 31 GIVEN UNDER MY HAND AND SEAL OF OFFICE this ____________day of 32 _______________________, 20__. 33 34 35 __________________________________ 36 Notary Public in and for the State of Texas 37 38 END OF SECTION 39 40 41 42 43 44 45 46 Doc ID: 130d4382ec524a6c79fad79d89958c8f4e7a6d78 Sean Butler Butler-Cohen LLC 20th October 21 00 52 43 - 1 beveloper A�varded Project Agreement Page 1 of4 1 2 SECTYON 00 52 43 AGRE�MENT 3 THIS AGREEMENT, authorized an �10/20/2Q2I is xnac�e by and I�etween the 4 Developer, T�-inity Basin P�eparato�y, Inc., authorized to do business in Te�as ("Developer") , 5 and Butlez�-Cohen LCC, auihorized to do bLisiness i� Texas, acting by and tht o�tgh its duly 6 autho�-ized rep�•esentatzve, ("Contt•actoi"). 7 Developer and Cantraeior, in consideration of ti�e muhaal covenanis i�ereinafter set foitli, agree as 8 follows: 9 Art�cle 1. WORK ia 11 12 13 14 IS iG 17 18 19 20 Cont�acto;- shall complete all �Nork as speciiied or indicated in the Contract Doc�zments for the Project identi�'ied herein. Article 2. PRO�ECT The project for which the Work under the Contract Documents �nay be the whole or only a pa��t is generally described as �ollaws: Trinity Basin — Bolt Campus — CFA Scope of Work CFA21-0126, CPN103S37 Article 3. C�NTRACT TIME 3.1 Ti�ne is of the essence. AIl time Iiznzts for Milestones, if any, and Final Acceptanca as stated in the Contract Documents a�•e af thc �sse�ce to this Contract. 21 3.2 Pinal Acceptance. 22 The Worie will be coznplete fnr Final Acceptance within SO calet�dar days after the date 23 wl�en the Contract Time cainmcnces ta i�u�� as provided in Paragrapla �2.Q4 o�ilae Standard 2�4 City Conditzons of the Construction Contract for D�velopet Awarded Projects. 25 33 Liq��idated da�nages 26 27 28 29 30 31 32 33 34 35 Contractor recognizes that time is af the essence of this Agreement and that D�veloper will suffer financzal loss if th� Work is not completed withiza the times specified in Paragraph 3.2 above, pit�s ai�y extension ihereof allowed in accordance with Article 10 af thc Standard City Conditions of the Constraction Contract far Developer Awarded Pi•ojects. Tlae Cpnt�actoz• also recognizes t}�e delays, expense and diffe�alties involved in pz•oving in a legal praceeding tl�e actual loss suffered by t}le DeveIoper if the Woz•� is not complet�d on iiane. Accordingly, instead of reqi�iring a�y such proof , Contractor agrees that as liq�idated damages for deIay (but nat as a pe��alty), Contraetor shall pay Developet• Fiftv Dnllal•s ($50.00} for each day thai expires after the ti�ne speeified in Patagraph 3.2 for Rinal Accepiance untii tl�e City issues the Final Lette�• of Aceeptance. CiTY OF FpRT WORTH 7'riirity Basi�z Bolt Cainpits STANDARD COrISTRUCTION SPEGIFICAT[ON DOCLTMENTS — C7�VLLDP�R AWARflED PR03ECTS C�'.421-DI26 Revised.i�ne ]b, 201G n..,. �n. �onaeoon....�ne..r_,.�na..a�n,aonnco,.osn,.�..r_,.t�o ($321,895.96). oa sz a3 - a i7eveloper Awarded Projeet A�reement Page 3 of4 67 Article b. INDEMNI�ICATION 68 G9 70 7I 72 73 7� 75 76 77 78 79 80 8I 82 83 84 85 86 87 88 6.1 Contractor covenants and agrees to i�demnify, hold harmless and defe�d, at its own expense, the city, its of�cers, servants and employees, from and against any a�d all clai�s arising ouf of, or alleged to arise out of, the waa•k and servxces to be perfornned by the contractar, ifs of�cers, agenfs, emplayees, s�hcontractors, licenses or invitees under t�is caEitract, This indemni�catian rovision is s eci�cali intended to o erate and be effective even if it is alle ed or roven fE�at all or same of the dama es bei�n sou ht were caused in whole or in art b an aet omission or ne ii ence of the cit . Thfs indetnnity pro�vision is intended to include, withou� limitation, indernnity for cpsts, expenses a�d lega[ fees incurred by the city i� defending against si�ch claims and ca��ses a€ aciions. 6.2 Canh•�ctor covenants arid agrees to indemnify and ho[d harrnless, at its orvn expense, the city, its o��icers, se�•vants and employees, fro�n and against any and all loss, damage or destruction oi' property of the city, arising out of, or alleged to arise out of, the wor[� and services ta be performed by the contractor, i�s of�cers, agents, emp�oyees, s�bcantractors, licensees or invitees under this contract. This indemnification provision is specifically intended to aperate and be effec�ive even if it is alie�ed or praven that aII or some of �he datna�es bein� sou�ht were caused� in whole or in nart, by any act, omission or negli�ence of the city. Article 7. MTSCELLANEOUS 89 7,1 Terms. 90 Terms used in this Agre�ment are defined ir� Article 1 Qf the Standard City Conditinns of 91 �he Const��uction Contract far Develaper Awarded Projects, 92 '7.2 Assignrnent of Co�tract. 93 This A�eemez�t, including all of the Co��tz•act Doc�.��ne�ats �ay �ot be assigned by the 44 Coniracto�' witlzout th� advanced express writte� ca�sent of the Developer. 95 7.3 Strtccessors and Assigns. 46 Developer and Cont�•actoz eac� binds itself, its partners, successars, assigns a�d legal 97 representatives to the other party he�eto, in respect to all covenants, agreements and 98 obligations contain�d in the Contract Docu�nen�s. 49 7.4 Severability. I00 Any provision or part of the Cont�act Documents held to be uneonstit�itional, void or 1�1 unenfarceable by a cou�t of coznpetent jurisdictian shall be deeined sri�icken, and all 162 ��e�naining provisions shall cantinue to be valid and binding upon DEVELOPER and i b3 CONTRACTOR. io4 7.5 Govei�ning Law and Venue. 105 This Agreeinent, including all of the Contract Docuinents is perfor�nable in th� Stat� of 106 Texas. Vei3ue shall be Ta�•rant County, Texas, or the United States Dist��ict Co�rt for the 107 Northe�-� District oiTexas, Fort Worth Division. C{TY OI' FORT WORTH Ti•i�rrty B�si�a Bolt Canipz�s STANDAI2D CONSTRUCTtON SPECIFICATIDN DOCUMENTS -� �EVELOPER AWARDEp Pi20JECTS CF�f21-OI26 Itevised Ju«e 16, 201fi n,.., in. 4�n.�.c�on....rn.t..r_,.�nt...l�n.�onnco„otn..�,.r_.a�o 00 52 43 - 4 Developer Awarded Praject Ag€eement �age 4 of 4 10$ 109 7.6 A�tharity to Sign, 110 111 112 113 114 115 116 117 Cont�actor shall at�ach evidence of authozity ta sign Agreement, if other than d��ly atiit��o�•ized szgnatozy of the Con�ractor, IN WITNESS WHEItEO�, D�v�loper ancE Contractor have executed this Agx•ee�ent in tnultipie caunte��pai�is. This Agceement is effective as of the last date signed by tlie Parties ("Effective Date"). Cont�actor: B�tl�r-Cohen LLC DeveIoper: Trinity Basin Preparatoiy By: � /�' � , liU � B /�{� c�� {Signature) ignature} Eric M. Cohen Rand Shaffet (Printed Name} (Printed Natne} Title: President Title: CEO Coinpany Name: Butler-Cohen LLC Cotnpany nam�: T�-inity Basin Preparatory, Inc. Address: Address: 3200 Southwest Fwy. Suite I575 2730 N. Hwy 35� City/State/Zip: Hous#on, TX 77027 Ci IStatelZi : Grand Prauie, TX 75050 10/20/2021 Date 118 l0�2o�2a21 Date CTTY OF FORT WORTH Ti•iraity Basin Bali Canrpirs STANDARI� CO?�iSTItUCTIQN SPEC[PICATIOi�i bOCU3v[EAITS — BBVBLOP�R AWARDEI] PROJECTS CFrt21-0126 Revised Jeme I6, 20 E 6 n..., in. ann,��oon,.,.cn,�,.r_„-rnr...e-�n.�annco..atn,.�..,c.��o ACORD 101 (2008/01) The ACORD name and logo are registered marks of ACORD © 2008 ACORD CORPORATION. All rights reserved. THIS ADDITIONAL REMARKS FORM IS A SCHEDULE TO ACORD FORM, FORM NUMBER:FORM TITLE: ADDITIONAL REMARKS ADDITIONAL REMARKS SCHEDULE Page of AGENCY CUSTOMER ID: LOC #: AGENCY CARRIER NAIC CODE POLICY NUMBER NAMED INSURED EFFECTIVE DATE: BUTLERCOHE 1 1 Brady,Chapman,Holland &Associates Butler-Cohen,LLC 3200 Southwest Freeway #1575 Houston TX 77027 25 CERTIFICATE OF LIABILITY INSURANCE Builders Risk includes additional named insured (but only to the extent of their financial interest in Covered Property:Owners of Covered Property;Mortgagees or loss payees;Contractors,subcontractors and sub-sub contractors and lessors or lessees per form CMT2210413 when required my written contract. Builders Risk Continued: $2,000,000 Group 1 Limit At Any One Location (Frame &Joisted Masonry Projects)outside Tier 1 Counties $25,000,000 Group 2 Limit At Any One Location (Noncombustible or Better Construction outside of Tier 1 Counties located in Tier 2 Counties $25,000,000 Group 3 Limit At Any One Location (Noncombustible or Better Construction outside of Tier 1 and Tier 2 Counties $5,000,000 Group 4 Limit At Any One Location (Masonry Noncombustible or better Construction inside Tier 1 Counties) $15,000,000 Earth Movement –(Low Hazard Counties)Occurrence/Annual Aggregate $5,000,000 Flood Applicable to Zone,B,X (shaded)&Zone X-500 Occurrence /Annual Aggregate $15,000,000 Flood Applicable to Zone C,and Zone X (un-shaded)–Occurrence/Annual Aggregate $500,000 Limit At A Temporary Location (Storage) $500,000 Transit Limit Builders Deductibles: $2,500.00 Per Occurrence (Except) $25,000.00 Rain,Snow,Sleet or Ice Change $25,000.00 Named Storm applicable to Group 1 $1%Named Storm applicable to Group 2 $5%Subj.to $100,000 Min.applicable to Group 4 $25,000.00 Earth Movement $25,000.00 Flood applicable to Zone C or X (unshaded) $50,000.00 Flood applicable to Zone B,Zone X(shaded or Zone X-500 Professional/Pollution Limits:$5,000,000 Ea.Incident/$5,000,000 Aggregate Trinity Basin -Bolt Project Certificate Holders include The City of Fort Worth,Its officers,employees,and servants. 61 UEA HN 6816 All, except Additional insureds that are insured under a separate additional insured endorsement on this policy All Policy No. 61 UEA HN 6816 PQLICY NLlMBER: 51 L3EA HN5816 C�MMERClAL GENERAL LIABIL[TY CG 24 04 05 OS VtifAIVER �F TRANSFER �F RIGHTS �F REC�VERY AGAI N5T �TH E R5 T� US This endorsement modifies insurance pravided under the following: COMMERCIRI� GEN�RAL LIABILITY CE]VERAGE PRRT Pf��QDUCT5IC�MPLETE� OPERATIDNS LfABlLITY COVERAGE PART SCHE�LILE Hame �f Person Qr �rganixation: PER LIST ON FILE GV�TH AG��CY Information repuired to complete this Schedufa, if not shown ahove, will be ihe following is added to Paragraph 8. Transfer Qf RigE�is C}f Recovery AgainSt O#hers To Us of 5ectian lV — Conditions: We waive any right of recovery we may ha�e against the persan or arganizatian shown in tne Schedule above be�ause of payments w� make for injury ar damage arising out af your or�going operations ❑r "yti�r work" dane under a cc�ntract with t#�at person or arganization and included in the "produ�ts- campleted operatians hazard". This waiver applies only to the person or organization shown in the Schedule above. own in the Declarations. CG 24 04 05 D9 Q Insurance 5ervices Dffi�e, InG., 2QD8 Page 1 of 1 PQI.ICY NLiMBER: 61 vEA xtv687.5 +�.,; .�•• � THtS ENDORSEMENT CHANGES THE POLiCY. PLEASE REAI] 1T CAREF�LLY. N�TICE �F CANCELLATI�N T� DESIGNATED CERTIFICATE H�L�ER SCHEDUL� Number of Days No#ice: Name of Certificate Fivlder: PER SCHEI?C]LE �N FILE WITH AGENCY Part A: 30 Par# B: 3 � Mailing Address: Part C: � Q This palicy is subject to the fallowing additional Condifians when a number of days are shown in the Schedule tor any of the aba�e Parts. A. ff this poiicy is cancelled �y the Company, other than for nonpayment of premium, natice of such cancellation will be pro�ided ta the cerfificate holder in the Schedule, at least the num�er of days in ad�ance of the cancellation effective date, as shown in Part A. B. If ihis policy is canceilad by the �om�any for nqnpayment e�f premium, noti�e af such �ancelkatian will be provided to the certificate ha�der in the 5chedule within the number of days noti�e af the cancellation effe�tive date, as si�own in �'art B. C. lf this palicy is canceEled by the insured, notice of such canceliatian will be provided ta the certificate halder in the Schedule, within fhe number ❑f days natice af Che cancelfation effective date, as shawn in Part C. If nati�e is mailed, praof of mailing notice tv the certificate �alder's mailing address as shown in the Scheduie will �e sufficient proaf of natice. If the number af days notice in the Schedule for any Part is left folank ar is shawn as �era, no r�atice wi11 be {�rovided to the 5cheduled certificat� halder under that Part. Any nv#ificatian rights provided f�y tY�is endarsement apply only to active certificate ho�der�s] who were issued a certificate af insurance appli�a�le to this poficy's term. Form IH 03 08 fl6 11 Page 1�f 1 4 2D11, The Hartford Policy No. 61 UEA HN6815 Policy No. 61 UEA HN6815 Policy No. 61 UEA HN6815 Policy No. 61 UEA HN6815 Policy No. 61 UEA HN6815 Policy No. 61 UEA HN6815 4/15/2021 4/12/2021 4/15/2022 4/15/2021 4/12/2021 4/15/2022 Policy No.61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 Policy No. 61 RHA HN6989 83 CPI EB7514 83 CPI EB7514 Page 18 of 24 Form CL 00 05 10 15 1.If all of the other insurance permits contribution by equal shares, we will follow this method also. Under this approach, each insurer contributes equal amounts until it has paid its applicable limit of insurance or none of the loss remains, whichever comes first. 2.If any of the other insurance does not permit contribution by equal shares, we will contribute by limits. Under this method, each insurer’s share is based on the ratio of its applicable limit of insurance to the total applicable limits of insurance of all insurers. d.An "insured" must submit all "claims", "professional incidents", "protective incidents", "pollution incidents" and "pollution injuries" for defense and indemnity to any other applicable or potentially applicable insurance. When any other insurance has a duty to defend a "claim", we will have no duty to pay "claim expense". If no such other insurance defends the "claim" and we have an obligation to pay "claim expense" under this insurance, we will have the right to control the defense of an "insured" with counsel of our mutual agreement as set forth in SECTION V – CONDITIONS,Paragraph 3. Defense of Claim. 19. Additional Insureds (Applicable to Coverage Parts D, F and G Only) This Policy extends coverage to "additional insureds" under COVERAGE D - CONSTRUCTION JOB SITE POLLUTION, COVERAGE F – CONSTRUCTION RELATED TRANSPORTATION POLLUTION,and COVERAGE G – NON-OWNED DISPOSAL SITE POLLUTION.Coverage for "additional insureds" is extended: a.Only when a Limit of Insurance for such Coverage Part is shown in the Declarations; and b.With respect to the "additional insured’s" liability resulting solely from "covered operations" or "completed operations" at a "construction jobsite", "transportation" to or from a "construction jobsite", or disposal of waste or materials generated at a "construction jobsite" performed by an "insured" or by those acting on behalf of an "insured" other than the "additional insured"; and c.Only for the period of time required by the written contract or written agreement, or written permit or written license, between the "insured" and "additional insured". Coverage for "additional insureds" shall not exceed the lesser of the applicable Limit of Insurance available under this Policy or the Limit of Insurance required by written contract or written agreement, or written permit or written license, between the "insured" and the "additional insured." If coverage under this Policy is extended to an "additional insured" under this SECTION V - CONDITIONS, Paragraph 19.,subject to all limitations set forth herein, the "additional insured" will be deemed an "insured" under this Policy. SECTION VI – EXTENDED REPORTING PERIODS (CLAIMS MADE AND REPORTED COVERAGES) This Section applies to any Coverage Part or endorsement to this Policy issued on a Claims Made and Reported basis. 1. Basic Extended Reporting Period We will provide a basic "extended reporting period", as described below, if: a.This Policy is canceled or not renewed by us for any reason other than nonpayment of premium, fraud or misrepresentation; or b.We renew or replace this Policy with insurance that does not apply to "claims", "protective indemnity claims", "professional incidents", "pollution incidents" or "pollution injury" that would be covered under this Policy. c.Subject to SECTION VI – EXTENDED REPORTING PERIODS,Paragraphs 1a.and 1b.above, a basic "extended reporting period" is automatically provided without additional charge. This period starts with the end of the "policy period" and lasts for 90 days. The basic "extended reporting period" does not apply to "claims", "protective indemnity claims", "professional incidents", or "pollution incidents" that are covered under any subsequent insurance providing coverage to an "insured", or that would be covered by the subsequent insurance, except for exhaustion of limits. 2.Supplemental Extended Reporting Period We will provide a supplemental "extended reporting period" at the written request of the first Named Insured made no later than 60 days after the end of the "policy period." The supplemental "extended reporting period" will be provided by endorsement to this Policy for an additional premium charge. The endorsement shall set forth all terms and conditions applicable to the supplemental "extended reporting period". Policy NO. 83CP1EB7514 D�VELOPMFNT B�N� GUARtiNTE�ING PEI�FQRMANCE AND FAIEMENT �F IMPROV�MENTS Bond No. IL2S2537-2�1Q$ I{NOW AY,Y, iVIEN F3Y T���;SE PRESENTS, #hat we,� (Trittity Basir� preparato�'y, �n�.}, as Principal, and, {Lexingtpn N�t�o�al Insurance Corporatiun}, � curporatian organixed a�d exi5ting under tlie lawa of the State of IFlorids��, and tully authoriced ta transact bnsine�s in tt�c Statc of 7'exas, as �uret�, a�'e held and �rrnly 6oand u�tto CITY O� 1�'4�'T Wl7RT�#, TL+'XAS, 2�0 'Cexas Street, Fort Wort�, Texas, 761U2, �s Qbligce, in the penal surri of Tk�rce FIundred Twenty-�ne Thousand, �.ight Hundred Ni�tety�Fivc Dollars and �ixty-Ninc Ccnts ($321,$95.�i9Z�law�u� rnoney of the United States of A�neri¢s�, for the payment of which well and truly to he rnade, vve bind aurselves, aun c�:irs, exe�utars, administrators, successars and assigns, jointly �nd severally, �rmly by these p�resertts. WHEAREAS, !{T'rinity Ba5in Pt�epai'�tory, Inc.a has agreed ta corts#ruct in �('Y"rinity Sasin �'rcparaxory —13olt — C�'A IYp. CFA21�0126 — Project No. 1Q3537Z, in �hc CI7'� OI+' N ORT WUR'1'H, `fEXAS the Following irnprovements: '(W;tter, Sewei•, �'avin�, Stprm DraSn, S#rcrt Ligl�ts�� WHEItEAS, in the event of �ankruptc�, dcf;tult or ather nonperfarrnnartcc by Princi�al, clairras against Principal ar the development, Qbligce n»y be left without adequat� satisfaction. N�W, T�[EREFORE, THE C�NDITIDN Or THIS O���GATION YS SUCH, th$t if the said Principal shall canstru�t, ur have constructed, the improv�ments herein described, und shall pay fo�' the cost of all lahor, materials and equxp�ttent furnished in canttection wfth the constructian of said impravements, and sh��� save the Obligee harmles� from a�y loss, cost or damage by rcroson� af its failure to complete the const�'uction of said im�rovements ar by a•easan af its failure to pay fo�' tlye cost af same, #he�t this ubligatian shall be uull and voi[i, atherwise ta reinain in fvl! fo�'CC dnd eifect; r�n� upan receipt of a claim by the Caty of Furt Worth indicating that #hc construction of said improvements has not �een cnmpleted, or that the casts %r sam� have nat been p�id, the Sure#y w��l pay to thc City of Fprf' Worth such arnount up to thc arnaxmt of this bo�cl whieh will �Iluw the City af Far# Worth to �omplete constructNon Qf said improveme�tts and to pay fnr #he ensts of same. We liereby agree with you that the draft{s) drawn under and in compliance with tl�e telrxtts of this bond vvila he duly hanored upon pt�ese�ttaEion at: [�ut'ety);Lcxington Nat�onal Insurs�nce Cor�ara#iun �ail eode: � {Surety �Address) �'.O. Bax 6D9$, Lutherville,lV�p 21094 IAttn: �,isa R. Slatcr lor by facsimile to (sut'ety:� Lexington National Insurance Cnmpany,' Fax Nunnbcr (4�U) b2S-0865;confrimed by �t phone call jat {41.0) 625-0$4U� FROVIDED �U1tTHFR, th�t this bond sl�all a�#o�tatie�lly be increased by #he �mount of �ny change order, suppletnental agreement or arn�ndteucnt which increase the price of the aforementioned contract. PRQV[Ia�D FURTHER, tl�at if any lega[ action �e tiled on this band, the laws aF #he St�►te of Texag 5h�a� �lpply and that venue shsll lie exclusi�ely in 'Tarrant County, Texas. AND PR013YDED FURTE�, that the sai� surety, for v��ue rcceived, hereby sfi�ulates and agrees that no cl�arge, ex#en5ion of time, alteration oar addikinn to tlie terms of ar►y contract far the �ublic affcct N#s obligatian on this band, attd it does herehy waive notiee of any svch change, exten5rar� of tirttc, �Iteration or addition ta thc terms of such cnntraci', This bond is given pursuan# #o the pro�isions af Sectivn 212,073 of the Texas Local Gavernment Code, as sucl� �nnay amended from time to time. Signed, sea�ed and dated this ��� day of,� �(20 �.�, rl'rinitv �asit� �'reparatory, Inc? ��'riricipal, �y: . Lexin ton Natianal InSu�'ancc Cor orstian � �Surety �y: ��- ���, ---- � 1� Chris Kplger, Attor y-in-Fact `����tiiui� rr�ff� ����`�.�ypNAL IIW���.f �,titi �..���•f..... '�` � frf ti �o i 4�,�DRq�,.-v� : � �'3" ;C' j =�'� 1989 a;�� t�: o� �,s+• :�r � � : •b � •. �frf ■ *�����**��'+• ,�ti� }'��i '�� � R 10 p' �tr�r �lr�ir�li�t����r IMP4RTANT NDTICE - TH15 POWER OF A7T4RNEY 15 VOID IF "LNlC Qr�g�nal" WA7ERMARK I5 MQT PRESENT P�WE�i OF ATTaRNEY lexingtan N�tionaf Insurance Cnrpnration Lexing�prl N��ional Insurance Corporatipri, a carporatian duly OCg�rlized under the Iewg o} tha 5tate ot F[orida and having iis principa! administrative ofTiCe irl8�ltirrtare Counly, Maryland, daes hereby m�ke, Constilute and appaint: Chr�stopher K�lger and Aaron Steffey as ils irue and lawful altamey-in-fact, each in t�eir seperate capacity, with full power and au#hority la execute, acknowtedge, seal and deliver on its behalf as surety �r1y bond or undeHaking pf �1,5pp,U00 or less. This Power of Attorney Is vpid if used for any bond over ihat ampunt. This P�wer Of Atiorney is granied under and by autharity of the fpllOvuing resolulions ad�pted by the Board af �ireClors of !he COmpany an Fe6ruary 15, 2D�8; Be it Ftesolv�d, th211he PresidenE or any Vice-President shall 5e snd is hereby vesied wlih [ull pawer and authority lo appoint sUit$ble persans as Attarney-In-FaCt t0 represent and acl fpr and on hehalf of the Cpmpany subjecl 10 the follawing provisians; Attorney-in-Fact m2y be giv�n full power and au�hp�ity for and in Ihe name af a�d on !he behalf aF khe Company, to execute, acknowtedge a�d deli�er any and all trondB. �ontracts, or indernnity and other condilian�] pr pbligalary undertakings, irlCluding any and all Consenls for the release ef r�t8111ed percenlages and/or final estimates on enginBering and canstructlon Cprltt�Gts, and any all nalices and doeumenlS CanCelling or terminaiing the Company's liabili#y thereunder and any such instrumerlls so executed by any Attorney-in Fac1 shall be hinding upon lhe Cpmpany as if signed by Ih8 President and sealed by 1he Corparate Secret8ry, R�SpLV�� further, thal the si�nalure af lhe President or a�ry ViCE-President oF LEXINGTpN NAiIOMAL INSURANGE CORP�RATION may be affixed by faGslrttile ta any power of atlomey, 8r1d the signalure af the Secretary or any Assistant SeCretary and ihe seal of the Cemp$ny m2y be a(fixed hy facsfmlle lo $ny cerlificate of sueh ppwer, or any such power ot CBflificate bearing such faCsimile signature Or Se�l Shall be valid and bindfng an the Company. Any SUCh pCwer so executed and SB$led and certified by cerlifiCate so execuled and sealed �nriih respeCl 10 any band to which it is a#taChed continue to he valld and binding upon Ihe Comp�rly. IN WIiN�9S WWEREDF, thB Campany have caused thls insirument lo he slgned �nd Iheir corporale seal io be hereta affixed. �-�'�--��'-+ ��. �a., •. 4 Ronald A, Frank, Presiden� � ^��9 State of Maryland .� hF r� Counly af HarFord County, SS: B2fOre me, a notary puhlic, personally appeared, Ronald A. Frank, President of Lexir�gtOr1 Natianal InsuranCe Corparaiion, who proved to me on Ihe basis of satisfacfory evidence lo h� Ehe persnn wha9e riame is subscribed io ihe uvithin inslrume�l and acknpvv�pdged to me Ihai he execuied lhe same in his capacity, and that by his signature an khe instnament the perspn, qr the entity upGn behalf o( which Fhe person �Cled, executed the insErument. f certify under the PENAL�Y oi PERJURY UndeY the laws nC the 5late af Maryland that the foregvEng p�ragraph is true and CorraCt. WITNEBS my hand and qNicial seal. Cnmmissipn �xpires; D5I23124 I! ,; , �--� f � / I, Lis2� R. Slater, 5eoretary of �exington National Insurance Carporalian, do here�y certify that the abave and foregoing is true and correci copy of a Pawer 4(A1tOmey, executed by said company, which is stlll in fui! torCe �nd effect; funhermvre, 1�1� resolutions oF the Baerds af �irectors, set oui in lhe Power of Atlurney are in full Torce and eFfeCt. n Wilness ereof„ ave hereunla set my hand ��2Q� Corpotate Seal: F w+i�tP��wr oi nnarna, r4,m cs xos i.Po, and affixed the se�l of said Company at Baltimore, Maryland thls��y o( LISaR, ater, ecrelary ���k���r����rl/�l��f�i�i �� �� ���i\Y��-+��� fff� y ��� ��Q �I�� • ��� r • � � ['7 r �z:� ���� a;c��= ��c. ; �x � �� '•. :' •� : f . . . f}Ir ���**ri*rs•��* ��titi •,���,�,� � O R � D �`����`, �n'l]i;1�INITY AGRi;1:M[�.�v-r.a�ri� c�t�ar�r• ct��c�c n�aTiiar���a,�•�a�v 1'he undcrsi6ned re�rc�cnRs ikxat a�! sta�eir�cn�s mttdC in ihi5 application tur� l�'uc iiitcl ��iadc ��i�hout reservation tn induc� I.lI\]Il€!IUfl N:l�liYll:ll lnsurancc (:c�rpp���kion ("Sul'Cty�`) i4 CxiC�ld surCly crcdit in a�iy manner or tun�unt, includin� buF noc limi�ed tca praviding or havin� prnvicicrl �-cc�ucsted ban€i(s), i,icl��di�sb .ut}' int�dilica�ion;; thcrcto. ����1C Llf1C�LC51€,I]L'L� ;1�,1'4'('h: ( I} 10 p.�y prci�7iui5ts tivf�cii cluc:; (2) tit cl�iiucr t:vidcncq ti�ktis(�tclory to Surcry ol'tiic rcl�a�c nl`,ill li,3bi]itY; �3} 14 C1C01141'A[C fl]lLG indcmnii'y 5urcty i'rom 317C� 1�+;illiS[ Fl�� C�F1i117E, �u'titiCti, [�.tln..�g�g p� tiny typc (iiicluili:t� punitivc). cas(s, EXj]L'115C9. 41'(f�1'5, .judgmcnts, ur �djudicaliunti �vhafsncvcr ti�liich 5urcty ntt�y iTicur i�i .2nY n7itnnE4- fClillC4l LO lIlL' CXlCltti[(711 UI�SUI-Cfj' CI'ki�ll, (coElcc[ivcly .:L055"); �tI} tll:fl �lll'L'1}' SI7FIII �1ifVC t�1C 1'I�ISl, fl[ lls 5[7IC (IttiCi�cliilil, �q p���, 1�just or comprcainisc any 1,(]�� Bl1C� I�lc: VOLiC�SCr Or ulhcr c�icic�cc nt� ti4�C�1 paymcnt, s<tticmcnt or co�rrprn�t�isc.,ti�l,c�hcr �;urcly ti�;�s Eiablc thcr�lbr ��r noi, sh�ll bc prima facic cuidaticc of �hc f�ct iand cxtent aFuuclorsigned's liability, {5) 4<� place 5urcty i�i funds within liircc tlu}•s �af dcmancl, t��c amout�t of Sur�:(y dc����5 �����wsary co protcc[ itsc[f I'r�xn any l.()�� pr ppl�»tial I.(}�S, �vhclhcr ar not Surciy has madc papmcnt or pns[ed ;i reservc. Sui�cty li.lving ihc righl Ip uwC Zll 41' �ai11't nf tflCsc f�untls in p,lymCnS nr 9�11[Cm�n� of' �tty 1_05S ar in r�inilaurscmen[ lt7 Surcl}� ftx' paymcn( ol'siyitiic; (G) thal Ss�rely m�y brin� sc���rntc s�iits to rccovcr l�crcu�lder as cait�scs ol'uctiun slzrill accruc ,uld th�[ ihe bringif�g nf wuit nr rccovcry �,i'�uci��n��}� upon flny cnusc nf sictiun sh�ll n❑t ��rcjudico oe bar thc bri�iging oCotlicr suits �i��u�� stll7cr causes oi'�tctio��, whcthcr Itor4tolorc or thcrcaftor arisin�: (7) that at] olhcr ��i8hls Surciy inay Itavc uiuicrsigrtcs3 uncicr oti�cr or ��dditioiral agrccirYcnls crE'i��dcmnily or any oilicr �vrit[�n �i�.rccm�ni r�lat�d tcr �hc cklcnsion af surcry crcclil. shnll bc in �dcliiinn �o ond no1 i�i lieu oftl�c riglrt5 nfTc>rdcci 5urc4y� uncf4r lhis Agrcc:��cnt; (8j tls:L� 3CSLll'l:Ly' f1;117iLlfL';ti all af,�ny p,�r3 of any bocirl, ilsiu oll ll�c lcrms uf tl�i4 11g�+ecmcnl sl��l! npply and nperalc I'or tltic �cnctit af sucl� rciusurcr, il5 illClf 117�CfCtiL Il7flj� il�}�Ci11; (�} thflt tl7csc cnvcr��,r�s 51r�11 hc hi�,ding upo�� undcrsignccl, i=s Izcirs, ctccutarrs, administratars, succcssars u�tid isssigns: (1{}) 1h�15urcty Slisill li;jvo Ihc: ri�hl lo d�clinc to is�i�e or lu cancel hpnd(y} ;�t any tiutie, frce ofc��im inr It�ss or damage by w7dcr,ig�tcd, orrcl 5urcty ;;hall h4 il�l({l'I' I10 GISI1�,111011 lU [IISi:I45C Ei5 ['L':15[7115 LI1C1"CtOf, !he provisions af fliEy lfr�v to il�c conlr�ary bcing lie��cby �vaived; � I�� ill.li IIl{: C:XL'f[:ltiL', {{�I,��, �f or f�rilure by Surc�y �u cxcrc:isc ui'al4Y f1��1�, ramedy or potivcr �vlr.l�tiUL:4�L:f tillylll [lQ� �)�'�GjUCI4' SLII'Z�}''s sirxultancous ul'subSec�ucnt GxCi'cISC Ot' C61151I1L11C fllly �ViUVCY ul�::u�Iz crr OkhCi' P�alllS. fCI11Cf�1�5 UI' �701VC�S; � �Z� llltYl Lu14ic:�Sf�rtC{� �,�ill prnvidc reasoEeszblc �1CCL`5� Ia nik rccords co�rccrnin�, ihc csl.�[c ancl upon rcqucst shall �,rn�ida �i wrictcn rcpart of thc coni[iliu�s of !hc csla�c. Tl�c u�icicrsigncd �,r�intti, ussignv, �iicii�cti ;incl convcys 90 5urcly zis wccuri�y, a licn on ;tn<i sccur'i(y inlcrest in and u� undorsigncd's intcrest in thc cs�.itc and uncfcrsig��ed's ii�teresi, titic and righte in thc prc�cecds v!'any insta•anc� policy nfforcEin� cnvcrage for all ar pnrl af �ny bnnd ubligatian. ,inci i» tho conlr��cls or obkigfllions (unii aEl prnc�cc3s U3urcc�f �v11I7011[ I11111it411L7�]} LE7ft�.11lS(: 117 f1111' ]llil]111G1' 1VIli1LSO45'S`.]'.iS :l f(:�LI�� {1� tEll: (:\�E:f151p11 4f sure�y ci�:dit. Wlrilc al�c licn and �urcty intor4sls arc cl'fcclivc immcdialcl; , Su�cly may c7�G�Ctti4 S�ti I'CI1lCT�iC5 1YIlI1 I'Ctij7CL'L [U ti41CI1 411I}' IIl 1�7L' CYCIlI aC: zi) im�cryi�n4C�'s tailura la fulfill ��iy obligatio�r w6�jtso��er Fnr whici, (iJ ba�id(s) nre providctl: ii) ccrntaincrl in any i�ond;s], or iii) cn�ki��incd tvill,in ;�ny othcr s�grccmcnt tivil8 lho Surcly; �nci [�} .�ny assignmcnl lry u�icicrsigitccl ior lhc bcn��i! nE�crcrliturs or nny ngr�c�ncnt ur prc�cccding of ]iquitlalitm, rceciv�rship nr banlcrup�c}� u-h�t�oc�cr. Uncicrsignccl Iticrcby authurii�s 5urcly ta file s�ny sucl7 lin<�ncin6 stake��te�at as Surcty dccnts ncccssary ur .i�i�yruPri�il� lo p41�1�;C1 iilC itCll5 tltlCl sCCurity i�iicrcnl granlcd harcitt. 'i'he undcrsig»ed �r};rccs ti> iizdcmniij� and hold harmlcss tlrc Sw�cty for <<II lc�.ol Iccti :u�41 collcction-rclatc[I cx�,cnsc� incurr4[1 by 1hc 5urciy in nay litigatic}n �,cs~vco�, tho Surcty ancl tl�e tiiicicrsigricil to cnlincc tl�c �cn�,s al Ihis Akrcciueni, `l'his Agrccmenl sh��lE not bc iucc•gccl i�Eto <u�y j��dg�7�cnt, but instca<I si�nll sitrvivc il�c judgmcnt. 1-hc und4rsig�ied siilll Uc li�rblc io 5urc�y I'rrr .�l[ Icg,il fcas Ifll(I OlI1C1' �ii7S[ ,jiiClbmcn[ c.��)Ci7yUS ��7C4lffC(I i]y the Surcty in .��ic�npting �a cniirrcc c,r collccs �any.judgmc�rt, �f'��at uncicrsi�,nccl atHltsyriics Surcly lo inv�stigalc si;�lamcnls rnucle lierci�r, F�ncl Ic� c�l�tain crcclil raporl iniiar�n�nlinn li�aan crGdit rcportin�y sourccslburc.iuti, and kn chuck cruciil �vith crarliturs tSIuII61' ICiI[�in� in5litalicros, {i¢��I IpS1�Y4]'slLlillOfl'l.C5.11ly �7fCtiGll OT ip['l1}Cf L'IT1�7IOyeror flny othcr perhan, firm nr corpnratiai, [O I'1IP1715I1 Irit�Otn�tlii4u C[Snccrnin� undcryi�ned in conn�ctio�� w1111 lhc Surcty's cx�cnsian a1'surcty crcdit �,r,d Svith tmdcrsigi�ed's compliancc w;tE7 nhligatica„s hervunder a�id undcr aiiy boncE or undcriyin� t�Ulig�itl0[l. illlii UlStICCsl�iICCI I1crc:I�y rclCil545 any of'the f1�01'ClS1CiltiOnC[� I�i�an7 Ii.t�7ili�y in C0�15CL]41CI1CC OI� I�ll['1lI5Il[tl� Of (IISL'IIISIII€, SIICEI llllpl'Itlllli0fl. u� rr��Ncxr���, �s: - SOLL, PIi{]PRIFTQRS�I[P, owner must si�n Rg (11'1C1Cip�tl. Also the pwnCC 1Etd spouse must Si�tl Ik7diVidu711y. � 1'AK'f'Iw1FRSHII�, one at�thoriaec� partner must si�r7 Cur principaL Also �II �uthorized pariners Znd lheir spouses must si�n indi�i�E�E�lly. - CORPORA7'IOiV, I'resident inust sign f'or principal. Alsp siockhoiders of co�•p�r�tion otiv«ing 10°14 or more and their s��ou5cs n5us[ sibn iridividua�ly. - LLC, thc mana,�ing mcn�bcr �t7usi sign on behalf oi tlie LLC. Alsa all auihorizcd ittEl[l�lf�T$CS/111�I11I)�I'S �Rtl{I I�1011" SPU11585 I1lLI5t sign indivicEually. S1�"11C{I LE715 z81h d��, pf Septembcr �1'I[7G�j�] Nc�171C; 7rinity�asin Pr�p�r��ory.lnc, 20 2� ("�ype or Print Principal Nam�) Randal C. 5haffor, PresVdent and CEp g�. � (Type ar Pi�int Name a�t�f '["itle) 5ignature Dated this � d�ty of ���C�fVI�' 2�� �� � ss's 'g alure � A�plicant's Signature ���_�� ��)I-IRf Ilill7lC� (print namc) i�li11CSS'S 51�*[18tU1'C (print ryamc) Witness's signatw�e W itness's Sig�i�ture (Arin� t�aanc) Wii�iess's signature Applicant's Sigtiature (print nlme} nt name) Applic�nl's Signature (print naine} Applinant's Signa�ure (prinl name) (print nan,e) Applicant's 5ignature ��)fllli I1TiT7�� Witroess's signature Ap�lica�t's Signatura T �larint i�ame) fi�s•int nai��c} 96 0062 [9-2 MAfNTENANCE Bf]ND Page 2 oC3 1 2 iVQW THF.REFi7RE. the candition afihis ohligation is such that if Principa[ shaA 3 remedy any de%ciive Work, for which timely notice was provided hy Developer or Ciry, to a � completion satisfactory to t}�e Gity, then t�is abligation shali be�ome null and vaid; otherwise ta 5 remain in full for�cc and effect. d 7 PRDVIDED, HDW�VER, if Principal shall fail sa to repair or re�anstruct any timely 8 noti�ed defective Work, it is agreed that the DeWeloper or City may cause any and all such 9 dei'ective Work to be repaired andlor re�onstructed with all associated costs therevf being borne 10 by the FrinCipai and the Surety under this Mais�tenance Bond; and ll 12 PRdV1I]Ea FURTHF,R, that if any legal a�tion be filed on this Band, �en�e s�a11 �ie in 13 Tarrant County, Texas or the United States District Caurt for the Northem District af Texas, Fort 14 Worth Di�ision; a�d 1S 16 PR�ViQED Fi1RTHER, that this obligation shalt be �ontinuous in nature and 17 successi�e reco�eries may be had herean far su�cessi�e breaches. 18 19 2� GITY OF FORT WORTEI Tirniry Basin Baf� Cnmpas 5iAN17ARR CiiY CQNDfT10N5 — DEVEL4PER AWARDED PRd]ECTS CFA�1-0!2G Rc�isedJanuery 31, 2DIi (Please Pr _______________ Sean Bulter - President P��ER �F ATT�RI�TEY pirect Inqulrres�Cla+ms tv: rr�� �a��FORo 6DND, T-12 Ons FlaRford Plaza HaRford, Can rreeticuf fl6 i 55 8or d.Cia�m s�thehartford.com cslL' 888-Z66-3A88 orfar: 860-757-5935 fCI�OW A�L PER50N$ 6Y THEB� PRESENTS THAT: Ageney �ame: F7XLLI5 OF TE%AS INC A enc GaJa: 6i-Fiii276 � Hartford Fire Insuranca Company, � co�poratiou duly ar�nixed ur�der tIie lawf of the 5tate of Canne�ticut � Hartford Casualty Insurance Cornpany, a ceiporetion duly organixed under the Isws of the State af Tndiazia � Hai'tfard Aecl[[enE and Indemnity Corr�pany, a tarporatian du�y arganixed under tl�e Iaws of the Sfatt of Counectitut � Hartford Unciarwri6ers insuranGa Company, e coiporetian duly orgasuxed vnder the iaws of ths 5tat� of Cvnneeticut L] Twin City Fra Irrsurance Company, t corporatian dvlyarganiud under the iawa of t6e State af indiaaa � HartFvrd Irrsurance Company of Ellina#s, n torporation duIy organized under the laws of the Stalc af niinais � Fiartfvrd lnsurence Company af the Midwest, a corporatian duly organizcd under ffis laws of the 5tate of indiana � HartFord Insuran�e Gompany of the 5outheast, s cosparation duiy organ�ted under thc laws of thc Statc of Flrn�ida having �,air hare o`5ce i� Hartfo�d, Connecii�ut, [hereinatter ['allecfively reTerred to as the 'Companies'} da hereGy rr;ake, cors�:Lifv� 2r1� 2Na6iiii, upfofheamauntuf IInlimited : Carlos A. Albelo. Stephanie Gunderson. navid Stephen Wightman of x0U52'ON. Texas their true and IaurFul P3to�ney(s)-En-Fact, each in thei� separate capa�ity if more than one is named abo�e, fo sign its name as sure'•.y(es} anEy as deGneaied above by �. and to execufe, seal and acknew[eclge any and all bands, undertakings, co�tracts and other vuri�+ken insiruments in 4he nature ti�reaf, an behalf af tl�e Companies in t��ir 6usiness of guaranteeing the fdelif}+ of persvns, guaranteeing fhe perFvrmance of contracts and exer.uting or guaranteeing honds and under`�.akings rBqui�ed or perrr�itted in any actions vr proceedings a{iawed hy faw. [r� �tness Whsreof, and as authorized by a Ftesoli.3tion of the Boarci of �irecEvrs of the Companies on May 6, 2015 the Companfes ha�e caus2d fhese presents fo be signed by its Senior Ves President and i#s corparate sea�s tv be herefa afi�xed, d�ly attested by its ,4ssisEant Secrafary. FuRher, pursuanf to Resolut�on vf the Soard af �ireetors af the Campanies, the Carnpanies here6y unambiguausly affirn that J'�ey ace and wili he bvund by any mechanicafly appfied signaiures applied ta this Pvwer of Attomey. rt �. tl� r �y�14f��� �y+Rl cr�.r- �.�.� }iti °'�, �s� ��'QL� ♦ ' ," "�+, R � � � �.: � � � y :� ,..�..,,�•; � s iaa r $ , _ _ s�v =, � � �*�+� � ��!�#� s,' �ss7f_ - F! ' t 9:�F;:;,saaa`'' i�9r4 t ��f. 14y '�nz�nr••;` '1+�•a�,�x � %�'- 4T �i� yi���2�"F , r' .v� �� �:.r�;•. .r • �ti r �� "';s • -a � * 4 v�_ • 5 � 4��a rR y"j► • ��� �� �-- � _-� � John Gray, Assistant Secretary M. ROss Fisher, Senior Voe President STATE �F COiV�4ECTICUT � �, Hartfard co�Krr oF H�Rr�aRD pn this 5th day af January, 201$, be#ore me personafEy came M. Ross Fisher, tv me knawn, whe being by me duiy swom, did cle�+ose and say: fhat he resides in che Cvunfy af !-lari�ord, State of Connectic�t; that he is the 5enior Vice President of t�e Companies, the �orpa�-atiQns descrbed in and whiGh exe�uted the a6ove insW�ent; ki�at he knows the seals of the said corporations; that the seals a;f�ced tQ the said ins{rur�ent are suth corparate seals; that they were so afrixed 6y autharity af tha Boards aF Di�ecFars v( said corporatio�s and tna� he signed his name f.hereta by Iike authority. �%T. ayh ����'� ���s�...� }�Zv�.ra.�t� • a�� • 1CmsLlern 7, bfaywrd �� Nomr} Publ�c CERTIFiCAT� �y ����a EXp�res Suly 3I, �IY1l E, the undersigned, Assis4ant Vlce P�esfdent of the Cvmpanfes, OQ HERESY CERTIF'r' �at th abave and foregaing is a tr�e and aorr�rt ropy pp the power af Attamey exectrtad by said Campanies, whi�h Is stl�l ]n full forca effaciive as o(� ���� �+ �n � f 5igned and seafed at fhtr Gity af Hartfard. �'-'���~� � �'�1+5 f �M+ u..r �� �yyTf !{�yt �� q yr: ta . � ' � _� ,q�_ �' �yr. ' � ��p�y , `;. �, � �.cl�r�Uf�i� a �p� �" �4 � qP' 'ia�:i � . � � y� ����;� �=��� ��`�n9exr�+� +r�•��i�*��' {,:i 1AT4,-rr ��• 1p�Y �� i T4 /J,�� `r� riF l . �� -^�' � ,j� . ..•� tit ! i • ��, ,e '� Jf . A r `_ � �-<v�. R-�"x� r �'�� .�,r.•'' �+�� + �•-�r f� % C� �lr�iLcv �"u� Kev� He�}cman. Assistant V�� President [nA }iix CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS Trinity Basin Preparatory - Bolt CPN 103537 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS TABLE OF CONTENTS Page Article 1 – Definitions and Terminology .......................................................................................................... 1  1.01 Defined Terms ............................................................................................................................... 1  1.02 Terminology .................................................................................................................................. 5  Article 2 – Preliminary Matters ......................................................................................................................... 6  2.01 Before Starting Construction ........................................................................................................ 6  2.02 Preconstruction Conference .......................................................................................................... 6  2.03 Public Meeting .............................................................................................................................. 6  Article 3 – Contract Documents and Amending ............................................................................................... 6  3.01 Reference Standards ..................................................................................................................... 6  3.02 Amending and Supplementing Contract Documents .................................................................. 6  Article 4 – Bonds and Insurance ....................................................................................................................... 7  4.01 Licensed Sureties and Insurers ..................................................................................................... 7  4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7  4.03 Certificates of Insurance ............................................................................................................... 7  4.04 Contractor’s Insurance .................................................................................................................. 9  4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12  Article 5 – Contractor’s Responsibilities ........................................................................................................ 12  5.01 Supervision and Superintendent ................................................................................................. 12  5.02 Labor; Working Hours ................................................................................................................ 13  5.03 Services, Materials, and Equipment ........................................................................................... 13  5.04 Project Schedule .......................................................................................................................... 14  5.05 Substitutes and “Or-Equals” ....................................................................................................... 14  5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16  5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16  5.08 Wage Rates.................................................................................................................................. 18  5.09 Patent Fees and Royalties ........................................................................................................... 19  5.10 Laws and Regulations ................................................................................................................. 19  5.11 Use of Site and Other Areas ....................................................................................................... 19  5.12 Record Documents ...................................................................................................................... 20  5.13 Safety and Protection .................................................................................................................. 21  5.14 Safety Representative ................................................................................................................. 21  5.15 Hazard Communication Programs ............................................................................................. 22  5.16 Submittals .................................................................................................................................... 22  5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23  Trinity Basin Preparatory - Bolt CPN 103537 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.18 Indemnification ........................................................................................................................... 24  5.19 Delegation of Professional Design Services .............................................................................. 24  5.20 Right to Audit: ............................................................................................................................ 25  5.21 Nondiscrimination....................................................................................................................... 25  Article 6 – Other Work at the Site ................................................................................................................... 26  6.01 Related Work at Site ................................................................................................................... 26  Article 7 – City’s Responsibilities................................................................................................................... 26  7.01 Inspections, Tests, and Approvals .............................................................................................. 26  7.02 Limitations on City’s Responsibilities ....................................................................................... 26  7.03 Compliance with Safety Program ............................................................................................... 27  Article 8 – City’s Observation Status During Construction ........................................................................... 27  8.01 City’s Project Representative ..................................................................................................... 27  8.02 Authorized Variations in Work .................................................................................................. 27  8.03 Rejecting Defective Work .......................................................................................................... 27  8.04 Determinations for Work Performed .......................................................................................... 28  Article 9 – Changes in the Work ..................................................................................................................... 28  9.01 Authorized Changes in the Work ............................................................................................... 28  9.02 Notification to Surety .................................................................................................................. 28  Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28  10.01 Change of Contract Price ............................................................................................................ 28  10.02 Change of Contract Time............................................................................................................ 28  10.03 Delays .......................................................................................................................................... 28  Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29  11.01 Notice of Defects ........................................................................................................................ 29  11.02 Access to Work ........................................................................................................................... 29  11.03 Tests and Inspections .................................................................................................................. 29  11.04 Uncovering Work ....................................................................................................................... 30  11.05 City May Stop the Work ............................................................................................................. 30  11.06 Correction or Removal of Defective Work ................................................................................ 30  11.07 Correction Period ........................................................................................................................ 30  11.08 City May Correct Defective Work ............................................................................................. 31  Article 12 – Completion .................................................................................................................................. 32  12.01 Contractor’s Warranty of Title ................................................................................................... 32  12.02 Partial Utilization ........................................................................................................................ 32  12.03 Final Inspection ........................................................................................................................... 32  12.04 Final Acceptance ......................................................................................................................... 33  Article 13 – Suspension of Work .................................................................................................................... 33  13.01 City May Suspend Work ............................................................................................................ 33  Article 14 – Miscellaneous .............................................................................................................................. 34  14.01 Giving Notice .............................................................................................................................. 34  Trinity Basin Preparatory - Bolt CPN 103537 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 14.02 Computation of Times ................................................................................................................ 34  14.03 Cumulative Remedies ................................................................................................................. 34  14.04 Survival of Obligations ............................................................................................................... 35  14.05 Headings ...................................................................................................................................... 35  Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 1 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 1 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 1 – DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms A. Wherever used in these General Conditions or in other Contract Documents, the terms listed below have the meanings indicated which are applicable to both the singular and plural thereof, and words denoting gender shall include the masculine, feminine and neuter. Said terms are generally capitalized or written in italics, but not always. When used in a context consistent with the definition of a listed-defined term, the term shall have a meaning as defined below whether capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Agreement - The written instrument which is evidence of the agreement between Developer and Contractor covering the Work 2. Asbestos—Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 3. Business Day – A business day is defined as a day that the City conducts normal business, generally Monday through Friday, except for federal or state holidays observed by the City. 4. Buzzsaw – City’s on-line, electronic document management and collaboration system. 5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight. 6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by, its governing body through its City Manager, his designee, or agents authorized pursuant to its duly authorized charter on his behalf. 7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City for the Construction of one or more following public facilities within the City public right-of- way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs. A CFA may include private facilities within the right-of-way dedicated as private right-of- way or easement on a recorded plat. 8. Contract—The entire and integrated written document incorporating the Contract Documents between the Developer, Contractor, and/or City concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral. 9. Contract Documents—Those items that make up the contract and which must include the Agreement, and it’s attachments such as standard construction specifications, standard City Conditions, other general conditions of the Developer, including: a. An Agreement Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 2 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 2 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 b. Attachments to the Agreement i. Bid Form ii. Vendor Compliance with State Law Non-Resident Bidder iii. Prequalification Statement c. Current Prevailing Wage Rates Table (if required by City) d. Insurance Accord Form e. Payment Bond f. Performance Bond g. Maintenance Bond h. Power of Attorney for Bonds i. Workers Compensation Affidavit j. MWBE Commitment Form( If required by City) k. General Conditions l. Supplementary Conditions m. The Standard City Conditions n. Specifications specifically made part of the Contract Documents by attachment, if not attached, as incorporated by reference and described in the Table of Contents of the Project’s Contract Documents o. Drawings p. Documentation submitted by contractor prior to Notice of Award. q. The following which may be delivered or issued after the effective date if the Agreement and, if issued become an incorporated part of the Contract Documents i. Notice to Proceed ii. Field Orders iii. Change Orders iv. Letters of Final Acceptance r. Approved Submittals, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. 10. Contractor—The individual or entity with whom Developer has entered into the Agreement. 11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day. 12. Developer – An individual or entity that desires to make certain improvements within the City of Fort Worth 13. Drawings—That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Submittals are not Drawings as so defined. 14. Engineer—The licensed professional engineer or engineering firm registered in the State of Texas performing professional services for the Developer. 15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor that the Work specified in the Contract Documents has been completed to the satisfaction of the City. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 3 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 3 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 16. Final Inspection – Inspection carried out by the City to verify that the Contractor has completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in conformance with the Contract Documents. 17. General Requirements—A part of the Contract Documents between the Developer and a Contractor. 18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 20. Milestone—A principal event specified in the Contract Documents relating to an intermediate Contract Time prior to Final Acceptance of the Work. 21. Non-Participating Change Order—A document, which is prepared for and reviewed by the City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 22. Participating Change Order—A document, which is prepared for and approved by the City, which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 23. Plans – See definition of Drawings. 24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with the General Requirements, describing the sequence and duration of the activities comprising the Contractor’s plan to accomplish the Work within the Contract Time. 25. Project—The Work to be performed under the Contract Documents. 26. Project Representative—The authorized representative of the City who will be assigned to the Site. 27. Public Meeting – An announced meeting conducted by the Developer to facilitate public participation and to assist the public in gaining an informed view of the Project. 28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday thru Friday (excluding legal holidays). 29. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 4 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 4 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities. 31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or Developer upon which the Work is to be performed, including rights-of-way, permits, and easements for access thereto, and such other lands furnished by City or Developer which are designated for the use of Contractor. 32. Specifications—That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto. Specifications may be specifically made a part of the Contract Documents by attachment or, if not attached, may be incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each Project. 33. Standard City Conditions – That part of the Contract Documents setting forth requirements of the City. 34. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site. 35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. 36. Superintendent – The representative of the Contractor who is available at all times and able to receive instructions from the City and/or Developer and to act for the Contractor. 37. Supplementary Conditions—That part of the Contract Documents which amends or supplements the General Conditions. 38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor. 39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including but not limited to, those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems. 40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday, Sunday or legal holiday, as approved in advance by the City. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 5 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 5 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 41. Work—The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction including any Participating Change Order, Non-Participating Change Order, or Field Order, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents. 42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or legal holidays authorized by the City for contract purposes, in which weather or other conditions not under the control of the Contractor will permit the performance of the principal unit of work underway for a continuous period of not less than 7 hours between 7 a.m. and 6 p.m. 1.02 Terminology A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in the Bidding Requirements or Contract Documents, have the indicated meaning. B. Defective: 1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it: a. does not conform to the Contract Documents; or b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or c. has been damaged prior to City’s written acceptance. C. Furnish, Install, Perform, Provide: 1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or the word “Supply,” or any combination or similar directive or usage thereof, shall mean furnishing and incorporating in the Work including all necessary labor, materials, equipment, and everything necessary to perform the Work indicated, unless specifically limited in the context used. D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 6 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 6 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 2 – PRELIMINARY MATTERS 2.01 Before Starting Construction Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting the Work. New schedules will be submitted to City when Participating Change Orders or Non- Participating Change Orders occur. 2.02 Preconstruction Conference Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as specified in the Contract Documents. 2.03 Public Meeting Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor attending the Public Meeting as scheduled by the City. ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING 3.01 Reference Standards A. Standards, Specifications, Codes, Laws, and Regulations 1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. 2. No provision or instruction shall be effective to assign to City, or any of its officers, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.02 Amending and Supplementing Contract Documents A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by a Participating Change Order or a Non-Participating Change Order. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work not involving a change in Contract Price or Contract Time, may be authorized, by one or more of the following ways: 1. A Field Order; Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 7 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 7 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or 2. City’s written interpretation or clarification. ARTICLE 4 – BONDS AND INSURANCE 4.01 Licensed Sureties and Insurers All bonds and insurance required by the Contract Documents to be purchased and maintained by Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the State of Texas to issue bonds or insurance policies for the limits and coverage so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided Section 4.04. 4.02 Performance, Payment, and Maintenance Bonds A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as security for the faithful performance and payment of all of Contractor’s obligations under the Contract Documents. B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount equal to the Contract Price as security to protect the City against any defects in any portion of the Work described in the Contract Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final Acceptance by the City. C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney which shall show that it is effective on the date the agent or attorney-in-fact signed each bond. D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in the State of Texas or it ceases to meet the requirements of Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 4.01 and 4.02.C. 4.03 Certificates of Insurance Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee identified in these Standard City Conditions certificates of insurance (and other evidence of insurance requested by City or any other additional insured) which Contractor is required to purchase and maintain. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 8 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 8 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. The certificate of insurance shall document the City, an as “Additional Insured” on all liability policies. 2. The Contractor’s general liability insurance shall include a, “per project” or “per location”, endorsement, which shall be identified in the certificate of insurance provided to the City. 3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured, be complete in its entirety, and show complete insurance carrier names as listed in the current A.M. Best Property & Casualty Guide 4. The insurers for all policies must be licensed and/or approved to do business in the State of Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-: VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength and solvency to the satisfaction of Risk Management. If the rating is below that required, written approval of City is required. 5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of the City. In addition, the Contractor agrees to waive all rights of subrogation against the Engineer (if applicable), and each additional insured identified in these Standard City Conditions. Failure of the City to demand such certificates or other evidence of full compliance with the insurance requirements or failure of the City to identify a deficiency from evidence that is provided shall not be construed as a waiver of Contractor’s obligation to maintain such lines of insurance coverage. 6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess Liability insurance for any differences is required. Excess Liability shall follow form of the primary coverage. 7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with or prior to the date of the effective date of the agreement and the certificate of insurance shall state that the coverage is claims-made and the retroactive date. The insurance coverage shall be maintained for the duration of the Contract and for three (3) years following Final Acceptance provided under the Contract Documents or for the warranty period, whichever is longer. An annual certificate of insurance submitted to the City shall evidence such insurance coverage. 8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the required lines of coverage, nor decrease the limits of said coverage unless such endorsements are approved in writing by the City. In the event a Contract has been bid or executed and the exclusions are determined to be unacceptable or the City desires additional insurance coverage, and the City desires the contractor/engineer to obtain such coverage, the contract price shall be adjusted by the cost of the premium for such additional coverage plus 10%. 9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance coverage shall be approved by the City in regards to asset value and stockholders' equity. In Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 9 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 9 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 lieu of traditional insurance, alternative coverage maintained through insurance pools or risk retention groups, must also be approved by City. 10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a first-dollar basis, must be acceptable to and approved by the City. 11. City, at its sole discretion, reserves the right to review the insurance requirements and to make reasonable adjustments to insurance coverage’s and their limits when deemed necessary and prudent by the City based upon changes in statutory law, court decision or the claims history of the industry as well as of the contracting party to the City. The City shall be required to provide prior notice of 90 days, and the insurance adjustments shall be incorporated into the Work by Change Order. 12. City shall be entitled, upon written request and without expense, to receive copies of policies and endorsements thereto and may make any reasonable requests for deletion or revision or modifications of particular policy terms, conditions, limitations, or exclusions necessary to conform the policy and endorsements to the requirements of the Contract. Deletions, revisions, or modifications shall not be required where policy provisions are established by law or regulations binding upon either party or the underwriter on any such policies. 13. City shall not be responsible for the direct payment of insurance premium costs for Contractor’s insurance. 4.04 Contractor’s Insurance A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’ Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for Employers’ Liability as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor’s performance of the Work and Contractor’s other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers’ compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor’s employees. 3. The limits of liability for the insurance shall provide the following coverages for not less than the following amounts or greater where required by Laws and Regulations a. Statutory limits b. Employer's liability Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 10 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 10 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1) $100,000 each accident/occurrence 2) $100,000 Disease - each employee 3) $500,000 Disease - policy limit B. Commercial General Liability. Coverage shall include but not be limited to covering liability (bodily injury or property damage) arising from: premises/operations, independent contractors, products/completed operations, personal injury, and liability under an insured contract. Insurance shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other insurance or self-insurance programs afforded to the City. The Commercial General Liability policy, shall have no exclusions by endorsements that would alter of nullify premises/operations, products/completed operations, contractual, personal injury, or advertising injury, which are normally contained with the policy, unless the City approves such exclusions in writing. 1. For construction projects that present a substantial completed operation exposure, the City may require the contractor to maintain completed operations coverage for a minimum of no less than three (3) years following the completion of the project 2. Contractor's Liability Insurance under this Section which shall be on a per project basis covering the Contractor with minimum limits of: a. $1,000,000 each occurrence b. $2,000,000 aggregate limit 3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance) making the General Aggregate Limits apply separately to each job site. 4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U” coverage’s. Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance. C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”, defined as autos owned, hired and non-owned and provide indemnity for claims for damages because bodily injury or death of any person and or property damage arising out of the work, maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable. 1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in an amount not less than the following amounts: a. Automobile Liability - a commercial business policy shall provide coverage on "Any Auto", defined as autos owned, hired and non-owned. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 11 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 11 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1) $1,000,000 each accident on a combined single limit basis. Split limits are acceptable if limits are at least: 2) $250,000 Bodily Injury per person 3) $500,000 Bodily Injury per accident / 4) $100,000 Property Damage D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of railroad right-of-way, the Contractor shall comply with the following requirements: 1. The Contractor’s construction activities will require its employees, agents, subcontractors, equipment, and material deliveries to cross railroad properties and tracks owned and operated by: ____________________________________________________________ Write the name of the railroad company. (If none, then write none) 2. The Contractor shall conduct its operations on railroad properties in such a manner as not to interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use or operation of its/their trains or other property. Such operations on railroad properties may require that Contractor to execute a “Right of Entry Agreement” with the particular railroad company or companies involved, and to this end the Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute the right-of-entry (if any) required by a railroad company. The requirements specified herein likewise relate to the Contractor’s use of private and/or construction access roads crossing said railroad company’s properties. 3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide coverage for not less than the following amounts, issued by companies satisfactory to the City and to the Railroad Company for a term that continues for so long as the Contractor’s operations and work cross, occupy, or touch railroad property: a. General Aggregate: _____________________________________ Enter limits provided by Railroad Company (If none, write none) b. Each Occurrence: : _____________________________________ Enter limits provided by Railroad Company (If none, write none) 4. With respect to the above outlined insurance requirements, the following shall govern: a. Where a single railroad company is involved, the Contractor shall provide one insurance policy in the name of the railroad company. However, if more than one grade separation or at-grade crossing is affected by the Project at entirely separate locations on the line or lines of the same railroad company, separate coverage may be required, each in the amount stated above. b. Where more than one railroad company is operating on the same right-of-way or where several railroad companies are involved and operated on their own separate rights-of- NONE NONE NONE Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 12 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 12 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 way, the Contractor may be required to provide separate insurance policies in the name of each railroad company. c. If, in addition to a grade separation or an at-grade crossing, other work or activity is proposed on a railroad company’s right-of-way at a location entirely separate from the grade separation or at-grade crossing, insurance coverage for this work must be included in the policy covering the grade separation. d. If no grade separation is involved but other work is proposed on a railroad company’s right-of-way, all such other work may be covered in a single policy for that railroad, even though the work may be at two or more separate locations. 5. No work or activities on a railroad company’s property to be performed by the Contractor shall be commenced until the Contractor has furnished the City with an original policy or policies of the insurance for each railroad company named, as required above. All such insurance must be approved by the City and each affected Railroad Company prior to the Contractor’s beginning work. 6. The insurance specified above must be carried until all Work to be performed on the railroad right-of-way has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition, insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way. Such insurance must name the railroad company as the insured, together with any tenant or lessee of the railroad company operating over tracks involved in the Project. E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or other loss of insurance coverage. Contractor shall stop work until replacement insurance has been procured. There shall be no time credit for days not worked pursuant to this section. 4.05 Acceptance of Bonds and Insurance; Option to Replace If City has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis of non-conformance with the Contract Documents, the Developer and City shall so notify the Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor shall provide to the City such additional information in respect of insurance provided as the Developer or City may reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required by the Contract Documents, the Developer or City shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES 5.01 Supervision and Superintendent A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 13 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 13 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. B. At all times during the progress of the Work, Contractor shall assign a competent, English- speaking, Superintendent who shall not be replaced without written notice to City. The Superintendent will be Contractor’s representative at the Site and shall have authority to act on behalf of Contractor. All communication given to or received from the Superintendent shall be binding on Contractor. C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction. 5.02 Labor; Working Hours A. Contractor shall provide competent, suitably qualified personnel to perform construction as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during Regular Working Hours. Contractor will not permit the performance of Work beyond Regular Working Hours or for Weekend Working Hours without City’s written consent (which will not be unreasonably withheld). Written request (by letter or electronic communication) to perform Work: 1. for beyond Regular Working Hours request must be made by noon at least two (2) Business Days prior 2. for Weekend Working Hours request must be made by noon of the preceding Thursday 3. for legal holidays request must be made by noon two Business Days prior to the legal holiday. 5.03 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, Contractor required testing, start-up, and completion of the Work. B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 14 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 14 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier, except as otherwise may be provided in the Contract Documents. 5.04 Project Schedule A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01 and the General Requirements as it may be adjusted from time to time as provided below. 1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and the General Requirements) proposed adjustments in the Project Schedule. 2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be submitted in accordance with the requirements of Article 9. Adjustments in Contract Time for projects with City participation shall be made by participating change orders. 5.05 Substitutes and “Or-Equals” A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or “or-equal” item or no substitution is permitted, other items of material or equipment of other Suppliers may be submitted to City for review under the circumstances described below. 1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by City as an “or-equal” item, in which case review and approval of the proposed item may, in City’s sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of material or equipment will be considered functionally equal to an item so named if: a. City determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength, and design characteristics; 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; and 3) it has a proven record of performance and availability of responsive service; and b. Contractor certifies that, if approved and incorporated into the Work: 1) there will be no increase in cost to the City or increase in Contract Time; and Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 15 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 15 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. 2. Substitute Items: a. If in City’s sole discretion an item of material or equipment proposed by Contractor does not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a proposed substitute item. b. Contractor shall submit sufficient information as provided below to allow City to determine if the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by City from anyone other than Contractor. c. Contractor shall make written application to City for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application shall comply with Section 01 25 00 and: 1) shall certify that the proposed substitute item will: i. perform adequately the functions and achieve the results called for by the general design; ii. be similar in substance to that specified; iii. be suited to the same use as that specified; and 2) will state: i. the extent, if any, to which the use of the proposed substitute item will prejudice Contractor’s achievement of final completion on time; ii. whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for other work on the Project) to adapt the design to the proposed substitute item; iii. whether incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty; and 3) will identify: i. all variations of the proposed substitute item from that specified; ii. available engineering, sales, maintenance, repair, and replacement services; and Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 16 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 16 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 4) shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and Damage Claims of other contractors affected by any resulting change. B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by City. Contractor shall submit sufficient information to allow City, in City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. Contractor shall make written application to City for review in the same manner as those provided in Paragraph 5.05.A.2. C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require Contractor to furnish additional data about the proposed substitute. City will be the sole judge of acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review is complete, which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination. D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall indemnify and hold harmless City and anyone directly or indirectly employed by them from and against any and all claims, damages, losses and expenses (including attorneys fees) arising out of the use of substituted materials or equipment. E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City approves a substitute so proposed or submitted by Contractor, Contractor may be required to reimburse City for evaluating each such proposed substitute. Contractor may also be required to reimburse City for the charges for making changes in the Contract Documents. F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or “or-equal” at Contractor’s expense. G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute shall be incorporated to the Contract by Participating Change Order. 5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) A. The Contractor and any subcontractors are required to be prequalified for the work types requiring pre-qualification 5.07 Concerning Subcontractors, Suppliers, and Others A. Minority and Women Owned Business Enterprise Compliance: Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 17 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 17 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Required for this Contract. (Check this box if there is any City Participation) Not Required for this Contract. It is City policy to ensure the full and equitable participation by Minority and Women Business Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent of the City’s MWBE Ordinance (as amended) by the following: 1. Contractor shall, upon request by City, provide complete and accurate information regarding actual work performed by a MWBE on the Contract and payment therefor. 2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without written consent of the City. Any unjustified change or deletion shall be a material breach of Contract and may result in debarment in accordance with the procedures outlined in the Ordinance. 3. Contractor shall, upon request by City, allow an audit and/or examination of any books, records, or files in the possession of the Contractor that will substantiate the actual work performed by an MWBE. Material misrepresentation of any nature will be grounds for termination of the Contract. Any such misrepresentation may be grounds for disqualification of Contractor to bid on future contracts with the City for a period of not less than three years. B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just as Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract Documents: 1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between City and any such Subcontractor, Supplier or other individual or entity; nor 2. shall create any obligation on the part of City to pay or to see to the payment of any moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and Regulations. C. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor. D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any of the Work shall communicate with City through Contractor. E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate agreement between Contractor and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract X Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 18 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 18 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Documents, Contractor shall provide City contract numbers and reference numbers to the Subcontractors and/or Suppliers. 5.08 Wage Rates Required for this Contract. Not Required for this Contract. A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of Chapter 2258, Texas Government Code (as amended), including the payment of not less than the rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in accordance with Chapter 2258. Such prevailing wage rates are included in these Contract Documents. B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage shall, upon demand made by the City, pay to the City $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated in these contract documents. This penalty shall be retained by the City to offset its administrative costs, pursuant to Texas Government Code 2258.023. C. Complaints of Violations and City Determination of Good Cause. On receipt of information, including a complaint by a worker, concerning an alleged violation of 2258.023, Texas Government Code, by a Contractor or Subcontractor, the City shall make an initial determination, before the 31st day after the date the City receives the information, as to whether good cause exists to believe that the violation occurred. The City shall notify in writing the Contractor or Subcontractor and any affected worker of its initial determination. Upon the City’s determination that there is good cause to believe the Contractor or Subcontractor has violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and wages due under the prevailing wage rates, such amounts being subtracted from successive progress payments pending a final determination of the violation. D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker does not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to Paragraph C above. If the persons required to arbitrate under this section do not agree on an arbitrator before the 11th day after the date that arbitration is required, a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the arbitration. The decision and award of the arbitrator is final and binding on all parties and may be enforced in any court of competent jurisdiction. E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3) years following the date of acceptance of the work, maintain records that show (i) the name and X Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 19 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 19 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 occupation of each worker employed by the Contractor in the construction of the Work provided for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right to Audit, shall pertain to this inspection. F. Progress Payments. With each progress payment or payroll period, whichever is less, the Contractor shall submit an affidavit stating that the Contractor has complied with the requirements of Chapter 2258, Texas Government Code. G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at all times. H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its Subcontractors to comply with Paragraphs A through G above. 5.09 Patent Fees and Royalties A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product, or device not specified in the Contract Documents. 5.10 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s compliance with any Laws or Regulations. B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor’s responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor’s obligations under Paragraph 3.01. 5.11 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas: 1. Contractor shall confine construction equipment, the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 20 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 20 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work. 2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is carrying on operations in a portion of a street, right-of-way, or easement greater than is necessary for proper execution of the Work, the City may require the Contractor to finish the section on which operations are in progress before work is commenced on any additional area of the Site. 3. Should any Damage Claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim. 4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against City. B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations. C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice (by letter or electronic communication), and shall be entitled to recover its cost in doing so. The City may withhold Final Acceptance until clean-up is complete and cost are recovered. D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and the Work and make it ready for utilization by City or adjacent property owner. At the completion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition or better all property disturbed by the Work. E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 5.12 Record Documents A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change Orders, Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 21 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 21 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon completion of the Work, these record documents, any operation and maintenance manuals, and Submittals will be delivered to City prior to Final Inspection. Contractor shall include accurate locations for buried and imbedded items. 5.13 Safety and Protection A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Such responsibility does not relieve Subcontractors of their responsibility for the safety of persons or property in the performance of their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the course of construction. B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation, and replacement of their property. C. Contractor shall comply with the applicable requirements of City’s safety programs, if any. D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any, with which City’s employees and representatives must comply while at the Site. E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor. F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and City has accepted the Work. 5.14 Safety Representative Contractor shall inform City in writing of Contractor’s designated safety representative at the Site. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 22 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 22 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.15 Hazard Communication Programs Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers in accordance with Laws or Regulations. 5.16 Submittals A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal will be identified as required by City. 1. Submit number of copies specified in the General Requirements. 2. Data shown on the Submittals will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show City the services, materials, and equipment Contractor proposes to provide and to enable City to review the information for the limited purposes required by Paragraph 5.16.C. 3. Submittals submitted as herein provided by Contractor and reviewed by City for conformance with the design concept shall be executed in conformity with the Contract Documents unless otherwise required by City. 4. When Submittals are submitted for the purpose of showing the installation in greater detail, their review shall not excuse Contractor from requirements shown on the Drawings and Specifications. 5. For-Information-Only submittals upon which the City is not expected to conduct review or take responsive action may be so identified in the Contract Documents. 6. Submit required number of Samples specified in the Specifications. 7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers, the use for which intended and other data as City may require to enable City to review the submittal for the limited purposes required by Paragraph 5.16.C. B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to City’s review and acceptance of the pertinent submittal will be at the sole expense and responsibility of Contractor. C. City’s Review: 1. City will provide timely review of required Submittals in accordance with the Schedule of Submittals acceptable to City. City’s review and acceptance will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 23 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 23 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and acceptance of a separate item as such will not indicate approval of the assembly in which the item functions. 3. City’s review and acceptance shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Section 01 33 00 and City has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for complying with the requirements of the Contract Documents. 5.17 Contractor’s General Warranty and Guarantee A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract Documents and will not be defective. City and its officers, directors, members, partners, employees, agents, consultants, and subcontractors shall be entitled to rely on representation of Contractor’s warranty and guarantee. B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse, modification, or improper maintenance or operation by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or 2. normal wear and tear under normal usage. C. Contractor’s obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor’s obligation to perform the Work in accordance with the Contract Documents: 1. observations by City; 2. recommendation or payment by City or Developer of any progress or final payment; 3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by City; 4. use or occupancy of the Work or any part thereof by City; 5. any review and acceptance of a Submittal by City; 6. any inspection, test, or approval by others; or Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 24 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 24 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 7. any correction of defective Work by City. D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other work or property resulting therefrom which shall appear within a period of two (2) years from the date of Final Acceptance of the Work unless a longer period is specified and shall furnish a good and sufficient maintenance bond, complying with the requirements of Article 4.02.B. The City will give notice of observed defects with reasonable promptness. 5.18 Indemnification A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the City, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licenses or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the City in defending against such claims and causes of actions. B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the City, arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. 5.19 Delegation of Professional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such services are required to carry out Contractor’s responsibilities for construction means, methods, techniques, sequences and procedures. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, City will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, and Submittals prepared by such professional. Submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional’s written approval when submitted to City. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 25 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 25 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided City has specified to Contractor performance and design criteria that such services must satisfy. D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. City’s review and acceptance of Submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 5.16.C. 5.20 Right to Audit: A. The City reserves the right to audit all projects utilizing City funds B. The Contractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of the Contractor involving transactions relating to this Contract. Contractor agrees that the City shall have access during Regular Working Hours to all necessary Contractor facilities and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Contractor reasonable advance notice of intended audits. C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the subcontractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of such Subcontractor, involving transactions to the subcontract, and further, that City shall have access during Regular Working Hours to all Subcontractor facilities, and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Subcontractor reasonable advance notice of intended audits. D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published in the Texas Administrative Code in effect as of the time copying is performed. 5.21 Nondiscrimination A. The City is responsible for operating Public Transportation Programs and implementing transit- related projects, which are funded in part with Federal financial assistance awarded by the U.S. Department of Transportation and the Federal Transit Administration (FTA), without discriminating against any person in the United States on the basis of race, color, or national origin. B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of the Act and the Regulations as further defined in the Supplementary Conditions for any project receiving Federal assistance. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 26 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 26 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 6 – OTHER WORK AT THE SITE 6.01 Related Work at Site A. City may perform other work related to the Project at the Site with City’s employees, or other City contractors, or through other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Contract Documents, then written notice thereof will be given to Contractor prior to starting any such other work; and B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner, and City, if City is performing other work with City’s employees or other City contractors, proper and safe access to the Site, provide a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering such work; provided, however, that Contractor may cut or alter others' work with the written consent of City and the others whose work will be affected. C. If the proper execution or results of any part of Contractor’s Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor’s Work except for latent defects in the work provided by others. ARTICLE 7 – CITY’S RESPONSIBILITIES 7.01 Inspections, Tests, and Approvals City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph 11.03. 7.02 Limitations on City’s Responsibilities A. The City shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. City will not be responsible for Contractor’s failure to perform the Work in accordance with the Contract Documents. B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 27 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 27 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 7.03 Compliance with Safety Program While at the Site, City’s employees and representatives shall comply with the specific applicable requirements of Contractor’s safety programs of which City has been informed pursuant to Paragraph 5.13. ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION 8.01 City’s Project Representative City will provide one or more Project Representative(s) during the construction period. The duties and responsibilities and the limitations of authority of City’s representative during construction are set forth in the Contract Documents. A. City’s Project Representative will make visits to the Site at intervals appropriate to the various stages of construction as City deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor’s executed Work. Based on information obtained during such visits and observations, City’s Project Representative will determine, in general, if the Work is proceeding in accordance with the Contract Documents. City’s Project Representative will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts will be directed toward providing City a greater degree of confidence that the completed Work will conform generally to the Contract Documents. B. City’s Project Representative’s visits and observations are subject to all the limitations on authority and responsibility in the Contract Documents. 8.02 Authorized Variations in Work City’s Project Representative may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on City Developer, and also on Contractor, who shall perform the Work involved promptly. 8.03 Rejecting Defective Work City will have authority to reject Work which City’s Project Representative believes to be defective, or will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. City will have authority to conduct special inspection or testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or completed. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 28 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 28 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 8.04 Determinations for Work Performed Contractor will determine the actual quantities and classifications of Work performed. City’s Project Representative will review with Contractor the preliminary determinations on such matters before rendering a written recommendation. City’s written decision will be final (except as modified to reflect changed factual conditions or more accurate data). ARTICLE 9 – CHANGES IN THE WORK 9.01 Authorized Changes in the Work A. Without invalidating the Contract and without notice to any surety, City may, at any time or from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). Extra Work shall be memorialized by a Participating Change Order which may or may not precede an order of Extra work. B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a project with City participation, a Field Order may be issued by the City. 9.02 Notification to Surety If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any such change. ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME 10.01 Change of Contract Price A. The Contract Price may only be changed by a Participating Change Order for projects with City participation. 10.02 Change of Contract Time A. The Contract Time may only be changed by a Participating Change Order for projects with City participation. 10.03 Delays A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 29 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 29 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 11.01 Notice of Defects Notice of all defective Work of which City has actual knowledge will be given to Contractor. Defective Work may be rejected, corrected, or accepted as provided in this Article 13. 11.02 Access to Work City, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor’s safety procedures and programs so that they may comply therewith as applicable. 11.03 Tests and Inspections A. Contractor shall give City timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full responsibility for arranging and obtaining such independent inspections, tests, retests or approvals, pay all costs in connection therewith, and furnish City the required certificates of inspection or approval; excepting, however, those fees specifically identified in the Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR) inspections, which shall be paid as described in the Supplementary Conditions. C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work. Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by City. D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by City. 1. City will coordinate such Testing to the extent possible, with Contractor; 2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other similar negative result, the Contractor shall be responsible for paying for any and all retests. Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative result and require a retest. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 30 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 30 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the Testing Lab by Contractor. City will forward all invoices for retests to Developer/Contractor. 4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance until the Testing Lab is Paid E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of City, Contractor shall, if requested by City, uncover such Work for observation. 11.04 Uncovering Work A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s expense. 11.05 City May Stop the Work If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of City to stop the Work shall not give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of any of them. 11.06 Correction or Removal of Defective Work A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has been rejected by City, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others). Failure to require the removal of any defective Work shall not constitute acceptance of such Work. B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07, Contractor shall take no action that would void or otherwise impair City’s special warranty and guarantee, if any, on said Work. 11.07 Correction Period A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 31 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 31 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Documents), any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor’s use by City or permitted by Laws and Regulations as contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without cost to City and in accordance with City’s written instructions: 1. repair such defective land or areas; or 2. correct such defective Work; or 3. if the defective Work has been rejected by City, remove it from the Project and replace it with Work that is not defective, and 4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor. C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 11.07, the correction period hereunder with respect to such Work may be required to be extended for an additional period of one year after the end of the initial correction period. City shall provide 30 days written notice to Contractor and Developer should such additional warranty coverage be required. Contractor’s obligations under this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any applicable statute of limitation or repose. 11.08 City May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from City to correct defective Work, or to remove and replace rejected Work as required by City in accordance with Paragraph 11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such deficiency. B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed expeditiously. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto, and incorporate in the Work all materials and equipment incorporated in the Work, stored at the Site or for which City has paid Contractor but which are Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 32 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 32 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants, employees, and City’s other contractors, access to the Site to enable City to exercise the rights and remedies under this Paragraph. C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph 13.09 will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price. D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the performance of the Work attributable to the exercise of City’s rights and remedies under this Paragraph 11.09. ARTICLE 12 – COMPLETION 12.01 Contractor’s Warranty of Title Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment will pass to City no later than the time of Final Acceptance and shall be free and clear of all Liens. 12.02 Partial Utilization A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which City, determines constitutes a separately functioning and usable part of the Work that can be used by City for its intended purpose without significant interference with Contractor’s performance of the remainder of the Work. City at any time may notify Contractor in writing to permit City to use or occupy any such part of the Work which City determines to be ready for its intended use, subject to the following conditions: 1. Contractor at any time may notify City in writing that Contractor considers any such part of the Work ready for its intended use. 2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and Contractor shall make an inspection of that part of the Work to determine its status of completion. If City does not consider that part of the Work to be substantially complete, City will notify Contractor in writing giving the reasons therefor. 3. Partial Utilization will not constitute Final Acceptance by City. 12.03 Final Inspection A. Upon written notice from Contractor that the entire Work is complete in accordance with the Contract Documents: Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 33 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 33 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. within 10 days, City will schedule a Final Inspection with Contractor. 2. City will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. 12.04 Final Acceptance A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction of the following: 1. All documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.03; 2. consent of the surety, if any, to Final Acceptance; 3. a list of all pending or released Damage Claims against City that Contractor believes are unsettled; and 4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to City) of all Lien rights arising out of or Liens filed in connection with the Work. 5. after all Damage Claims have been resolved: a. directly by the Contractor or; b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s insurance provider for resolution. 6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or other requirements of the Contract Documents which specifically continue thereafter. ARTICLE 13 – SUSPENSION OF WORK 13.01 City May Suspend Work A. At any time and without cause, City may suspend the Work or any portion thereof by written notice to Contractor and which may fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. During temporary suspension of the Work covered by these Contract Documents, for any reason, the City will stop contract time on City participation projects. B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the control of and without the fault or negligence of the Contractor, and should it be determined by mutual consent of the Contractor and City that a solution to allow construction to proceed is not Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 34 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 34 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 available within a reasonable period of time, Contractor may request an extension in Contract Time, directly attributable to any such suspension. C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall store all materials in such a manner that they will not obstruct or impede the public unnecessarily nor become damaged in any way, and he shall take every precaution to prevent damage or deterioration of the work performed; he shall provide suitable drainage about the work, and erect temporary structures where necessary. ARTICLE 14 – MISCELLANEOUS 14.01 Giving Notice A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if: 1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended; or 2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. B. Business address changes must be promptly made in writing to the other party. C. Whenever the Contract Documents specifies giving notice by electronic means such electronic notice shall be deemed sufficient upon confirmation of receipt by the receiving party. 14.02 Computation of Times When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day of the period. 14.03 Cumulative Remedies The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. Trinity Basin Preparatory - Bolt CPN 103537 00 73 10- 35 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 35 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 14.04 Survival of Obligations All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor. 14.05 Headings Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. Trinity Basin Preparatory - Bolt CPN 103537 01 11 00 - 1 DAP SUMMARY OF WORK Page 1 of 3 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects CPN 103537 Revised December 20, 2012 SECTION 01 11 00 1 SUMMARY OF WORK 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Summary of Work to be performed in accordance with the Contract Documents 6 B. Deviations from this City of Fort Worth Standard Specification 7 1. None. 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract 10 2. Division 1 - General Requirements 11 1.2 PRICE AND PAYMENT PROCEDURES 12 A. Measurement and Payment 13 1. Work associated with this Item is considered subsidiary to the various items bid. 14 No separate payment will be allowed for this Item. 15 1.3 REFERENCES [NOT USED] 16 1.4 ADMINISTRATIVE REQUIREMENTS 17 A. Work Covered by Contract Documents 18 1. Work is to include furnishing all labor, materials, and equipment, and performing 19 all Work necessary for this construction project as detailed in the Drawings and 20 Specifications. 21 B. Subsidiary Work 22 1. Any and all Work specifically governed by documentary requirements for the 23 project, such as conditions imposed by the Drawings or Contract Documents in 24 which no specific item for bid has been provided for in the Proposal and the item is 25 not a typical unit bid item included on the standard bid item list, then the item shall 26 be considered as a subsidiary item of Work, the cost of which shall be included in 27 the price bid in the Proposal for various bid items. 28 C. Use of Premises 29 1. Coordinate uses of premises under direction of the City. 30 2. Assume full responsibility for protection and safekeeping of materials and 31 equipment stored on the Site. 32 3. Use and occupy only portions of the public streets and alleys, or other public places 33 or other rights-of-way as provided for in the ordinances of the City, as shown in the 34 Contract Documents, or as may be specifically authorized in writing by the City. 35 a. A reasonable amount of tools, materials, and equipment for construction 36 purposes may be stored in such space, but no more than is necessary to avoid 37 delay in the construction operations. 38 01 11 00 - 2 DAP SUMMARY OF WORK Page 2 of 3 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects CPN 103537 Revised December 20, 2012 b. Excavated and waste materials shall be stored in such a way as not to interfere 1 with the use of spaces that may be designated to be left free and unobstructed 2 and so as not to inconvenience occupants of adjacent property. 3 c. If the street is occupied by railroad tracks, the Work shall be carried on in such 4 manner as not to interfere with the operation of the railroad. 5 1) All Work shall be in accordance with railroad requirements set forth in 6 Division 0 as well as the railroad permit. 7 D. Work within Easements 8 1. Do not enter upon private property for any purpose without having previously 9 obtained permission from the owner of such property. 10 2. Do not store equipment or material on private property unless and until the 11 specified approval of the property owner has been secured in writing by the 12 Contractor and a copy furnished to the City. 13 3. Unless specifically provided otherwise, clear all rights-of-way or easements of 14 obstructions which must be removed to make possible proper prosecution of the 15 Work as a part of the project construction operations. 16 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants, 17 lawns, fences, culverts, curbing, and all other types of structures or improvements, 18 to all water, sewer, and gas lines, to all conduits, overhead pole lines, or 19 appurtenances thereof, including the construction of temporary fences and to all 20 other public or private property adjacent to the Work. 21 5. Notify the proper representatives of the owners or occupants of the public or private 22 lands of interest in lands which might be affected by the Work. 23 a. Such notice shall be made at least 48 hours in advance of the beginning of the 24 Work. 25 b. Notices shall be applicable to both public and private utility companies and any 26 corporation, company, individual, or other, either as owners or occupants, 27 whose land or interest in land might be affected by the Work. 28 c. Be responsible for all damage or injury to property of any character resulting 29 from any act, omission, neglect, or misconduct in the manner or method or 30 execution of the Work, or at any time due to defective work, material, or 31 equipment. 32 6. Fence 33 a. Restore all fences encountered and removed during construction of the Project 34 to the original or a better than original condition. 35 b. Erect temporary fencing in place of the fencing removed whenever the Work is 36 not in progress and when the site is vacated overnight, and/or at all times to 37 provide site security. 38 c. The cost for all fence work within easements, including removal, temporary 39 closures and replacement, shall be subsidiary to the various items bid in the 40 project proposal, unless a bid item is specifically provided in the proposal. 41 01 11 00 - 3 DAP SUMMARY OF WORK Page 3 of 3 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects CPN 103537 Revised December 20, 2012 1.5 SUBMITTALS [NOT USED] 1 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.9 QUALITY ASSURANCE [NOT USED] 5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6 1.11 FIELD [SITE] CONDITIONS [NOT USED] 7 1.12 WARRANTY [NOT USED] 8 PART 2 - PRODUCTS [NOT USED] 9 PART 3 - EXECUTION [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 01 25 00 - 1 DAP SUBSTITUTION PROCEDURES Page 1 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 SECTION 01 25 00 SUBSTITUTION PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. The procedure for requesting the approval of substitution of a product that is not equivalent to a product which is specified by descriptive or performance criteria or defined by reference to 1 or more of the following: a. Name of manufacturer b. Name of vendor c. Trade name d. Catalog number 2. Substitutions are not "or-equals". B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Request for Substitution - General 1. Within 30 days after award of Contract (unless noted otherwise), the City will consider formal requests from Contractor for substitution of products in place of those specified. 2. Certain types of equipment and kinds of material are described in Specifications by means of references to names of manufacturers and vendors, trade names, or catalog numbers. a. When this method of specifying is used, it is not intended to exclude from consideration other products bearing other manufacturer's or vendor's names, trade names, or catalog numbers, provided said products are "or-equals," as determined by City. 3. Other types of equipment and kinds of material may be acceptable substitutions under the following conditions: a. Or-equals are unavailable due to strike, discontinued production of products meeting specified requirements, or other factors beyond control of Contractor; or, Trinity Basin Preparatory - Bolt CPN 103537 01 25 00 - 2 DAP SUBSTITUTION PROCEDURES Page 2 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 b. Contractor proposes a cost and/or time reduction incentive to the City. 1.5 SUBMITTALS A. See Request for Substitution Form (attached) B. Procedure for Requesting Substitution 1. Substitution shall be considered only: a. After award of Contract b. Under the conditions stated herein 2. Submit 3 copies of each written request for substitution, including: a. Documentation 1) Complete data substantiating compliance of proposed substitution with Contract Documents 2) Data relating to changes in construction schedule, when a reduction is proposed 3) Data relating to changes in cost b. For products 1) Product identification a) Manufacturer's name b) Telephone number and representative contact name c) Specification Section or Drawing reference of originally specified product, including discrete name or tag number assigned to original product in the Contract Documents 2) Manufacturer's literature clearly marked to show compliance of proposed product with Contract Documents 3) Itemized comparison of original and proposed product addressing product characteristics including, but not necessarily limited to: a) Size b) Composition or materials of construction c) Weight d) Electrical or mechanical requirements 4) Product experience a) Location of past projects utilizing product b) Name and telephone number of persons associated with referenced projects knowledgeable concerning proposed product c) Available field data and reports associated with proposed product 5) Samples a) Provide at request of City. b) Samples become the property of the City. c. For construction methods: 1) Detailed description of proposed method 2) Illustration drawings C. Approval or Rejection 1. Written approval or rejection of substitution given by the City 2. City reserves the right to require proposed product to comply with color and pattern of specified product if necessary to secure design intent. 3. In the event the substitution is approved, if a reduction in cost or time results, it will be documented by Change Order. Trinity Basin Preparatory - Bolt CPN 103537 01 25 00 - 3 DAP SUBSTITUTION PROCEDURES Page 3 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 4. Substitution will be rejected if: a. Submittal is not through the Contractor with his stamp of approval b. Request is not made in accordance with this Specification Section c. In the Developer’s opinion, acceptance will require substantial revision of the original design d. In the City’s or Developer’s opinion, substitution will not perform adequately the function consistent with the design intent 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. In making request for substitution or in using an approved product, the Contractor represents that the Contractor: 1. Has investigated proposed product, and has determined that it is adequate or superior in all respects to that specified, and that it will perform function for which it is intended 2. Will provide same guarantee for substitute item as for product specified 3. Will coordinate installation of accepted substitution into Work, to include building modifications if necessary, making such changes as may be required for Work to be complete in all respects 4. Waives all claims for additional costs related to substitution which subsequently arise 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE Trinity Basin Preparatory - Bolt CPN 103537 01 25 00 - 4 DAP SUBSTITUTION PROCEDURES Page 4 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 EXHIBIT A REQUEST FOR SUBSTITUTION FORM: TO: PROJECT: DATE: We hereby submit for your consideration the following product instead of the specified item for the above project: SECTION PARAGRAPH SPECIFIED ITEM Proposed Substitution: Reason for Substitution: Include complete information on changes to Drawings and/or Specifications which proposed substitution will require for its proper installation. Fill in Blanks Below: A. Will the undersigned contractor pay for changes to the building design, including engineering and detailing costs caused by the requested substitution? B. What effect does substitution have on other trades? C. Differences between proposed substitution and specified item? D. Differences in product cost or product delivery time? E. Manufacturer's guarantees of the proposed and specified items are: Equal Better (explain on attachment) The undersigned states that the function, appearance and quality are equivalent or superior to the specified item. Submitted By: For Use by City Signature Recommended Recommended as noted Firm Not recommended Received late Address By Date Date Remarks Telephone For Use by City: Approved Rejected City Date Trinity Basin Preparatory - Bolt CPN 103537 01 31 19 - 1 DAP PRECONSTRUCTION MEETING Page 1 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 SECTION 01 31 19 PRECONSTRUCTION MEETING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provisions for the preconstruction meeting to be held prior to the start of Work to clarify construction contract administration procedures B. Deviations from this City of Fort Worth Standard Specification 1. No construction schedule required unless requested by the City. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Attend preconstruction meeting. 2. Representatives of Contractor, subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents. 3. Meeting administered by City may be tape recorded. a. If recorded, tapes will be used to prepare minutes and retained by City for future reference. B. Preconstruction Meeting 1. A preconstruction meeting will be held within 14 days after the delivery of the distribution package to the City. a. The meeting will be scheduled and administered by the City. 2. The Project Representative will preside at the meeting, prepare the notes of the meeting and distribute copies of same to all participants who so request by fully completing the attendance form to be circulated at the beginning of the meeting. 3. Attendance shall include: a. Developer and Consultant b. Contractor's project manager c. Contractor's superintendent d. Any subcontractor or supplier representatives whom the Contractor may desire to invite or the City may request Trinity Basin Preparatory - Bolt CPN 103537 01 31 19 - 2 DAP PRECONSTRUCTION MEETING Page 2 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 e. Other City representatives f. Others as appropriate 4. Preliminary Agenda may include: a. Introduction of Project Personnel b. General Description of Project c. Status of right-of-way, utility clearances, easements or other pertinent permits d. Contractor’s work plan and schedule e. Contract Time f. Notice to Proceed g. Construction Staking h. Progress Payments i. Extra Work and Change Order Procedures j. Field Orders k. Disposal Site Letter for Waste Material l. Insurance Renewals m. Payroll Certification n. Material Certifications and Quality Control Testing o. Public Safety and Convenience p. Documentation of Pre-Construction Conditions q. Weekend Work Notification r. Legal Holidays s. Trench Safety Plans t. Confined Space Entry Standards u. Coordination with the City’s representative for operations of existing water systems v. Storm Water Pollution Prevention Plan w. Coordination with other Contractors x. Early Warning System y. Contractor Evaluation z. Special Conditions applicable to the project aa. Damages Claims bb. Submittal Procedures cc. Substitution Procedures dd. Correspondence Routing ee. Record Drawings ff. Temporary construction facilities gg. MBE/SBE procedures hh. Final Acceptance ii. Final Payment jj. Questions or Comments Trinity Basin Preparatory - Bolt CPN 103537 01 31 19 - 3 DAP PRECONSTRUCTION MEETING Page 3 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE Trinity Basin Preparatory - Bolt CPN 103537 01 31 20 - 1 DAP PROJECT MEETINGS Page 1 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 SECTION 01 31 20 PROJECT MEETINGS [Specifier: This Specification is intended for use on projects designated as Tier 3 or Tier 4.] PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provisions for project meetings throughout the construction period to enable orderly review of the progress of the Work and to provide for systematic discussion of potential problems B. Deviations this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Schedule, attend and administer as specified, periodic progress meetings, and specially called meetings throughout progress of the Work. 2. Representatives of Contractor, subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents. 3. Meetings administered by City may be tape recorded. a. If recorded, tapes will be used to prepare minutes and retained by City for future reference. 4. Meetings, in addition to those specified in this Section, may be held when requested by the City, Engineer or Contractor. B. Pre-Construction Neighborhood Meeting 1. After the execution of the Agreement, but before construction is allowed to begin, attend 1 Public Meeting with affected residents to: a. Present projected schedule, including construction start date b. Answer any construction related questions 2. Meeting Location a. Location of meeting to be determined by the City. 3. Attendees Trinity Basin Preparatory - Bolt CPN 103537 01 31 20 - 2 DAP PROJECT MEETINGS Page 2 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 a. Contractor b. Project Representative c. Other City representatives 4. Meeting Schedule a. In general, the neighborhood meeting will occur within the 2 weeks following the pre-construction conference. b. In no case will construction be allowed to begin until this meeting is held. C. Progress Meetings 1. Formal project coordination meetings will be held periodically. Meetings will be scheduled and administered by Project Representative. 2. Additional progress meetings to discuss specific topics will be conducted on an as- needed basis. Such additional meetings shall include, but not be limited to: a. Coordinating shutdowns b. Installation of piping and equipment c. Coordination between other construction projects d. Resolution of construction issues e. Equipment approval 3. The Project Representative will preside at progress meetings, prepare the notes of the meeting and distribute copies of the same to all participants who so request by fully completing the attendance form to be circulated at the beginning of each meeting. 4. Attendance shall include: a. Contractor's project manager b. Contractor's superintendent c. Any subcontractor or supplier representatives whom the Contractor may desire to invite or the City may request d. Engineer's representatives e. City’s representatives f. Others, as requested by the Project Representative 5. Preliminary Agenda may include: a. Review of Work progress since previous meeting b. Field observations, problems, conflicts c. Items which impede construction schedule d. Review of off-site fabrication, delivery schedules e. Review of construction interfacing and sequencing requirements with other construction contracts f. Corrective measures and procedures to regain projected schedule g. Revisions to construction schedule h. Progress, schedule, during succeeding Work period i. Coordination of schedules j. Review submittal schedules k. Maintenance of quality standards l. Pending changes and substitutions m. Review proposed changes for: 1) Effect on construction schedule and on completion date 2) Effect on other contracts of the Project n. Review Record Documents o. Review monthly pay request Trinity Basin Preparatory - Bolt CPN 103537 01 31 20 - 3 DAP PROJECT MEETINGS Page 3 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 p. Review status of Requests for Information 6. Meeting Schedule a. Progress meetings will be held periodically as determined by the Project Representative. 1) Additional meetings may be held at the request of the: a) City b) Engineer c) Contractor 7. Meeting Location a. The City will establish a meeting location. 1) To the extent practicable, meetings will be held at the Site. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE Trinity Basin Preparatory - Bolt CPN 103537 01 32 16 - 1 DAP CONSTRUCTION PROGRESS SCHEDULE Page 1 of 5 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 SECTION 01 32 16 CONSTRUCTION PROGRESS SCHEDULE PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. General requirements for the preparation, submittal, updating, status reporting and management of the Construction Progress Schedule 2. Specific requirements are presented in the City of Fort Worth Schedule Guidance Document B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES A. Definitions 1. Schedule Tiers a. Tier 1 - No schedule submittal required by contract. Small, brief duration projects b. Tier 2 - No schedule submittal required by contract, but will require some milestone dates. Small, brief duration projects c. Tier 3 - Schedule submittal required by contract as described in the Specification and herein. Majority of City projects, including all bond program projects d. Tier 4 - Schedule submittal required by contract as described in the Specification and herein. Large and/or complex projects with long durations 1) Examples: large water pump station project and associated pipeline with interconnection to another governmental entity e. Tier 5 - Schedule submittal required by contract as described in the Specification and herein. Large and/or very complex projects with long durations, high public visibility 1) Examples might include a water or wastewater treatment plant 2. Baseline Schedule - Initial schedule submitted before work begins that will serve as the baseline for measuring progress and departures from the schedule. 3. Progress Schedule - Monthly submittal of a progress schedule documenting progress on the project and any changes anticipated. Trinity Basin Preparatory - Bolt CPN 103537 01 32 16 - 2 DAP CONSTRUCTION PROGRESS SCHEDULE Page 2 of 5 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 4. Schedule Narrative - Concise narrative of the schedule including schedule changes, expected delays, key schedule issues, critical path items, etc B. Reference Standards 1. City of Fort Worth Schedule Guidance Document 1.4 ADMINISTRATIVE REQUIREMENTS A. Baseline Schedule 1. General a. Prepare a cost-loaded baseline Schedule using approved software and the Critical Path Method (CPM) as required in the City of Fort Worth Schedule Guidance Document. b. Review the draft cost-loaded baseline Schedule with the City to demonstrate understanding of the work to be performed and known issues and constraints related to the schedule. c. Designate an authorized representative (Project Scheduler) responsible for developing and updating the schedule and preparing reports. B. Progress Schedule 1. Update the progress Schedule monthly as required in the City of Fort Worth Schedule Guidance Document. 2. Prepare the Schedule Narrative to accompany the monthly progress Schedule. 3. Change Orders a. Incorporate approved change orders, resulting in a change of contract time, in the baseline Schedule in accordance with City of Fort Worth Schedule Guidance Document. C. Responsibility for Schedule Compliance 1. Whenever it becomes apparent from the current progress Schedule and CPM Status Report that delays to the critical path have resulted and the Contract completion date will not be met, or when so directed by the City, make some or all of the following actions at no additional cost to the City a. Submit a Recovery Plan to the City for approval revised baseline Schedule outlining: 1) A written statement of the steps intended to take to remove or arrest the delay to the critical path in the approved schedule 2) Increase construction manpower in such quantities and crafts as will substantially eliminate the backlog of work and return current Schedule to meet projected baseline completion dates 3) Increase the number of working hours per shift, shifts per day, working days per week, the amount of construction equipment, or any combination of the foregoing, sufficiently to substantially eliminate the backlog of work 4) Reschedule activities to achieve maximum practical concurrency of accomplishment of activities, and comply with the revised schedule 2. If no written statement of the steps intended to take is submitted when so requested by the City, the City may direct the Contractor to increase the level of effort in manpower (trades), equipment and work schedule (overtime, weekend and holiday work, etc.) to be employed by the Contractor in order to remove or arrest the delay to the critical path in the approved schedule. a. No additional cost for such work will be considered. Trinity Basin Preparatory - Bolt CPN 103537 01 32 16 - 3 DAP CONSTRUCTION PROGRESS SCHEDULE Page 3 of 5 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 D. The Contract completion time will be adjusted only for causes specified in this Contract. a. Requests for an extension of any Contract completion date must be supplemented with the following: 1) Furnish justification and supporting evidence as the City may deem necessary to determine whether the requested extension of time is entitled under the provisions of this Contract. a) The City will, after receipt of such justification and supporting evidence, make findings of fact and will advise the Contractor, in writing thereof. 2) If the City finds that the requested extension of time is entitled, the City's determination as to the total number of days allowed for the extensions shall be based upon the approved total baseline schedule and on all data relevant to the extension. a) Such data shall be included in the next updating of the Progress schedule. b) Actual delays in activities which, according to the Baseline schedule, do not affect any Contract completion date shown by the critical path in the network will not be the basis for a change therein. 2. Submit each request for change in Contract completion date to the City within 30 days after the beginning of the delay for which a time extension is requested but before the date of final payment under this Contract. a. No time extension will be granted for requests which are not submitted within the foregoing time limit. b. From time to time, it may be necessary for the Contract schedule or completion time to be adjusted by the City to reflect the effects of job conditions, weather, technical difficulties, strikes, unavoidable delays on the part of the City or its representatives, and other unforeseeable conditions which may indicate schedule adjustments or completion time extensions. 1) Under such conditions, the City will direct the Contractor to reschedule the work or Contract completion time to reflect the changed conditions and the Contractor shall revise his schedule accordingly. a) No additional compensation will be made to the Contractor for such schedule changes except for unavoidable overall contract time extensions beyond the actual completion of unaffected work, in which case the Contractor shall take all possible action to minimize any time extension and any additional cost to the City. b) Available float time in the Baseline schedule may be used by the City as well as by the Contractor. 3. Float or slack time is defined as the amount of time between the earliest start date and the latest start date or between the earliest finish date and the latest finish date of a chain of activities on the Baseline Schedule. a. Float or slack time is not for the exclusive use or benefit of either the Contractor or the City. b. Proceed with work according to early start dates, and the City shall have the right to reserve and apportion float time according to the needs of the project. Trinity Basin Preparatory - Bolt CPN 103537 01 32 16 - 4 DAP CONSTRUCTION PROGRESS SCHEDULE Page 4 of 5 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 c. Acknowledge and agree that actual delays, affecting paths of activities containing float time, will not have any effect upon contract completion times, providing that the actual delay does not exceed the float time associated with those activities. E. Coordinating Schedule with Other Contract Schedules 1. Where work is to be performed under this Contract concurrently with or contingent upon work performed on the same facilities or area under other contracts, the Baseline Schedule shall be coordinated with the schedules of the other contracts. a. Obtain the schedules of the other appropriate contracts from the City for the preparation and updating of Baseline schedule and make the required changes in his schedule when indicated by changes in corresponding schedules. 2. In case of interference between the operations of different contractors, the City will determine the work priority of each contractor and the sequence of work necessary to expedite the completion of the entire Project. a. In such cases, the decision of the City shall be accepted as final. b. The temporary delay of any work due to such circumstances shall not be considered as justification for claims for additional compensation. 1.5 SUBMITTALS A. Baseline Schedule 1. Submit Schedule in native file format and pdf format as required in the City of Fort Worth Schedule Guidance Document. a. Native file format includes: 1) Primavera (P6 or Primavera Contractor) 2. Submit draft baseline Schedule to City prior to the pre-construction meeting and bring in hard copy to the meeting for review and discussion. B. Progress Schedule 1. Submit progress Schedule in native file format and pdf format as required in the City of Fort Worth Schedule Guidance Document. 2. Submit progress Schedule monthly no later than the last day of the month. C. Schedule Narrative 1. Submit the schedule narrative in pdf format as required in the City of Fort Worth Schedule Guidance Document. 2. Submit schedule narrative monthly no later than the last day of the month. D. Submittal Process 1. The City administers and manages schedules through Buzzsaw. 2. Contractor shall submit documents as required in the City of Fort Worth Schedule Guidance Document. 3. Once the project has been completed and Final Acceptance has been issued by the City, no further progress schedules are required. Trinity Basin Preparatory - Bolt CPN 103537 01 32 16 - 5 DAP CONSTRUCTION PROGRESS SCHEDULE Page 5 of 5 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. The person preparing and revising the construction Progress Schedule shall be experienced in the preparation of schedules of similar complexity. B. Schedule and supporting documents addressed in this Specification shall be prepared, updated and revised to accurately reflect the performance of the construction. C. Contractor is responsible for the quality of all submittals in this section meeting the standard of care for the construction industry for similar projects. 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE Trinity Basin Preparatory - Bolt CPN 103537 01 32 33 - 1 DAP PRECONSTRUCTION VIDEO Page 1 of 2 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 SECTION 01 32 33 PRECONSTRUCTION VIDEO PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Administrative and procedural requirements for: a. Preconstruction Videos B. Deviations from this City of Fort Worth Standard Specification 1. Though not mandatory, it is highly recommended on infill developer projects. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Preconstruction Video 1. Produce a preconstruction video of the site/alignment, including all areas in the vicinity of and to be affected by construction. a. Provide digital copy of video upon request by the City. 2. Retain a copy of the preconstruction video until the end of the maintenance surety period. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] Trinity Basin Preparatory - Bolt CPN 103537 01 32 33 - 2 DAP PRECONSTRUCTION VIDEO Page 2 of 2 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE Trinity Basin Preparatory - Bolt CPN 103537 01 33 00 - 1 DAP SUBMITTALS Page 1 of 8 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 SECTION 01 33 00 DAP SUBMITTALS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. General methods and requirements of submissions applicable to the following Work-related submittals: a. Shop Drawings b. Product Data (including Standard Product List submittals) c. Samples d. Mock Ups B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Notify the City in writing, at the time of submittal, of any deviations in the submittals from the requirements of the Contract Documents. 2. Coordination of Submittal Times a. Prepare, prioritize and transmit each submittal sufficiently in advance of performing the related Work or other applicable activities, or within the time specified in the individual Work Sections, of the Specifications. b. Contractor is responsible such that the installation will not be delayed by processing times including, but not limited to: a) Disapproval and resubmittal (if required) b) Coordination with other submittals c) Testing d) Purchasing e) Fabrication f) Delivery g) Similar sequenced activities c. No extension of time will be authorized because of the Contractor's failure to transmit submittals sufficiently in advance of the Work. Trinity Basin Preparatory - Bolt CPN 103537 01 33 00 - 2 DAP SUBMITTALS Page 2 of 8 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 d. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor. B. Submittal Numbering 1. When submitting shop drawings or samples, utilize a 9-character submittal cross- reference identification numbering system in the following manner: a. Use the first 6 digits of the applicable Specification Section Number. b. For the next 2 digits number use numbers 01-99 to sequentially number each initial separate item or drawing submitted under each specific Section number. c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e. A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical submittal number would be as follows: 03 30 00-08-B 1) 03 30 00 is the Specification Section for Concrete 2) 08 is the eighth initial submittal under this Specification Section 3) B is the third submission (second resubmission) of that particular shop drawing C. Contractor Certification 1. Review shop drawings, product data and samples, including those by subcontractors, prior to submission to determine and verify the following: a. Field measurements b. Field construction criteria c. Catalog numbers and similar data d. Conformance with the Contract Documents 2. Provide each shop drawing, sample and product data submitted by the Contractor with a Certification Statement affixed including: a. The Contractor's Company name b. Signature of submittal reviewer c. Certification Statement 1) “By this submittal, I hereby represent that I have determined and verified field measurements, field construction criteria, materials, dimensions, catalog numbers and similar data and I have checked and coordinated each item with other applicable approved shop drawings." D. Submittal Format 1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches. 2. Bind shop drawings and product data sheets together. 3. Order a. Cover Sheet 1) Description of Packet 2) Contractor Certification b. List of items / Table of Contents c. Product Data /Shop Drawings/Samples /Calculations E. Submittal Content 1. The date of submission and the dates of any previous submissions Trinity Basin Preparatory - Bolt CPN 103537 01 33 00 - 3 DAP SUBMITTALS Page 3 of 8 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 2. The Project title and number 3. Contractor identification 4. The names of: a. Contractor b. Supplier c. Manufacturer 5. Identification of the product, with the Specification Section number, page and paragraph(s) 6. Field dimensions, clearly identified as such 7. Relation to adjacent or critical features of the Work or materials 8. Applicable standards, such as ASTM or Federal Specification numbers 9. Identification by highlighting of deviations from Contract Documents 10. Identification by highlighting of revisions on resubmittals 11. An 8-inch x 3-inch blank space for Contractor and City stamps F. Shop Drawings 1. As specified in individual Work Sections includes, but is not necessarily limited to: a. Custom-prepared data such as fabrication and erection/installation (working) drawings b. Scheduled information c. Setting diagrams d. Actual shopwork manufacturing instructions e. Custom templates f. Special wiring diagrams g. Coordination drawings h. Individual system or equipment inspection and test reports including: 1) Performance curves and certifications i. As applicable to the Work 2. Details a. Relation of the various parts to the main members and lines of the structure b. Where correct fabrication of the Work depends upon field measurements 1) Provide such measurements and note on the drawings prior to submitting for approval. G. Product Data 1. For submittals of product data for products included on the City’s Standard Product List, clearly identify each item selected for use on the Project. 2. For submittals of product data for products not included on the City’s Standard Product List, submittal data may include, but is not necessarily limited to: a. Standard prepared data for manufactured products (sometimes referred to as catalog data) 1) Such as the manufacturer's product specification and installation instructions 2) Availability of colors and patterns 3) Manufacturer's printed statements of compliances and applicability 4) Roughing-in diagrams and templates 5) Catalog cuts 6) Product photographs Trinity Basin Preparatory - Bolt CPN 103537 01 33 00 - 4 DAP SUBMITTALS Page 4 of 8 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 7) Standard wiring diagrams 8) Printed performance curves and operational-range diagrams 9) Production or quality control inspection and test reports and certifications 10) Mill reports 11) Product operating and maintenance instructions and recommended spare-parts listing and printed product warranties 12) As applicable to the Work H. Samples 1. As specified in individual Sections, include, but are not necessarily limited to: a. Physical examples of the Work such as: 1) Sections of manufactured or fabricated Work 2) Small cuts or containers of materials 3) Complete units of repetitively used products color/texture/pattern swatches and range sets 4) Specimens for coordination of visual effect 5) Graphic symbols and units of Work to be used by the City for independent inspection and testing, as applicable to the Work I. Do not start Work requiring a shop drawing, sample or product data nor any material to be fabricated or installed prior to the approval or qualified approval of such item. 1. Fabrication performed, materials purchased or on-site construction accomplished which does not conform to approved shop drawings and data is at the Contractor's risk. 2. The City will not be liable for any expense or delay due to corrections or remedies required to accomplish conformity. 3. Complete project Work, materials, fabrication, and installations in conformance with approved shop drawings, applicable samples, and product data. J. Submittal Distribution 1. Electronic Distribution a. Confirm development of Project directory for electronic submittals to be uploaded to City’s Buzzsaw site, or another external FTP site approved by the City. b. Shop Drawings 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals b) If Contractor requires more than 1 hard copy of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. c. Product Data 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals d. Samples 1) Distributed to the Project Representative 2. Hard Copy Distribution (if required in lieu of electronic distribution) Trinity Basin Preparatory - Bolt CPN 103537 01 33 00 - 5 DAP SUBMITTALS Page 5 of 8 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 a. Shop Drawings 1) Distributed to the City 2) Copies a) 8 copies for mechanical submittals b) 7 copies for all other submittals c) If Contractor requires more than 3 copies of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. b. Product Data 1) Distributed to the City 2) Copies a) 4 copies c. Samples 1) Distributed to the Project Representative 2) Copies a) Submit the number stated in the respective Specification Sections. 3. Distribute reproductions of approved shop drawings and copies of approved product data and samples, where required, to the job site file and elsewhere as directed by the City. a. Provide number of copies as directed by the City but not exceeding the number previously specified. K. Submittal Review 1. The review of shop drawings, data and samples will be for general conformance with the design concept and Contract Documents. This is not to be construed as: a. Permitting any departure from the Contract requirements b. Relieving the Contractor of responsibility for any errors, including details, dimensions, and materials c. Approving departures from details furnished by the City, except as otherwise provided herein 2. The review and approval of shop drawings, samples or product data by the City does not relieve the Contractor from his/her responsibility with regard to the fulfillment of the terms of the Contract. a. All risks of error and omission are assumed by the Contractor, and the City will have no responsibility therefore. 3. The Contractor remains responsible for details and accuracy, for coordinating the Work with all other associated work and trades, for selecting fabrication processes, for techniques of assembly and for performing Work in a safe manner. 4. If the shop drawings, data or samples as submitted describe variations and show a departure from the Contract requirements which City finds to be in the interest of the City and to be so minor as not to involve a change in Contract Price or time for performance, the City may return the reviewed drawings without noting an exception. 5. Submittals will be returned to the Contractor under 1 of the following codes: a. Code 1 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or comments on the submittal. a) When returned under this code the Contractor may release the equipment and/or material for manufacture. b. Code 2 Trinity Basin Preparatory - Bolt CPN 103537 01 33 00 - 6 DAP SUBMITTALS Page 6 of 8 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of the notations and comments IS NOT required by the Contractor. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. c. Code 3 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is assigned when notations and comments are extensive enough to require a resubmittal of the package. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. b) This resubmittal is to address all comments, omissions and non-conforming items that were noted. c) Resubmittal is to be received by the City within 15 Calendar Days of the date of the City's transmittal requiring the resubmittal. d. Code 4 1) "NOT APPROVED" is assigned when the submittal does not meet the intent of the Contract Documents. a) The Contractor must resubmit the entire package revised to bring the submittal into conformance. b) It may be necessary to resubmit using a different manufacturer/vendor to meet the Contract Documents. 6. Resubmittals a. Handled in the same manner as first submittals 1) Corrections other than requested by the City 2) Marked with revision triangle or other similar method a) At Contractor’s risk if not marked b. Submittals for each item will be reviewed no more than twice at the City’s expense. 1) All subsequent reviews will be performed at times convenient to the City and at the Contractor's expense, based on the City's or City Representative’s then prevailing rates. 2) Provide Contractor reimbursement to the City within 30 Calendar Days for all such fees invoiced by the City. c. The need for more than 1 resubmission or any other delay in obtaining City's review of submittals, will not entitle the Contractor to an extension of Contract Time. 7. Partial Submittals a. City reserves the right to not review submittals deemed partial, at the City’s discretion. b. Submittals deemed by the City to be not complete will be returned to the Contractor, and will be considered "Not Approved" until resubmitted. c. The City may at its option provide a list or mark the submittal directing the Contractor to the areas that are incomplete. 8. If the Contractor considers any correction indicated on the shop drawings to constitute a change to the Contract Documents, then written notice must be provided thereof to the Developer at least 7 Calendar Days prior to release for manufacture. Trinity Basin Preparatory - Bolt CPN 103537 01 33 00 - 7 DAP SUBMITTALS Page 7 of 8 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 9. When the shop drawings have been completed to the satisfaction of the City, the Contractor may carry out the construction in accordance therewith and no further changes therein except upon written instructions from the City. 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days following receipt of submittal by the City. L. Mock ups 1. Mock Up units as specified in individual Sections, include, but are not necessarily limited to, complete units of the standard of acceptance for that type of Work to be used on the Project. Remove at the completion of the Work or when directed. M. Qualifications 1. If specifically required in other Sections of these Specifications, submit a P.E. Certification for each item required. N. Request for Information (RFI) 1. Contractor Request for additional information a. Clarification or interpretation of the contract documents b. When the Contractor believes there is a conflict between Contract Documents c. When the Contractor believes there is a conflict between the Drawings and Specifications 1) Identify the conflict and request clarification 2. Sufficient information shall be attached to permit a written response without further information. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] Trinity Basin Preparatory - Bolt CPN 103537 01 33 00 - 8 DAP SUBMITTALS Page 8 of 8 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised August 30, 2013 PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days Trinity Basin Preparatory - Bolt CPN 103537 01 45 23 DAP TESTING AND INSPECTION SERVICES Page 1 of 2 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised March 20, 2020 SECTION 01 45 23 TESTING AND INSPECTION SERVICES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Testing and inspection services procedures and coordination B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. a. Contractor is responsible for performing, coordinating, and payment of all Quality Control testing. b. City is responsible for performing and payment for first set of Quality Assurance testing. 1) If the first Quality Assurance test performed by the City fails, the Contractor is responsible for payment of subsequent Quality Assurance testing until a passing test occurs. a) Final acceptance will not be issued by City until all required payments for testing by Contractor have been paid in full. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Testing 1. Complete testing in accordance with the Contract Documents. 2. Coordination a. When testing is required to be performed by the City, notify City, sufficiently in advance, when testing is needed. b. When testing is required to be completed by the Contractor, notify City, sufficiently in advance, that testing will be performed. 3. Distribution of Testing Reports a. Electronic Distribution 1) Confirm development of Project directory for electronic submittals to be uploaded to the City’s document management system, or another form of distribution approved by the City. Trinity Basin Preparatory - Bolt CPN 103537 01 45 23 DAP TESTING AND INSPECTION SERVICES Page 2 of 2 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised March 20, 2020 2) Upload test reports to designated project directory and notify appropriate City representatives via email of submittal posting. 3) Hard Copies a) 1 copy for all submittals submitted to the Project Representative b. Hard Copy Distribution (if required in lieu of electronic distribution) 1) Tests performed by City a) Distribute 1 hard copy to the Contractor 2) Tests performed by the Contractor a) Distribute 3 hard copies to City’s Project Representative 4. Provide City’s Project Representative with trip tickets for each delivered load of Concrete or Lime material including the following information: a. Name of pit b. Date of delivery c. Material delivered B. Inspection 1. Inspection or lack of inspection does not relieve the Contractor from obligation to perform work in accordance with the Contract Documents. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that electronic submittals be uploaded through the City’s document management system. Trinity Basin Preparatory - Bolt CPN 103537 01 50 00 - 1 DAP TEMPORARY FACILITIES AND CONTROLS Page 1 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised JULY 1, 2011 SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provide temporary facilities and controls needed for the Work including, but not necessarily limited to: a. Temporary utilities b. Sanitary facilities c. Storage Sheds and Buildings d. Dust control e. Temporary fencing of the construction site B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Temporary Utilities 1. Obtaining Temporary Service a. Make arrangements with utility service companies for temporary services. b. Abide by rules and regulations of utility service companies or authorities having jurisdiction. c. Be responsible for utility service costs until Work is approved for Final Acceptance. 1) Included are fuel, power, light, heat and other utility services necessary for execution, completion, testing and initial operation of Work. 2. Water a. Contractor to provide water required for and in connection with Work to be performed and for specified tests of piping, equipment, devices or other use as required for the completion of the Work. b. Provide and maintain adequate supply of potable water for domestic consumption by Contractor personnel and City’s Project Representatives. c. Coordination 1) Contact City 1 week before water for construction is desired Trinity Basin Preparatory - Bolt CPN 103537 01 50 00 - 2 DAP TEMPORARY FACILITIES AND CONTROLS Page 2 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised JULY 1, 2011 d. Contractor Payment for Construction Water 1) Obtain construction water meter from City for payment as billed by City’s established rates. 3. Electricity and Lighting a. Provide and pay for electric powered service as required for Work, including testing of Work. 1) Provide power for lighting, operation of equipment, or other use. b. Electric power service includes temporary power service or generator to maintain operations during scheduled shutdown. 4. Telephone a. Provide emergency telephone service at Site for use by Contractor personnel and others performing work or furnishing services at Site. 5. Temporary Heat and Ventilation a. Provide temporary heat as necessary for protection or completion of Work. b. Provide temporary heat and ventilation to assure safe working conditions. B. Sanitary Facilities 1. Provide and maintain sanitary facilities for persons on Site. a. Comply with regulations of State and local departments of health. 2. Enforce use of sanitary facilities by construction personnel at job site. a. Enclose and anchor sanitary facilities. b. No discharge will be allowed from these facilities. c. Collect and store sewage and waste so as not to cause nuisance or health problem. d. Haul sewage and waste off-site at no less than weekly intervals and properly dispose in accordance with applicable regulation. 3. Locate facilities near Work Site and keep clean and maintained throughout Project. 4. Remove facilities at completion of Project C. Storage Sheds and Buildings 1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor above ground level for materials and equipment susceptible to weather damage. 2. Storage of materials not susceptible to weather damage may be on blocks off ground. 3. Store materials in a neat and orderly manner. a. Place materials and equipment to permit easy access for identification, inspection and inventory. 4. Equip building with lockable doors and lighting, and provide electrical service for equipment space heaters and heating or ventilation as necessary to provide storage environments acceptable to specified manufacturers. 5. Fill and grade site for temporary structures to provide drainage away from temporary and existing buildings. 6. Remove building from site prior to Final Acceptance. D. Temporary Fencing 1. Provide and maintain for the duration or construction when required in contract documents E. Dust Control Trinity Basin Preparatory - Bolt CPN 103537 01 50 00 - 3 DAP TEMPORARY FACILITIES AND CONTROLS Page 3 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised JULY 1, 2011 1. Contractor is responsible for maintaining dust control through the duration of the project. a. Contractor remains on-call at all times b. Must respond in a timely manner F. Temporary Protection of Construction 1. Contractor or subcontractors are responsible for protecting Work from damage due to weather. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 INSTALLATION A. Temporary Facilities 1. Maintain all temporary facilities for duration of construction activities as needed. 3.5 [REPAIR] / [RESTORATION] 3.6 RE-INSTALLATION 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES A. Temporary Facilities Trinity Basin Preparatory - Bolt CPN 103537 01 50 00 - 4 DAP TEMPORARY FACILITIES AND CONTROLS Page 4 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised JULY 1, 2011 1. Remove all temporary facilities and restore area after completion of the Work, to a condition equal to or better than prior to start of Work. 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE Trinity Basin Preparatory - Bolt CPN 103537 01 55 26 - 1 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 1 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 SECTION 01 55 26 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Administrative procedures for: a. Street Use Permit b. Modification of approved traffic control c. Removal of Street Signs B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 3. Section 34 71 13 – Traffic Control 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES A. Reference Standards 1. Reference standards cited in this specification refer to the current reference standard published at the time of the latest revision date logged at the end of this specification, unless a date is specifically cited. 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD). 1.4 ADMINISTRATIVE REQUIREMENTS A. Traffic Control 1. General a. When traffic control plans are included in the Drawings, provide Traffic Control in accordance with Drawings and Section 34 71 13. b. When traffic control plans are not included in the Drawings, prepare traffic control plans in accordance with Section 34 71 13 and submit to City for review. 1) Allow minimum 10 working days for review of proposed Traffic Control. B. Street Use Permit 1. Prior to installation of Traffic Control, a City Street Use Permit is required. a. To obtain Street Use Permit, submit Traffic Control Plans to City Transportation and Public Works Department. Trinity Basin Preparatory - Bolt CPN 103537 01 55 26 - 2 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 2 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 1) Allow a minimum of 5 working days for permit review. 2) Contractor’s responsibility to coordinate review of Traffic Control plans for Street Use Permit, such that construction is not delayed. C. Modification to Approved Traffic Control 1. Prior to installation traffic control: a. Submit revised traffic control plans to City Department Transportation and Public Works Department. 1) Revise Traffic Control plans in accordance with Section 34 71 13. 2) Allow minimum 5 working days for review of revised Traffic Control. 3) It is the Contractor’s responsibility to coordinate review of Traffic Control plans for Street Use Permit, such that construction is not delayed. D. Removal of Street Sign 1. If it is determined that a street sign must be removed for construction, then contact City Transportation and Public Works Department, Signs and Markings Division to remove the sign. E. Temporary Signage 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting requirements of the latest edition of the Texas Manual on Uniform Traffic Control Devices (MUTCD). 2. Install temporary sign before the removal of permanent sign. 3. When construction is complete, to the extent that the permanent sign can be reinstalled, contact the City Transportation and Public Works Department, Signs and Markings Division, to reinstall the permanent sign. F. Traffic Control Standards 1. Traffic Control Standards can be found on the City’s Buzzsaw website. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Trinity Basin Preparatory - Bolt CPN 103537 01 55 26 - 3 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 3 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 Revision Log DATE NAME SUMMARY OF CHANGE Trinity Basin Preparatory - Bolt CPN 103537 01 57 13 - 1 DAP STORM WATER POLLUTION PREVENTION Page 1 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 SECTION 01 57 13 STORM WATER POLLUTION PREVENTION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Procedures for Storm Water Pollution Prevention Plans B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 3. Section 31 25 00 – Erosion and Sediment Control 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Construction Activities resulting in less than 1 acre of disturbance a. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 2. Construction Activities resulting in greater than 1 acre of disturbance a. Measurement and Payment shall be in accordance with Section 31 25 00. 1.3 REFERENCES A. Abbreviations and Acronyms 1. Notice of Intent: NOI 2. Notice of Termination: NOT 3. Storm Water Pollution Prevention Plan: SWPPP 4. Texas Commission on Environmental Quality: TCEQ 5. Notice of Change: NOC A. Reference Standards 1. Reference standards cited in this Specification refer to the current reference standard published at the time of the latest revision date logged at the end of this Specification, unless a date is specifically cited. 2. Integrated Storm Management (iSWM) Technical Manual for Construction Controls 1.4 ADMINISTRATIVE REQUIREMENTS A. General 1. Contractor is responsible for resolution and payment of any fines issued associated with compliance to Stormwater Pollution Prevention Plan. Trinity Basin Preparatory - Bolt CPN 103537 01 57 13 - 2 DAP STORM WATER POLLUTION PREVENTION Page 2 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 B. Construction Activities resulting in: 1. Less than 1 acre of disturbance a. Provide erosion and sediment control in accordance with Section 31 25 00 and Drawings. 2. 1 to less than 5 acres of disturbance a. Texas Pollutant Discharge Elimination System (TPDES) General Construction Permit is required b. Complete SWPPP in accordance with TCEQ requirements 1) TCEQ Small Construction Site Notice Required under general permit TXR150000 a) Sign and post at job site b) Prior to Preconstruction Meeting, send 1 copy to City Department of Transportation and Public Works, Environmental Division, (817) 392- 6088. 2) Provide erosion and sediment control in accordance with: a) Section 31 25 00 b) The Drawings c) TXR150000 General Permit d) SWPPP e) TCEQ requirements 3. 5 acres or more of Disturbance a. Texas Pollutant Discharge Elimination System (TPDES) General Construction Permit is required b. Complete SWPPP in accordance with TCEQ requirements 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee a) Sign and post at job site b) Send copy to City Department of Transportation and Public Works, Environmental Division, (817) 392-6088. 2) TCEQ Notice of Change required if making changes or updates to NOI 3) Provide erosion and sediment control in accordance with: a) Section 31 25 00 b) The Drawings c) TXR150000 General Permit d) SWPPP e) TCEQ requirements 4) Once the project has been completed and all the closeout requirements of TCEQ have been met a TCEQ Notice of Termination can be submitted. a) Send copy to City Department of Transportation and Public Works, Environmental Division, (817) 392-6088. 1.5 SUBMITTALS A. SWPPP 1. Submit in accordance with Section 01 33 00, except as stated herein. a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City as follows: 1) 1 copy to the City Project Manager a) City Project Manager will forward to the City Department of Transportation and Public Works, Environmental Division for review Trinity Basin Preparatory - Bolt CPN 103537 01 57 13 - 3 DAP STORM WATER POLLUTION PREVENTION Page 3 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised July 1, 2011 B. Modified SWPPP 1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City in accordance with Section 01 33 00. 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE Trinity Basin Preparatory - Bolt CPN 103537 01 58 13 - 1 DAP TEMPORARY PROJECT SIGNAGE Page 1 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 SECTION 01 58 13 TEMPORARY PROJECT SIGNAGE PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Temporary Project Signage Requirements B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 2.2 EQUIPMENT, PRODUCT TYPES, AND MATERIALS A. Design Criteria 1. Provide free standing Project Designation Sign in accordance with City’s Standard Details for project signs. Trinity Basin Preparatory - Bolt CPN 103537 01 58 13 - 2 DAP TEMPORARY PROJECT SIGNAGE Page 2 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 B. Materials 1. Sign a. Constructed of ¾-inch fir plywood, grade A-C (exterior) or better 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 INSTALLATION A. General 1. Provide vertical installation at extents of project. 2. Relocate sign as needed, upon request of the City. B. Mounting options a. Skids b. Posts c. Barricade 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE A. General 1. Maintenance will include painting and repairs as needed or directed by the City. 3.14 ATTACHMENTS [NOT USED] END OF SECTION Trinity Basin Preparatory - Bolt CPN 103537 01 58 13 - 3 DAP TEMPORARY PROJECT SIGNAGE Page 3 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M. Domenech Revised for DAP application Trinity Basin Preparatory - Bolt CPN 103537 01 60 00 DAP PRODUCT REQUIREMENTS Page 1 of 2 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised March 20, 2020 SECTION 01 60 00 PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. References for Product Requirements and City Standard Products List B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES [NOT USED] 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A list of City approved products for use is available through the City’s website at: https://apps.fortworthtexas.gov/ProjectResources/ and following the directory path: 02 - Construction Documents\Standard Products List A. Only products specifically included on City’s Standard Product List in these Contract Documents shall be allowed for use on the Project. 1. Any subsequently approved products will only be allowed for use upon specific approval by the City. B. Any specific product requirements in the Contract Documents supersede similar products included on the City’s Standard Product List. 1. The City reserves the right to not allow products to be used for certain projects even though the product is listed on the City’s Standard Product List. C. Although a specific product is included on City’s Standard Product List, not all products from that manufacturer are approved for use, including but not limited to, that manufacturer’s standard product. D. See Section 01 33 00 for submittal requirements of Product Data included on City’s Standard Product List. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] Trinity Basin Preparatory - Bolt CPN 103537 01 60 00 DAP PRODUCT REQUIREMENTS Page 2 of 2 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised March 20, 2020 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 10/12/12 D. Johnson Modified Location of City’s Standard Product List 4/7/2014 M.Domenech Revised for DAP application 03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that the City approved products list is accessible through the City’s website. Trinity Basin Preparatory - Bolt CPN 103537 01 66 00 - 1 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 1 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 SECTION 01 66 00 PRODUCT STORAGE AND HANDLING REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Scheduling of product delivery 2. Packaging of products for delivery 3. Protection of products against damage from: a. Handling b. Exposure to elements or harsh environments B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY AND HANDLING A. Delivery Requirements 1. Schedule delivery of products or equipment as required to allow timely installation and to avoid prolonged storage. 2. Provide appropriate personnel and equipment to receive deliveries. 3. Delivery trucks will not be permitted to wait extended periods of time on the Site for personnel or equipment to receive the delivery. Trinity Basin Preparatory - Bolt CPN 103537 01 66 00 - 2 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 2 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 4. Deliver products or equipment in manufacturer's original unbroken cartons or other containers designed and constructed to protect the contents from physical or environmental damage. 5. Clearly and fully mark and identify as to manufacturer, item and installation location. 6. Provide manufacturer's instructions for storage and handling. B. Handling Requirements 1. Handle products or equipment in accordance with these Contract Documents and manufacturer’s recommendations and instructions. C. Storage Requirements 1. Store materials in accordance with manufacturer’s recommendations and requirements of these Specifications. 2. Make necessary provisions for safe storage of materials and equipment. a. Place loose soil materials and materials to be incorporated into Work to prevent damage to any part of Work or existing facilities and to maintain free access at all times to all parts of Work and to utility service company installations in vicinity of Work. 3. Keep materials and equipment neatly and compactly stored in locations that will cause minimum inconvenience to other contractors, public travel, adjoining owners, tenants and occupants. a. Arrange storage to provide easy access for inspection. 4. Restrict storage to areas available on construction site for storage of material and equipment as shown on Drawings, or approved by City’s Project Representative. 5. Provide off-site storage and protection when on-site storage is not adequate. a. Provide addresses of and access to off-site storage locations for inspection by City’s Project Representative. 6. Do not use lawns, grass plots or other private property for storage purposes without written permission of owner or other person in possession or control of premises. 7. Store in manufacturers’ unopened containers. 8. Neatly, safely and compactly stack materials delivered and stored along line of Work to avoid inconvenience and damage to property owners and general public and maintain at least 3 feet from fire hydrant. 9. Keep public and private driveways and street crossings open. 10. Repair or replace damaged lawns, sidewalks, streets or other improvements to satisfaction of City’s Project Representative. a. Total length which materials may be distributed along route of construction at one time is 1,000 linear feet, unless otherwise approved in writing by City’s Project Representative. Trinity Basin Preparatory - Bolt CPN 103537 01 66 00 - 3 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 3 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 ERECTION [NOT USED] 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL A. Tests and Inspections 1. Inspect all products or equipment delivered to the site prior to unloading. B. Non-Conforming Work 1. Reject all products or equipment that are damaged, used or in any other way unsatisfactory for use on the project. 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION A. Protect all products or equipment in accordance with manufacturer's written directions. B. Store products or equipment in location to avoid physical damage to items while in storage. C. Protect equipment from exposure to elements and keep thoroughly dry if required by the manufacturer. 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Trinity Basin Preparatory - Bolt CPN 103537 01 66 00 - 4 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 4 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application Trinity Basin Preparatory - Bolt CPN 103537 01 70 00 - 1 DAP MOBILIZATION AND REMOBILIZATION Page 1 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 SECTION 01 70 00 MOBILIZATION AND REMOBILIZATION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Mobilization and Demobilization a. Mobilization 1) Transportation of Contractor’s personnel, equipment, and operating supplies to the Site 2) Establishment of necessary general facilities for the Contractor’s operation at the Site 3) Premiums paid for performance and payment bonds 4) Transportation of Contractor’s personnel, equipment, and operating supplies to another location within the designated Site 5) Relocation of necessary general facilities for the Contractor’s operation from 1 location to another location on the Site. b. Demobilization 1) Transportation of Contractor’s personnel, equipment, and operating supplies away from the Site including disassembly 2) Site Clean-up 3) Removal of all buildings and/or other facilities assembled at the Site for this Contract c. Mobilization and Demobilization do not include activities for specific items of work that are for which payment is provided elsewhere in the contract. 2. Remobilization a. Remobilization for Suspension of Work specifically required in the Contract Documents or as required by City includes: 1) Demobilization a) Transportation of Contractor’s personnel, equipment, and operating supplies from the Site including disassembly or temporarily securing equipment, supplies, and other facilities as designated by the Contract Documents necessary to suspend the Work. b) Site Clean-up as designated in the Contract Documents 2) Remobilization a) Transportation of Contractor’s personnel, equipment, and operating supplies to the Site necessary to resume the Work. b) Establishment of necessary general facilities for the Contractor’s operation at the Site necessary to resume the Work. 3) No Payments will be made for: a) Mobilization and Demobilization from one location to another on the Site in the normal progress of performing the Work. b) Stand-by or idle time c) Lost profits 3. Mobilizations and Demobilization for Miscellaneous Projects a. Mobilization and Demobilization Trinity Basin Preparatory - Bolt CPN 103537 01 70 00 - 2 DAP MOBILIZATION AND REMOBILIZATION Page 2 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 1) Mobilization shall consist of the activities and cost on a Work Order basis necessary for: a) Transportation of Contractor’s personnel, equipment, and operating supplies to the Site for the issued Work Order. b) Establishment of necessary general facilities for the Contractor’s operation at the Site for the issued Work Order 2) Demobilization shall consist of the activities and cost necessary for: a) Transportation of Contractor’s personnel, equipment, and operating supplies from the Site including disassembly for each issued Work Order b) Site Clean-up for each issued Work Order c) Removal of all buildings or other facilities assembled at the Site for each Work Oder b. Mobilization and Demobilization do not include activities for specific items of work for which payment is provided elsewhere in the contract. 4. Emergency Mobilizations and Demobilization for Miscellaneous Projects a. A Mobilization for Miscellaneous Projects when directed by the City and the mobilization occurs within 24 hours of the issuance of the Work Order. B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Mobilization and Demobilization a. Measure 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 2. Remobilization for suspension of Work as specifically required in the Contract Documents a. Measurement 1) Measurement for this Item shall be per each remobilization performed. b. Payment 1) The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price per each “Specified Remobilization” in accordance with Contract Documents. c. The price shall include: 1) Demobilization as described in Section 1.1.A.2.a.1) 2) Remobilization as described in Section 1.1.A.2.a.2) d. No payments will be made for standby, idle time, or lost profits associated this Item. Trinity Basin Preparatory - Bolt CPN 103537 01 70 00 - 3 DAP MOBILIZATION AND REMOBILIZATION Page 3 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 3. Remobilization for suspension of Work as required by City a. Measurement and Payment 1) This shall be submitted as a Contract Claim in accordance with Article 10 of Section 00 72 00. 2) No payments will be made for standby, idle time, or lost profits associated with this Item. 4. Mobilizations and Demobilizations for Miscellaneous Projects a. Measurement 1) Measurement for this Item shall be for each Mobilization and Demobilization required by the Contract Documents b. Payment 1) The Work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price per each “Work Order Mobilization” in accordance with Contract Documents. Demobilization shall be considered subsidiary to mobilization and shall not be paid for separately. c. The price shall include: 1) Mobilization as described in Section 1.1.A.3.a.1) 2) Demobilization as described in Section 1.1.A.3.a.2) d. No payments will be made for standby, idle time, or lost profits associated this Item. 5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects a. Measurement 1) Measurement for this Item shall be for each Mobilization and Demobilization required by the Contract Documents b. Payment 1) The Work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price per each “Work Order Emergency Mobilization” in accordance with Contract Documents. Demobilization shall be considered subsidiary to mobilization and shall not be paid for separately. c. The price shall include 1) Mobilization as described in Section 1.1.A.4.a) 2) Demobilization as described in Section 1.1.A.3.a.2) d. No payments will be made for standby, idle time, or lost profits associated this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS [NOT USED] 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] Trinity Basin Preparatory - Bolt CPN 103537 01 70 00 - 4 DAP MOBILIZATION AND REMOBILIZATION Page 4 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application Trinity Basin Preparatory - Bolt CPN 103537 01 71 23 - 1 CONSTRUCTION STAKING AND SURVEY Page 1 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103537 Revised February 14, 2018 SECTION 01 71 23 1 CONSTRUCTION STAKING AND SURVEY 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Requirements for construction staking and construction survey 6 B. Deviations from this City of Fort Worth Standard Specification 7 1. See Changes (Highlighted in Yellow). 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10 2. Division 1 – General Requirements 11 1.2 PRICE AND PAYMENT PROCEDURES 12 A. Measurement and Payment 13 1. Construction Staking 14 a. Measurement 15 1) Measurement for this Item shall be by lump sum. 16 b. Payment 17 1) The work performed and the materials furnished in accordance with this 18 Item shall be paid for at the lump sum price bid for “Construction Staking”. 19 2) Payment for “Construction Staking” shall be made in partial payments 20 prorated by work completed compared to total work included in the lump 21 sum item. 22 c. The price bid shall include, but not be limited to the following: 23 1) Verification of control data provided by Developer’s Project 24 Representative. 25 2) Placement, maintenance and replacement of required stakes and markings 26 in the field. 27 3) Preparation and submittal of construction staking documentation in the 28 form of “cut sheets” using the City’s standard template. 29 2. Construction Survey 30 a. Measurement 31 1) This Item is considered subsidiary to the various Items bid. 32 b. Payment 33 1) The work performed and the materials furnished in accordance with this 34 Item are subsidiary to the various Items bid and no other compensation will be 35 allowed. 36 3. As-Built Survey 37 a. Measurement 38 1) Measurement for this Item shall be by lump sum. 39 b. Payment 40 1) The work performed and the materials furnished in accordance with this 41 Item shall be paid for at the lump sum price bid for “As-Built Survey”. 42 01 71 23 - 2 CONSTRUCTION STAKING AND SURVEY Page 2 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103537 Revised February 14, 2018 2) Payment for “As-Built Survey” shall be made in partial payments prorated 1 by work completed compared to total work included in the lump sum item. 2 c. The price bid shall include, but not be limited to the following: 3 1) Field measurements and survey shots to identify location of completed 4 facilities. 5 2) Documentation and submittal of as-built survey data onto contractor redline 6 plans and digital survey files. 7 8 1.3 REFERENCES 9 A. Definitions 10 1. Construction Survey - The survey measurements made prior to or while 11 construction is in progress to control elevation, horizontal position, dimensions and 12 configuration of structures/improvements included in the Project Drawings. 13 2. As-built Survey –The measurements made after the construction of the 14 improvement features are complete to provide position coordinates for the features 15 of a project. 16 3. Construction Staking – The placement of stakes and markings to provide offsets 17 and elevations to cut and fill in order to locate on the ground the designed 18 structures/improvements included in the Project Drawings. Construction staking 19 shall include staking easements and/or right of way if indicated on the plans. 20 4. Survey “Field Checks” – Measurements made after construction staking is 21 completed and before construction work begins to ensure that structures marked on 22 the ground are accurately located per Project Drawings. 23 B. Technical References 24 1. City of Fort Worth – Construction Staking Standards (available on City’s Buzzsaw 25 website) – 01 71 23.16.01_ Attachment A_Survey Staking Standards 26 2. City of Fort Worth - Standard Survey Data Collector Library (fxl) files (available 27 on City’s Buzzsaw website). 28 3. Texas Department of Transportation (TxDOT) Survey Manual, latest revision 29 4. Texas Society of Professional Land Surveyors (TSPS), Manual of Practice for Land 30 Surveying in the State of Texas, Category 5 31 32 1.4 ADMINISTRATIVE REQUIREMENTS 33 A. The Contractor’s selection of a surveyor must comply with Texas Government 34 Code 2254 (qualifications based selection) for this project. 35 1.5 SUBMITTALS 36 A. Submittals, if required, shall be in accordance with Section 01 33 00. 37 B. All submittals shall be received and reviewed by the City prior to delivery of work. 38 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 39 A. Field Quality Control Submittals 40 1. Documentation verifying accuracy of field engineering work, including coordinate 41 conversions if plans do not indicate grid or ground coordinates. 42 01 71 23 - 3 CONSTRUCTION STAKING AND SURVEY Page 3 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103537 Revised February 14, 2018 2. Submit “Cut-Sheets” conforming to the standard template provided by the City 1 (refer to 01 71 23.16.01 – Attachment A – Survey Staking Standards). 2 1.7 CLOSEOUT SUBMITTALS 3 B. As-built Redline Drawing Submittal 4 1. Submit As-Built Survey Redline Drawings documenting the locations/elevations of 5 constructed improvements signed and sealed by Registered Professional Land 6 Surveyor (RPLS) responsible for the work (refer to 01 71 23.16.01 – Attachment A 7 – Survey Staking Standards) . 8 2. Contractor shall submit the proposed as-built and completed redline drawing 9 submittal one (1) week prior to scheduling the project final inspection for City 10 review and comment. Revisions, if necessary, shall be made to the as-built redline 11 drawings and resubmitted to the City prior to scheduling the construction final 12 inspection. 13 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 14 1.9 QUALITY ASSURANCE 15 A. Construction Staking 16 1. Construction staking will be performed by the Contractor. 17 2. Coordination 18 a. Contact City and Developer’s Project Representative at least one week in 19 advance notifying the City of when Construction Staking is scheduled. 20 b. It is the Contractor’s responsibility to coordinate staking such that 21 construction activities are not delayed or negatively impacted. 22 3. General 23 a. Contractor is responsible for preserving and maintaining stakes. If 24 Developer’s Project Representative is required to re-stake for any reason, the 25 Contractor will be responsible for costs to perform staking. If in the opinion of 26 the City, a sufficient number of stakes or markings have been lost, destroyed 27 disturbed or omitted that the contracted Work cannot take place then the 28 Contractor will be required to stake or re-stake the deficient areas. 29 B. Construction Survey 30 1. Construction Survey will be performed by the Contractor. 31 2. Coordination 32 a. Contractor to verify that horizontal and vertical control data established in the 33 design survey and required for construction survey is available and in place. 34 3. General 35 a. Construction survey will be performed in order to construct the work shown 36 on the Construction Drawings and specified in the Contract Documents. 37 b. For construction methods other than open cut, the Contractor shall perform 38 construction survey and verify control data including, but not limited to, the 39 following: 40 1) Verification that established benchmarks and control are accurate. 41 2) Use of Benchmarks to furnish and maintain all reference lines and grades 42 for tunneling. 43 3) Use of line and grades to establish the location of the pipe. 44 01 71 23 - 4 CONSTRUCTION STAKING AND SURVEY Page 4 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103537 Revised February 14, 2018 4) Submit to the City copies of field notes used to establish all lines and 1 grades, if requested, and allow the City to check guidance system setup prior 2 to beginning each tunneling drive. 3 5) Provide access for the City, if requested, to verify the guidance system and 4 the line and grade of the carrier pipe. 5 6) The Contractor remains fully responsible for the accuracy of the work and 6 correction of it, as required. 7 7) Monitor line and grade continuously during construction. 8 8) Record deviation with respect to design line and grade once at each pipe 9 joint and submit daily records to the City. 10 9) If the installation does not meet the specified tolerances (as outlined in 11 Sections 33 05 23 and/or 33 05 24), immediately notify the City and correct 12 the installation in accordance with the Contract Documents. 13 C. As-Built Survey 14 1. Required As-Built Survey will be performed by the Contractor. 15 2. Coordination 16 a. Contractor is to coordinate with City to confirm which features require as-17 built surveying. 18 b. It is the Contractor’s responsibility to coordinate the as-built survey and 19 required measurements for items that are to be buried such that construction 20 activities are not delayed or negatively impacted. 21 c. For sewer mains and water mains 12” and under in diameter, it is acceptable 22 to physically measure depth and mark the location during the progress of 23 construction and take as-built survey after the facility has been buried. The 24 Contractor is responsible for the quality control needed to ensure accuracy. 25 3. General 26 a. The Contractor shall provide as-built survey including the elevation and 27 location (and provide written documentation to the City) of construction 28 features during the progress of the construction including the following: 29 1) Water Lines 30 a) Top of pipe elevations and coordinates for waterlines at the following 31 locations: 32 (1) Minimum every 250 linear feet, including 33 (2) Horizontal and vertical points of inflection, curvature, 34 etc. 35 (3) Fire line tee 36 (4) Plugs, stub-outs, dead-end lines 37 (5) Casing pipe (each end) and all buried fittings 38 2) Sanitary Sewer 39 a) Top of pipe elevations and coordinates for force mains and siphon 40 sanitary sewer lines (non-gravity facilities) at the following locations: 41 (1) Minimum every 250 linear feet and any buried fittings 42 (2) Horizontal and vertical points of inflection, curvature, 43 etc. 44 3) Stormwater – Not Applicable 45 b. The Contractor shall provide as-built survey including the elevation and 46 location (and provide written documentation to the City) of construction 47 features after the construction is completed including the following: 48 1) Manholes 49 01 71 23 - 5 CONSTRUCTION STAKING AND SURVEY Page 5 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103537 Revised February 14, 2018 a) Rim and flowline elevations and coordinates for each manhole 1 2) Water Lines 2 a) Cathodic protection test stations 3 b) Sampling stations 4 c) Meter boxes/vaults (All sizes) 5 d) Fire hydrants 6 e) Valves (gate, butterfly, etc.) 7 f) Air Release valves (Manhole rim and vent pipe) 8 g) Blow off valves (Manhole rim and valve lid) 9 h) Pressure plane valves 10 i) Underground Vaults 11 (1) Rim and flowline elevations and coordinates for each 12 Underground Vault. 13 3) Sanitary Sewer 14 a) Cleanouts 15 (1) Rim and flowline elevations and coordinates for each 16 b) Manholes and Junction Structures 17 (1) Rim and flowline elevations and coordinates for each 18 manhole and junction structure. 19 4) Stormwater – Not Applicable 20 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 21 1.11 FIELD [SITE] CONDITIONS [NOT USED] 22 1.12 WARRANTY 23 PART 2 - PRODUCTS 24 A. A construction survey will produce, but will not be limited to: 25 1. Recovery of relevant control points, points of curvature and points of intersection. 26 2. Establish temporary horizontal and vertical control elevations (benchmarks) 27 sufficiently permanent and located in a manner to be used throughout construction. 28 3. The location of planned facilities, easements and improvements. 29 a. Establishing final line and grade stakes for piers, floors, grade beams, parking 30 areas, utilities, streets, highways, tunnels, and other construction. 31 b. A record of revisions or corrections noted in an orderly manner for reference. 32 c. A drawing, when required by the client, indicating the horizontal and vertical 33 location of facilities, easements and improvements, as built. 34 4. Cut sheets shall be provided to the City inspector and Survey Superintendent for all 35 construction staking projects. These cut sheets shall be on the standard city template 36 which can be obtained from the Survey Superintendent (817-392-7925). 37 5. Digital survey files in the following formats shall be acceptable: 38 a. AutoCAD (.dwg) 39 b. ESRI Shapefile (.shp) 40 c. CSV file (.csv), formatted with X and Y coordinates in separate columns (use 41 standard templates, if available) 42 6. Survey files shall include vertical and horizontal data tied to original project 43 control and benchmarks, and shall include feature descriptions 44 01 71 23 - 6 CONSTRUCTION STAKING AND SURVEY Page 6 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103537 Revised February 14, 2018 PART 3 - EXECUTION 1 3.1 INSTALLERS 2 A. Tolerances: 3 1. The staked location of any improvement or facility should be as accurate as 4 practical and necessary. The degree of precision required is dependent on many 5 factors all of which must remain judgmental. The tolerances listed hereafter are 6 based on generalities and, under certain circumstances, shall yield to specific 7 requirements. The surveyor shall assess any situation by review of the overall plans 8 and through consultation with responsible parties as to the need for specific 9 tolerances. 10 a. Earthwork: Grades for earthwork or rough cut should not exceed 0.1 ft. vertical 11 tolerance. Horizontal alignment for earthwork and rough cut should not exceed 12 1.0 ft. tolerance. 13 b. Horizontal alignment on a structure shall be within .0.1ft tolerance. 14 c. Paving or concrete for streets, curbs, gutters, parking areas, drives, alleys and 15 walkways shall be located within the confines of the site boundaries and, 16 occasionally, along a boundary or any other restrictive line. Away from any 17 restrictive line, these facilities should be staked with an accuracy producing no 18 more than 0.05ft. tolerance from their specified locations. 19 d. Underground and overhead utilities, such as sewers, gas, water, telephone and 20 electric lines, shall be located horizontally within their prescribed areas or 21 easements. Within assigned areas, these utilities should be staked with an 22 accuracy producing no more than 0.1 ft tolerance from a specified location. 23 e. The accuracy required for the vertical location of utilities varies widely. Many 24 underground utilities require only a minimum cover and a tolerance of 0.1 ft. 25 should be maintained. Underground and overhead utilities on planned profile, 26 but not depending on gravity flow for performance, should not exceed 0.1 ft. 27 tolerance. 28 B. Surveying instruments shall be kept in close adjustment according to manufacturer’s 29 specifications or in compliance to standards. The City reserves the right to request a 30 calibration report at any time and recommends regular maintenance schedule be 31 performed by a certified technician every 6 months. 32 1. Field measurements of angles and distances shall be done in such fashion as to 33 satisfy the closures and tolerances expressed in Part 3.1.A. 34 2. Vertical locations shall be established from a pre-established benchmark and 35 checked by closing to a different bench mark on the same datum. 36 3. Construction survey field work shall correspond to the client’s plans. Irregularities 37 or conflicts found shall be reported promptly to the City. 38 4. Revisions, corrections and other pertinent data shall be logged for future reference. 39 40 3.2 EXAMINATION [NOT USED] 41 01 71 23 - 7 CONSTRUCTION STAKING AND SURVEY Page 7 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103537 Revised February 14, 2018 3.3 PREPARATION [NOT USED] 1 3.4 APPLICATION 2 3.5 REPAIR / RESTORATION 3 A. If the Contractor’s work damages or destroys one or more of the control 4 monuments/points set by the Developer’s Project Representative, the monuments shall be 5 adequately referenced for expedient restoration. 6 1. Notify City or Developer’s Project Representative if any control data needs to be 7 restored or replaced due to damage caused during construction operations. 8 a. Contractor shall perform replacements and/or restorations. 9 b. The City or Developer’s Project Representative may require at any time a 10 survey “Field Check” of any monument or benchmarks that are set be verified 11 by the Developer’s Project Representative before further associated work can 12 move forward. 13 3.6 RE-INSTALLATION [NOT USED] 14 3.7 FIELD [OR] SITE QUALITY CONTROL 15 A. It is the Contractor’s responsibility to maintain all stakes and control data placed by the 16 Developer’s Project Representative in accordance with this Specification. This includes 17 easements and right of way, if noted on the plans. 18 B. Do not change or relocate stakes or control data without approval from the City. 19 3.8 SYSTEM STARTUP 20 A. Survey Checks 21 1. The City reserves the right to perform a Survey Check at any time deemed 22 necessary. 23 2. Checks by City personnel or 3rd party contracted surveyor are not intended to 24 relieve the contractor of his/her responsibility for accuracy. 25 26 3.9 ADJUSTING [NOT USED] 27 3.10 CLEANING [NOT USED] 28 3.11 CLOSEOUT ACTIVITIES [NOT USED] 29 3.12 PROTECTION [NOT USED] 30 3.13 MAINTENANCE [NOT USED] 31 3.14 ATTACHMENTS [NOT USED] 32 33 34 35 01 71 23 - 8 CONSTRUCTION STAKING AND SURVEY Page 8 of 8 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103537 Revised February 14, 2018 END OF SECTION 1 2 Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 8/31/2017 M. Owen Added instruction and modified measurement & payment under 1.2; added definitions and references under 1.3; modified 1.6; added 1.7 closeout submittal requirements; modified 1.9 Quality Assurance; added PART 2 – PRODUCTS ; Added 3.1 Installers; added 3.5 Repair/Restoration; and added 3.8 System Startup. 2/14/2018 M Owen Removed “blue text”; revised measurement and payment sections for Construction Staking and As-Built Survey; added reference to selection compliance with TGC 2254; revised action and Closeout submittal requirements; added acceptable depth measurement criteria; revised list of items requiring as-built survey “during” and “after” construction; and revised acceptable digital survey file format 3 01 74 23 - 1 DAP CLEANING Page 1 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 SECTION 01 74 23 CLEANING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Intermediate and final cleaning for Work not including special cleaning of closed systems specified elsewhere B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 3. Section 32 92 13 – Hydro-Mulching, Seeding and Sodding 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Scheduling 1. Schedule cleaning operations so that dust and other contaminants disturbed by cleaning process will not fall on newly painted surfaces. 2. Schedule final cleaning upon completion of Work and immediately prior to final inspection. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 STORAGE, AND HANDLING A. Storage and Handling Requirements 1. Store cleaning products and cleaning wastes in containers specifically designed for those materials. Trinity Basin Preparatory - Bolt CPN 103537 01 74 23 - 2 DAP CLEANING Page 2 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 2.2 MATERIALS A. Cleaning Agents 1. Compatible with surface being cleaned 2. New and uncontaminated 3. For manufactured surfaces a. Material recommended by manufacturer 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 APPLICATION [NOT USED] 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING A. General 1. Prevent accumulation of wastes that create hazardous conditions. 2. Conduct cleaning and disposal operations to comply with laws and safety orders of governing authorities. 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in storm or sanitary drains or sewers. 4. Dispose of degradable debris at an approved solid waste disposal site. 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an alternate manner approved by City and regulatory agencies. Trinity Basin Preparatory - Bolt CPN 103537 01 74 23 - 3 DAP CLEANING Page 3 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 6. Handle materials in a controlled manner with as few handlings as possible. 7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with this project. 8. Remove all signs of temporary construction and activities incidental to construction of required permanent Work. 9. If project is not cleaned to the satisfaction of the City, the City reserves the right to have the cleaning completed at the expense of the Contractor. 10. Do not burn on-site. B. Intermediate Cleaning during Construction 1. Keep Work areas clean so as not to hinder health, safety or convenience of personnel in existing facility operations. 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish. 3. Confine construction debris daily in strategically located container(s): a. Cover to prevent blowing by wind b. Store debris away from construction or operational activities c. Haul from site at a minimum of once per week 4. Vacuum clean interior areas when ready to receive finish painting. a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance. 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which may become airborne or transported by flowing water during the storm. C. Exterior (Site or Right of Way) Final Cleaning 1. Remove trash and debris containers from site. a. Re-seed areas disturbed by location of trash and debris containers in accordance with Section 32 92 13. 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object that may hinder or disrupt the flow of traffic along the roadway. 3. Clean any interior areas including, but not limited to, vaults, manholes, structures, junction boxes and inlets. 4. If no longer required for maintenance of erosion facilities, and upon approval by City, remove erosion control from site. 5. Clean signs, lights, signals, etc. 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] Trinity Basin Preparatory - Bolt CPN 103537 01 74 23 - 4 DAP CLEANING Page 4 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application Trinity Basin Preparatory - Bolt CPN 103537 01 77 19 - 1 DAP CLOSEOUT REQUIREMENTS Page 1 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 SECTION 01 77 19 CLOSEOUT REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. The procedure for closing out a contract B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Guarantees, Bonds and Affidavits 1. No application for final payment will be accepted until all guarantees, bonds, certificates, licenses and affidavits required for Work or equipment as specified are satisfactorily filed with the City. B. Release of Liens or Claims 1. No application for final payment will be accepted until satisfactory evidence of release of liens has been submitted to the City. 1.5 SUBMITTALS A. Submit all required documentation to City’s Project Representative. Trinity Basin Preparatory - Bolt CPN 103537 01 77 19 - 2 DAP CLOSEOUT REQUIREMENTS Page 2 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 CLOSEOUT PROCEDURE A. Prior to requesting Final Inspection, submit: 1. Project Record Documents in accordance with Section 01 78 39 2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section 01 74 23. C. Final Inspection 1. After final cleaning, provide notice to the City Project Representative that the Work is completed. a. The City will make an initial Final Inspection with the Contractor present. b. Upon completion of this inspection, the City will notify the Contractor, in writing within 10 business days, of any particulars in which this inspection reveals that the Work is defective or incomplete. 2. Upon receiving written notice from the City, immediately undertake the Work required to remedy deficiencies and complete the Work to the satisfaction of the City. 3. Upon completion of Work associated with the items listed in the City's written notice, inform the City, that the required Work has been completed. Upon receipt of this notice, the City, in the presence of the Contractor, will make a subsequent Final Inspection of the project. 4. Provide all special accessories required to place each item of equipment in full operation. These special accessory items include, but are not limited to: a. Specified spare parts b. Adequate oil and grease as required for the first lubrication of the equipment c. Initial fill up of all chemical tanks and fuel tanks d. Light bulbs e. Fuses f. Vault keys g. Handwheels h. Other expendable items as required for initial start-up and operation of all equipment D. Notice of Project Completion Trinity Basin Preparatory - Bolt CPN 103537 01 77 19 - 3 DAP CLOSEOUT REQUIREMENTS Page 3 of 3 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 1. Once the City Project Representative finds the Work subsequent to Final Inspection to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet). E. Supporting Documentation 1. Coordinate with the City Project Representative to complete the following additional forms: a. Final Payment Request b. Statement of Contract Time c. Affidavit of Payment and Release of Liens d. Consent of Surety to Final Payment e. Pipe Report (if required) f. Contractor’s Evaluation of City g. Performance Evaluation of Contractor F. Letter of Final Acceptance 1. Upon review and acceptance of Notice of Project Completion and Supporting Documentation, in accordance with General Conditions, City will issue Letter of Final Acceptance and release the Final Payment Request for payment. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application Trinity Basin Preparatory - Bolt CPN 103537 01 78 23 - 1 DAP OPERATION AND MAINTENANCE DATA Page 1 of 5 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 SECTION 01 78 23 OPERATION AND MAINTENANCE DATA PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Product data and related information appropriate for City's maintenance and operation of products furnished under Contract 2. Such products may include, but are not limited to: a. Traffic Controllers b. Irrigation Controllers (to be operated by the City) c. Butterfly Valves B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Schedule 1. Submit manuals in final form to the City within 30 calendar days of product shipment to the project site. 1.5 SUBMITTALS A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be approved by the City prior to delivery. 1.6 INFORMATIONAL SUBMITTALS A. Submittal Form 1. Prepare data in form of an instructional manual for use by City personnel. 2. Format a. Size: 8 ½ inches x 11 inches b. Paper 1) 40 pound minimum, white, for typed pages 2) Holes reinforced with plastic, cloth or metal c. Text: Manufacturer’s printed data, or neatly typewritten Trinity Basin Preparatory - Bolt CPN 103537 01 78 23 - 2 DAP OPERATION AND MAINTENANCE DATA Page 2 of 5 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 d. Drawings 1) Provide reinforced punched binder tab, bind in with text 2) Reduce larger drawings and fold to size of text pages. e. Provide fly-leaf for each separate product, or each piece of operating equipment. 1) Provide typed description of product, and major component parts of equipment. 2) Provide indexed tabs. f. Cover 1) Identify each volume with typed or printed title "OPERATING AND MAINTENANCE INSTRUCTIONS". 2) List: a) Title of Project b) Identity of separate structure as applicable c) Identity of general subject matter covered in the manual 3. Binders a. Commercial quality 3-ring binders with durable and cleanable plastic covers b. When multiple binders are used, correlate the data into related consistent groupings. 4. If available, provide an electronic form of the O&M Manual. B. Manual Content 1. Neatly typewritten table of contents for each volume, arranged in systematic order a. Contractor, name of responsible principal, address and telephone number b. A list of each product required to be included, indexed to content of the volume c. List, with each product: 1) The name, address and telephone number of the subcontractor or installer 2) A list of each product required to be included, indexed to content of the volume 3) Identify area of responsibility of each 4) Local source of supply for parts and replacement d. Identify each product by product name and other identifying symbols as set forth in Contract Documents. 2. Product Data a. Include only those sheets which are pertinent to the specific product. b. Annotate each sheet to: 1) Clearly identify specific product or part installed 2) Clearly identify data applicable to installation 3) Delete references to inapplicable information 3. Drawings a. Supplement product data with drawings as necessary to clearly illustrate: 1) Relations of component parts of equipment and systems 2) Control and flow diagrams b. Coordinate drawings with information in Project Record Documents to assure correct illustration of completed installation. c. Do not use Project Record Drawings as maintenance drawings. 4. Written text, as required to supplement product data for the particular installation: a. Organize in consistent format under separate headings for different procedures. b. Provide logical sequence of instructions of each procedure. Trinity Basin Preparatory - Bolt CPN 103537 01 78 23 - 3 DAP OPERATION AND MAINTENANCE DATA Page 3 of 5 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 5. Copy of each warranty, bond and service contract issued a. Provide information sheet for City personnel giving: 1) Proper procedures in event of failure 2) Instances which might affect validity of warranties or bonds C. Manual for Materials and Finishes 1. Submit 5 copies of complete manual in final form. 2. Content, for architectural products, applied materials and finishes: a. Manufacturer's data, giving full information on products 1) Catalog number, size, composition 2) Color and texture designations 3) Information required for reordering special manufactured products b. Instructions for care and maintenance 1) Manufacturer's recommendation for types of cleaning agents and methods 2) Cautions against cleaning agents and methods which are detrimental to product 3) Recommended schedule for cleaning and maintenance 3. Content, for moisture protection and weather exposure products: a. Manufacturer's data, giving full information on products 1) Applicable standards 2) Chemical composition 3) Details of installation b. Instructions for inspection, maintenance and repair D. Manual for Equipment and Systems 1. Submit 5 copies of complete manual in final form. 2. Content, for each unit of equipment and system, as appropriate: a. Description of unit and component parts 1) Function, normal operating characteristics and limiting conditions 2) Performance curves, engineering data and tests 3) Complete nomenclature and commercial number of replaceable parts b. Operating procedures 1) Start-up, break-in, routine and normal operating instructions 2) Regulation, control, stopping, shut-down and emergency instructions 3) Summer and winter operating instructions 4) Special operating instructions c. Maintenance procedures 1) Routine operations 2) Guide to "trouble shooting" 3) Disassembly, repair and reassembly 4) Alignment, adjusting and checking d. Servicing and lubrication schedule 1) List of lubricants required e. Manufacturer's printed operating and maintenance instructions f. Description of sequence of operation by control manufacturer 1) Predicted life of parts subject to wear 2) Items recommended to be stocked as spare parts g. As installed control diagrams by controls manufacturer h. Each contractor's coordination drawings 1) As installed color coded piping diagrams Trinity Basin Preparatory - Bolt CPN 103537 01 78 23 - 4 DAP OPERATION AND MAINTENANCE DATA Page 4 of 5 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 i. Charts of valve tag numbers, with location and function of each valve j. List of original manufacturer's spare parts, manufacturer's current prices, and recommended quantities to be maintained in storage k. Other data as required under pertinent Sections of Specifications 3. Content, for each electric and electronic system, as appropriate: a. Description of system and component parts 1) Function, normal operating characteristics, and limiting conditions 2) Performance curves, engineering data and tests 3) Complete nomenclature and commercial number of replaceable parts b. Circuit directories of panelboards 1) Electrical service 2) Controls 3) Communications c. As installed color coded wiring diagrams d. Operating procedures 1) Routine and normal operating instructions 2) Sequences required 3) Special operating instructions e. Maintenance procedures 1) Routine operations 2) Guide to "trouble shooting" 3) Disassembly, repair and reassembly 4) Adjustment and checking f. Manufacturer's printed operating and maintenance instructions g. List of original manufacturer's spare parts, manufacturer's current prices, and recommended quantities to be maintained in storage h. Other data as required under pertinent Sections of Specifications 4. Prepare and include additional data when the need for such data becomes apparent during instruction of City's personnel. 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Provide operation and maintenance data by personnel with the following criteria: 1. Trained and experienced in maintenance and operation of described products 2. Skilled as technical writer to the extent required to communicate essential data 3. Skilled as draftsman competent to prepare required drawings Trinity Basin Preparatory - Bolt CPN 103537 01 78 23 - 5 DAP OPERATION AND MAINTENANCE DATA Page 5 of 5 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 1.5.A.1 – title of section removed 4/7/2014 M.Domenech Revised for DAP Application Trinity Basin Preparatory - Bolt CPN 103537 01 78 39 - 1 DAP PROJECT RECORD DOCUMENTS Page 1 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 SECTION 01 78 39 PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Work associated with the documenting the project and recording changes to project documents, including: a. Record Drawings b. Water Meter Service Reports c. Sanitary Sewer Service Reports d. Large Water Meter Reports B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to City’s Project Representative. 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Accuracy of Records 1. Thoroughly coordinate changes within the Record Documents, making adequate and proper entries on each page of Specifications and each sheet of Drawings and other Documents where such entry is required to show the change properly. 2. Accuracy of records shall be such that future search for items shown in the Contract Documents may rely reasonably on information obtained from the approved Project Record Documents. Trinity Basin Preparatory - Bolt CPN 103537 01 78 39 - 2 DAP PROJECT RECORD DOCUMENTS Page 2 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 3. To facilitate accuracy of records, make entries within 24 hours after receipt of information that the change has occurred. 4. Provide factual information regarding all aspects of the Work, both concealed and visible, to enable future modification of the Work to proceed without lengthy and expensive site measurement, investigation and examination. 1.10 STORAGE AND HANDLING A. Storage and Handling Requirements 1. Maintain the job set of Record Documents completely protected from deterioration and from loss and damage until completion of the Work and transfer of all recorded data to the final Project Record Documents. 2. In the event of loss of recorded data, use means necessary to again secure the data to the City's approval. a. In such case, provide replacements to the standards originally required by the Contract Documents. 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 2.2 RECORD DOCUMENTS A. Job set 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no charge to the Contractor, 1 complete set of all Documents comprising the Contract. B. Final Record Documents 1. At a time nearing the completion of the Work and prior to Final Inspection, provide the City 1 complete set of all Final Record Drawings in the Contract. 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 MAINTENANCE DOCUMENTS A. Maintenance of Job Set 1. Immediately upon receipt of the job set, identify each of the Documents with the title, "RECORD DOCUMENTS - JOB SET". Trinity Basin Preparatory - Bolt CPN 103537 01 78 39 - 3 DAP PROJECT RECORD DOCUMENTS Page 3 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 2. Preservation a. Considering the Contract completion time, the probable number of occasions upon which the job set must be taken out for new entries and for examination, and the conditions under which these activities will be performed, devise a suitable method for protecting the job set. b. Do not use the job set for any purpose except entry of new data and for review by the City, until start of transfer of data to final Project Record Documents. c. Maintain the job set at the site of work. 3. Coordination with Construction Survey a. At a minimum clearly mark any deviations from Contract Documents associated with installation of the infrastructure. 4. Making entries on Drawings a. Record any deviations from Contract Documents. b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the change by graphic line and note as required. c. Date all entries. d. Call attention to the entry by a "cloud" drawn around the area or areas affected. e. In the event of overlapping changes, use different colors for the overlapping changes. 5. Conversion of schematic layouts a. In some cases on the Drawings, arrangements of conduits, circuits, piping, ducts, and similar items, are shown schematically and are not intended to portray precise physical layout. 1) Final physical arrangement is determined by the Contractor, subject to the City's approval. 2) However, design of future modifications of the facility may require accurate information as to the final physical layout of items which are shown only schematically on the Drawings. b. Show on the job set of Record Drawings, by dimension accurate to within 1 inch, the centerline of each run of items. 1) Final physical arrangement is determined by the Contractor, subject to the City's approval. 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in ceiling plenum", "exposed", and the like). 3) Make all identification sufficiently descriptive that it may be related reliably to the Specifications. c. The City may waive the requirements for conversion of schematic layouts where, in the City's judgment, conversion serves no useful purpose. However, do not rely upon waivers being issued except as specifically issued in writing by the City. B. Final Project Record Documents 1. Transfer of data to Drawings a. Carefully transfer change data shown on the job set of Record Drawings to the corresponding final documents, coordinating the changes as required. b. Clearly indicate at each affected detail and other Drawing a full description of changes made during construction, and the actual location of items. c. Call attention to each entry by drawing a "cloud" around the area or areas affected. Trinity Basin Preparatory - Bolt CPN 103537 01 78 39 - 4 DAP PROJECT RECORD DOCUMENTS Page 4 of 4 CITY OF FORT WORTH [Insert Project Name] STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number] Revised April 7, 2014 d. Make changes neatly, consistently and with the proper media to assure longevity and clear reproduction. 2. Transfer of data to other Documents a. If the Documents, other than Drawings, have been kept clean during progress of the Work, and if entries thereon have been orderly to the approval of the City, the job set of those Documents, other than Drawings, will be accepted as final Record Documents. b. If any such Document is not so approved by the City, secure a new copy of that Document from the City at the City's usual charge for reproduction and handling, and carefully transfer the change data to the new copy to the approval of the City. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP Application Trinity Basin Preparatory - Bolt CPN 103537 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN 103537 Revised July 27, 2021 APPENDIX GC-4.01 Availability of Lands GC-4.02 Subsurface and Physical Conditions GC-4.04 Underground Facilities GC-4.06 Hazardous Environmental Condition at Site GC-6.06.D Minority and Women Owned Business Enterprise Compliance GC-6.07 Wage Rates GC-6.09 Permits and Utilities GC-6.24 Nondiscrimination GR-01 60 00 Product Requirements CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN 103537 Revised July 27, 2021 GC-4.02 Subsurface and Physical Conditions THIS PAGE LEFT INTENTIONALLY BLANK GEOTECHNICAL ENGINEERING STUDY TRINITY BASIN PREPARATORY ACADEMY BOLT CAMPUS FORT WORTH, TEXAS Presented To: Butler-Cohen, LLC May 2021 PROJECT NO. 2334-21-03 �� 7fi3fi Pebhle I]rivc 1 �.l�iGINEER�NG, INC. ��Ctru�,�tth,�r��fis����s www.cmjen�,rr.com May fi, 2021 Repar# Na. 2�34-21-03 Butler-Coh�n, LLC 3�00 �outhwest Freeway, 5uite 1575 Hous#on, T�xas 77027 A##n� Mr. Josh C�ntreras GEOTECHMCAL ENGINE�RIMG STU�Y TRINITY BASIN PREPARATORY ACADEMY BDLT CAM�US F4RT WORTH, TEXAS Dear Mr. Contreras; Submitted here are the results of a geotechnical engineering study forthe referenced project. This study w�s perfarmed in ger�eral accordance with our Prvpasal Nv. 2� �8042 dated March �9, 2029 . �'he geotechnical services were autharized or� April 6, 2�21 via Professi�nai Services Contract with Butler-Cohen, LLG. Engineering anafyses and recammendations are contained in tI1B t�Xt SBCtiDf1 of th� repart. Resuits of our field and laboratory services are included in the appendix of the report. We wvuld appreciate the o�parkunity to be considered for providing the canstruction mater9al testing serv�ces during the construction phase �f this praject. We appreciate the appartunity to be of service. Please contact us if you have any questions or if we may be of further service at this time. Respectfully submitted, C�VIJ �NGINE�RING, INC. � THXAS �'IRM ��+C:�S'�'�LATEON NC). F-9177 r �' I� .� Ma##hew W. Kammerdi�ner, P.E. Project Engine�r Texas No. 12781$ ;��t��� °� r�;�,��!� .• • i r '•. t: .* :.i....* .................:.* �AiTHEW W. K1V#�MERQiENE •i�y�i�����aa��}44�i����• • • �; 127818 �. . ,, , � '` � �,o, . ••...��,,,�� � ������� �=�: �� � � r�`� .}ame P. Sappington IV, P.�. Pre�ic�ent Texas� No. 974Q2 copies submi#ted: (2) Mr_ Josh Cantreras; Butler-Cohen, Inc. (mail and email) Phnne (817) 2$4-9444 F�x (817) 589-9993 Metm (817) 58�)-9992 TABLE OF CONTENTS Page 1.0 INTRODUCTION ------------------------------------------------------------------------------------------------------- 1 2.0 FIELD EXPLORATION AND LABORATORY TESTING ------------------------------------------------------ 2 3.0 SUBSURFACE CONDITIONS -------------------------------------------------------------------------------------- 3 4.0 FOUNDATION RECOMMENDATIONS --------------------------------------------------------------------------- 5 5.0 FLOOR SLABS & EXTERIOR FLATWORK -------------------------------------------------------------------- 10 6.0 EXPANSIVE SOIL CONSIDERATIONS ------------------------------------------------------------------------- 14 7.0 RETAINING STRUCTURES ---------------------------------------------------------------------------------------- 15 8.0 SEISMIC CONSIDERATIONS ------------------------------------------------------------------------------------- 19 9.0 EARTHWORK ---------------------------------------------------------------------------------------------------------- 19 10.0 PAVEMENTS ----------------------------------------------------------------------------------------------------------- 23 11.0 CONSTRUCTION OBSERVATIONS ----------------------------------------------------------------------------- 27 12.0 REPORT CLOSURE ------------------------------------------------------------------------------------------------- 28 APPENDIX A Plate Plan of Borings --------------------------------------------------------------------------------------------------------------- A.1 Unified Soil Classification System --------------------------------------------------------------------------------------- A.2 Key to Classification and Symbols -------------------------------------------------------------------------------------- A.3 Logs of Borings ----------------------------------------------------------------------------------------------------- A.4 – A.10 Free Swell Test Results -------------------------------------------------------------------------------------------------- A.11 Report No. 2334-21-03 CMJ ENGINEERING, INC. 1 1.0 INTRODUCTION 1.1 Project Description The project site is located at 412 West Bolt Street in Fort Worth, Texas. The project, as currently planned, will consist of a new school building with a footprint of approximately 53,000 square feet. A play field area and new area paving and drives are also planned. Plate A.1, Plan of Borings, presents the project vicinity and approximate locations of the exploration borings. 1.2 Purpose and Scope The purpose of this geotechnical engineering study has been to determine the general subsurface conditions, evaluate the engineering characteristics of the subsurface materials encountered, and develop recommendations for the type or types of foundations suitable for the project. To accomplish its intended purposes, the study has been conducted in the following phases: (1) drilling sample borings to determine the general subsurface conditions and to obtain samples for testing; (2) performing laboratory tests on appropriate samples to determine pertinent engineering properties of the subsurface materials; and (3) performing engineering analyses, using the field and laboratory data to develop geotechnical recommendations for the proposed construction. The design is currently in progress and the location and/or elevation of the structure could change. Once the final design is near completion (80-percent to 90-percent stage), it is recommended that CMJ Engineering, Inc. be retained to review those portions of the construction documents pertaining to the geotechnical recommendations, as a means to determine that our recommendations have been interpreted as intended. 1.3 Report Format The text of the report is contained in Sections 1 through 12. All plates and large tables are contained in Appendix A. The alpha-numeric plate and table numbers identify the appendix in which they appear. Small tables of less than one page in length may appear in the body of the text and are numbered according to the section in which they occur. Report No. 2334-21-03 CMJ ENGINEERING, INC. 2 Units used in the report are based on the English system and may include tons per square foot (tsf), kips (1 kip = 1,000 pounds), kips per square foot (ksf), pounds per square foot (psf), pounds per cubic foot (pcf), and pounds per square inch (psi). 2.0 FIELD EXPLORATION AND LABORATORY TESTING 2.1 Field Exploration Subsurface materials at the project site were explored by seven (7) vertical soil borings. Borings B- 1 through B-3 were drilled to depths of 25 to 35 feet in the area of the proposed building. Borings B- 4 through B-7 were drilled to a depth of 5 feet in association with the play field and area paving and drives. The borings were drilled using continuous flight augers at the approximate locations shown on the Plan of Borings, Plate A.1. The boring logs are included on Plates A.4 through A.10 and keys to classifications and symbols used on the logs are provided on Plates A.2 and A.3. Undisturbed samples of cohesive soils were obtained with nominal 3-inch diameter thin-walled (Shelby) tube samplers at the locations shown on the logs of borings. The Shelby tube sampler consists of a thin-walled steel tube with a sharp cutting edge connected to a head equipped with a ball valve threaded for rod connection. The tube is pushed into the soil by the hydraulic pulldown of the drilling rig. The soil specimens were extruded from the tube in the field, logged, tested for consistency with a hand penetrometer, sealed, and packaged to limit loss of moisture. The consistency of cohesive soil samples was evaluated in the field using a calibrated hand penetrometer. In this test a 0.25-inch diameter piston is pushed into the relatively undisturbed sample at a constant rate to a depth of 0.25 inch. The results of these tests, in tsf, are tabulated at respective sample depths on the logs. When the capacity of the penetrometer is exceeded, the value is tabulated as 4.5+. To evaluate the relative density and consistency of the harder formations, a modified version of the Texas Cone Penetration test was performed at selected locations. Texas Department of Transportation (TxDOT) Test Method Tex-132-E specifies driving a 3-inch diameter cone with a 170- pound hammer freely falling 24 inches. This results in 340 foot-pounds of energy for each blow. This method was modified by utilizing a 140-pound hammer freely falling 30 inches. This results in 350 foot-pounds of energy for each hammer blow. In relatively soft materials, the penetrometer cone Report No. 2334-21-03 CMJ ENGINEERING, INC. 3 is driven 1 foot and the number of blows required for each 6-inch penetration is tabulated at respective test depths, as blows per 6 inches on the log. In hard materials (rock or rock-like), the penetrometer cone is driven with the resulting penetrations, in inches, recorded for the first and second 50 blows, a total of 100 blows. The penetration for the total 100 blows is recorded at the respective testing depths on the boring logs. 2.2 Laboratory Testing Laboratory soil tests were performed on selected representative samples recovered from the borings. In addition to the classification tests (liquid limits and plastic limits), moisture content, unit weight, and unconfined compressive strength tests were performed. Results of the laboratory classification, moisture content, unit weight, and unconfined compression tests conducted for this project are included on the boring logs. Free swell tests were performed on specimens from selected samples of the clays. These tests were performed to help in evaluating the swell potential of near-surface soils in the area of the proposed structure. The results of the swell tests are presented on Plate A.11. The above laboratory tests were performed in general accordance with applicable ASTM procedures, or generally accepted practice. 3.0 SUBSURFACE CONDITIONS 3.1 Soil Conditions Specific types and depths of subsurface strata encountered at the boring locations are shown on the boring logs in Appendix A. The generalized subsurface stratigraphies encountered in the borings are discussed below. Note that depths on the borings refer to the depth from the existing grade or ground surface present at the time of the investigation, and the boundaries between the various soil types are approximate. Borings B-7 was drilled in a paved area consisting of 4 inches of asphalt underlain by 6 inches of sand base material. Crushed asphalt with a thickness of 2 feet was present at the surface in Boring B-4. Soils encountered consist of dark brown, brown, light brown, olive brown, and light reddish Report No. 2334-21-03 CMJ ENGINEERING, INC. 4 brown clays and silty clays. The surficial soils encountered in Borings B-1, B-2, B-5, and B-7 are noted as fill to depths of 1 to 3 feet and occasionally contain asphalt fragments. The various soils often contain calcareous nodules and occasionally contain calcareous deposits, ironstone nodules, iron stains, gravel, and fractured limestone seams. Tan limestone, often occurring weathered or containing clay seams was next encountered in Borings B-1, B-3 and B-5 at depths of 1 to 3 feet. The tan limestone is generally moderately hard to very hard (rock basis) with Texas Cone Penetrometer (THD) values of 1 to 3 inches of penetration per 100 blows. Tan silty clay containing limestone layers is present beneath the tan limestone in Boring B-1 at a depth of 11 feet, extending to a depth of 14 feet. The various soils encountered in the borings had tested Liquid Limits (LL) ranging from 36 to 81 with Plasticity Indices (PI) ranging from 20 to 52 and are classified as CL and CH by the Unified Classification System (USCS). The clayey soils varied from firm to hard (soil basis) in consistency with pocket penetrometer readings of 1.25 to over 4.5 tsf. Tested unit weight values were 85 to 109 pcf and tested unconfined compressive strengths ranged from 2,930 to 3,820 psf. Gray clayey shale was next encountered in Boring B-2 at a depth of 24 feet. The gray clayey shale is soft (rock basis) with a pocket penetrometer reading of over 4.5 tsf. Gray limestone and/or gray shale was next present in Borings B-1 through B-3 at depths of 14 to 25 feet and continued through boring termination at depths of 25 to 35 feet. The gray limestone and gray shale are generally moderately hard to very hard (rock basis) with Texas Cone Penetrometer (THD) values of 1 to 4¼ inches of penetration per 100 blows. The Atterberg Limits tests indicate the various clays encountered at this site are moderately active to highly active with respect to moisture induced volume changes. Active clays can experience volume changes (expansion or contraction) with fluctuations in their moisture content. 3.2 Ground-Water Observations The borings were drilled using continuous flight augers in order to observe ground-water seepage during drilling. Ground-water seepage was encountered during drilling in Boring B-2 at 9 feet below existing grade. Ground-water levels of 21 and 12 feet were observed in Boring B-2 at drilling Report No. 2334-21-03 CMJ ENGINEERING, INC. 5 completion and several hours after drilling completion, respectively. No seepage was encountered during drilling or at completion in the remaining borings. Table 3.2-1 summarizes water level data. While it is not possible to accurately predict the magnitude of subsurface water fluctuation that might occur based upon these short-term observations, it should be recognized that ground-water conditions will vary with fluctuations in rainfall. Seepage near the observed levels should be anticipated throughout the year. TABLE 3.2-1 Ground-Water Observations Boring No. Seepage During Drilling (ft.) Water at Completion (ft.) Water at End of Day (ft.) B-1 Dry Dry Dry B-2 9 21 12 B-3 Dry Dry Dry B-4 Dry Dry Dry B-5 Dry Dry Dry B-6 Dry Dry Dry B-7 Dry Dry Dry Fluctuations of the ground-water level can occur due to seasonal variations in the amount of rainfall; site topography and runoff; hydraulic conductivity of soil strata; and other factors not evident at the time the borings were performed. The possibility of ground-water level fluctuations should be considered when developing the design and construction plans for the project. 4.0 FOUNDATION RECOMMENDATIONS 4.1 General Foundation Considerations Two independent design criteria must be satisfied in the selection of the type of foundation to support the proposed structure. First, the ultimate bearing capacity, reduced by a sufficient factor of safety, must not be exceeded by the bearing pressure transferred to the foundation soils. Second, due to consolidation or expansion of the underlying soils during the operating life of the structure, total and differential vertical movements must be within tolerable limits. The recommended foundation alternatives for the proposed structure are discussed below. Report No. 2334-21-03 CMJ ENGINEERING, INC. 6 The moisture induced volume changes associated with the moderately active to highly active clays present at this site indicate that shallow or near surface footings could be subject to differential movements of a potentially detrimental magnitude. The most positive foundation system for the proposed structure would be situated below the zone of most significant seasonal moisture variations. A deep foundation system transferring column loads to a suitable bearing stratum is considered the most positive foundation system. Straight drilled reinforced concrete shafts penetrating the gray limestone and gray shale offer a positive foundation system and are recommended. Recommendations for this system are presented below. 4.2 Straight Shaft Design Parameters 4.2.1 Design Criteria Recommendations and parameters for the design of cast-in-place straight-shaft drilled piers are outlined below. Specific recommendations for the construction and installation of the drilled piers are included in the following section, and shall be followed during construction. Bearing Stratum Moderately hard to very hard gray LIMESTONE or gray SHALE Depth of Bearing Stratum: Approximately 14 to 25 feet below existing grades Required Penetration: All piers should penetrate into the bearing stratum a minimum of 3 feet. Allowable End Bearing Capacity: 18,000 psf Allowable Skin Friction: Applicable below a minimum penetration of 3 feet into gray limestone or shale and below any temporary casing; 2,900 psf for compressive loads and 2,000 psf for tensile loads The minimum recommended pier diameter is 18 inches. The above values contain a safety factor of three (3). Drilled shafts should extend through any clayey shale or weathered seams and layers and bear only in unweathered gray limestone or gray shale. Penetrations greater than the minimum penetration may be required to develop additional skin friction and/or uplift resistance. Excavations for the shafts should be maintained in the dry. It should be anticipated that ground- water seepage and possibly caving soils will be encountered during installation of select straight Report No. 2334-21-03 CMJ ENGINEERING, INC. 7 shafts and that temporary casing will likely be required for select straight shafts for proper shaft installation. In order to develop full load carrying capacity in skin friction, adjacent should have a minimum center- to-center spacing of 3 times the diameter of the larger shaft. Closer spacing may require some reductions in skin friction and/or changes in installation sequences. Closely spaced shafts should be examined on a case-by-case basis. As a general guide, the design skin friction will vary linearly from the full value at a spacing of 3 diameters to 50 percent of the design value at 1 diameter. Settlements for properly installed and constructed straight shafts in the gray limestone and gray shale will be primarily elastic and are estimated to be one inch or less. 4.2.2 Lateral Load Design Values Drilled shaft design parameters for use with Lpile based on our laboratory test results are presented in Table 4.2.2-1 together with our recommended design stratigraphy. Exposed clay soils surrounding the drilled shaft are recommended to be neglected in the lateral load analyses because of the potential for shrinkage cracks forming along the sides of the drilled shafts. For the gray limestone and gray shale, the “Weak Rock” model is suitable for use with Lpile. TABLE 4.2.2-1 – RECOMMENDED LATERAL LOAD DESIGN VALUES Soil Type Design Depth Interval (ft) Design Total Unit Weight (pcf) Design Strength Design ε50 k-value (pci) Clay Soils (undrained condition) 10 – to top of Rock* 120 Cohesion (psi) Friction Angle (degrees) 0.02 100 4 0 Clay Soils (undrained condition) 10 – to top of Rock* 120 3 12 0.02 100 Gray Limestone & Gray Shale (Estimated RQD 60%) 14 – 25 (See Section 4.2.1) 140 Uniaxial Compressive Strength (psi) 0.0005 E (psi) = 1X105 165 * Lateral shaft resistance should not be considered within the upper 10 feet due to the potential for shrinkage cracks forming along the sides of the drilled shafts. Tan limestone should be neglected due to variable occurrence. Report No. 2334-21-03 CMJ ENGINEERING, INC. 8 4.3 Soil Induced Uplift Loads The drilled shafts could experience tensile loads as a result of post construction heave in the site soils. The magnitude of these loads varies with the shaft diameter, soil parameters, and particularly the in-situ moisture levels at the time of construction. In order to aid in the structural design of the reinforcement, the reinforcement quantity should be adequate to resist tensile forces based on soil adhesion equal to 1,800 psf acting over the upper 10 feet of the pier shaft. This load must be resisted by the dead load on the shaft, continuous vertical reinforcing steel in the shaft, and a shaft adhesion developed within the bearing strata as previously discussed. In order to aid in the structural design of the reinforcement, minimum reinforcing should be equal to 0.5 percent of the shaft area. 4.4 Drilled Shaft Construction Considerations. Drilled pier construction should be monitored by a representative of the geotechnical engineer to observe, among other things, the following items: ● Identification of bearing material ● Adequate penetration of the shaft excavation into the bearing layer ● The base and sides of the shaft excavation are clean of loose cuttings ● If seepage is encountered, whether it is of sufficient amount to require the use of temporary steel casing. If casing is needed it is important that the field representative observe that a high head of plastic concrete is maintained within the casing at all times during their extraction to prevent the inflow of water Precautions should be taken during the placement of reinforcing steel and concrete to prevent loose, excavated soil from falling into the excavation. Concrete should be placed as soon as practical after completion of the drilling, cleaning, and observation. Excavation for a drilled pier should be filled with concrete before the end of the workday, or sooner if required to prevent deterioration of the bearing material. Prolonged exposure or inundation of the bearing surface with water will result in changes in strength and compressibility characteristics. If delays occur, the drilled pier excavation should be deepened as necessary and cleaned, in order to provide a fresh bearing surface. Excavations for the shafts should be maintained in the dry. It should be anticipated that ground- water seepage will likely be encountered during straight shaft installation of select straight shafts and that temporary casing will be required select straight shafts for proper shaft installation. The casing should be seated below the zone of seepage with all water and most loose material removed prior Report No. 2334-21-03 CMJ ENGINEERING, INC. 9 to beginning the design penetration. Care must then be taken that a sufficient head of plastic concrete is maintained within the casing during extraction. The concrete should have a slump of 6 inches plus or minus 1 inch. The concrete should be placed in a manner to prevent the concrete from striking the reinforcing cage or the sides of the excavation. Concrete should be tremied to the bottom of the excavation to control the maximum free fall of the plastic concrete to less than 10 feet or focus the concrete between reinforcing steel to prevent segregation. A drilling rig of sufficient size and weight will be necessary for drilling and/or coring through the hard layers to reach the desired bearing stratum and achieve the required penetration. It should be anticipated that hard to very hard zones can be present in the tan limestone, gray limestone and gray shale. The hard to very hard layers can complicate pier drilling operations. In addition to the above guidelines, the specifications from the Association of Drilled Shaft Contractors Inc. "Standards and Specifications for the Foundation Drilling Industry" as Revised 1999 or other recognized specifications for proper installation of drilled shaft foundation systems should be followed. 4.5 Grade Beams All grade beams should be supported by the drilled shafts. A minimum 10-inch void space should be provided beneath all grade beams to prevent contact with the swelling clay soils. This void will serve to minimize distress resulting from swell pressures generated by the clays. Grade beams may be cast on cardboard carton forms or formed above grade. If cardboard carton forms are used, care should be taken to not crush the carton forms, or allow the carton forms to become wet prior to or during concrete placement operations. A soil retainer should be provided to help prevent in-filling of this void. Backfill against the exterior face of grade beams or panels should be properly compacted on-site clays. Compaction should be a minimum of 93 percent of ASTM D 698, at a minimum of 2 Report No. 2334-21-03 CMJ ENGINEERING, INC. 10 percentage points above the optimum moisture content determined by that test. This clay fill is intended to reduce surface water infiltration beneath the structure. 5.0 FLOOR SLABS & EXTERIOR FLATWORK 5.1 Potential Vertical Movements Lightly loaded floor slabs and exterior flatwork placed on-grade will be subject to movement as a result of moisture induced volume changes in the moderately active to highly active clays and indeterminate settlement of the existing fills. The clays expand (heave) with increases in moisture and contract (shrink) with decreases in moisture. The movement typically occurs as post construction heave. The potential magnitude of the moisture induced movements is rather indeterminate. It is influenced by the soil properties, overburden pressures, and to a great extent by soil moisture levels at the time of construction. The greatest potential for post-construction movement occurs when the soils are in a dry condition at the time of construction. Based on the conditions encountered in the borings, the potential moisture induced movements are estimated to be on the order of 4½ inches for soils in a dry condition where the slabs are situated near present existing grades. Soil movements, significantly larger than estimated, could occur due to inadequate site grading, poor drainage, ponding of rainfall, and/or leaking pipelines. In-situ moisture conditions at the time of exploration for this study were favorably high. Such conditions are considered to be present due to the long-term presence of the previous structure and pavement in this area. Based on the elevated in-situ moisture conditions and swell test result, the estimated potential moisture induced movements are on the order of 1½ inches from present in-situ moisture conditions. Site grading will affect potential movements. For example, fills using on-site or similar clays will increase potential movements. Cuts would decrease potential movements by removing clays. The recommendations provided below should be reviewed to evaluate the effects of grading on the potential moisture-induced movements once grading plans are available. Report No. 2334-21-03 CMJ ENGINEERING, INC. 11 5.2 Structurally Suspended Floor Slab The most positive method of preventing slab distress due to swelling soils is to structurally suspend the interior slab. Due to the expansion potential of the site clays we recommend that the suspended floor slab be constructed on carton forms with a minimum 10-inch void space or crawl space. Care should be taken to assure that the void boxes are not allowed to become wet or crushed prior to or during concrete placement and finishing operations. Corrugated steel, placed on the top of the carton forms, could be used to reduce the risk of crushing of the carton forms during concrete placement and finishing operations. As a quality control measure during construction, "actual" concrete quantities placed should be checked against "anticipated" quantities. Significant concrete "overage" would be an early indication of a collapsed void. If a crawl space is utilized, provision should be made to provide drainage of the crawl space below the slab, in the event water becomes trapped or seeps into this area. Drain inlets which are tied into the storm sewer or a sump and pump system may be necessary. Also, because of capillary moisture buildup, proper ventilation should be provided in the crawl space below the slab. Ventilation of the void and a vapor barrier below the floors should be provided if high humidity can cause problems with floor tile adhesives. Vehicle or pedestrian ramps leading up to the building should be structurally connected to the building grade beams to avoid abrupt differential movement between the building slab and the ramps. Transitioning details will be required at the points where ramps connect with paving and slab on- grade elements. In addition, ramp slabs should be constructed so that slopes sufficient for effective drainage of surface water are still provided after potential differential movements. 5.3 Ground Supported Floor Slabs & Exterior Flatwork In conjunction with drilled shafts, interior slabs and/or exterior flatwork can be placed on a prepared subgrade. Ground-supported floor slab construction should only be considered if slab movement can be tolerated. The level of acceptable movement varies with the user, but methods are normally selected with the goal of limiting slab movements to about one inch or less. Reductions in anticipated movements can be achieved by using methods developed in this area to reduce on-grade slab movements. The more commonly used methods consist of placing non-expansive select fill beneath Report No. 2334-21-03 CMJ ENGINEERING, INC. 12 the slab and moisture conditioning the soils. The use of these methods will not eliminate the risk of unacceptable movements. Readers should understand that a ground-supported floor slab can heave considerably if placed on dry, expansive clays. As previously discussed, in-situ moisture conditions at the time of exploration for this study were favorably high. If present moisture levels can be maintained prior to construction, the installation of a minimum 1-foot thick non-expansive select fill cap should reduce potential movements to on the order of 1 inch. No special moisture-conditioning of the pad subgrade would be necessary. A pre-construction moisture evaluation is required to verify if elevated moisture levels are present in the clays. If the soils are dry relative to present in-situ moisture levels, the installation of a minimum of 1 foot of non-expansive select fill over a minimum of 9 feet of moisture conditioned clays should reduce potential movements to on the order of 1 inch. Moisture conditioning can be achieved by mechanically reworking the clays as described below. Slabs not capable of tolerating this level of movement should be structurally suspended. These recommendations should be reviewed once a grading plan is finalized. Excavation of the tan limestone is not necessary to complete the removal process; however zones of limestone seams, layers, and boulders which are 1-foot in thickness or less within the clays must be removed and will require significant processing effort in order to re-utilize as fill. Therefore, it is recommended a representative of CMJ be retained during the removal process to verify the presence of the weathered and fractured limestone versus clays, and observe the appropriate clay removal. Where finished grade results in cuts, seasonal water seeps can occur where the tan limestones are approached or exposed. Subsoil drains may be required in some areas to intercept this seepage. This can be evaluated after a grading plan is finalized. Strong consideration should be given to extending the moisture conditioning process beyond the building line to include entrances, sidewalks, flatwork, pavement, porticos or any other areas sensitive to movement. Outside the building, a single lift of select fill (6 to 8 inches) is recommended to minimize drying during construction. Report No. 2334-21-03 CMJ ENGINEERING, INC. 13 Soil treatments presented in this section are referenced as an alternative to the use of a structurally suspended slab. The owner must fully understand that if the flatwork is placed on-grade, some movement and resultant cracking within the flatwork may occur. This upward slab movement and cracking is usually difficult and costly to repair, and may require continued maintenance expense. These methods of treatment are presented as an option for the owner’s consideration. The options may or may not be practical or economically feasible, depending on the expected performance of the proposed structure. The owner should be aware that this method will not prevent movement of soil-supported elements, and can only reduce the magnitude of the movement. A properly engineered and constructed vapor barrier should be provided beneath slabs-on-grade which will be carpeted or receive moisture sensitive coverings or adhesives. In general, the following procedure is recommended to be performed to provide a moisture- conditioned pad: 5.3.1 Mechanical Reworking of Near-Surface Clays with 1’ Select Fill Cap In general, the procedure is performed as follows: 1. Remove all existing pavements, surface vegetation, trees and associated root mats, organic topsoil and any other deleterious material. 2. Excavate clays to a minimum of 9.5 feet below finished grade. It is not necessary to remove intact tan limestone to achieve the recommended depth of excavation. Scarify the exposed clay subgrade, if present, at the base of the excavation to a depth of 8 inches, adjust the moisture, and compact at a minimum of 4 percentage points above optimum moisture to between 93 and 98 percent of Standard Proctor density (ASTM D 698). Over-compaction should not be allowed. More granular soils may need to be compacted closer to optimum moisture at the discretion of the geotechnical engineer. 3. Fill pad to 1 foot below final grade using site excavated or similar clay soils. Compact in maximum 9-inch loose lifts at a minimum of 4 percentage points above optimum moisture to between 93 and 98 percent of Standard Proctor density (ASTM D 698). Field density tests should be taken as each lift of fill material is placed. Each lift should be compacted, tested, and documented prior to subsequent lift placement. Over-compaction should not be allowed. 4. Complete pad fill using a minimum of 1 foot of sandy clay/clayey sand non-expansive select fill with a Liquid Limit less than 35 and a Plasticity Index (PI) between 5 and 16. The select fill should be compacted in maximum 9-inch loose lifts at -2 to +3 percentage points of the soil’s optimum moisture content at a minimum of 95 percent of Standard Proctor density (ASTM D 698). The select fill should be placed within 48 hours of completing the installation of the moisture conditioned soils. Report No. 2334-21-03 CMJ ENGINEERING, INC. 14 The above earthwork operations should be continuously observed and tested by an experienced geotechnician working in conjunction with the project geotechnical engineer. 6.0 EXPANSIVE SOIL CONSIDERATIONS 6.1 Site Drainage An important feature of the project is to provide positive drainage away from the proposed building. If water is permitted to stand next to or below the structure, excessive soil movements (heave) can occur. This could result in differential floor slab or foundation movement. A well-designed site drainage plan is of utmost importance and surface drainage should be provided during construction and maintained throughout the life of the structure. Consideration should be given to the design and location of gutter downspouts, planting areas, or other features which would produce moisture concentration adjacent to or beneath the structure or paving. Consideration should be given to the use of self-contained, watertight planters. Joints next to the structure should be sealed with a flexible joint sealer to prevent infiltration of surface water. Proper maintenance should include periodic inspection for open joints and cracks and resealing as necessary. Rainwater collected by the gutter system should be transported by pipe to a storm drain or to a paved area. If downspouts discharge next to the structure onto flatwork or paved areas, the area should be watertight in order to eliminate infiltration next to the building. 6.2 Additional Design Considerations The following information has been assimilated after examination of numerous projects constructed in active soils throughout the area. It is presented here for your convenience. If these features are incorporated in the overall design of the project, the performance of the structure should be improved. • Special consideration should be given to completion items outside the building area, such as stairs, sidewalks, signs, etc. They should be adequately designed to sustain the potential vertical movements mentioned in the report. • Roof drainage should be collected by a system of gutters and downspouts and transmitted away from the structure where the water can drain away without entering the building subgrade. Report No. 2334-21-03 CMJ ENGINEERING, INC. 15 • Sidewalks should not be structurally connected to the building. They should be sloped away from the building so that water will drain away from the structure. • The paving and the general ground surface should be sloped away from the building on all sides so that water will always drain away from the structure. Water should not be allowed to pond near the building after the slab has been placed. • Trees and deep rooted shrubs should not be used as landscaping around the structure perimeter as the root systems can lead to desiccation of the subgrade soils. Any existing trees or trees to be planted should be at a distance from the building such that the building will not fall within the drip line of the mature plants (usually one to one-and-one-half times the mature height of the tree). If existing tree removal is not an acceptable option, a vertical root barrier, extending to a minimum depth of 4 feet, should be constructed around the perimeter of the foundation in proximity to the area described above. • Every attempt should be made to limit the extreme wetting or drying of the subsurface soils since swelling and shrinkage will result. Standard construction practices of providing good surface water drainage should be used. A positive slope of the ground away from the foundation should be provided to carry off the run-off water both during and after construction. • Backfill for utility lines or along the perimeter beams should consist of on-site material so that they will be stable. If the backfill is too dense or too dry, swelling may form a mound along the ditch line. If the backfill is too loose or too wet, settlement may form a sink along the ditch line. Either case is undesirable since several inches of movement is possible and floor cracks are likely to result. The soils should be processed using the previously discussed compaction criteria. • Utility line details and fixtures must consider the potential for differential movement beneath any piping. In conjunction with a structural slab all underground utility lines should be isolated from expansive clays. A similar 10-inch void is recommended between the utility bottom and underlying clay soils. This prevents the utility lines from uplifting into the suspended slab. 7.0 RETAINING STRUCTURES 7.1 General Retaining Wall Considerations Five geotechnical design criteria must be satisfied in the selection of the type and configuration of the retaining walls. These criteria are; the wall must have an acceptable factor of safety with respect to (1) overturning failure, (2) a sliding (translation) failure, (3) a bearing capacity failure, and (4) a global (deep-seated) slope failure. In addition, (5) the deformation of the wall caused by deflection from earth pressure, and from settlement or heave of the foundation soils or backfill soils, must be within tolerable limits during the functional life of the structure. Report No. 2334-21-03 CMJ ENGINEERING, INC. 16 7.2 Foundations If the retaining walls are sensitive to movements, we recommend they be supported on a deep foundation as previously discussed. If the previously discussed differential movements are acceptable, the retaining wall foundations may be founded atop stiff to hard clayey soils or tan limestone using shallow spread or continuous footings. The retaining wall foundations may be designed for an allowable bearing pressure of 2.0 ksf. A minimum footing dimension of 2 feet is recommended. In addition, the footing should be placed atop natural soils a minimum of 2 feet below lowest adjacent grade and below any existing fill. It should be noted that retaining wall foundations are typically subjected to non-uniform pressure across the foundation, and possibly negative pressure (separation of foundation from soil) under a portion of the foundation, due to the overturning moment induced by the lateral earth pressures. The allowable foundation pressures given above are for the maximum pressure induced by the foundation loads, and not the average pressure under the foundation base. The horizontal bases of the footings will develop resistance to sliding by means of a combination of friction and adhesion (for cohesive foundation materials). Given the nature of the foundation materials, an adhesion of 500 psf may be used for earth formed footings. An ultimate friction factor of 0.3 may be used to calculate sliding resistance of the footings bearing on site soils or limestone. Sliding resistance may be increased in areas where keyways are present beneath the wall footings. The vertical earth-formed sides of keyways will resist lateral forces by developing passive earth pressures. A passive lateral earth pressure coefficient of 2.0 should be used for passive resistance calculations where passive resistance is developed against a vertical earth-formed side of a keyway, based on a soil unit weight of 125 pcf, per foot of footing height. Foundations for the retaining walls designed in accordance with these recommendations will have a minimum factor of safety of 3 with respect to a bearing capacity failure, and should experience a total settlement of 1 inch or less and a differential settlement of ½ inch or less, after construction. It should be anticipated that retaining walls will experience differential movements as a result of moisture induced volume changes in the underlying clays where present, as previously discussed. Report No. 2334-21-03 CMJ ENGINEERING, INC. 17 7.3 Lateral Earth Pressures 7.3.1 General The retaining walls must be designed for lateral pressures including, but not necessarily limited to, earth, water, surcharge, swelling, and vibration. In addition, the lateral pressures will be influenced by whether the backfill is drained or undrained, and above or below the ground-water table. 7.3.2 Equivalent Fluid Pressures Lateral earth pressures on retaining walls will depend on a variety of factors, including the type of soils behind the wall, the condition of the soils, and the drainage conditions behind the wall. Recommended lateral earth pressures expressed as equivalent fluid pressures, per foot of wall height, are presented in Table 7.3.2-1 for a wall with a level backfill behind the top of the wall. The equivalent fluid pressure for an undrained condition should be used if a drainage system is not present to remove water trapped in the backfill and behind the wall. Pressures are provided for at - rest and active earth pressure conditions. In order to allow for an active condition the top of the wall(s) must deflect on the order of 0.4 percent. TABLE 7.3.2-1 – Equivalent Fluid Pressures Backfill Material At-Rest Equivalent Fluid Pressure (pcf) Active Equivalent Fluid Pressure (pcf) Drained Undrained Drained Undrained Excavated on-site clay or clay fill material 100 110 85 100 Select fill or on-site soils meeting material specifications 65 90 50 85 Free draining granular backfill material 50 90 35 80 For the select fill or free draining granular backfill these values assume that a “full” wedge of the material is present behind the wall. The wedge is defined where the wall backfill limits extend outward at least 2 feet from the base of the wall and then upward on a 1H:2V slope. For narrower backfill widths of granular or select fill soils, the equivalent fluid pressures for the on-site soils should be used. Report No. 2334-21-03 CMJ ENGINEERING, INC. 18 7.3.3 Additional Lateral Pressures The location and magnitude of permanent surcharge loads (if present) should be determined, and the additional pressure generated by these loads such as the weight of construction equipment and vehicular loads that are used at the time the structures are being built must also be considered in the design. The effect of this or any other surcharge loading may be accounted for by adding an additional uniform load to the full depth of the side walls equivalent to one-half of the expected vertical surcharge intensity for select backfill materials, or equal to the full vertical surcharge intensity for clay backfill. The equivalent fluid pressures, given here, do not include a safety factor. Analysis of surcharge loads (if any) should be performed on a case-by-case basis. This is not included in the scope of this study. These services can be provided as additional services upon request. 7.4 Wall Backfill Material Requirements Granular Wall Backfill: All free draining granular wall backfill material should be a crushed stone, sand/gravel mixture, or sand/crushed stone mixture. The material should have less than 3 percent passing the No. 200 sieve and less than 30 percent passing the No. 40 sieve. The minus No. 40 sieve material should be non-plastic. Granular wall backfill should not be water jetted during installation. Select Fill Behind Walls: All wall select backfill should consist of clayey sand and/or sandy clay material with a plasticity index of 16 or less, with a liquid limit not exceeding 35. The select fill should be placed in maximum 8-inch lifts and compacted to between 95 and 100 percent of Standard Proctor density (ASTM D 698) within a moisture range of plus to minus 3 percentage points of the optimum moisture. Compaction within five feet of the walls should be accomplished using hand compaction equipment and should be compacted between 90 and 95 percent of the Standard Proctor Density. On-Site Soil Backfill: For wall backfill areas with site-excavated materials or similar imported materials, all oversized fragments larger than four inches in maximum dimension should be removed from the backfill materials prior to placement. The backfill should be free of all organic and deleterious materials, and should be placed in maximum 8-inch compacted lifts at a minimum of 95 percent of Standard Proctor density (ASTM D 698) within a moisture range of plus to minus 3 percentage points of optimum moisture. Compaction within five feet of the walls should be Report No. 2334-21-03 CMJ ENGINEERING, INC. 19 accomplished using hand compaction equipment, and should be between 90 and 95 percent of the Standard Proctor Density. 7.5 Wall Backfill Settlement Settlement of the wall backfill should be anticipated. Piping and conduits through the fill should be designed for potential soil loading due to fill settlement. Floor slabs, sidewalls, and pavements over fills also may settle. Backfill compacted to the density recommended above is anticipated to settle on the order of 0.2 to 0.5 percent of the fill thickness. 7.6 Wall Drainage The design recommendations presented above assume hydrostatic pressure will not develop behind the retaining walls. In order to achieve the “drained” condition for lateral earth pressure for low- permeability walls (concrete, masonry, etc.), a vertical drainage blanket or geocomposite drainage member must be installed adjacent to the wall on the backfill side. Drainage could be provided using a collector pipe or weep holes near the base of the retaining wall. Drains should be properly filtered to minimize the potential for erosion through these drains, and /or the plugging of drain lines. Design or specific recommendations for drainage members is beyond the scope for this study. These services can be provided as an additional service upon request. In order to achieve the “drained” condition, the entire backfill material must be free draining. It is recommended that the backfill-wall geometry be such that the backfill will not become saturated from rainfall, ground water, adjacent water courses, or other sources. 8.0 SEISMIC CONSIDERATIONS Based on the conditions encountered in the borings for the above referenced project the IBC-2015 site classification is TYPE C for seismic evaluation. 9.0 EARTHWORK 9.1 Site Preparation The project site should be stripped of vegetation, roots, old construction debris, and other organic material. It is estimated that the depth of stripping will be on the order of 4 to 6 inches. The actual stripping depth should be based on field observations with particular attention given to old drainage Report No. 2334-21-03 CMJ ENGINEERING, INC. 20 areas, uneven topography, and excessively wet soils. The stripped areas should be observed to determine if additional excavation is required to remove weak or otherwise objectionable materials that would adversely affect the fill placement or other construction activities. The subgrade should be firm and able to support the construction equipment without displacement. Soft or yielding subgrade should be corrected and made stable before construction proceeds. The subgrade should be proof rolled to detect soft spots, which if exist, should be excavated to provide a firm and otherwise suitable subgrade. Proof rolling should be performed using a heavy pneumatic tired roller, loaded dump truck, or similar piece of equipment (minimum 25 tons). The proof rolling operations should be observed by the project geotechnical engineer or his/her representative. 9.2 Placement and Compaction Fill material should be placed in loose lifts not exceeding 8 inches in uncompacted thickness. The uncompacted lift thickness should be reduced to 4 inches for structure backfill zones requiring hand- operated power compactors or small self-propelled compactors. The fill material should be uniform with respect to material type and moisture content. Clods and chunks of material should be broken down and the fill material mixed by disking, blading, or plowing, as necessary, so that a material of uniform moisture and density is obtained for each lift. Water required for sprinkling to bring the fill material to the proper moisture content should be applied evenly through each layer. The on-site soils are suitable for use in general site grading. Imported fill material should be clean soil with a Liquid Limit less than 60 and no rock greater than 4 inches in maximum dimension. The fill materials should be free of vegetation and debris. The fill material should be compacted to a density ranging from 95 to 100 percent of maximum dry density as determined by ASTM D 698, Standard Proctor. In conjunction with the compacting operation, the fill material should be brought to the proper moisture content. The moisture content for general earth fill should range from 2 percentage points below optimum to 5 percentage points above optimum (-2 to +5). These ranges of moisture contents are given as maximum recommended ranges. For some soils and under some conditions, the contractor may have to maintain a more narrow range of moisture content (within the recommended range) in order to consistently achieve the recommended density. Report No. 2334-21-03 CMJ ENGINEERING, INC. 21 Field density tests should be taken as each lift of fill material is placed. As a guide, one field density test per lift for each 5,000 square feet of compacted area is recommended. For small areas or critical areas the frequency of testing may need to be increased to one test per 2,500 square feet. A minimum of 2 tests per lift should be required. The earthwork operations should be observed and tested on a continuing basis by an experienced geotechnician working in conjunction with the project geotechnical engineer. Each lift should be compacted, tested, and approved before another lift is added. The purpose of the field density tests is to provide some indication that uniform and adequate compaction is being obtained. The actual quality of the fill, as compacted, should be the responsibility of the contractor and satisfactory results from the tests should not be considered as a guarantee of the quality of the contractor's filling operations. If fill is to be placed on existing slopes that are steeper than five horizontal to one vertical, then the fill materials should be benched into the existing slopes in such a manner as to provide a good contact between the two materials and allow relatively horizontal lift placement. 9.3 Trench Backfill Trench backfill for pipelines or other utilities should be properly placed and compacted. Overly dense or dry backfill can swell and create a mound along the completed trench line. Loose or wet backfill can settle and form a depression along the completed trench line. Distress to overlying structures, pavements, etc. is likely if heaving or settlement occurs. On-site soil fill material is recommended for trench backfill. Care should be taken not to use free draining granular material, to prevent the backfilled trench from becoming a french drain and piping surface or subsurface water beneath structures, pipelines, or pavements. If a higher class bedding material is required for the pipelines, a lean concrete bedding will limit water intrusion into the trench and will not require compaction after placement. The soil backfill should be placed in approximately 4- to 6-inch loose lifts. The density and moisture content should be as recommended for fill in Section 9.2, Placement and Compaction, of this report. A minimum of one field density test should be taken per lift for each 150 linear feet of trench, with a minimum of 2 tests per lift. Report No. 2334-21-03 CMJ ENGINEERING, INC. 22 9.4 Excavation Based on the exploration borings, major excavations will encounter intact limestone units in select areas. These limestones are generally moderately hard to very hard and will require heavy duty specialized equipment for excavation. These limestones require additional effort to excavate, particularly in narrow utility trenches. Rock teeth on heavy duty trenching equipment are typically required to excavate these limestones. In addition, overexcavation should be anticipated within the limestones. Overexcavation may result from large blocks or chunks breaking along weathered seams or jointed seams beyond the planned excavation. Seasonal water seeps can occur where the tan limestones are approached or exposed by cuts. Subsoil drains may be required in some areas to intercept this seepage. This can be evaluated after grading has been performed. The side slopes of excavations through the overburden soils should be made in such a manner to provide for their stability during construction. Existing structures, pipelines or other facilities, which are constructed prior to or during the currently proposed construction and which require excavation, should be protected from loss of end bearing or lateral support. Temporary construction slopes and/or permanent embankment slopes should be protected from surface runoff water. Site grading should be designed to allow drainage at planned areas where erosion protection is provided, instead of allowing surface water to flow down unprotected slopes. Trench safety recommendations are beyond the scope of this report. The contractor must comply with all applicable safety regulations concerning trench safety and excavations including, but not limited to, OSHA regulations. 9.5 Acceptance of Imported Fill Any soil imported from off-site sources should be tested for compliance with the recommendations for the particular application and approved by the project geotechnical engineer prior to the materials being used. The owner should also require the contractor to obtain a written, notarized certification from the landowner of each proposed off-site soil borrow source stating that to the best of the landowner's knowledge and belief there has never been contamination of the borrow source site with Report No. 2334-21-03 CMJ ENGINEERING, INC. 23 hazardous or toxic materials. The certification should be furnished to the owner prior to proceeding to furnish soils to the site. Soil materials derived from the excavation of underground petroleum storage tanks should not be used as fill on this project. 9.6 Soil Corrosion Potential Specific testing for soil corrosion potential was not included in the scope of this study. However, based upon past experience on other projects in the vicinity, the soils at this site may be corrosive. Standard construction practices for protecting metal pipe and similar facilities in contact with these soils should be used. 9.7 Erosion and Sediment Control All disturbed areas should be protected from erosion and sedimentation during construction, and all permanent slopes and other areas subject to erosion or sedimentation should be provided with permanent erosion and sediment control facilities. All applicable ordinances and codes regarding erosion and sediment control should be followed. 10.0 PAVEMENTS 10.1 Pavement Subgrade Preparation Finished grades near the presently existing grade will consist of moderately to highly plastic clays. These plastic clays are subject to loss in support value with moisture increases which occur beneath pavement sections. They react with hydrated lime, which serves to improve and maintain their support value. Treatment of these soils with hydrated lime will improve their subgrade characteristics to support area paving. Lime treatment is recommended for all subgrade areas. In lieu of a lime stabilized subgrade for pavement consisting of Portland cement concrete, the recommended Portland cement concrete (PCC) pavement thicknesses presented in Section 10.2 may be increased by 2 inches, and placed atop a properly compacted subgrade. Alternatively, in lieu of a lime stabilized subgrade, a flexible base meeting TxDOT Item 247, Type A, Grades 1 or 2 may be utilized on an equal basis and placed atop a properly prepared and compacted Report No. 2334-21-03 CMJ ENGINEERING, INC. 24 subgrade. The option of using a flexible base in lieu of lime stabilizing the subgrade presents a relatively quick, straight forward solution to preparing the subgrade prior to pavement placement. Prior to lime stabilization or compaction, the subgrade should be proofrolled with heavy pneumatic equipment (minimum 15 tons) with particular attention to existing fill areas. Any soft or pumping areas should be undercut to a firm subgrade and properly backfilled as described in the Earthwork section. The subgrade, stabilized or unstabilized, should be scarified to a minimum depth of 6 inches and uniformly compacted to a minimum of 95 percent of Standard Proctor density (ASTM D 698), to minus 2 to plus 4 percentage points of the optimum moisture content determined by that test. It should then be protected and maintained in a moist condition until the pavement is placed. We recommend a minimum of 8 percent hydrated lime be used to modify the clay subgrade soils. The amount of hydrated lime required to stabilize the subgrade should be on the order of 36 pounds per square yard for a 6-inch depth, based on a soil dry unit weight of 100 pcf. The hydrated lime should be thoroughly mixed and blended with the upper 6 inches of the clay subgrade (TxDOT Item 260). The hydrated lime should meet the requirements of Item 260 (Type A) in the Texas Department of Transportation (TxDOT) Standard Specifications for Construction of Highways, Streets and Bridges, 2014 Edition. Lime treatment should extend beyond exposed pavement edges to reduce the effects of shrinkage and associated loss of subgrade support. The presence of gravel, ironstone nodules and calcareous nodules in the surficial soils can complicate mixing of the soil and lime. Limestone fragments in the surficial clays and shallow occurrence of intact limestones can complicate mixing of the soil and lime. Pulverization and compaction equipment often break down the limestone to a material that also benefits from stabilization, although large rock fragments hamper conventional mixing procedures. This can best be evaluated by an on-site inspection after grading is completed. In addition, cuts can expose the limestone. Stabilization of exposed limestone is not necessary. These limestones provide excellent support in an undisturbed condition; however, they are difficult to cut to finished grade and some fill is usually required. Depending on the required grades, it may be advisable to undercut such areas and place either a flexible base material (TxDOT Item 247, Type A, Grades 1 or 2), a material suitable for stabilization, or to place a lime stabilized clay. Again, this can best be evaluated by an on-site inspection after grading is completed. Report No. 2334-21-03 CMJ ENGINEERING, INC. 25 We recommend that subgrade stabilization extend to at least one foot beyond pavement edges to aid in reducing pavement movements and cracking along the curb line due to seasonal moisture variations after construction. Each construction area should be shaped to allow drainage of surface water during earthwork operations, and surface water should be pumped immediately from each construction area after each rain and a firm subgrade condition maintained. Water should not be allowed to pond in order to prevent percolation and subgrade softening, and lime should be added to the subgrade after removal of all surface vegetation and debris. Sand should be specifically prohibited beneath pavement areas, since these more porous soils can allow water inflow, resulting in heave and strength loss of subgrade soils (lime stabilized soil will be allowed for fine grading). After fine grading each area in preparation for paving, the subgrade surface should be lightly moistened, as needed, and recompacted to obtain a tight non-yielding subgrade. Surface drainage is critical to the performance of this pavement. Water should be allowed to exit the pavement surface quickly. All pavement construction should be performed in accordance with the following procedures. 10.2 Pavement Sections The project may include the construction of parking lots and/or drives. At the time of this investigation, site paving plans or vehicle traffic studies were not available. Therefore, several rigid and flexible pavement sections are presented for a 20-year design life based on our experience with similar facilities for Light-Duty Parking Areas, Medium-Duty Parking Areas and Drives, and Medium- to Heavy-Duty Drives. In general, these areas are defined as follows: Light-Duty Parking Areas are those lots and drives subjected almost exclusively to passenger cars, with an occasional light- to medium-duty truck (2 to 3 per week) Medium-Duty Parking Areas and Drives are those lots subjected to a variety of light-duty vehicles to medium-duty vehicles and an occasional heavy-duty truck, including an 85-kip fire apparatus (1 to 2 per week). Medium- to Heavy-Duty Drives are those drives subjected to a variety of light to heavy-duty vehicles. These pavements include areas subject to significant truck traffic or trash vehicles. We recommend that rigid pavements be utilized at this project whenever possible, since they tend to provide better long-term performance when subjected to significant slow moving and turning traffic. Report No. 2334-21-03 CMJ ENGINEERING, INC. 26 If asphaltic concrete pavement is used, we recommend a full depth asphaltic concrete section having a minimum total thickness of 5 inches for light-duty parking areas and drives and 6 inches for medium- duty parking areas. A minimum surface course thickness of 2 inches is recommended for asphaltic concrete pavements. If Portland cement concrete pavement is used, a minimum thickness of 5 inches of concrete is recommended for light-duty parking areas, 6 inches for medium-duty parking areas and drives, and 7 inches for medium to heavy-duty areas. A California Bearing Ratio or other strength tests were not performed because they were not within the scope of our services on this project. A subgrade modulus of 100 psi was considered appropriate for the near-surface soils. If heavier vehicles are planned, the above cross sections can be confirmed by performing strength tests on the subgrade materials once the traffic characteristics are established. Periodic maintenance of pavement structures normally improves the durability of the overall pavement and enhances its expected life. The above sections should be considered minimum pavement thicknesses and higher traffic volumes and heavy trucks may require thicker pavement sections. Additional recommendations can be provided after traffic volumes and loads are known. Periodic maintenance should be anticipated for minimum pavement thickness. This maintenance should consist of sealing cracks and timely repair of isolated distressed areas. 10.3 Pavement Material Requirements Reinforced Portland Cement Concrete: Reinforced Portland cement concrete pavement should consist of Portland cement concrete having a 28-day compressive strength of at least 3,500 psi. The mix should be designed in accordance with the ACI Code 318 using 3 to 6 percent air entrainment. The pavement should be adequately reinforced with temperature steel and all construction joints or expansion/contraction joints should be provided with load transfer dowels. The spacing of the joints will depend primarily on the type of steel used in the pavement. We recommend using No. 3 steel rebar spaced at 18 inches on center in both the longitudinal and transverse direction. Control joints formed by sawing are recommended every 12 to 15 feet in both the longitudinal and transverse Report No. 2334-21-03 CMJ ENGINEERING, INC. 27 direction. The cutting of the joints should be performed as soon as the concrete has “set-up” enough to allow for sawing operations. Hot Mix Asphaltic Concrete Surface Course: Item 340, Type D, Texas Department of Transportation Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges, 2014 Edition. Hot Mix Asphaltic Concrete Base Course: Item 340, Type A or B, Texas Department of Transportation Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges, 2014 Edition. Lime Stabilized Subgrade: Lime treatment for base course (road mix) - Item 260, Texas Department of Transportation Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges, 2014 Edition. Flexible Base: Crushed Stone Flexible Base – Item 247, Type A, Grades 1 or 2, Texas Department of Transportation Standard Specifications for Construction of Maintenance of Highways, Streets, and Bridges, 2014 Edition. 10.4 General Pavement Considerations The design of the pavement drainage and grading should consider the potential for differential ground movement due to future soil swelling on the order of 4½ inches. In order to minimize rainwater infiltration through the pavement surface, and thereby minimizing future upward movement of the pavement slabs, all cracks and joints in the pavement should be sealed on a routine basis after construction. Reduction in potential differential ground movement can be reduced in a similar manner as discussed in Section 5.3. Should reduction levels per Section 5.3 or an intermediate level of movement reduction be desired, contact this office for additional recommendations. 11.0 CONSTRUCTION OBSERVATIONS In any geotechnical investigation, the design recommendations are based on a limited amount of information about the subsurface conditions. In the analysis, the geotechnical engineer must Report No. 2334-21-03 CMJ ENGINEERING, INC. 28 assume the subsurface conditions are similar to the conditions encountered in the borings. However, quite often during construction anomalies in the subsurface conditions are revealed. Should such anomalies be discovered Butler-Cohen, LLC should immediately notify CMJ Engineering, Inc. before proceeding further with construction to allow CMJ Engineering, Inc. to reconsider its recommendations as necessary. It is also recommended that Butler-Cohen, LLC retain CMJ Engineering, Inc. to observe earthwork and foundation installation and perform materials evaluation during the construction phase of the project. This enables the geotechnical engineer to stay abreast of the project and to be readily available to evaluate unanticipated conditions, to conduct additional tests if required and, when necessary, to recommend alternative solutions to unanticipated conditions. Until these construction phase services are performed by the project geotechnical engineer, the recommendations contained in this report on such items as final foundation bearing elevations, proper soil moisture condition, and other such subsurface related recommendations shall only be considered as preliminary, and not final, recommendations. It is proposed that construction phase observation and materials testing commence by the project geotechnical engineer at the outset of the project. Experience has shown that the most suitable method for procuring these services is for the owner or the owner's design engineers to contract directly with the project geotechnical engineer. This results in a clear, direct line of communication between the owner and the owner's design engineers and the geotechnical engineer. 12.0 REPORT CLOSURE The boring logs shown in this report contain information related to the types of soil encountered at specific locations and times and show lines delineating the interface between these materials. The logs also contain our field representative's interpretation of conditions that are believed to exist in those depth intervals between the actual samples taken. Therefore, these boring logs contain both factual and interpretive information. Laboratory soil classification tests were also performed on samples from selected depths in the borings. The results of these tests, along with visual-manual procedures were used to generally classify each stratum. Therefore, it should be understood that the classification data on the logs of borings represent visual estimates of classifications for those portions of each stratum on which the full range of laboratory soil classification tests were not performed. It is not implied that these logs are representative of subsurface conditions at other locations and times. Report No. 2334-21-03 CMJ ENGINEERING, INC. 29 With regard to ground water conditions, this report presents data on ground water levels as they were observed during the course of the field work. In particular, water level readings have been made in the borings at the times and under conditions stated in the text of the report and on the boring logs. It should be noted that fluctuations in the level of the ground-water table can occur with passage of time due to variations in rainfall, temperature and other factors. Also, this report does not include quantitative information on rates of flow of ground water into excavations, on pumping capacities necessary to dewater the excavations, or on methods of dewatering excavations. Unanticipated soil conditions at a construction site are commonly encountered and cannot be fully predicted by mere soil samples, test borings or test pits. Such unexpected conditions frequently require that additional expenditures be made by the owner to attain a properly designed and constructed project. Therefore, provision for some contingency fund is recommended to accommodate such potential extra cost. The analyses, conclusions and recommendations contained in this report are based on site conditions as they existed at the time of our field investigation and further on the assumption that the exploratory borings are representative of the subsurface conditions throughout the site; that is, the subsurface conditions everywhere are not significantly different from those disclosed by the borings at the time they were completed. If, during construction, different subsurface conditions from those encountered in our borings are observed, or appear to be present in excavations, we must be advised promptly so that we can review these conditions and reconsider our recommendations where necessary. If there is a substantial lapse of time between submission of this report and the start of the work at the site (more than twelve months is considered a substantial lapse of time; however, depending on the circumstances, less than six months may be considered a substantial lapse of time), if conditions have changed due either to natural causes or to construction operations at or adjacent to the site, or if structure locations, structural loads or finish grades are changed, we urge that we be promptly informed and retained to review our report to determine the applicability of the conclusions and recommendations, considering the changed conditions and/or time lapse. In this regard, if (a) construction at the site does not start within twelve months of the date of this report and (b) CMJ Engineering, Inc. is not present at the site when construction starts to confirm that conditions have not changed since the date of this report, the information in this report cannot be relied upon or used for any purpose. Report No. 2334-21-03 CMJ ENGINEERING, INC. 30 Further, it is urged that CMJ Engineering, Inc. be retained to review those portions of the plans and specifications for this particular project that pertain to earthwork and foundations as a means to determine whether the plans and specifications are consistent with the recommendations contained in this report. In addition, we are available to observe construction, particularly the compaction of structural fill, or backfill and the construction of foundations as recommended in the report, and such other field observations as might be necessary. The scope of our services did not include any environmental assessment or investigation for the presence or absence of wetlands or hazardous or toxic materials in the soil, surface water, ground water or air, on or below or around the site. This report has been prepared for use in developing an overall design concept. Paragraphs, statements, test results, boring logs, diagrams, etc. should not be taken out of context, nor utilized without a knowledge and awareness of their intent within the overall concept of this report. The reproduction of this report, or any part thereof, supplied to persons other than the owner, should indicate that this study was made for design purposes only and that verification of the subsurface conditions for purposes of determining difficulty of excavation, trafficability, etc. are responsibilities of the contractor. This report has been prepared for the exclusive use of Butler-Cohen, LLC and their consultants for specific application to design of this project only, and not for additions or modifications to the project. The only warranty made by us in connection with the services provided is that we have used that degree of care and skill ordinarily exercised under similar conditions by reputable members of our profession practicing in the same or similar locality. No other warranty, expressed or implied, is made or intended. * * * * 0 50 100 FEET APPROXIMATE SCALE PLAN OF BORINGS Bolt Campus Fort Worth, Texas A.1 Plate CMJ Project No. 2334-21-03 Trinity Basin Preparatory B-2 LEGEND: Approximate Site Boundary Boring Location B-1 B-4 B-5 B-3 B-6 B-7 EAST DREW STREET EAST MASON STREETEAST MAY STREETWEST BOLT STREET SECURED PLAY FIELD PROPOSED TRINITY BASIN PREPARATORY SCHOOL PROPOSED PARKING Fine-grained soils (More than half of material is smaller than No. 200 sieve)Sands (More than half of coarse fraction is smaller than No. 4 sieve size)Gravels (More than half of coarse fraction is larger than No. 4 sieve size)Sands with fines (Appreciable amount of fines)Clean sands (Little or no fines)Gravels with fines (Appreciable amount of fines)Clean gravels (Little or no fines)Pt OH CH MH OL CL ML SC SM SP SW GC GM GP GW Grp. Sym. Peat and other highly organic soils Organic clays of medium to high plasticity, organic silts Inorganic clays of high plasticity, fat clays Inorganic silts, micaceous or diatomaceous fine sandy or silty soils, elastic silts Organic silts and organic silty clays of low plasticity Inorganic clays of low to medium plasticity, gravelly clays, sandy clays, silty clays, and lean clays Inorganic silts and very fine sands, rock flour, silty or clayey fine sands, or clayey silts with slight plasticity Clayey sands, sand-clay mixtures Silty sands, sand-silt mixtures Poorly graded sands; gravelly sands, little or no fines Well-graded sands, gravelly sands, little or no fines Clayey gravels, gravel-sand- clay mixtures Silty gravels, gravel-sand-silt mixtures Poorly graded gravels, gravel- sand mixtures, little or no fines Well-graded gravels, gravel- sand mixtures, little or no fines Typical Names Determine percentages of sand and gravel from grain size curve. Less than 5 percent.....................................................GW, GP, SW, SP More than 12 percent....................................................GM, GC, SM, SC 5 to 12 percent...........................Borderline cases requiring dual symbolsLiquid and Plastic limits above "A" line with P.I. greater than 7 Liquid and Plastic limits below "A" line or P.I. less than 4 Not meeting all gradation Liquid and Plastic limits above "A" line with P.I. greater than 7 Liquid and Plastic limits below "A" line or P.I. greater than 4 Not meeting all gradation PLATE A.2 requirements for SW requirements for GW UNIFIED SOIL CLASSIFICATION SYSTEMCoarse-grained soils (more than half of the material is larger than No. 200 sieve size)Depending on percentage of fines (fraction smaller than No. 200 sieve size), coarse-grained soils are classified as follows:Laboratory Classification Criteria Highly Organic soilsSilts and clays (Liquid limit greater than 50)Silts and clays (Liquid limit less than 50)Liquid and plastic limits plotting between 4 and 7 are borderline cases requiring use of dual symbols Liquid and plastic limits plotting in hatched zone between 4 and 7 are borderline cases requiring use of dual symbols Major Divisions 0 10 20 30 40 50 60 70 80 90 1000 10 20 30 40 50 60 CL-ML4 7 CL CH OH and MH ML and OL Liquid Limit Plasticity ChartPlasticity IndexCu= ----- D60 D10 greater than 6:CC= -------------- (D30)2 D10 x D60 between 1 and 3 Cu= ----- D60 D10 greater than 4:CC= -------------- (D30)2 D10 x D60 between 1 and 3 SOIL OR ROCK TYPES GRAVEL LEAN CLAY LIMESTONE SAND SANDY SHALE SILT SILTY SANDSTONE HIGHLY PLASTIC CLAY CLAYEY CONGLOMERATE Shelby Tube Auger Split Spoon Rock Core Cone Pen No Recovery TERMS DESCRIBING CONSISTENCY, CONDITION, AND STRUCTURE OF SOIL Fine Grained Soils (More than 50% Passing No. 200 Sieve) Descriptive Item Penetrometer Reading, (tsf) Soft 0.0 to 1.0 Firm 1.0 to 1.5 Stiff 1.5 to 3.0 Very Stiff 3.0 to 4.5 Hard 4.5+ Coarse Grained Soils (More than 50% Retained on No. 200 Sieve) Penetration Resistance Descriptive Item Relative Density (blows/foot) 0 to 4 Very Loose 0 to 20% 4 to 10 Loose 20 to 40% 10 to 30 Medium Dense 40 to 70% 30 to 50 Dense 70 to 90% Over 50 Very Dense 90 to 100% Soil Structure Calcareous Contains appreciable deposits of calcium carbonate; generally nodular Slickensided Having inclined planes of weakness that are slick and glossy in appearance Laminated Composed of thin layers of varying color or texture Fissured Containing cracks, sometimes filled with fine sand or silt Interbedded Composed of alternate layers of different soil types, usually in approximately equal proportions TERMS DESCRIBING PHYSICAL PROPERTIES OF ROCK Hardness and Degree of Cementation Very Soft or Plastic Can be remolded in hand; corresponds in consistency up to very stiff in soils Soft Can be scratched with fingernail Moderately Hard Can be scratched easily with knife; cannot be scratched with fingernail Hard Difficult to scratch with knife Very Hard Cannot be scratched with knife Poorly Cemented or Friable Easily crumbled Cemented Bound together by chemically precipitated material; Quartz, calcite, dolomite, siderite, and iron oxide are common cementing materials. Degree of Weathering Unweathered Rock in its natural state before being exposed to atmospheric agents Slightly Weathered Noted predominantly by color change with no disintegrated zones Weathered Complete color change with zones of slightly decomposed rock Extremely Weathered Complete color change with consistency, texture, and general appearance approaching soil KEY TO CLASSIFICATION AND SYMBOLS PLATE A.3 64 43 22 10 2.25 100/1.5" 100/1.25" 100/1" 100/3.25" 100/3" 21CLAY, dark brown, w/ gravel, iron stains, and ironstone nodules, stiff (FILL) LIMESTONE, tan, weathered, hard SILTY CLAY, tan, w/ tan limestone layers LIMESTONE, gray, hard to very hard - w/ shale seams, moderately hard below 19' SHALE, gray, moderately hard REC %PlasticityIndexBoring No. Location Stratum DescriptionDepth, Ft.CMJ 2334-21-03 Water Observations Type SamplesLOG OF BORING NO. B-1 CME-55 w/ CFA 4-15-21 RQD %Blows/Ft. orPen Reading,T.S.F.Passing No 200Sieve, %LiquidLimit, %PlasticLimit, %MoistureContent, %Unit Dry Wt.Lbs./Cu. Ft.UnconfinedCompressionPounds/Sq. Ft.Project No. Project Completion Depth Completion Date Surface Elevation SymbolPLATE A.4 Trinity Basin Prep - Bolt Campus Fort Worth, TX Dry during drilling; dry at completionSee Plate A.1 25.0' B-1 5 10 15 20 25 ENGINEERING INC.LOG OF BORING 2334-21-03.GPJ CMJ.GDT 5/6/21 52 75 36 34 57 20 14 23 31 31 31 30 23 20 32 20 91 93 109 2930 4.5+ 4.0 2.75 2.0 2.5 1.75 1.25 4.0 1.5 4.5+ 100/4.25" 100/3.5" 18 18 16 CLAY, dark brown and brown, w/ iron stains, ironstone nodules, and gravel, stiff to hard (FILL) - w/ light reddish brown below 2' CLAY, dark brown, w/ calcareous nodules and gravel, stiff - w/ ironstone nodules below 7' SILTY CLAY, light brown, w/ calcareous nodules, calcareous deposits, iron stains, and ironstone nodules, firm to very stiff - w/ olive brown below 19' CLAYEY SHALE, gray, w/ calcareous nodules, soft SHALE, gray, moderately hard REC %PlasticityIndexBoring No. Location Stratum DescriptionDepth, Ft.CMJ 2334-21-03 Water Observations Type SamplesLOG OF BORING NO. B-2 CME-55 w/ CFA 4-15-21 RQD %Blows/Ft. orPen Reading,T.S.F.Passing No 200Sieve, %LiquidLimit, %PlasticLimit, %MoistureContent, %Unit Dry Wt.Lbs./Cu. Ft.UnconfinedCompressionPounds/Sq. Ft.Project No. Project Completion Depth Completion Date Surface Elevation SymbolPLATE A.5 Trinity Basin Prep - Bolt Campus Fort Worth, TX Seepage at 9' during drilling; water at 21' at completion; water at 12' at end of day See Plate A.1 35.0' B-2 5 10 15 20 25 30 35 ENGINEERING INC.LOG OF BORING 2334-21-03.GPJ CMJ.GDT 5/6/21 74 37 49 22 29 28 11 2.0 2.5 100/3" 100/1.75" 100/1" 100/2.25" 100/2.625" 25 15 CLAY, dark brown and brown, w/ calcareous nodules, and gravel, stiff LIMESTONE, tan, w/ clay seams, moderately hard - hard to very hard below 9' SHALE, gray LIMESTONE, gray, w/ shale seams, moderately hard REC %PlasticityIndexBoring No. Location Stratum DescriptionDepth, Ft.CMJ 2334-21-03 Water Observations Type SamplesLOG OF BORING NO. B-3 CME-55 w/ CFA 4-15-21 RQD %Blows/Ft. orPen Reading,T.S.F.Passing No 200Sieve, %LiquidLimit, %PlasticLimit, %MoistureContent, %Unit Dry Wt.Lbs./Cu. Ft.UnconfinedCompressionPounds/Sq. Ft.Project No. Project Completion Depth Completion Date Surface Elevation SymbolPLATE A.6 Trinity Basin Prep - Bolt Campus Fort Worth, TX Dry during drilling; dry at completionSee Plate A.1 25.0' B-3 5 10 15 20 25 ENGINEERING INC.LOG OF BORING 2334-21-03.GPJ CMJ.GDT 5/6/21 20 18 382.0 CRUSHED ASPHALT, 2 feet thick CLAY, dark brown, w/ calcareous nodules, stiff REC %PlasticityIndexBoring No. Location Stratum DescriptionDepth, Ft.CMJ 2334-21-03 Water Observations Type SamplesLOG OF BORING NO. B-4 CME-55 w/ CFA 4-15-21 RQD %Blows/Ft. orPen Reading,T.S.F.Passing No 200Sieve, %LiquidLimit, %PlasticLimit, %MoistureContent, %Unit Dry Wt.Lbs./Cu. Ft.UnconfinedCompressionPounds/Sq. Ft.Project No. Project Completion Depth Completion Date Surface Elevation SymbolPLATE A.7 Trinity Basin Prep - Bolt Campus Fort Worth, TX Dry during drilling; dry at completionSee Plate A.1 5.0' B-4 5 ENGINEERING INC.LOG OF BORING 2334-21-03.GPJ CMJ.GDT 5/6/21 81 52 37 30 23 95 31501.5 2.75 100/1.75" 29CLAY, dark brown, w/ calcareous nodules, ironstone nodules, gravel, and asphalt fragments, stiff to hard (FILL) LIMESTONE, tan, weathered, hard REC %PlasticityIndexBoring No. Location Stratum DescriptionDepth, Ft.CMJ 2334-21-03 Water Observations Type SamplesLOG OF BORING NO. B-5 CME-55 w/ CFA 4-15-21 RQD %Blows/Ft. orPen Reading,T.S.F.Passing No 200Sieve, %LiquidLimit, %PlasticLimit, %MoistureContent, %Unit Dry Wt.Lbs./Cu. Ft.UnconfinedCompressionPounds/Sq. Ft.Project No. Project Completion Depth Completion Date Surface Elevation SymbolPLATE A.8 Trinity Basin Prep - Bolt Campus Fort Worth, TX Dry during drilling; dry at completionSee Plate A.1 5.0' B-5 5 ENGINEERING INC.LOG OF BORING 2334-21-03.GPJ CMJ.GDT 5/6/21 24 34 36 35 85 2970 2.0 1.5 1.75 2.25 2.0 CLAY/SILTY CLAY, dark brown, w/ calcareous nodules and gravel, stiff REC %PlasticityIndexBoring No. Location Stratum DescriptionDepth, Ft.CMJ 2334-21-03 Water Observations Type SamplesLOG OF BORING NO. B-6 CME-55 w/ CFA 4-15-21 RQD %Blows/Ft. orPen Reading,T.S.F.Passing No 200Sieve, %LiquidLimit, %PlasticLimit, %MoistureContent, %Unit Dry Wt.Lbs./Cu. Ft.UnconfinedCompressionPounds/Sq. Ft.Project No. Project Completion Depth Completion Date Surface Elevation SymbolPLATE A.9 Trinity Basin Prep - Bolt Campus Fort Worth, TX Dry during drilling; dry at completionSee Plate A.1 5.0' B-6 5 ENGINEERING INC.LOG OF BORING 2334-21-03.GPJ CMJ.GDT 5/6/21 44 27 20 33 30 99 38203.75 2.75 3.5 4.5+ 17 ASPHALT, 4 inches thick SAND BASE, 6 inches thick SILTY CLAY, dark brown, w/ calcareous nodules and gravel, stiff to very stiff - FILL above 2' - w/ fractured limestone seams, hard below 4'REC %PlasticityIndexBoring No. Location Stratum DescriptionDepth, Ft.CMJ 2334-21-03 Water Observations Type SamplesLOG OF BORING NO. B-7 CME-55 w/ CFA 4-15-21 RQD %Blows/Ft. orPen Reading,T.S.F.Passing No 200Sieve, %LiquidLimit, %PlasticLimit, %MoistureContent, %Unit Dry Wt.Lbs./Cu. Ft.UnconfinedCompressionPounds/Sq. Ft.Project No. Project Completion Depth Completion Date Surface Elevation SymbolPLATE A.10 Trinity Basin Prep - Bolt Campus Fort Worth, TX Dry during drilling; dry at completionSee Plate A.1 5.0' B-7 5 ENGINEERING INC.LOG OF BORING 2334-21-03.GPJ CMJ.GDT 5/6/21 FREE SWELL TEST RESULTS Project: Trinity Basin Prep – Bolt Campus Fort Worth, Texas Project No.: 2334-21-03 Boring No. Depth Interval (ft.) Sample Description Liquid Limit LL Plastic Limit PL Plasticity Index PI Moisture Content % Percent Swell (%) Initial Final B-2 7 – 8 Clay 75 18 57 30.0 31.0 0.4 B-2 14 – 15 Silty Clay 36 16 20 19.6 20.9 0.0 Free swell tests performed at approximate overburden pressure CMJ ENGINEERING, INC. PLATE A.11 CITY OF FORT WORTH Trinity Basin Preparatory - Bolt STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN 103537 Revised July 27, 2021 GR-01 60 00 Product Requirements THIS PAGE LEFT INTENTIONALLY BLANK Approval Spec No.Classsification Manufacturer Model No.National Spec Size Storm Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 03/19/2021) 9/28/2018 33 05 13 Manhole Frames and Covers AccuCast (Govind Steel Company, LTD)MHRC #220605 ASTM A48 AASHTO M306 **24" Dia 9/28/2018 33 05 13 Manhole Cover Neenah Foundry NF-1274-T91 ASTM A48 AASHTO M306 32" Dia 9/28/2018 33 05 13 Manhole Frames and Covers Neenah Foundry NF-1743-LM (Hinged)ASTM A48 AASHTO M306 32" Dia 9/28/2018 33 05 13 Manhole Frame Neenah Foundry NF-1930-30 ASTM A48 AASHTO M306 32.25" Dia 9/28/2018 33 05 13 Manhole Frames and Covers Neenah Foundry R-1743-HV ASTM A48 AASHTO M306 32" Dia 4/3/2019 33 05 13 Manhole Frames and Covers SIP Industries ++2279ST ASTM A48 AASHTO M306 **24" Dia 4/3/2019 33 05 13 Manhole Frames and Covers SIP Industries ++2280ST ASTM A48 AASHTO M306 32" Dia 10/8/2020 33 05 13 Manhole Frames and Covers EJ ( Formally East Jordan Iron Works)EJ1033 Z2/A ASTM A536 AASHTO M306 32.25" Dia CITY OF FORT WORTH TRANSPORTATION & PUBLIC WORKS DEPARTMENT STORMWATER MANAGEMENT DIVISION STANDARD PRODUCT LIST **Note: All new development and new installation mahnole lids shall meet the minimum 30-inch opening requirement as specified in City Specification 33 05 13. Any smaller opening sizes will only be allowed for existing manholes that require replacement frames and covers. Updated: 03/19/2021 * From Original Standard Products List Approval Spec No.Classsification Manufacturer Model No.National Spec Size Storm Sewer - Inlet & Structures 33-05-13 (Rev 03/19/2021) 10/08/20 33 49 20 Curb Inlets Forterrra FRT-10x3-405-PRECAST ASTM C913 10' X 3' 10/08/20 33 49 20 Curb Inlets Forterrra FRT-10x3-406-PRECAST ASTM C913 10' X 3' 10/08/20 33 49 20 Curb Inlets Forterrra FRT-10x4.5-407-PRECAST ASTM C913 10' X 4.5' 10/08/20 33 49 20 Curb Inlets Forterrra FRT-10x4.5-420-PRECAST ASTM C913 10' X 4.5' 10/08/20 33 39 20 Manhole Forterrra FRT-4X4-409-PRECAST-TOP ASTM C913 4' X 4' 10/08/20 33 39 20 Manhole Forterrra FRT-4X4-409-PRECAST-BASE ASTM C913 4' X 4' 10/08/20 33 39 20 Manhole Forterrra FRT-5X5-410-PRECAST-TOP ASTM C913 5' X 5' 10/08/20 33 39 20 Manhole Forterrra FRT-5X5-410-PRECAST-BASE ASTM C913 5' X 5' 10/08/20 33 39 20 Manhole Forterrra FRT-6X6-411-PRECAST-TOP ASTM C913 6' X 6' 10/08/20 33 39 20 Manhole Forterrra FRT-6X6-411-PRECAST-BASE ASTM C913 6' X 6' 3/19/2021 33 49 20 Curb Inlets Thompson Pipe Group TPG-10X3-405-PRECAST INLET ASTM 615 10' X 3' 3/19/2021 33 49 20 Curb Inlets Thompson Pipe Group TPG-15X3-405-PRECAST INLET ASTM 615 15' x 3' 3/19/2021 33 49 20 Curb Inlets Thompson Pipe Group TPG-20X3-405-PRECAST INLET ASTM 615 20' x 3' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-4X4-409-PRECAST TOP ASTM 615 4' X 4' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-4X4-409-PRECAST BASE ASTM 615 4' X 4' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-4X4-412-PRECAST 4-FT RISER ASTM 615 4' X 4' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-5X5-410-PRECAST TOP ASTM 615 5' X 5' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-5X5-410-PRECAST BASE ASTM 615 5' X 5' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-5X5-412-PRECAST 5-FT RISER ASTM 615 5' X 5' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-6X6-411-PRECAST TOP ASTM 615 6' X 6' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-6X6-411-PRECAST BASE ASTM 615 6' X 6' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-6X6-412-PRECAST 6-FT RISER ASTM 615 6' X 6' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-7X7-411-PRECAST TOP ASTM 615 7' X 7' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-7X7-411-PRECAST BASE ASTM 615 7' X 7' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-7X7-412-PRECAST 4-FT RISER ASTM 615 7' X 7' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-8X8-411-PRECAST TOP ASTM 615 8' X 8' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-8X8-411-PRECAST BASE ASTM 615 8' X 8' 3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-8X8-412-PRECAST 5-FT RISER ASTM 615 8' X 8' 3/19/2021 33 49 20 Drop Inlet Thompson Pipe Group TPG-4X4-408-PRECAST INLET ASTM 615 4' X 4' 3/19/2021 33 49 20 Drop Inlet Thompson Pipe Group TPG-5X5-408-PRECAST INLET ASTM 615 5' X 5' 3/19/2021 33 49 20 Drop Inlet Thompson Pipe Group TPG-6X6-408-PRECAST INLET ASTM 615 6' X 6' CITY OF FORT WORTH TRANSPORTATION & PUBLIC WORKS DEPARTMENT STORMWATER MANAGEMENT DIVISION STANDARD PRODUCT LIST Updated: 03/19/21 * From Original Standard Products List Approval Spec No. Classsification Manufacturer Model No. National Spec SizeStorm Sewer - Pipes 33-05-13 (Rev 03/19/21)4/9/2021 33 41 13 Storm Drain Pipes Advanced Drainage Systems, Inc. (ADS) ADS HP Storm Polypropylene (PP) Pipe ASTM F2881 & AASHTO M33012" - 60" CITY OF FORT WORTHTRANSPORTATION & PUBLIC WORKS DEPARTMENT STORMWATER MANAGEMENT DIVISION STANDARD PRODUCT LISTUpdated: 04/14/21 CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Updated: April 09, 2021 The Fort Worth Water Department’s Standard Products List has been developed to minimize the submittal review of products which meet the Fort Worth Water Department’s Standard Specifications during utility construction projects. When Technical Specifications for specific products, are included as part of the Construction Contract Documents, the requirements of the Technical Specification will override the Fort Worth Water Department’s Standard Specifications and the Fort Worth Water Department’s Standard Products List and approval of the specific products will be based on the requirements of the Technical Specification whether or not the specific product meets the Fort Worth Water Department’s Standard Specifications or is on the Fort Worth Water Department’s Standard Products List. Table of Content (Click on items to go directly to the page) Items Page A.Water & Sewer 1. Manholes & Bases/Components ........................................................... 1 2.Manholes & Bases/Fiberglass ............................................................... 2 3.Manholes & Bases/Frames & Covers/Rectangular ............................... 3 4.Manholes & Bases/Frames & Covers/Round ....................................... 4 5.Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight .. 5 6.Manholes & Bases/Precast Concrete .................................................... 6 7.Manholes & Bases/Rehab Systems/Cementitious ................................ 7 8.Manholes & Bases/Rehab Systems/NonCementitious ......................... 8 9.Manhole Insert (Field Operations Use Only) ........................................ 9 10. Pipe Casing Spacer ............................................................................... 10 11. Pipes/Ductile Iron ................................................................................. 11 12. Utility Line Marker ............................................................................... 12 B.Sewer 13. Coatings/Epoxy ..................................................................................... 13 14. Coatings/Polyurethane .......................................................................... 14 15. Combination Air Valves ....................................................................... 15 16. Pipes/Concrete ...................................................................................... 16 17. Pipe Enlargement System (Method) ..................................................... 17 18. Pipes/Fiberglass Reinforced Pipe ......................................................... 18 19. Pipes/HDPE .......................................................................................... 19 20. Pipes/PVC (Pressure Sewer) ................................................................. 20 21. Pipes/PVC* ........................................................................................... 21 22. Pipes/Rehab/CIPP ................................................................................. 22 23. Pipes/Rehab/Fold & Form .................................................................... 23 24. Pipes/Open Profile Large Diameter ...................................................... 24 C.Water 25. Appurtenances ....................................................................................... 25 26. Bolts, Nuts, and Gaskets ....................................................................... 26 27. Combination Air Release Valve ........................................................... 27 28. Dry Barrel Fire Hydrants ...................................................................... 28 29. Meters ................................................................................................... 29 30. Pipes/PVC (Pressure Water) ................................................................. 30 31. Pipes/Valves & Fittings/Ductile Iron Fittings ....................................... 31 32. Pipes/Valves & Fittings/Resilient Seated Gate Valve .......................... 32 33. Pipes/Valves & Fittings/Rubber Seated Butterfly Valve ...................... 33 34. Polyethylene Encasement ..................................................................... 34 35. Sampling Stations ................................................................................. 35 36. Automatic Flusher ................................................................................. 36 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeWater & Sewer - Manholes & Bases/Components 33-39-10 (Rev 2/3/16)07/23/97 33 05 13 Urethane Hydrophilic WaterstopAsahi Kogyo K.K.Adeka Ultra-Seal P-201ASTM D2240/D412/D79204/26/00 33 05 13 Offset Joint for 4' Diam. MHHanson Concrete ProductsDrawing No. 35-0048-00104/26/00 33 05 13 Profile Gasket for 4' Diam. MH.Press-Seal Gasket Corp.250-4G GasketASTM C-443/C-361SS MH1/26/99 33 05 13 HDPE Manhole Adjustment RingsLadtech, IncHDPE Adjustment RingNon-traffic area5/13/05 33 05 13 Manhole External WrapCanusa - CPSWrapidSeal Manhole Encapsulation SystemCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.* From Original Standard Products ListClick to Return to the Table of Content1Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Fiberglass 33-39-13 (1/8/13)1/26/99 33 39 13 Fiberglass ManholeFluid Containment, Inc.FlowtiteASTM 3753Non-traffic area08/30/06 33 39 13 Fiberglass ManholeL.F. ManufacturingNon-traffic area* From Original Standard Products ListClick to Return to the Table of Content2Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Frames & Covers/Rectangular 33-05-13 (Rev 2/3/16)*33 05 13 Manhole Frames and CoversWestern Iron Works, Bass & Hays Foundry100124"x40" WD* From Original Standard Products ListClick to Return to the Table of Content3Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 2/3/16)*33 05 13 Manhole Frames and CoversWestern Iron Works, Bass & Hays Foundry3002424" Dia.*33 05 13 Manhole Frames and CoversMcKinley Iron Works Inc.A 24 AM24" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR-1272ASTM A48 & AASHTO M30624" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR- 165-LM (Hinged)ASTM A48 & AASHTO M30624" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryNF 1274ASTM A48 & AASHTO M30630" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR-1743-LM (Hinged)ASTM A48 & AASHTO M30630" dia.33 05 13 Manhole Frames and CoversSigma CorporationMH-144N33 05 13 Manhole Frames and CoversSigma CorporationMH-143N33 05 13 Manhole Frames and CoversPont-A-MoussonGTS-STD24" dia.33 05 13 Manhole Frames and CoversNeenah Casting24" dia.10/31/06 33 05 13 Manhole Frames and Covers (Hinged)PowersealHinged Ductile Iron Manhole ASTM A53624" Dia.7/25/03 33 05 13 Manhole Frames and CoversSaint-Gobain Pipelines (Pamrex/rexus)RE32-R8FS30" Dia.01/31/06 33 05 13 30" Dia. MH Ring and CoverEast Jordan Iron WorksV1432-2 and V1483 DesignsAASHTO M306-0430" Dia.11/02/10 33 05 13 30" Dia. MH Ring and CoverSigma CorporationMH1651FWN & MH1650230" Dia07/19/11 33 05 13 30" Dia. MH Ring and CoverStar Pipe ProductsMH32FTWSS-DC 30" Dia08/10/11 33 05 13 30" Dia. MH Ring and CoverAccucast220700 Heavy Duty with Gasket Ring30" Dia10/14/13 33 05 13 30" Dia. MH Ring and Cover (Hinged & Lockable)East Jordan Iron Works 30" ERGO XL Assembly with Cam Lock/MPIC/T-Gasket ASSHTO M105 & ASTM A53630" Dia06/01/17 34 05 13 30" Dia. MH Ring and Cover (Hinged & Lockable) CISIP Industries2280 (32")ASTM A 4830" Dia.09/16/19 33 05 13.10 30" Dia. MH Ring and Cover Composite Access Products, L.P.CAP-ONE-30-FTW, Composite, w/ Lock w/o Hing30" Dia.* From Original Standard Products ListClick to Return to the Table of Content4Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16)*33 05 13 Manhole Frames and CoversPont-A-MoussonPamtight24" Dia.*33 05 13 Manhole Frames and CoversNeenah Casting24" Dia.*33 05 13 Manhole Frames and CoversWestern Iron Works,Bass & Hays Foundry300-24P24" Dia.*33 05 13 Manhole Frames and CoversMcKinley Iron Works Inc.WPA24AM24" Dia.03/08/00 33 05 13 Manhole Frames and CoversAccucastRC-2100ASTM A 4824" Dia.04/20/01 33 05 13 Manhole Frames and Covers(SIP)Serampore Industries Private Ltd.300-24-23.75 Ring and CoverASTM A 4824" Dia.* From Original Standard Products ListClick to Return to the Table of Content5Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Precast Concrete (Rev 1/8/13)*33 39 10 Manhole, Precast ConcreteHydro Conduit CorpSPL Item #49ASTM C 47848"*33 39 10 Manhole, Precast ConcreteWall Concrete Pipe Co. Inc.ASTM C-44348"09/23/96 33 39 10 Manhole, Precast ConcreteConcrete Product Inc.48" I.D. Manhole w/ 32" ConeASTM C 47848" w/32" cone05/08/18 33 39 10 Manhole, Precast ConcreteThe Turner Company48", 60" I.D. Manhole w/ 32" ConeASTM C 47848", 60"10/27/06 33 39 10 Manhole, Precast ConcreteOldcastle Precast Inc.48" I.D. Manhole w/ 24" ConeASTM C 47848" Diam w 24" Ring06/09/10 33 39 10 Manhole, Precast (Reinforce Polymer)ConcreteUS Composite PipeReinforced Polymer Concrete ASTM C-7648" to 72"09/06/19 33 39 20 Manhole, Precast ConcreteForterra Pipe and Precast60" & 72" I.D. Manhole w/32" ConeASTM C-7660" & 72"* From Original Standard Products ListClick to Return to the Table of Content6Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Rehab Systems/Cementitious*E1-14 Manhole Rehab SystemsQuadex04/23/01E1-14 Manhole Rehab SystemsStandard Cement Materials, Inc.Reliner MSPE1-14 Manhole Rehab SystemsAP/M Permaform4/20/01E1-14 Manhole Rehab SystemStrong CompanyStrong Seal MS2A Rehab System5/12/03E1-14 Manhole Rehab System (Liner)Poly-triplex TechnologiesMH repair product to stop infiltrationASTM D581308/30/06General Concrete RepairFlexKrete TechnologiesVinyl Polyester Repair ProductMisc. Use* From Original Standard Products ListClick to Return to the Table of Content7Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Rehab Systems/NonCementitious05/20/96E1-14 Manhole Rehab SystemsSprayroq, Spray Wall Polyurethane CoatingASTM D639/D790*E1-14 Manhole Rehab SystemsSun Coast12/14/01Coating for Corrosion protection(Exterior)ERTECHSeries 20230 and 2100 (Asphatic Emulsion)For Exterior Coating of Concrete Structures Only01/31/06Coatings for Corrosion ProtectionChestertonArc 791, S1HB, S1, S2Acid Resistance TestSewer Applications8/28/2006Coatings for Corrosion ProtectionWarren EnvironmentalS-301 and M-301Sewer Applications08/30/06Coatings for Corrosion ProtectionCitadelSLS-30 Solids EpoxySewer Applications03/19/1833 05 16, 33 39 10, 33 39 20 Coating for Corrosion protection(Exterior)Sherwin WilliamsRR&C Dampproofing Non-Fibered Spray Grade (Asphatic Emulsion)For Exterior Coating of Concrete Structures Only* From Original Standard Products ListClick to Return to the Table of Content8Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manhole Inserts - Field Operations Use Only (Rev 2/3/16)*33 05 13 Manhole InsertKnutson EnterprisesMade to Order - PlasticASTM D 1248For 24" dia.*33 05 13 Manhole InsertSouth Western PackagingMade to Order - PlasticASTM D 1248For 24" dia.*33 05 13 Manhole InsertNoflow-InflowMade to Order - PlasticASTM D 1248For 24" dia.09/23/96 33 05 13 Manhole InsertSouthwestern Packing & Seals, Inc.LifeSaver - Stainless SteelFor 24" dia.09/23/96 33 05 13 Manhole InsertSouthwestern Packing & Seals, Inc.TetherLok - Stainless SteelFor 24" dia* From Original Standard Products ListClick to Return to the Table of Content9Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Pipe Casing Spacers 33-05-24 (07/01/13)11/04/02Steel Band Casing SpacersAdvanced Products and Systems, Inc.Carbon Steel Spacers, Model SI02/02/93Stainless Steel Casing SpacerAdvanced Products and Systems, Inc.Stainless Steel Spacer, Model SSI04/22/87Casing SpacersCascade Waterworks ManufacturingCasing Spacers09/14/10Stainless Steel Casing SpacerPipeline Seal and InsulatorStainless Steel Casing SpacerUp to 48"09/14/10Coated Steel Casin SpacersPipeline Seal and InsulatorCoated Steel Casin SpacersUp to 48" 05/10/11Stainless Steel Casing SpacerPowerseal4810 PowerchockUp to 48"03/19/18Casing SpacersBWMSS-12 Casing Spacer(Stainless Steel)03/19/18Casing SpacersBWMFB-12 Casing Spacer (Coated Carbon Steel) for Non_pressure Pipe and Grouted Casing* From Original Standard Products ListClick to Return to the Table of Content10Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Pipes/Ductile Iron 33-11-10(1/8/13)*33 11 10 Ductile Iron PipeGriffin Pipe Products, Co.Super Bell-Tite Ductile Iron Pressure Pipe, AWWA C150, C1513" thru 24"08/24/18 33 11 10 Ductile Iron PipeAmerican Ductile Iron Pipe Co.American Fastite Pipe (Bell Spigot)AWWA C150, C1514" thru 30"08/24/18 33 11 10 Ductile Iron PipeAmerican Ductile Iron Pipe Co.American Flex Ring (Restrained Joint)AWWA C150, C1514" thru 30"*33 11 10 Ductile Iron PipeU.S. Pipe and Foundry Co.AWWA C150, C151*33 11 10 Ductile Iron PipeMcWane Cast Iron Pipe Co.AWWA C150, C151* From Original Standard Products ListClick to Return to the Table of Content11Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Utility Line Marker (08/24/2018)* From Original Standard Products ListClick to Return to the Table of Content12Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Coatings/Epoxy 33-39-60 (01/08/13)02/25/02Epoxy Lining SystemSauereisen, IncSewerGard 210RSLA County #210-1.3312/14/01Epoxy Lining SystemErtech Technical CoatingsErtech 2030 and 2100 Series04/14/05Interior Ductile Iron Pipe CoatingInduronProtecto 401ASTM B-117Ductile Iron Pipe Only01/31/06Coatings for Corrosion ProtectionChestertonArc 791, S1HB, S1, S2Acid Resistance TestSewer Applications8/28/2006Coatings for Corrosion ProtectionWarren EnvironmentalS-301 and M-301Sewer Applications* From Original Standard Products ListClick to Return to the Table of Content13Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Coatings/Polyurethane* From Original Standard Products ListClick to Return to the Table of Content14Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Combination Air Valves 05/25/18 33-31-70 Air Release ValveA.R.I. USA, Inc.D025LTP02(Composite Body)2"* From Original Standard Products ListClick to Return to the Table of Content15Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Concrete*E1-04 Conc. Pipe, ReinforcedWall Concrete Pipe Co. Inc.ASTM C 76*E1-04 Conc. Pipe, ReinforcedHydro Conduit CorporationClass III T&G, SPL Item #77ASTM C 76*E1-04 Conc. Pipe, ReinforcedHanson Concrete ProductsSPL Item #95-Manhole, #98- PipeASTM C 76*E1-04 Conc. Pipe, ReinforcedConcrete Pipe & Products Co. Inc.ASTM C 76* From Original Standard Products ListClick to Return to the Table of Content16Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipe Enlargment System (Method)33-31-23 (01/18/13)PIM SystemPIM CorporationPolyethylenePIM Corp., Piscata Way, N.J. Approved PreviouslyMcConnell SystemsMcLat ConstructionPolyethyleneHouston, TexasApproved PreviouslyTRS SystemsTrenchless Replacement SystemPolyethyleneCalgary, CanadaApproved Previously* From Original Standard Products ListClick to Return to the Table of Content17Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipe/Fiberglass Reinforced Pipe 33-31-13(1/8/13)7/21/97 33 31 13 Cent. Cast Fiberglass (FRP)Hobas Pipe USA, Inc.Hobas Pipe (Non-Pressure)ASTM D3262/D375403/22/10 33 31 13 Fiberglass Pipe (FRP)AmeronBondstrand RPMP PipeASTM D3262/D375404/09/21Glass-Fiber Reinforced Polymer Pipe (FRP)Thompson Pipe GroupThompson Pipe (Flowtite)ASTM D3262/D37544/14/05Polymer Modified Concrete PipeAmitech USAMeyer Polycrete PipeASTM C33, A276, F4778" to 102", Class V06/09/10E1-9 Reinforced Polymer Concrete PipeUS Composite PipeReinforced Polymer Concrete PipeASTM C-76* From Original Standard Products ListClick to Return to the Table of Content18Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/HDPE 33-31-23(1/8/13)*High-density polyethylene pipePhillips Driscopipe, Inc.Opticore Ductile Polyethylene PipeASTM D 12488"*High-density polyethylene pipePlexco Inc.ASTM D 12488"*High-density polyethylene pipePolly Pipe, Inc.ASTM D 12488"High-density polyethylene pipeCSR Hydro Conduit/Pipeline SystemsMcConnell Pipe EnlargementASTM D 1248* From Original Standard Products ListClick to Return to the Table of Content19Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/PVC (Pressure Sewer) 33-11-12 (4/1/13)12/02/11 33-11-12 DR-14 PVC Pressure PipePipelife JetstreamPVC Pressure PipeAWWA C9004" thru 12"10/22/14 33-11-12 DR-14 PVC Pressure PipeRoyal Building ProductsRoyal Seal PVC Pressure PipeAWWA C9004" thru 12"* From Original Standard Products ListClick to Return to the Table of Content20Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/PVC* 33-31-20 (7/1/13)*33-31-20 PVC Sewer PipeJ-M Manufacturing Co., Inc. (JM Eagle)SDR-26ASTM D 30344" - 15"12/23/97* 33-31-20 PVC Sewer PipeDiamond Plastics CorporationSDR-26ASTM D 30344" thru 15"*33-31-20 PVC Sewer PipeLamson Vylon PipeASTM F 7894" thru 15"01/18/18 33-31-20 PVC Sewer PipeVinyltech PVC PipeGravity SewerASTM D30344" thru 15"11/11/98 33-31-20 PVC Sewer PipeDiamond Plastics Corporation "S" Gravity Sewer PipeASTM F 67918" to 27"*33-31-20 PVC Sewer PipeJ-M Manufacturing Co, Inc. (JM Eagle)SDR 26/35 PS 115/46ASTM F 67918" - 28"09/11/12 33-31-20 PVC Sewer PipePipelife Jet StreamSDR-26 and SDR-35ASTM F-67918"05/06/0533-31-20PVC Solid Wall PipeDiamond Plastics CorporationSDR 26/35 PS 115/46ASTM F-67918" to 48"04/27/0633-31-20PVC Sewer Fittings HarcoSDR-26 and SDR-35 Gasket Fittings ASTM D-3034, D-1784, etc4" - 15"*33-31-20PVC Sewer FittingsPlastic Trends, In.cGasketed PVC Sewer Main FittingsASTM D 30343/19/2018 33 31 20 PVC Sewer PipePipelife Jet StreamSDR 35ASTM F67918"- 24"3/19/2018 33 31 20 PVC Sewer PipePipelife Jet StreamSDR 26ASTM D30344"- 15"3/29/2019 33 31 20Gasketed Fittings (PVC)GPK Products, Inc.SDR 26ASTM D3034/F-6794"- 15"10/21/2020 33 31 20 PVC Sewer PipeNAPCOSDR 26ASTM D30344" - 15"10/22/2020 33 31 20 PVC Sewer PipeSanderson Pipe Corp.SDR 26ASTM D30344"- 15"10/21/2020 33 31 20 PVC Sewer PipeNAPCOSDR 26/35 PS 115/46ASTM F-67918"- 36"* From Original Standard Products ListClick to Return to the Table of Content21Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Rehab/CIPP 33-31-12 (01/18/13)*Cured in Place PipeInsituform Texark, IncASTM F 121605/03/99Cured in Place PipeNational Envirotech GroupNational Liner, (SPL) Item #27ASTM F-1216/D-581305/29/96Cured in Place PipeReynolds Inc/Inliner Technolgy (Inliner USA)Inliner TechnologyASTM F 1216* From Original Standard Products ListClick to Return to the Table of Content22Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Rehab/Fold & Form*Fold and Form PipeCullum Pipe Systems, Inc.11/03/98Fold and Form PipeInsituform Technologies, Inc.Insituform "NuPIpe"ASTM F-1504Fold and Form PipeAmerican Pipe & Plastics, Inc.Demo. Purpose Only12/04/00Fold and Form PipeUltralinerUltraliner PVC Alloy PipelinerASTM F-1504, 1871, 186706/09/03Fold and Form PipeMiller Pipeline Corp.EX MethodASTM F-1504, F-1947Up to 18" diameter* From Original Standard Products ListClick to Return to the Table of Content23Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Open Profile Large Diameter09/26/91 E100-2 PVC Sewer Pipe, RibbedLamson Vylon PipeCarlon Vylon H.C. Closed Profile Pipe,ASTM F 67918" to 48"09/26/91 E100-2 PVC Sewer Pipe, RibbedExtrusion Technologies, Inc.Ultra-Rib Open Profile Sewer PipeASTM F 67918" to 48"E100-2 PVC Sewer Pipe, RibbedUponor ETI Company11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Double WallAdvanced Drainage Systems (ADS) SaniTite HP Double Wall (Corrugated)ASTM F 273624"-30"11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Triple WallAdvanced Drainage Systems (ADS)SaniTite HP Triple Wall PipeASTM F 276430" to 60"05/16/11Steel Reinforced Polyethylene PipeConTech Construction ProductsDurmaxxASTM F 256224" to 72"* From Original Standard Products ListClick to Return to the Table of Content24Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Appurtenances 33-12-10 (07/01/13)01/18/18 33-12-10 Double Strap SaddleRomac202NS Nylon CoatedAWWA C8001"-2" SVC, up to 24" Pipe08/28/02Double Strap SaddleSmith Blair #317 Nylon Coated Double Strap Saddle07/23/12 33-12-10 Double Strap Service SaddleMueller CompanyDR2S Double (SS) Strap DI SaddleAWWA C8001"-2" SVC, up to 24" Pipe10/27/87Curb Stops-Ball Meter ValvesMcDonald6100M,6100MT & 610MT 3/4" and 1"10/27/87Curb Stops-Ball Meter ValvesMcDonald4603B, 4604B, 6100M, 6100TM and 6101M 1½" and 2"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesFord Meter Box Co., Inc.FB600-7NL, FB1600-7-NL, FV23-777-W-NL, L22-77NLAWWA C8002"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesFord Meter Box Co., Inc.FB600-6-NL, FB1600-6-NL, FV23-666-W-NL, L22-66NLAWWA C8001-1/2"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesFord Meter Box Co., Inc.FB600-4-NL, FB1600-4-NL, B11-444-WR-NL, B22444-WR-NL, L28-44NLAWWA C8001"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesMueller Co., Ltd.B-25000N, B-24277N-3, B-20200N-3, H-15000N, , H-1552N, H142276NAWWA C800, ANSF 61, ANSI/NSF 3722"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesMueller Co., Ltd.B-25000N, B-20200N-3, B-24277N-3,H-15000N, H-14276N, H-15525NAWWA C800, ANSF 61, ANSI/NSF 3721-1/2"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesMueller Co., Ltd.B-25000N, B-20200N-3,H-15000N, H-15530NAWWA C800, ANSF 61, ANSI/NSF 3721"01/26/00Coated Tapping Saddle with Double SS StrapsJCM Industries, Inc.#406 Double Band SS Saddle1"-2" Taps on up to 12" 0/5/21/12 33-12-25 Tapping Sleeve (Coated Steel)JCM Industries, Inc.412 Tapping Sleeve ESSAWWA C-223Up to 30" w/12" Out05/10/11Tapping Sleeve (Stainless Steel)Powerseal3490AS (Flange) & 3490MJ4"-8" and 16"02/29/12 33-12-25 Tapping Sleeve (Coated Steel)RomacFTS 420AWWA C-223U p to 42" w/24" Out02/29/12 33-12-25 Tapping Sleeve (Stainless Steel)RomacSST Stainless SteelAWWA C-223Up to 24" w/12" Out02/29/12 33-12-25 Tapping Sleeve (Stainless Steel)RomacSST III Stainless SteelAWWA C-223Up to 30" w/12" Out05/10/11Joint Repair ClampPowerseal3232 Bell Joint Repair Clamp4" to 30"Plastic Meter Box w/Composite LidDFW Plastics Inc.DFW37C-12-1EPAF FTWPlastic Meter Box w/Composite LidDFW Plastics Inc.DFW39C-12-1EPAF FTW08/30/06Plastic Meter Box w/Composite LidDFW Plastics Inc.DFW65C-14-1EPAF FTWClass "A"Concrete Meter BoxBass & HaysCMB37-B12 1118 LID-9Concrete Meter BoxBass & HaysCMB-18-Dual 1416 LID-9Concrete Meter BoxBass & HaysCMB65-B65 1527 LID-9* From Original Standard Products ListClick to Return to the Table of Content25Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Bolts, Nuts, and Gaskets 33-11-05 (01/08/13)* From Original Standard Products ListClick to Return to the Table of Content26Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Combination Air Release 33-31-70 (01/08/13)*E1-11 Combination Air Release ValveGA Industries, Inc.Empire Air and Vacuum Valve, Model 935 ASTM A 126 Class B, ASTM A 240 - float, ASTM A 307 - Cover Bolts1" & 2"*E1-11 Combination Air Release ValveMultiplex Manufacturing Co.Crispin Air and Vacuum Valves, Model No. 1/2", 1" & 2"*E1-11 Combination Air Release ValveValve and Primer Corp.APCO #143C, #145C and #147C1", 2" & 3"* From Original Standard Products ListClick to Return to the Table of Content27Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Dry Barrel Fire Hydrants 33-12-40 (01/15/14)10/01/87 E-1-12 Dry Barrel Fire HydrantAmerican-Darling ValveDrawing Nos. 90-18608, 94-18560AWWA C-50203/31/88 E-1-12 Dry Barrel Fire HydrantAmerican Darling ValveShop Drawing No. 94-18791 AWWA C-50209/30/87 E-1-12 Dry Barrel Fire HydrantClow CorporationShop Drawing No. D-19895AWWA C-50201/12/93 E-1-12 Dry Barrel Fire HydrantAmerican AVK CompanyModel 2700AWWA C-50208/24/88 E-1-12 Dry Barrel Fire HydrantClow CorporationDrawings D20435, D20436, B20506AWWA C-502E-1-12 Dry Barrel Fire HydrantITT Kennedy ValveShop Drawing No. D-80783FWAWWA C-50209/24/87 E-1-12 Dry Barrel Fire HydrantM&H Valve CompanyShop Drawing No. 13476AWWA C-50210/14/87 E-1-12 Dry Barrel Fire HydrantMueller CompanyShop Drawings No. 6461 A-423 CenturionAWWA C-50201/15/88E1-12 Dry Barrel Fire HydrantMueller CompanyShop Drawing FH-12A-423 Super Centurion 200AWWA C-50210/09/87 E-1-12 Dry Barrel Fire HydrantU.S. Pipe & FoundryShop Drawing No. 960250AWWA C-50209/16/87 E-1-12 Dry Barrel Fire HydrantWaterous CompanyShop Drawing No. SK740803AWWA C-50208/12/16 33-12-40 Dry Barrel Fire HydrantEJ (East Jordan Iron Works)WaterMaster 5CD250* From Original Standard Products ListClick to Return to the Table of Content28Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Meters02/05/93 E101-5 Detector Check MeterAmes CompanyModel 1000 Detector Check ValveAWWA C5504" - 10"08/05/04Magnetic Drive Vertical TurbineHerseyMagnetic Drive VerticalAWWA C701, Class 13/4" - 6"* From Original Standard Products ListClick to Return to the Table of Content29Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/PVC (Pressure Water) 33-31-70 (01/08/13)01/18/18 33-11-12 PVC Pressure PipeVinyltech PVC PipeDR14AWWA C900, AWWA C605, ASTM D17844"-12"3/19/2018 33 11 12 PVC Pressure PipePipelife Jet StreamDR14AWWA C9004"-12"3/19/2018 33 11 12 PVC Pressure PipePipelife Jet StreamDR18AWWA C90016"-24"5/25/2018 33 11 12 PVC Pressure PipeDiamond Plastics CorporationDR 14AWWA C9004"-12"5/25/2018 33 11 12 PVC Pressure PipeDiamond Plastics CorporationDR 18AWWA C90016"-24"12/6/2018 33 11 12 PVC Pressure PipeJ-M Manufacturing Co., Inc d/b/a JM EagleDR 14AWWA C900-16UL 1285ANSI/NSF 61FM 16124"-28"12/6/2018 33 11 12 PVC Pressure PipeJ-M Manufacturing Co., Inc d/b/a JM EagleDR 18AWWA C900-16UL 1285ANSI/NSF 61FM 161216"-24"9/6/2019 33 11 12 PVC Pressure PipeUnderground Solutions Inc.DR14 Fusible PVCAWWA C9004" - 8"9/6/2019 33 11 12 PVC Pressure PipeNAPCODR18AWWA C90016" - 24"9/6/2019 33 11 12 PVC Pressure PipeNAPCODR14AWWA C9004"- 12"9/6/2019 33 11 12 PVC Pressure PipeSanderson Pipe Corp.DR14AWWA C9004"- 12"* From Original Standard Products ListClick to Return to the Table of Content30Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/Valves & Fittings/Ductile Iron Fittings 33-11-11 (01/08/13)07/23/92E1-07 Ductile Iron FittingsStar Pipe Products, Inc.Mechanical Joint FittingsAWWA C153 & C110*E1-07 Ductile Iron FittingsGriffin Pipe Products, Co.Mechanical Joint FittingsAWWA C 110*E1-07 Ductile Iron FittingsMcWane/Tyler Pipe/ Union Utilities DivisionMechanical Joint Fittings, SSB Class 350AWWA C 153, C 110, C 11108/11/98E1-07 Ductile Iron FittingsSigma, Co.Mechanical Joint Fittings, SSB Class 351AWWA C 153, C 110, C 11202/26/14E1-07 MJ FittingsAccucastClass 350 C-153 MJ FittingsAWWA C1534"-12"05/14/98E1-07 Ductile Iron Joint RestraintsFord Meter Box Co./Uni-FlangeUni-Flange Series 1400 AWWA C111/C1534" to 36"05/14/98E1-24 PVC Joint RestraintsFord Meter Box Co./Uni-FlangeUni-Flange Series 1500 Circle-LockAWWA C111/C1534" to 24" 11/09/04E1-07 Ductile Iron Joint RestraintsOne Bolt, Inc.One Bolt Restrained Joint FittingAWWA C111/C116/C1534" to 12"02/29/12 33-11-11 Ductile Iron Pipe Mechanical Joint RestraintEBAA Iron, Inc.Megalug Series 1100 (for DI Pipe)AWWA C111/C116/C1534" to 42"02/29/12 33-11-11 PVC Pipe Mechanical Joint RestraintEBAA Iron, Inc.Megalug Series 2000 (for PVC Pipe)AWWA C111/C116/C1534" to 24"08/05/04E1-07 Mechanical Joint Retainer Glands(PVC)Sigma, Co.Sigma One-Lok SLC4 - SLC10AWWA C111/C1534" to 10"03/06/19 33-11-11 Mechanical Joint Retainer Glands(PVC)Sigma, Co.Sigma One-Lok SLCS4 - SLCS12AWWA C111/C1534" to 12"08/05/04E1-07 Mechanical Joint Retainer Glands(PVC)Sigma, Co.Sigma One-Lok SLCEAWWA C111/C15312" to 24"08/10/98E1-07 MJ Fittings(DIP)Sigma, Co.Sigma One-Lok SLDEAWWA C1534" - 24"10/12/10E1-24 Interior Restrained Joint SystemS & B Techncial ProductsBulldog System ( Diamond Lok 21 & JM Eagle ASTM F-16244" to 12"08/16/06E1-07 Mechanical Joint FittingsSIP Industries(Serampore)Mechanical Joint FittingsAWWA C1534" to 24"11/07/16 33-11-11 Mechanical Joint Retainer GlandsStar Pipe Products, Inc.PVC Stargrip Series 4000ASTM A536 AWWA C11111/07/16 33-11-11 Mechanical Joint Retainer GlandsStar Pipe Products, Inc.DIP Stargrip Series 3000ASTM A536 AWWA C11103/19/18 33-11-11 Mechanical Joint Retainer GlandsSIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Black For DIPASTM A536 AWWA C1113"-48"03/19/18 33-11-11 Mechanical Joint Retainer GlandsSIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR14 PVC PipeASTM A536 AWWA C1114"-12"03/19/18 33-11-11 Mechanical Joint Retainer GlandsSIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR18 PVC PipeASTM A536 AWWA C11116"-24"* From Original Standard Products ListClick to Return to the Table of Content31Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/Valves & Fittings/Resilient Seated Gate Valve* 33-12-20 (05/13/15)Resilient Wedged Gate Valve w/no GearsAmerican Flow ControlSeries 2500 Drawing # 94-2024716"12/13/02Resilient Wedge Gate ValveAmerican Flow ControlSeries 2530 and Series 2536AWWA C51530" and 36"08/31/99Resilient Wedge Gate ValveAmerican Flow ControlSeries 2520 & 2524 (SD 94-20255)AWWA C51520" and 24"05/18/99Resilient Wedge Gate ValveAmerican Flow ControlSeries 2516 (SD 94-20247)AWWA C51516"10/24/00E1-26 Resilient Wedge Gate ValveAmerican Flow ControlSeries 2500 (Ductile Iron)AWWA C5154" to 12"08/05/04Resilient Wedge Gate ValveAmerican Flow Control42" and 48" AFC 2500AWWA C51542" and 48"05/23/91E1-26 Resilient Wedge Gate ValveAmerican AVK CompanyAmerican AVK Resilient Seaded GVAWWA C5094" to 12"01/24/02E1-26 Resilient Wedge Gate ValveAmerican AVK Company20" and smaller*E1-26 Resilient Seated Gate ValveKennedy4" - 12"*E1-26 Resilient Seated Gate ValveM&H4" - 12"*E1-26 Resilient Seated Gate ValveMueller Co.4" - 12"11/08/99Resilient Wedge Gate Valve Mueller Co.Series A2361 (SD 6647)AWWA C51516"01/23/03Resilient Wedge Gate ValveMueller Co.Series A2360 for 18"-24" (SD 6709)AWWA C51524" and smaller05/13/05Resilient Wedge Gate ValveMueller Co.Mueller 30" & 36", C-515AWWA C51530" and 36"01/31/06Resilient Wedge Gate ValveMueller Co.Mueller 42" & 48", C-515AWWA C51542" and 48"01/28/88E1-26 Resilient Wedge Gate ValveClow Valve Co.AWWA C5094" - 12"10/04/94Resilient Wedge Gate ValveClow Valve Co.16" RS GV (SD D-20995)AWWA C51516"11/08/99E1-26 Resilient Wedge Gate ValveClow Valve Co.Clow RW Valve (SD D-21652)AWWA C51524" and smaller11/29/04Resilient Wedge Gate Valve Clow Valve Co.Clow 30" & 36" C-515AWWA C51530" and 36" (Note 3)11/30/12Resilient Wedge Gate ValveClow Valve Co.Clow Valve Model 2638AWWA C51524" to 48" (Note 3)05/08/91E1-26 Resilient Seated Gate ValveStockham Valves & FittingsAWWA C 509, ANSI 420 - stem, ASTM A 276 Type 304 - Bolts & nuts4" - 12"*E1-26 Resilient Seated Gate ValveU.S. Pipe and Foundry Co.Metroseal 250, requirements SPL #743" to 16"10/26/16 33-12-20 Resilient Seated Gate ValveEJ (East Jordan Iron Works)EJ FlowMaster Gate Valve & Boxes08/24/18Matco Gate Valve Matco-Norca225 MRAWWA/ANSI C115/An21.154" to 16"* From Original Standard Products ListClick to Return to the Table of Content32Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/Valves & Fittings/Rubber Seated Butterfly Valve 33-12-21 (07/10/14)*E1-30 Rubber Seated Butterfly ValveHenry Pratt Co.AWWA C-50424"*E1-30 Rubber Seated Butterfly ValveMueller Co.AWWA C-50424"and smaller1/11/99E1-30 Rubber Seated Butterfly ValveDezurik Valves Co.AWWA C-50424" and larger06/12/03E1-30 Valmatic American Butterfly ValveValmatic Valve and Manufacturing Corp. Valmatic American Butterfly Valve.AWWA C-504Up to 84" diameter04/06/07E1-30 Rubber Seated Butterfly ValveM&H ValveM&H Style 4500 & 1450 AWWA C-50424" to 48"03/19/18 33 12 21 Rubber Seated Butterfly ValveG. A. Industries (Golden Anderson)AWWA C504 Butterfly ValveAWWA C-50430"-54"* From Original Standard Products ListClick to Return to the Table of Content33Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Polyethylene Encasement 33-11-10 (01/08/13)05/12/05E1-13 Polyethylene EncasmentFlexsol PackagingFulton Enterprises AWWA C1058 mil LLD05/12/05E1-13 Polyethylene EncasmentMountain States Plastics (MSP) and AEP Ind.Standard HardwareAWWA C1058 mil LLD05/12/05E1-13 Polyethylene EncasmentAEP IndustriesBullstrong by Cowtown Bolt & GasketAWWA C1058 mil LLD09/06/19 33-11-11 Polyethylene EncasmentNorthtown Products Inc. PE Encasement for DIPAWWA C1058 mil LLD* From Original Standard Products ListClick to Return to the Table of Content34Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Sampling Station3/12/96Water Sampling StationWater PlusB20 Water Sampling Station* From Original Standard Products ListClick to Return to the Table of Content35Updated:04/09/2021 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Automatic Flusher10/21/20Automated Flushing SystemMueller HydroguardHG6-A-IN-2-BRN-LPRR(Portable) HG2-A-IN--2-PVC-018-LPLG(Permanent)04/09/21Automated Flushing SystemKupferle Foundry CompanyEclipse #9800wc04/09/21Automated Flushing SystemKupferle Foundry CompanyEclipse #9700 (Portable)* From Original Standard Products ListClick to Return to the Table of Content36Updated:04/09/2021